Expressway defect filling device

Through the highway defect filling device, the electric hammer is used to drive the filling module and the feeding module to be efficiently inserted into the road surface. Combined with the suction pump and sealing module, it solves the problems of low efficiency and filler separation of traditional repair methods, and achieves efficient repair of highway pavement damage. .

CN221918914UActive Publication Date: 2024-10-29内蒙古交通集团有限公司 +3
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420408369.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-04
Publication Date
2024-10-29
Estimated Expiration
2034-03-04

AI Technical Summary

Technical Problem

Traditional highway damage repair methods are inefficient, require a large amount of work, and the filler easily detaches from the road surface, making it difficult to effectively repair.

Method used

A highway defect filling device is designed, which includes an electric hammer, a filling module and a feeding module. The electric hammer drives the filling module to move, and the feeding pipe is inserted into the damaged part of the road surface. Efficient filling transportation is achieved through the suction pump and sealing module. , reduce the repair workload.

Benefits of technology

It improves the efficiency of highway pavement repair, reduces the repair workload, ensures effective filling of fillers, and improves the repair effect.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221918914U_ABST
    Figure CN221918914U_ABST
Patent Text Reader

Abstract

The expressway defect filling device comprises a machine body, an electric hammer, a filling module and a feeding module, the feeding module is installed on one side of the electric hammer, the electric hammer is fixedly connected with the machine body, the filling module is installed on the machine body, the machine body comprises an installation base and an extension pipe, and the extension pipe is fixedly connected with the installation base. One end of the mounting seat is fixedly mounted at the end part of the electric hammer; according to the expressway defect filling device, the filling module is driven by the electric hammer to move, so that the end part of the material conveying pipe is pushed to collide with damaged parts such as cracks on an expressway pavement, then the material conveying pipe can be inserted into the damaged parts of the pavement, and then repairing filler is input into the filling module through the feeding module; the damaged part of the road surface is filled, and then the road surface of the expressway is repaired; the workload of road surface repairing is effectively reduced, and the repairing efficiency of the road surface is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of highway maintenance, in particular to a highway defect filling device. Background Art

[0002] Highway refers to public roads between cities, between urban and rural areas, and between villages that can be used for motor vehicles and have been accepted and approved by the transportation authority. It includes highways that have been built and approved by the transportation authority. It should also include highways that have been designed in accordance with national highway engineering technical standards, approved by relevant national administrative departments, and are under construction by the transportation authority.

[0003] When highways are open to traffic for a long time and the ground moves naturally, they often become damaged and cracked and need to be repaired. The traditional method of repairing highway damage is to excavate the damaged part as a whole to form a large enough pothole to fill it with fillers and repair the damaged part. This repair method requires the road surface to be expanded and a large amount of repair fillers to be filled. Not only is the repair efficiency low and the engineering workload large, but also because the surface of the pothole after expansion is relatively flat, the newly filled filler will detach from the highway road surface. Utility Model Content

[0004] In order to solve the above technical problems, a highway defect filling device is provided.

[0005] In order to achieve the above purpose, the following scheme is provided: a highway defect filling device, comprising a body, an electric hammer, a filling module and a feeding module, wherein the feeding module is installed on one side of the electric hammer, the electric hammer is fixedly connected to the body, the filling module is installed at the body, the body comprises a mounting seat and an extension tube, one end of the mounting seat is fixedly installed at the end of the electric hammer, the extension tube is fixedly installed at the other end of the mounting seat and the extension tube is connected to the mounting seat, a first mounting cavity, a feeding cavity and a second mounting cavity are sequentially arranged in the extension tube from top to bottom and the three are connected, The filling module includes a connecting rod, a feed pipe and a delivery pipe, one end of the connecting rod is installed at the electric hammer, the other end of the connecting rod is fixedly connected to one end of the feed pipe, the other end of the feed pipe is fixedly connected to one end of the delivery pipe, the other end of the delivery pipe is provided with a conical top, the feed pipe is located in the first installation cavity, and a plurality of feed holes are provided at the side of one end of the feed pipe close to the feed cavity, the delivery pipe is located at the feed cavity and the second installation cavity, the delivery pipe is connected to the feed pipe, and a plurality of discharge holes are evenly provided at one end of the delivery pipe close to the top.

[0006] Furthermore, it also includes a sealing module, which includes a first sealing sleeve, a sealing gasket and a second sealing sleeve. The first sealing sleeve is installed at the first installation cavity, the first sealing sleeve is arranged at the feed pipe, and a sealing gasket is arranged at the bottom of the feed cavity. The second sealing sleeve is installed in the second installation cavity, and the second sealing sleeve is arranged at the feed pipe.

[0007] Furthermore, the feeding module includes a suction pump, which is installed on the side of the electric hammer, and the suction pump is connected to the feeding cavity of the extension tube through a pipeline.

[0008] Furthermore, the electric hammer is provided with a main handle and a secondary handle, the main handle is provided with a plurality of control buttons, a controller is provided inside the electric hammer, and the controller is electrically connected to the electric hammer, the suction pump and the control buttons.

[0009] The working principle and advantages of the utility model are as follows: the highway defect filling device drives the filling module to move by an electric hammer, so that the end of the material delivery pipe pushes and hits the damaged parts of the highway pavement such as cracks, so that the material delivery pipe can be inserted into the damaged part of the pavement, and then the repair filler is input into the filling module through the feeding module to fill the damaged part of the pavement, thereby repairing the highway pavement; effectively reducing the workload of pavement repair and improving the efficiency of pavement repair. BRIEF DESCRIPTION OF THE DRAWINGS

[0010] Figure 1 It is the front view of the utility model;

[0011] Figure 2 It is a structural schematic diagram of the utility model.

[0012] The reference numerals in the drawings of the specification include:

[0013] 1. Electric hammer, 11. Main grip, 12. Control button, 13. Auxiliary grip, 2. Suction pump, 3. Mounting seat, 4. Extension tube, 41. First installation cavity, 42. Feed cavity, 43. Second installation cavity, 5. Connecting rod, 6. Feed pipe, 61. Feed hole, 7. Feed pipe, 71. Head, 72. Discharge hole, 81. First sealing sleeve, 82. Sealing pad, 83. Second sealing sleeve. DETAILED DESCRIPTION

[0014] The following is a further detailed description through specific implementation methods:

[0015] like Figure 1 to Figure 2 As shown:

[0016] A highway defect filling device comprises a machine body, an electric hammer 1, a filling module and a feeding module, wherein the feeding module is installed on one side of the electric hammer 1, and the electric hammer 1 is fixedly connected to the machine body; the machine body is used to install the filling module, the electric hammer 1 is used to drive the filling module to move, so that the filling module can be inserted into the damaged part of the road surface, and the feeding module is used to transport the filler to the filling module, so that the filling module can be inserted into the damaged part of the road surface;

[0017] The machine body is composed of a mounting seat 3 and an extension tube 4. The machine body is fixedly mounted on one end of the electric hammer 1 for mounting a drill bit, and the fixture for mounting the drill bit of the electric hammer 1 is located in the mounting seat 3. The extension tube 4 is mounted on the other end of the mounting seat 3, and the filling module is mounted in the extension tube 4. The extension tube 4 is provided with a first mounting cavity 5, a feed cavity 42, and a second mounting cavity 43 from top to bottom.

[0018] The filling module includes a connecting rod 5, a feed pipe 6 and a delivery pipe 7. The connecting rod 5, the feed pipe 6 and the delivery pipe 7 are coaxially arranged and fixedly connected in sequence from top to bottom. The feed pipe 6 is connected to the delivery pipe 7. The feed pipe 6 is located in the first installation cavity 5, and the feed pipe 6 can be moved down to the feed cavity 42. A plurality of feed holes 61 are provided at the side of the feed pipe 6, so that when the feed pipe 6 moves down to the feed cavity 42, the filler in the feed cavity 42 can enter the feed pipe 6 through the feed holes 61. The delivery pipe 7 is located in the second installation cavity 43 and the feed cavity 42. A conical top 71 is provided at the lower end of the feed pipe 6 to facilitate the insertion of the delivery pipe 7 into the damaged part of the road surface, and a delivery hole is provided at one end of the delivery pipe 7 close to the top 71 to facilitate the discharge of the filler at the feed pipe 6 from the delivery hole through the delivery pipe 7.

[0019] It also includes a sealing module, which includes a first sealing sleeve 81, a sealing gasket 82 and a second sealing sleeve 83. The first sealing sleeve 81 is installed in the first installation cavity 5 and is sleeved on the feed pipe 6, so that when the feed pipe 6 moves into the first installation cavity 5, the first sealing sleeve 81 can block the feed hole 61. A sealing gasket 82 is provided at the bottom of the feed cavity 42. The second sealing sleeve 83 is installed in the second installation cavity 43. The second sealing sleeve 83 is sleeved on the feed pipe 7, so that the second sealing sleeve 83 can block the feed pipe 7. The first sealing sleeve 81, the sealing gasket 82 and the second sealing sleeve 83 work together to prevent the filler in the feed cavity 42 from leaking to the outside.

[0020] The feeding module includes a suction pump 2, which is installed on the side of the electric hammer 1. The suction pump 2 is connected to the feeding cavity 42 of the extension tube 4 through a pipeline. The suction pump 2 absorbs external fillers such as asphalt oil, concrete mortar cement, etc., and then transports them to the feeding cavity 42.

[0021] The electric hammer 1 is provided with a main handle 11 and a sub-handle 13. The main handle 11 is provided with a plurality of control buttons 12. The control buttons 12 are used to control the operation of the electric hammer 1 and the suction pump 2. A controller is provided inside the electric hammer 1. The controller is an existing mature technology and will not be described in detail here. The controller is electrically connected to the electric hammer 1, the suction pump 2 and the control buttons 12.

[0022] The specific implementation process is as follows:

[0023] When using the highway defect filling device, the suction pump 2 is connected to the external filler through a pipeline, so that the suction pump 2 can absorb the filler; the user holds the device by holding the main grip 11 and the auxiliary grip 13, and aligns the head 71 with the defective part of the highway road surface. If the defective part is large in size, the electric hammer 1 is started to extend the feed pipe 7 out of the extension pipe 4, and the electric hammer 1 can be stopped, and then the feed pipe 7 can be inserted into the defective part; if the defective part is small in size, the user operates the control button 12 at the main grip 11 to start the electric hammer 1, and the electric hammer 1 drives the connecting rod 5, the feed pipe 6 and the feed pipe 7 to move. The material pipe 7 reciprocates, causing the top block to hammer the defect until the feed pipe 7 can be inserted into the defect; then the user starts the suction pump 2 by operating the control button 12, and the suction pump 2 pumps the material into the feed cavity 42. At this time, the feed pipe 6 is located in the feed cavity 42, and the filler in the feed cavity 42 enters the feed pipe 6 through the feed hole 61, and is then transported to the feed pipe 7, and then discharged from the discharge hole 72 at the feed pipe 7, and then filled into the defective part of the highway road surface, until the defective part is filled, and the feed pipe 7 can be pulled out from the defect.

[0024] The user can start the electric hammer 1 again and retract the feeding pipe 7 into the extension pipe 4 so that the second sealing sleeve 83 blocks the discharge hole 72 and the second sealing sleeve 83 blocks the feed hole 61 of the feed pipe 6 .

[0025] The highway defect filling device drives the filling module to move by an electric hammer 1, so that the end of the feed pipe 7 pushes and hits the damaged parts of the highway pavement, such as cracks, so that the feed pipe 7 can be inserted into the damaged part of the pavement, and then the repair filler is input into the filling module through the feeding module to fill the damaged part of the pavement, thereby repairing the highway pavement; effectively reducing the workload of pavement repair and improving the efficiency of pavement repair.

[0026] The above is only an embodiment of the utility model. The common sense such as the known specific structure and characteristics in the scheme is not described in detail here. The ordinary technicians in the relevant field know all the common technical knowledge in the technical field of the utility model before the application date or priority date, can obtain all the existing technologies in the field, and have the ability to apply the conventional experimental means before that date. The ordinary technicians in the relevant field can improve and implement this scheme in combination with their own abilities under the enlightenment given by this application. Some typical known structures or known methods should not become obstacles for ordinary technicians in the relevant field to implement this application. It should be pointed out that for the technicians in this field, without departing from the structure of the utility model, several deformations and improvements can be made, which should also be regarded as the protection scope of the utility model, which will not affect the effect of the implementation of the utility model and the applicability of the patent. The protection scope required by this application shall be based on the content of its claims, and the specific implementation methods and other records in the specification can be used to explain the content of the claims.

Claims

1. A highway defect filling device, characterized in that: The invention comprises a body, an electric hammer, a filling module and a feeding module, wherein the feeding module is installed on one side of the electric hammer, the electric hammer is fixedly connected to the body, and the filling module is installed at the body, the body comprises a mounting seat and an extension tube, one end of the mounting seat is fixedly installed at the end of the electric hammer, the extension tube is fixedly installed at the other end of the mounting seat and the extension tube is communicated with the mounting seat, a first mounting cavity, a feeding cavity and a second mounting cavity are sequentially arranged in the extension tube from top to bottom and the three are connected, the filling module comprises a connecting rod, a feeding pipe and a delivery pipe, one end of the connecting rod is installed at the electric hammer, the other end of the connecting rod is fixedly connected to one end of the feeding pipe, the other end of the feeding pipe is fixedly connected to one end of the delivery pipe, a conical top is arranged at the other end of the delivery pipe, the feeding pipe is located in the first mounting cavity, and a plurality of feeding holes are arranged at the side of one end of the feeding pipe close to the feeding cavity, the delivery pipe is located at the feeding cavity and the second mounting cavity, the delivery pipe is connected to the feeding pipe, and a plurality of discharge holes are evenly arranged at one end of the delivery pipe close to the top.

2. The highway defect filling device according to claim 1, characterized in that: It also includes a sealing module, which includes a first sealing sleeve, a sealing gasket and a second sealing sleeve. The first sealing sleeve is installed at the first installation cavity, the first sealing sleeve is arranged at the feed pipe, and a sealing gasket is arranged at the bottom of the feed cavity. The second sealing sleeve is installed in the second installation cavity, and the second sealing sleeve is arranged at the delivery pipe.

3. The highway defect filling device according to claim 1, characterized in that: The feeding module comprises a suction pump which is mounted on the side of the electric hammer and is connected to the feeding cavity of the extension tube through a pipeline.

4. The highway defect filling device according to claim 1, characterized in that: The electric hammer is provided with a main grip and a secondary grip, the main grip is provided with a plurality of control buttons, a controller is provided inside the electric hammer, and the controller is electrically connected with the electric hammer, the suction pump and the control buttons.