Pipe gallery type bridge anti-collision structure
By setting up pipe galleries and weep holes in the bridge anti-collision structure, the problems of difficult wiring and low construction safety on the outside of the bridge anti-collision structure are solved, the safe installation and maintenance of pipeline lines is realized, and a better protection of the environment and Construction safety.
Patent Information
- Application Number
- CN202420178745.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-24
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2034-01-24
AI Technical Summary
When the gaps along the length of the bridge are closely spaced, wiring on the outside of the bridge's anti-collision structure is difficult and dangerous. Existing technology cannot effectively ensure the normal operation and construction safety of the lines.
Design a pipe gallery type bridge anti-collision structure. A pipe gallery is installed inside the main body. The pipe gallery is connected to the operation hole and the drain hole, providing a closed environment to protect the pipeline lines, and management and maintenance are carried out through the operation hole, and the drain hole is eliminated. Water accumulation reduces construction risks.
It realizes the safe installation and maintenance of pipeline lines, provides a better protective environment, reduces construction risks and the possibility of line failures, and improves construction safety.
Smart Images

Figure CN221918964U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of bridges, and in particular to a pipe gallery type bridge anti-collision structure. Background Art
[0002] In important engineering construction such as road traffic, bridges are usually built according to the terrain. At the same time, in order to ensure the normal operation of roads, various systems such as electricity, monitoring, and communications are set up to ensure the normal operation of road traffic.
[0003] Various systems such as electricity, monitoring, and communications are usually connected in a wired manner. At present, the wiring on the bridge is often set on the outside of the anti-collision structure on both sides, which can not only achieve effective layout of the line, but also prevent vehicles or pedestrians from stepping on the line, which has positive significance. However, in actual situations, the gaps between some anti-collision structures in the length direction of the bridge are relatively close, and it is very difficult to lay the wiring on the outside of the anti-collision structure. Operators are often required to use machinery or hanging methods to reach the outside of the anti-collision structure for line laying, which is very troublesome and has a high risk factor, and the quality cannot be guaranteed. Utility Model Content
[0004] In order to solve the above technical problems or partially solve the above technical problems, the present application provides a corridor-type bridge anti-collision structure.
[0005] The present application provides a pipe gallery-type bridge anti-collision structure, including a main body, wherein a pipe gallery is arranged inside the main body along the length direction of the bridge, an operation hole is arranged on the side of the main body facing the inner side of the bridge, and the operation hole is connected to the pipe gallery; a drainage hole is arranged on the side of the main body facing the outer side of the bridge, and the drainage hole is connected to the pipe gallery.
[0006] Optionally, a side wall of the main body facing the outer side of the bridge is gradually inclined from top to bottom away from the inner side of the bridge.
[0007] Optionally, the main body includes a base and a stopper, the bottom of the base is arranged on the bridge deck, and the bottom of the stopper is connected to the top of the base; the width of the base along the bridge deck direction is greater than the width of the stopper along the bridge deck direction.
[0008] Optionally, a side wall of the base facing the inner side of the bridge is inclined gradually from top to bottom towards the inner side of the bridge.
[0009] Optionally, the pipe gallery is arranged inside the base.
[0010] Optionally, there are multiple operating holes, and the multiple operating holes are arranged at intervals along the length direction of the bridge.
[0011] Optionally, a closing plate may be removably provided on the operating hole.
[0012] Optionally, along the drainage direction of the drain hole, the drain hole is arranged to be gradually inclined downward.
[0013] Optionally, there are multiple drainage holes, and the multiple drainage holes are arranged at intervals along the length direction of the bridge.
[0014] Compared with the prior art, the technical solution provided by the embodiments of the present application has the following advantages:
[0015] The corridor-type bridge anti-collision structure provided in the present application has a corridor inside the main body, so that the pipeline line can be directly set inside the corridor, and the internal pipeline line can be managed and maintained through the operation holes. In addition, the drainage holes can discharge the accumulated water that accidentally flows into the corridor to avoid the accumulated water affecting the normal operation of the pipeline line. Compared with the current method of setting the pipeline line outside the anti-collision structure, the bridge anti-collision structure provided in the present application can provide a relatively closed environment for the pipeline line, thereby playing a good protective role for the pipeline line. In addition, when installing or maintaining the pipeline line, the operator can operate on the bridge deck, and the construction is very safe. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the present application and, together with the description, serve to explain the principles of the present application.
[0017] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative labor.
[0018] Figure 1 This is a schematic diagram of the structure of the pipe gallery type bridge anti-collision structure described in an embodiment of the present application;
[0019] Figure 2 A schematic diagram of an example bridge structure to which the pipe gallery type bridge anti-collision structure described in an embodiment of the present application is applied;
[0020] Figure 3 for Figure 2 Schematic diagram of the cross-sectional structure.
[0021] in,
[0022] 1. Main body; 10. Base; 11. Stopper; 2. Pipe gallery; 3. Drain hole; 4. Operation hole; 5. Bridge deck. DETAILED DESCRIPTION
[0023] In order to more clearly understand the above-mentioned purposes, features and advantages of the present application, the scheme of the present application will be further described below. It should be noted that the embodiments of the present application and the features in the embodiments can be combined with each other without conflict.
[0024] In the following description, many specific details are set forth to facilitate a full understanding of the present application, but the present application may also be implemented in other ways different from those described herein; obviously, the embodiments in the specification are only part of the embodiments of the present application, rather than all of the embodiments.
[0025] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by technicians in the technical field to which this application belongs; the terms used herein are only for the purpose of describing specific embodiments and are not intended to limit this application; the terms "including" and "having" in the specification and claims of this application and the above-mentioned figure descriptions and any variations thereof are intended to cover non-exclusive inclusions.
[0026] In the description of the embodiments of the present application, technical terms such as "first" and "second" are only used to distinguish different objects and cannot be understood as indicating or implying relative importance or implicitly indicating the number, specific order or primary and secondary relationship of the indicated technical features.
[0027] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present application. The appearance of the phrase in various locations in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those skilled in the art that the embodiments described herein may be combined with other embodiments.
[0028] In the description of the embodiments of the present application, the term "and / or" is only a description of the association relationship of the associated objects, indicating that there may be three relationships. For example, A and / or B can represent: A exists alone, A and B exist at the same time, and B exists alone. In addition, the character " / " in this article generally indicates that the associated objects before and after are in an "or" relationship.
[0029] In the description of the embodiments of the present application, the term "multiple" refers to more than two (including two). Similarly, "multiple groups" refers to more than two groups (including two groups), and "multiple pieces" refers to more than two pieces (including two pieces).
[0030] In the description of the embodiments of the present application, the technical terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, which are only for the convenience of describing the embodiments of the present application and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the embodiments of the present application.
[0031] In the description of the embodiments of the present application, unless otherwise clearly specified and limited, technical terms such as "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, and it can be the internal connection of two elements or the interaction relationship between two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the embodiments of the present application can be understood according to the specific circumstances.
[0032] Reference Figures 1 to 3 As shown, a corridor-type bridge anti-collision structure provided in this embodiment includes a main body 1, a corridor 2 is provided inside the main body 1 along the length direction of the bridge, an operation hole 4 is provided on the side of the main body 1 facing the inner side of the bridge, and the operation hole 4 is connected to the corridor 2; a drainage hole 3 is provided on the side of the main body 1 facing the outer side of the bridge, and the drainage hole 3 is connected to the corridor 2.
[0033] The main body 1 is usually made of concrete, and a steel frame structure may be provided inside the concrete to ensure its structural strength. In some other embodiments, the main body 1 may also be made of other materials such as metal or stone.
[0034] The pipe gallery 2 is arranged inside the main body 1, and the extension direction of the pipe gallery 2, that is, the length direction, is consistent with the length direction of the bridge. The interior of the pipe gallery 2 is used to lay pipelines; the cross section of the pipe gallery 2 can be rectangular or circular, and the specific shape can be set according to actual conditions, and is not limited in this embodiment. However, when it is circular or arc-shaped, the inner wall of the pipe gallery 2 will have better radial force resistance.
[0035] An operation hole 4 is provided on a side wall of the pipe gallery 2 facing the inner side of the bridge. The operation hole 4 is interconnected with the pipe gallery 2 and is used for managing and maintaining the pipeline lines in the pipe gallery 2. The size of the operation hole 4 can be set according to actual conditions, so as not to interfere with the management and maintenance of the pipeline lines.
[0036] At the same time, a drainage hole 3 is arranged on one side wall of the pipe gallery 2 facing the outside of the bridge. The drainage hole 3 is connected to the pipeline, that is, one end of the drainage hole is connected to the pipe gallery 2, and the other end is connected to the outside. When water accumulates unexpectedly in the pipe gallery 2, the water flow can be discharged to the outside of the bridge along the drainage hole 3, so as to avoid water accumulation inside the pipe gallery 2 and affect the normal operation of the pipeline line.
[0037] By setting up the pipe gallery 2 inside the main body 1, the pipeline line can be directly set inside the pipe gallery 2, and the internal pipeline line can be managed and maintained through the operation hole 4. The drain hole 3 set in addition can discharge the accumulated water that accidentally flows into the pipe gallery 2 to avoid the accumulated water affecting the normal operation of the pipeline line. Compared with the current method of setting the pipeline line outside the anti-collision structure, the bridge anti-collision structure provided in the present application can provide a relatively closed environment for the pipeline line, thereby playing a good protective role for the pipeline line. In addition, when installing or maintaining the pipeline line, the operator can operate on the bridge deck 5, and the construction is very safe.
[0038] In some other embodiments, a specific bracket may also be provided at the bottom of the pipe gallery 2. When laying pipeline lines inside the pipe gallery 2, the pipeline lines may be placed above the bracket so that there is a certain distance between the pipeline lines and the bottom of the pipe gallery 2, to prevent the pipeline lines from being soaked by accidental water accumulation, thereby affecting the normal operation of related equipment.
[0039] In some embodiments, a side wall of the main body 1 facing the outside of the bridge is gradually inclined from top to bottom away from the inside of the bridge.
[0040] The entire main body 1 is erected on both sides of the bridge along the length direction and has a certain height; in order to ensure that the main body 1 can have a greater resistance when it is accidentally hit by a vehicle on the bridge deck 5, in this embodiment, the side wall of the main body 1 facing the outside of the bridge is gradually inclined from top to bottom away from the inside of the bridge, so that the main body 1 has a lower center of gravity, thereby increasing its impact resistance, and at the same time reducing the probability of it tipping toward the outside of the bridge when hit.
[0041] In some embodiments, the main body 1 includes a base 10 and a stopper 11, the bottom of the base 10 is set on the bridge deck 5, and the bottom of the stopper 11 is connected to the top of the base 10; the width of the base 10 along the direction of the bridge deck 5 is greater than the width of the stopper 11 along the direction of the bridge deck 5.
[0042] The main body 1 can be structurally divided into two parts, including a base 10 relatively located at the bottom and a stopper 11 relatively located at the top. The bottom of the base 10 is connected to the bridge deck 5, and the bottom of the stopper 11 is connected to the top of the base 10. At the same time, the width of the base 10 along the direction of the bridge deck 5 is greater than the width of the stopper 11 along the direction of the bridge deck 5, so that the main body 1 presents a structure that is narrow at the top and wide at the bottom, thereby lowering the center of gravity of the entire main body 1, making it more stable when impacted.
[0043] In actual situations, the base 10 and the stopper 11 are usually formed in one piece, which simplifies the process and reduces the generation of connection stress.
[0044] In some embodiments, a side wall of the base 10 facing the inner side of the bridge is gradually inclined from top to bottom toward the inner side of the bridge.
[0045] One side wall of the base 10 facing the inner side of the bridge is gradually inclined from top to bottom towards the inner side of the bridge, so that the part of the base 10 facing the inner side of the bridge forms a convex structure facing the inner side of the bridge, so that when the vehicle is driving close to the edge of the bridge, the tires are the first to feel that the vehicle is about to scratch the main body 1. This feedback can remind the driver to correct the direction in time to avoid scratching the body of the vehicle, while also causing more serious damage to the main body 1.
[0046] In some embodiments, the pipe gallery 2 is disposed inside the base 10 .
[0047] The strength and internal space of the base 10 are superior to those of the stopper 11 , so the pipe gallery 2 is arranged inside the base 10 to better play the advantageous role of the pipe gallery 2 .
[0048] In some embodiments, there are multiple operating holes 4, and the multiple operating holes 4 are arranged at intervals along the length direction of the bridge.
[0049] During the molding process of the main body 1, operation holes 4 are reserved. In actual situations, the number of operation holes 4 can be determined according to specific conditions, such as the length of the main body 1 along the bridge direction, the volume of the main body 1, or the number of pipelines, so as to better manage and maintain the pipelines. In addition, the distance between adjacent operation holes 4 can also be specifically set according to actual conditions.
[0050] In some embodiments, a closing plate is detachably provided on the operating hole 4 .
[0051] During normal use, the operating hole 4 is in a closed state. For example, in the present embodiment, a closing plate is detachably provided on the operating hole 4. When management and maintenance are required, the closing plate can be opened, and when management and maintenance are not required, the closing plate can be closed. Specifically, in the present embodiment, the closing plate is detachably connected by bolts, and in some other embodiments, it can also be achieved by hinges.
[0052] In addition, in some other embodiments, a circle of countersunk grooves is provided on the edge of the operating hole 4 to limit the closing plate and also to make the sealing of the closing plate to the connecting hole more tight.
[0053] In some embodiments, along the drainage direction of the drainage hole 3 , the drainage hole 3 is gradually inclined downward.
[0054] In order to facilitate the drainage of accumulated water from the drainage hole 3, the drainage hole 3 is tilted as a whole, that is, one end of the connecting pipe gallery 2 is higher than the other end, so as to adapt to the water flow trend and achieve efficient and rapid drainage.
[0055] In some embodiments, there are multiple drainage holes 3, and the multiple drainage holes 3 are arranged at intervals along the length direction of the bridge.
[0056] The number of the drainage holes 3 can be set according to actual specific conditions, such as the length of the main body 1. When the length of the main body 1 is relatively long, more drainage holes 3 can be set to ensure the drainage effect.
[0057] It should be noted that the entire main body 1 can be prefabricated, and during the installation process, multiple main bodies 1 are butt-jointed together along the length direction of the bridge, thereby improving construction efficiency.
[0058] Specifically, the pipe corridors 2 between the multiple main bodies 1 connected together are interconnected; concrete sealing can be used between two adjacent main bodies 1, and slots and plug rods can be further reserved on a group of side walls to be connected on the main body 1 to ensure the connection strength after connection.
[0059] The above is only a specific implementation of the present application, so that those skilled in the art can understand or implement the present application. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein can be implemented in other embodiments without departing from the spirit or scope of the present application. Therefore, the present application will not be limited to the embodiments described herein, but will conform to the widest scope consistent with the principles and novel features applied for herein.
Claims
1. A pipe gallery type bridge anti-collision structure, characterized in that: The invention comprises a main body (1), wherein a pipe gallery (2) is arranged inside the main body (1) along the length direction of the bridge, an operation hole (4) is arranged on the side of the main body (1) facing the inside of the bridge, and the operation hole (4) is connected to the pipe gallery (2); and a drainage hole (3) is arranged on the side of the main body (1) facing the outside of the bridge, and the drainage hole (3) is connected to the pipe gallery (2).
2. The pipe gallery type bridge anti-collision structure according to claim 1 is characterized in that: A side wall of the main body (1) facing the outer side of the bridge is inclined from top to bottom gradually away from the inner side of the bridge.
3. The pipe gallery type bridge anti-collision structure according to claim 1 is characterized in that: The main body (1) comprises a base (10) and a stopper (11); the bottom of the base (10) is arranged on the bridge deck (5), and the bottom of the stopper (11) is connected to the top of the base (10); the width of the base (10) along the direction of the bridge deck (5) is greater than the width of the stopper (11) along the direction of the bridge deck (5).
4. The pipe gallery type bridge anti-collision structure according to claim 3 is characterized in that: A side wall of the base (10) facing the inner side of the bridge is inclined gradually from top to bottom towards the inner side of the bridge.
5. The pipe gallery type bridge anti-collision structure according to claim 3 is characterized in that: The pipe gallery (2) is arranged inside the base (10).
6. The pipe gallery type bridge anti-collision structure according to claim 1, characterized in that: The number of the operating holes (4) is multiple, and the multiple operating holes (4) are arranged at intervals along the length direction of the bridge.
7. The pipe gallery type bridge anti-collision structure according to claim 1 is characterized in that: The operating hole (4) is provided with a detachable closing plate.
8. The pipe gallery type bridge anti-collision structure according to claim 1, characterized in that: Along the drainage direction of the drainage hole (3), the drainage hole (3) is arranged to be gradually inclined downward.
9. The pipe gallery type bridge anti-collision structure according to claim 1, characterized in that: The number of the drainage holes (3) is multiple, and the multiple drainage holes (3) are arranged at intervals along the length direction of the bridge.