Prefabricated beam-column connecting component
By using T-shaped high-strength anti-corrosion steel pipes and pouring reinforcement layers in the connection of prefabricated beams and columns, combined with the double-headed stud locking mechanism, the safety hazards and corrosion problems of prefabricated beam-column connections in the existing technology are solved, and high strength and stability are achieved. Connected with prefabricated beams and columns with anti-corrosion effect.
Patent Information
- Application Number
- CN202420157112.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-23
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2034-01-23
Smart Images

Figure CN221919759U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of prefabricated components, in particular to a prefabricated beam-column connecting component. Background Art
[0002] Precast beam-column connection is a technology for connecting precast beams and columns in installation projects. The traditional methods are mainly as follows: The first is the additional reinforcement lap connection: This connection method usually does not extend the lower longitudinal reinforcement of the precast beam into the core area of the node, but overlaps the additional reinforcement in the core area of the node with the reinforcement extending from the beam end, and pours concrete to form an integral structure. A small U-shaped thin-walled keyway is often reserved at the end of the precast beam, the longitudinal reinforcement at the bottom of the beam is cut off at the end of the keyway, and the additional reinforcement runs through the core area of the node and is placed in the keyway. The second is a mixed connection of anchoring and lap connection: It combines the advantages of the additional reinforcement lap and anchoring methods. While setting a U-shaped keyway at the end of the beam, the lower bottom reinforcement of the precast beam extends out of the beam end and is anchored in the core area of the node, and additional reinforcement is added to strengthen the connection between the beam and the column.
[0003] In the prior art, the way of connecting beams and columns is also constantly changing to adapt to installation and construction under complex working conditions. For example, in the patent document with patent announcement number CN220035722U, a beam-column connector and a beam-column connection assembly are disclosed, whose main structure includes a first straight plate and a second straight plate, the first straight plate connects and fixes one side of the column, the second straight plate connects and fixes one side of the crossbeam, and then the straight plates are connected to the corresponding beams or main bodies by bolts, and the main strenuous parts are the bolts. This structure has a great safety hazard when the overall large load is installed and connected, especially for beam-column structures exposed outdoors for a long time, and the connection parts are prone to breakage when the bolts are corroded.
[0004] To this end, the utility model optimizes and improves the prefabricated beam-column connection problem in the prior art, and specially designs a component that can quickly realize the prefabricated beam-column connection while ensuring the strength and reliability of the connection, so as to better solve the problems existing in the prior art. Utility Model Content
[0005] The utility model is to solve one of the above technical problems, and the technical solution adopted is: a prefabricated beam-column connecting component, including a T-shaped high-strength anti-corrosion steel pipe, the upper part of the inner cavity of the T-shaped high-strength anti-corrosion steel pipe is a horizontally arranged square cavity for beam installation, the lower part of the inner cavity of the T-shaped high-strength anti-corrosion steel pipe is a vertically arranged square cavity for column installation, the top of the square cavity for column installation is connected with the middle part of the square cavity for beam installation, a square prefabricated beam is inserted and matched inside the square cavity for beam installation, and a square prefabricated beam is inserted and matched inside the square cavity for column installation It is equipped with a square prefabricated column, the top of the square prefabricated column abuts against the bottom of the square prefabricated beam, and the horizontal pipe sections of the T-shaped high-strength anti-corrosion steel pipe on both sides above the square prefabricated column are symmetrically installed with a beam connection assembly, and a column connection assembly is installed on the upper part of the square prefabricated column. The tops of the two beam connection assemblies are reinforced and fixed by upper protection reinforcement units at corresponding positions, and the bottoms of the two beam connection assemblies and both sides of the column connection assembly are reinforced and fixed by lateral protection reinforcement units.
[0006] In any of the above schemes, it is preferred that the beam body connection assembly includes a vertical connecting stud arranged vertically through the square prefabricated beam, both ends of the vertical connecting stud pass through the top and bottom of the horizontal pipe section of the T-shaped high-strength anti-corrosion steel pipe, and a beam body locking nut is screwed on the end external threaded section of the vertical connecting stud respectively, and the two beam body locking nuts cooperate to clamp the horizontal pipe section of the T-shaped high-strength anti-corrosion steel pipe.
[0007] In any of the above schemes, it is preferred that the column connection assembly includes a horizontal connecting stud that horizontally passes through the square prefabricated column, and both ends of the horizontal connecting stud pass through the left and right sides of the vertical pipe section of the T-shaped high-strength anti-corrosion steel pipe, and a column locking nut is screwed on the end external threaded section of the horizontal connecting stud respectively, and the two column locking nuts cooperate to clamp the vertical pipe section of the T-shaped high-strength anti-corrosion steel pipe.
[0008] In any of the above schemes, it is preferred that the upper protection reinforcement unit includes upper end angle steel plates integrally formed at the top of both ends of the horizontal pipe section of the T-shaped high-strength anti-corrosion steel pipe, and the front and rear sides of the two upper end angle steel plates are respectively fixedly welded with an upper baffle plate, and the two upper baffle plates and the two upper end angle steel plates form an upper perfusion cavity at the top of the horizontal pipe section of the T-shaped high-strength anti-corrosion steel pipe, and the upper perfusion cavity is perfused with high-temperature molten iron, and after the high-temperature molten iron is cooled and solidified, an upper perfusion reinforcement layer is formed for reinforcing the locking nuts of each beam body inside it.
[0009] In any of the above schemes, preferably, an upper cover plate is fixedly mounted on the top of the upper filling chamber, and a first filling port is provided in the middle of the upper cover plate.
[0010] In any of the above schemes, it is preferred that the lateral protection reinforcement unit includes lower end angle steel plates integrally formed at the bottom of both ends of the horizontal pipe section of the T-shaped high-strength anti-corrosion steel pipe, and also includes bottom angle steel plates integrally formed on both sides of the lower end of the vertical pipe section of the T-shaped high-strength anti-corrosion steel pipe, and lower baffles are fixedly welded on the front and rear sides of the lower end angle steel plates and the bottom angle steel plates located on the same side, respectively, the two lower baffles and the lower end angle steel plates and the bottom angle steel plates on the corresponding sides surround the corresponding outer side walls of the T-shaped high-strength anti-corrosion steel pipe into lateral perfusion cavities, and a bottom angle steel cover plate for sealing the opening of the two lateral perfusion cavities is fixedly installed on the outside of each of the lateral perfusion cavities, and a second perfusion port is provided on the upper part of the bottom angle steel cover plate, and high-temperature molten iron is perfused into each of the lateral perfusion cavities, and after the high-temperature molten iron is cooled and solidified, a lateral perfusion reinforcement layer is formed for reinforcing the locking nuts of each of the beam bodies inside it.
[0011] In any of the above solutions, preferably, first cover plate reinforcement members are symmetrically installed on the square prefabricated beams above both sides of the square prefabricated columns.
[0012] In any of the above schemes, it is preferred that the first cover plate reinforcement member includes a vertical reinforcement stud vertically inserted inside the square prefabricated beam, the upper and lower ends of the vertical reinforcement stud both pass through the horizontal section of the upper end angle steel plate and the horizontal section of the lower end angle steel plate at corresponding positions, and a first reinforcement nut is screwed on the external threaded section at both ends of the vertical reinforcement stud respectively, and each of the first reinforcement nuts is fixed to the vertical reinforcement stud by spot welding.
[0013] In any of the above solutions, preferably, a second cover plate reinforcement is installed on the upper part of the square prefabricated column.
[0014] In any of the above schemes, preferably, the second cover plate reinforcement member includes a horizontal reinforcement stud horizontally inserted inside the square prefabricated column, the left and right ends of the horizontal reinforcement stud both pass through the vertical section of the bottom angle steel plate and the horizontal section of the lower end angle steel plate at the corresponding position, and a second reinforcement nut is screwed on the external threaded section at both ends of the horizontal reinforcement stud respectively, and each of the second reinforcement nuts is fixed to the horizontal reinforcement stud by spot welding.
[0015] Compared with the prior art, the beneficial effects of the utility model are as follows:
[0016] 1. The connecting member in the utility model can realize the connection of the ends of the square prefabricated beams and square prefabricated columns. The entire connecting member can ensure the connection strength of the connecting parts and can be suitable for beam-column connection conditions with large loads.
[0017] 2. This prefabricated beam-column connection component relies on the T-shaped high-strength anti-corrosion steel pipe as a limiter to the external contour when connecting beams and columns to ensure that the connection is positioned in place. At the same time, the T-shaped high-strength anti-corrosion steel pipe is fixed to the square prefabricated beam by relying on the beam connection components, and the T-shaped high-strength anti-corrosion steel pipe is fixed to the square prefabricated column by relying on the column connection components. The overall connection has good stability and high reliability.
[0018] 3. Taking into account the end stability and anti-corrosion effect of the beam connection assembly and the column connection assembly which are the main connecting parts, the utility model designs an upper pouring reinforcement layer and lateral pouring reinforcement layers on both sides to complete the pouring reinforcement of the ends of the connecting parts, effectively achieving anti-slippage and at the same time achieving the purpose of anti-corrosion protection. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] In order to more clearly illustrate the technical solution of the specific implementation of the utility model, the following will briefly introduce the drawings required for the specific implementation. In all the drawings, similar elements or components are generally identified by similar reference numerals. In the drawings, each element or component is not necessarily drawn according to the actual scale.
[0020] Figure 1 It is a cross-sectional structural schematic diagram of the utility model in the installed state.
[0021] Figure 2 It is a schematic diagram of the cross-sectional structure of the utility model in a state where molten iron is not poured.
[0022] Figure 3 It is a schematic cross-sectional structure diagram of the T-shaped high-strength anti-corrosion steel pipe and the fixing components thereon in the utility model.
[0023] In the figure, 1. T-shaped high-strength anti-corrosion steel pipe; 101. horizontal pipe section; 102. vertical pipe section; 2. square cavity for beam installation; 3. square cavity for column installation; 4. square prefabricated beam; 5. square prefabricated column; 6. vertical connection stud; 7. beam locking nut; 8. horizontal connection stud; 9. column locking nut; 10. upper end angle steel plate; 11. upper baffle; 12. upper pouring cavity; 13. upper pouring reinforcement layer; 14. upper cover; 15. first pouring port; 16. lower end angle steel plate; 17. bottom angle steel plate; 18. lower baffle; 19. lateral pouring cavity; 20. bottom angle steel cover; 21. second pouring port; 22. lateral pouring reinforcement layer; 23. vertical reinforcement stud; 24. first reinforcement nut; 25. horizontal reinforcement stud; 26. second reinforcement nut. DETAILED DESCRIPTION
[0024] The following is a detailed description of the embodiments of the technical solution of the utility model in conjunction with the accompanying drawings. The following embodiments are only used to more clearly illustrate the technical solution of the utility model, and are therefore only used as examples, and cannot be used to limit the scope of protection of the utility model. Figure 1-Figure 3 as shown in .
[0025] Embodiment: A prefabricated beam-column connection component comprises a T-shaped high-strength anti-corrosion steel pipe 1, wherein the upper part of the inner cavity of the T-shaped high-strength anti-corrosion steel pipe 1 is a horizontally arranged square cavity 2 for mounting a beam body, and the lower part of the inner cavity of the T-shaped high-strength anti-corrosion steel pipe 1 is a vertically arranged square cavity 3 for mounting a column body, wherein the top of the square cavity 3 for mounting a column body is connected with the middle part of the square cavity 2 for mounting a beam body, a square prefabricated beam 4 is inserted and matched inside the square cavity 2 for mounting a beam body, and a square prefabricated column 5 is inserted and matched inside the square cavity 3 for mounting a column body, The top of the square prefabricated column 5 abuts against the bottom of the square prefabricated beam 4, and the horizontal pipe sections 101 of the T-shaped high-strength anti-corrosion steel pipe 1 on both sides above the square prefabricated column 5 are symmetrically installed with a beam connection assembly, and a column connection assembly is installed on the upper part of the square prefabricated column 5. The tops of the two beam connection assemblies are respectively reinforced and fixed by upper protective reinforcement units at corresponding positions, and the bottoms of the two beam connection assemblies and both sides of the column connection assembly are reinforced and fixed by lateral protective reinforcement units. The prefabricated beam-column connection component in this design relies on the T-shaped high-strength anti-corrosion steel pipe 1 as a whole to achieve the limitation of the shape, ensuring that the prefabricated beam-column parts can be installed in place through the preset beam installation square cavity 2 and column installation square cavity 3 during installation, ensuring the limitation of the periphery of the beam and column, and the installation positioning can be achieved through the limitation, ensuring the convenience of installation and reducing the difficulty of installation positioning.
[0026] In any of the above schemes, it is preferred that the beam body connection assembly includes a vertical connecting stud 6 arranged vertically through the square prefabricated beam 4, both ends of the vertical connecting stud 6 pass through the top and bottom of the horizontal pipe section 101 of the T-shaped high-strength anti-corrosion steel pipe 1, and a beam body locking nut 7 is screwed on the end external threaded section of the vertical connecting stud 6 respectively, and the two beam body locking nuts 7 cooperate to clamp the horizontal pipe section 101 of the T-shaped high-strength anti-corrosion steel pipe 1.
[0027] The beam connection assembly adopts a double-headed stud structure, and relies on the beam locking nuts 7 at the corresponding ends to achieve the locking and positioning of the square prefabricated beam 4 and the T-shaped high-strength anti-corrosion steel pipe 1. When the two beam locking nuts 7 are tightened, the positioning effect is improved.
[0028] In any of the above schemes, it is preferred that the column connection assembly includes a horizontal connecting stud 8 that is horizontally passed through the square prefabricated column 5, and both ends of the horizontal connecting stud 8 pass through the left and right sides of the vertical pipe section 102 of the T-shaped high-strength anti-corrosion steel pipe 1, and a column locking nut 9 is screwed on the end external threaded section of the horizontal connecting stud 8 respectively, and the two column locking nuts 9 cooperate to achieve clamping of the vertical pipe section 102 of the T-shaped high-strength anti-corrosion steel pipe 1.
[0029] The column connection assembly adopts a double-headed stud structure, and the column locking nuts 9 at the corresponding ends can realize the locking and positioning of the square prefabricated column 5 and the T-shaped high-strength anti-corrosion steel pipe 1. When the two column locking nuts 9 are tightened, the positioning effect is improved.
[0030] In any of the above schemes, it is preferred that the upper protection reinforcement unit includes an upper end angle steel plate 10 integrally formed at the top of both ends of the horizontal pipe section 101 of the T-shaped high-strength anti-corrosion steel pipe 1, and the front and rear sides of the two upper end angle steel plates 10 are respectively fixedly welded with an upper baffle plate 11, and the two upper baffle plates 11 and the two upper end angle steel plates 10 form an upper perfusion cavity 12 at the top of the horizontal pipe section 101 of the T-shaped high-strength anti-corrosion steel pipe 1, and the upper perfusion cavity 12 is perfused with high-temperature molten iron. After the high-temperature molten iron is cooled and solidified, an upper perfusion reinforcement layer 13 is formed for reinforcing the locking nuts 7 of each beam body inside it.
[0031] The upper protective reinforcement unit mainly relies on filling the upper perfusion cavity 12 with high-temperature molten iron and allowing the molten iron to overflow the beam locking nut 7 after the perfusion, thereby ensuring the reinforcement of the connection part of the beam locking nut 7, thereby relying on the upper perfusion reinforcement layer 13 to achieve reinforcement of the connection part.
[0032] In any of the above solutions, preferably, an upper cover plate 14 is fixedly mounted on the top of the upper filling chamber 12 , and a first filling port 15 is provided in the middle of the upper cover plate 14 .
[0033] The first pouring port 15 can ensure that the pouring is completed quickly in coordination with the external molten iron pouring equipment.
[0034] In any of the above schemes, it is preferred that the lateral protection reinforcement unit includes a lower end angle steel plate 16 integrally formed at the bottom of both ends of the horizontal pipe section 101 of the T-shaped high-strength anti-corrosion steel pipe 1, and also includes a bottom angle steel plate 17 integrally formed on both sides of the lower end of the vertical pipe section 102 of the T-shaped high-strength anti-corrosion steel pipe 1, and the front and rear sides of the lower end angle steel plate 16 and the bottom angle steel plate 17 on the same side are respectively fixedly welded with a lower baffle plate 18, and the two lower baffle plates 18 and the lower baffle plates on the corresponding sides are fixedly welded. The end angle steel plate 16 and the bottom angle steel plate 17 enclose the corresponding outer side wall of the T-shaped high-strength anti-corrosion steel pipe 1 to form a lateral perfusion cavity 19. A bottom angle steel cover plate 20 for sealing its opening is fixedly installed on the outside of the two lateral perfusion cavities 19 respectively. A second perfusion port 21 is provided on the upper part of the bottom angle steel cover plate 20. High-temperature molten iron is perfused in each of the lateral perfusion cavities 19. After the high-temperature molten iron is cooled and solidified, a lateral perfusion reinforcement layer 22 is formed for reinforcing the locking nuts 7 of the beam body inside it.
[0035] The lateral protection reinforcement unit mainly relies on filling the lateral perfusion cavity 19 with high-temperature molten iron and allowing the molten iron to overflow the beam locking nut 7 and the column locking nut 9 after the perfusion, thereby ensuring the reinforcement of the connection parts of the beam locking nut 7 and the column locking nut 9, thereby relying on the lateral perfusion reinforcement layer 22 to achieve reinforcement of the connection parts.
[0036] In any of the above solutions, preferably, first cover plate reinforcement members are symmetrically installed on the square prefabricated beams 4 above both sides of the square prefabricated columns 5 .
[0037] In any of the above schemes, it is preferred that the first cover plate reinforcement member includes a vertical reinforcement stud 23 vertically inserted into the square prefabricated beam 4, and the upper and lower ends of the vertical reinforcement stud 23 pass through the horizontal section of the upper end angle steel plate 10 and the horizontal section of the lower end angle steel plate 16 at the corresponding positions, and the external thread sections at both ends of the vertical reinforcement stud 23 are respectively screwed with a first reinforcement nut 24, and each of the first reinforcement nuts 24 is fixed to the vertical reinforcement stud 23 by spot welding.
[0038] The first cover plate reinforcement member relies on the vertical reinforcement studs 23 and each first reinforcement nut 24 to achieve locking and reinforcement of the upper cover plate 14 .
[0039] In any of the above solutions, preferably, a second cover plate reinforcement is installed on the upper part of the square prefabricated column 5.
[0040] In any of the above schemes, it is preferred that the second cover plate reinforcement member includes a horizontal reinforcement stud 25 horizontally inserted inside the square prefabricated column 5, and the left and right ends of the horizontal reinforcement stud 25 both pass through the vertical section of the bottom angle steel plate 17 and the horizontal section of the lower end angle steel plate 16 at the corresponding position, and a second reinforcement nut 26 is screwed on the external threaded section at both ends of the horizontal reinforcement stud 25, and each of the second reinforcement nuts 26 is fixed to the horizontal reinforcement stud 25 by spot welding.
[0041] The second cover plate reinforcement member relies on the horizontal reinforcement studs 25 and each second reinforcement nut 26 to achieve locking and reinforcement of the bottom angle steel cover plate 20.
[0042] Specific working principle: The entire prefabricated beam-column connection component relies on the T-shaped high-strength anti-corrosion steel pipe 1 to achieve the limitation of the shape, ensuring that the prefabricated beam-column parts can be installed in place through the preset beam installation square cavity 2 and column installation square cavity 3 during installation, ensuring the limitation of the periphery of the beam and column, and the installation positioning can be achieved through the limitation, ensuring the convenience of installation and reducing the difficulty of installation positioning.
[0043] In addition, after the preliminary adjustment of the beams and columns into place, the square prefabricated beams 4 are fixedly positioned by installing the beam connection components, and then the square prefabricated columns 5 are fixedly positioned by installing the column connection components. When the beam connection components and the column connection components are installed, the upper cover plate 14 and the bottom angle steel cover plate 20 are installed on the ends of the upper protective reinforcement unit and the lateral protective reinforcement units on both sides. After the installation is completed, molten iron is poured into the corresponding upper pouring cavity 12 and the lateral pouring cavity 19 through the corresponding molten iron pouring equipment to form a reinforcement layer to ensure the reinforcement position of the connection parts and improve the connection effect of the connection parts.
[0044] In summary, it can be seen that in the utility model, the connecting component can realize the connection of the ends of the square prefabricated beam 4 and the square prefabricated column 5. The entire connecting component can ensure the connection strength of the connection part and can be suitable for large-load beam-column connection conditions; the prefabricated beam-column connecting component relies on the T-shaped high-strength anti-corrosion steel pipe 1 as a limit fixation of the external contour when connecting the beam and the column to ensure that the connection is positioned in place, and at the same time relies on each beam connection component to fix the T-shaped high-strength anti-corrosion steel pipe 1 and the square prefabricated beam 4, and relies on the column connection component to fix the T-shaped high-strength anti-corrosion steel pipe 1 and the square prefabricated column 5, and the overall connection has good stability and high reliability; as the end stability and anti-corrosion effect of the beam connection component and the column connection component of the main connecting parts, the utility model designs the upper injection reinforcement layer 13 and the lateral injection reinforcement layer 22 on both sides to complete the injection reinforcement of the end of the connecting part, which effectively realizes anti-slippage and at the same time serves the purpose of anti-corrosion protection.
[0045] The above embodiments are only used to illustrate the technical solution of the utility model, rather than to limit it. Although the utility model is described in detail with reference to the above embodiments, ordinary technicians in this field should understand that they can still modify the technical solutions recorded in the above embodiments, or replace some or all of the technical features therein with equivalents. These modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the utility model. For technicians in this technical field, any replacement improvements or changes made to the implementation methods of the utility model fall within the protection scope of the utility model.
[0046] The matters not described in detail in the present invention are all known technologies to those skilled in the art.
Claims
1. A prefabricated beam-column connection component, characterized in that: The invention comprises a T-shaped high-strength anti-corrosion steel pipe, wherein the upper part of the inner cavity of the T-shaped high-strength anti-corrosion steel pipe is a horizontally arranged square cavity for mounting a beam body, and the lower part of the inner cavity of the T-shaped high-strength anti-corrosion steel pipe is a vertically arranged square cavity for mounting a column body, the top of the square cavity for mounting a column body is connected with the middle part of the square cavity for mounting a beam body, a square prefabricated beam is inserted and matched inside the square cavity for mounting a beam body, a square prefabricated column is inserted and matched inside the square cavity for mounting a column, the top of the square prefabricated column abuts against the bottom of the square prefabricated beam, and a beam connecting assembly is symmetrically installed on the horizontal pipe sections of the T-shaped high-strength anti-corrosion steel pipe on both sides above the square prefabricated column, and a column connecting assembly is cooperated and installed on the upper part of the square prefabricated column, the tops of the two beam connecting assemblies are respectively reinforced and fixed by upper protection reinforcement units at corresponding positions, and the bottoms of the two beam connecting assemblies and both sides of the column connecting assembly are reinforced and fixed by lateral protection reinforcement units.
2. The prefabricated beam-column connecting member according to claim 1, characterized in that: The beam body connection assembly includes a vertical connection stud that vertically passes through the square prefabricated beam, and both ends of the vertical connection stud pass through the top and bottom of the horizontal pipe section of the T-shaped high-strength anti-corrosion steel pipe. A beam body locking nut is screwed on the external threaded section at the end of the vertical connection stud, and the two beam body locking nuts cooperate to clamp the horizontal pipe section of the T-shaped high-strength anti-corrosion steel pipe.
3. The prefabricated beam-column connecting member according to claim 2, characterized in that: The column connection assembly includes a horizontal connecting stud that horizontally passes through the square prefabricated column. Both ends of the horizontal connecting stud pass through the left and right sides of the vertical pipe section of the T-shaped high-strength anti-corrosion steel pipe. A column locking nut is screwed on the end external threaded section of the horizontal connecting stud. The two column locking nuts cooperate to clamp the vertical pipe section of the T-shaped high-strength anti-corrosion steel pipe.
4. The prefabricated beam-column connecting member according to claim 3, characterized in that: The upper protection reinforcement unit includes upper end angle steel plates integrally formed at the top of both ends of the horizontal pipe section of the T-shaped high-strength anti-corrosion steel pipe, and the front and rear sides of the two upper end angle steel plates are respectively fixedly welded with an upper baffle plate. The two upper baffle plates and the two upper end angle steel plates form an upper perfusion cavity at the top of the horizontal pipe section of the T-shaped high-strength anti-corrosion steel pipe, and the upper perfusion cavity is perfused with high-temperature molten iron. After the high-temperature molten iron is cooled and solidified, an upper perfusion reinforcement layer is formed for reinforcing the locking nuts of each beam body inside it.
5. The prefabricated beam-column connecting member according to claim 4, characterized in that: An upper cover plate is fixedly installed on the top of the upper filling chamber, and a first filling port is arranged in the middle of the upper cover plate.
6. The prefabricated beam-column connecting member according to claim 5, characterized in that: The lateral protection reinforcement unit includes lower end angle steel plates integrally formed at the bottom of both ends of the horizontal pipe section of the T-shaped high-strength anti-corrosion steel pipe, and also includes bottom angle steel plates integrally formed on both sides of the lower end of the vertical pipe section of the T-shaped high-strength anti-corrosion steel pipe. Lower baffles are fixedly welded on the front and rear sides of the lower end angle steel plates and the bottom angle steel plates on the same side, respectively. The two lower baffles and the lower end angle steel plates and the bottom angle steel plates on the corresponding sides surround the corresponding outer side walls of the T-shaped high-strength anti-corrosion steel pipe into lateral perfusion cavities, and a bottom angle steel cover plate for sealing the opening of the two lateral perfusion cavities is fixedly installed on the outside of each of the lateral perfusion cavities, and a second perfusion port is provided on the upper part of the bottom angle steel cover plate. High-temperature molten iron is perfused into the interior of each of the lateral perfusion cavities. After the high-temperature molten iron is cooled and solidified, a lateral perfusion reinforcement layer is formed for reinforcing the locking nuts of each of the beam bodies inside it.
7. The prefabricated beam-column connecting member according to claim 6, characterized in that: First cover plate reinforcement members are symmetrically installed on the square prefabricated beams above both sides of the square prefabricated columns.
8. The prefabricated beam-column connecting member according to claim 7, characterized in that: The first cover plate reinforcement member includes a vertical reinforcement stud vertically inserted into the square prefabricated beam, the upper and lower ends of the vertical reinforcement stud both pass through the horizontal section of the upper end angle steel plate and the horizontal section of the lower end angle steel plate at the corresponding positions, and a first reinforcement nut is screwed on the external threaded section at both ends of the vertical reinforcement stud respectively, and each of the first reinforcement nuts is fixed to the vertical reinforcement stud by spot welding.
9. The prefabricated beam-column connecting member according to claim 8, characterized in that: A second cover plate reinforcement is installed on the upper part of the square prefabricated column.
10. The prefabricated beam-column connecting member according to claim 9, characterized in that: The second cover plate reinforcement member includes a horizontal reinforcement stud horizontally inserted inside the square prefabricated column, and the left and right ends of the horizontal reinforcement stud both pass through the vertical section of the bottom angle steel plate and the horizontal section of the lower end angle steel plate at the corresponding positions. A second reinforcement nut is screwed on the external threaded sections at both ends of the horizontal reinforcement stud respectively, and each of the second reinforcement nuts is fixed to the horizontal reinforcement stud by spot welding.