Connecting structure of wet joint at bottom of large prefabricated part

By arranging tenon structures and reserved ribs at the bottom of large prefabricated components, combined with wet joints and elevation adjustment gaskets, the problem of insufficient connection performance and seismic fortification capabilities of prefabricated assembly construction in the field of water engineering is solved, and a higher level of Structural safety and construction efficiency.

CN221919844UActive Publication Date: 2024-10-29SHANGHAI URBAN CONSTRUCTION MUNICIPAL ENGINEERING (GROUP) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323530998.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-25
Publication Date
2024-10-29
Estimated Expiration
2033-12-25

AI Technical Summary

Technical Problem

Prefabricated assembly construction is not widely used in the field of water engineering. There are problems such as low connection performance of prefabricated components, poor seismic fortification ability, poor waterproofing effect, and inability to serve as a load-bearing structure.

Method used

A tenon structure is set at the bottom of a large prefabricated component, and the wet joint is connected and fixed to the cast-in-place base plate. The reserved ribs are wrapped in the wet joint, and matching sockets are formed on both sides, combined with elevation adjustment gaskets. , achieving precise lifting and fixing of prefabricated components and cast-in-place base plates.

Benefits of technology

It improves the safety and construction accuracy of prefabricated components, shortens construction time, reduces installation costs, and improves the mechanical properties and durability of the overall structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221919844U_ABST
    Figure CN221919844U_ABST
Patent Text Reader

Abstract

The utility model relates to the field of prefabrication assembly, in particular to a connecting structure of wet joints at the bottom of a large prefabricated part, the bottom of a prefabricated partition wall is arranged to be of a tenon structure, reserved ribs are arranged at the bottom of the prefabricated partition wall and the top of a cast-in-place bottom plate, the wet joints are formed by pouring on the two sides of the tenon structure, and the reserved ribs are wrapped in the wet joints; a socket groove matched with the tenon structure is formed between the wet joints on the two sides, and the tenon structure is integrally inserted into the socket groove. The wet joint has the advantages that (1) the wet joint has better mechanical property and higher durability, and the connection integrity of the wet joint is better; (2) the reserved steel bars are accurately arranged, and staggered connection is adopted, so that a large amount of welding operation is omitted, and meanwhile, the integrity and the safety of the UHPC wet joint are improved; (3) an elevation adjusting steel gasket can be used for quickly and effectively adjusting the elevation and the flatness of the prefabricated part; the structure is simple and reasonable, construction is convenient, and popularization is facilitated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of prefabrication and assembly, in particular to a connection structure of a wet joint at the bottom of a large prefabricated component. Background Art

[0002] With the acceleration of my country's urbanization process, the existing single cast-in-place structure construction technology can no longer meet the main construction needs. Prefabrication construction can effectively save manpower and financial resources. Compared with cast-in-place construction, prefabrication construction can not only improve construction quality and safety, but also help reduce carbon emissions. At present, prefabrication technology has not been widely promoted in the field of water engineering.

[0003] The connection quality between prefabricated components and cast-in-place structures is the main factor affecting the overall structural performance. Ultra-high performance concrete (UHPC) is widely used in wet connections of prefabricated components. It has many advantages: high compressive strength, about three times that of traditional concrete; the addition of fibers gives ultra-high performance concrete excellent toughness and tensile properties, making the concrete structure have better structural reliability under overload conditions or earthquakes. Although ultra-high performance concrete (UHPC) has not been vigorously promoted in my country at present, it has a good development trend due to its ultra-high mechanical properties and ultra-high durability.

[0004] At present, prefabricated assembly construction is not widely used in the field of water engineering. At the same time, there are technical problems such as low overall performance of prefabricated components after connection, not conducive to seismic fortification, poor waterproofing effect of connection nodes, and inability to serve as load-bearing structures. Summary of the invention

[0005] The purpose of the utility model is to provide a connection structure of the wet joint at the bottom of a large prefabricated component in accordance with the above-mentioned deficiencies of the prior art, which improves the safety and accuracy of the lifting of the prefabricated component by reserving a mortise and tenon structure on the large prefabricated component and connecting and fixing it to the cast-in-place base plate through the wet joint, thereby indirectly shortening the construction time and reducing the installation cost of the prefabricated component.

[0006] The purpose of this utility model is achieved by the following technical solutions:

[0007] A connection structure for a wet joint at the bottom of a large prefabricated component, used for connecting a prefabricated partition wall and a cast-in-place base plate, characterized in that: the bottom of the prefabricated partition wall is arranged as a mortise and tenon structure, the bottom of the prefabricated partition wall and the top of the cast-in-place base plate are both provided with reserved reinforcement, wet joints are formed on both sides of the mortise and tenon structure by casting, and the reserved reinforcement is covered in the wet joint; a socket matching the mortise and tenon structure is formed between the wet joints on both sides, and the mortise and tenon structure is integrally inserted into the socket.

[0008] The reserved reinforcement at the bottom of the prefabricated partition wall and the reserved reinforcement at the top of the cast-in-place bottom plate are staggered, and a certain distance is spaced between the reserved reinforcements of the two.

[0009] A height adjustment gasket is arranged between the bottom surface of the tenon structure and the top surface of the cast-in-place base plate.

[0010] The step surface formed between the tenon structure and the prefabricated partition wall is an inclined surface.

[0011] The wet joint is a UHPC wet joint.

[0012] The advantages of the utility model are:

[0013] (1) It has better mechanical properties and higher durability, and the integrity of the wet joint connection is better;

[0014] (2) The reserved steel bars are precisely arranged and staggered, which saves a lot of welding work and improves the integrity and safety of the ultra-high performance concrete (UHPC) wet joints.

[0015] (3) The elevation adjustment steel gasket can quickly and effectively adjust the elevation and flatness of prefabricated components;

[0016] (4) The structure is simple and reasonable, the construction is convenient, and it is suitable for promotion. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a structural schematic diagram of the utility model;

[0018] Figure 2 It is a schematic diagram of the arrangement of the reserved ribs in the utility model. DETAILED DESCRIPTION

[0019] The following is a further detailed description of the features of the present invention and other related features through embodiments in conjunction with the accompanying drawings to facilitate understanding by technicians in the same industry:

[0020] like Figure 1-2 As shown, the marks 1-9 in the figure respectively represent: tenon structure 1, reserved reinforcement 2, UHPC wet joint 3, elevation adjustment steel gasket 4, prefabricated partition wall 5, cast-in-place bottom plate 6, prefabricated partition wall reserved reinforcement 7, cast-in-place bottom plate reserved reinforcement 8, step slope 9.

[0021] Example: Combination Figure 1 and Figure 2 As shown, the connection structure of the wet joint at the bottom of the large prefabricated component in this embodiment is used for the connection between the prefabricated partition wall 5 and the cast-in-place bottom plate 6, wherein the prefabricated partition wall 5 is a prefabricated component and the cast-in-place bottom plate 6 is a cast-in-place component. However, in some cases, even if the bottom plate is a prefabricated component, the connection structure in this embodiment can also be used to achieve the connection between the prefabricated partition wall and the prefabricated bottom plate.

[0022] Specifically, when the prefabricated partition wall 5 in this embodiment is prefabricated, on the premise that the overall height meets the design requirements, its bottom is prefabricated into a tenon structure 1, and symmetrical step slopes 9 are formed between the two sides of the tenon structure 1 and the main part of the prefabricated partition wall 5.

[0023] Reserved reinforcement 2 is provided at the bottom of the prefabricated partition wall 5 and the top of the cast-in-place bottom plate 6. Figure 2 As shown, it specifically includes a precast partition wall reserved reinforcement 7 and a cast-in-place bottom plate reserved reinforcement 8, and the two reserved reinforcements extend out of the corresponding component surface and extend vertically for a certain distance. That is, the precast partition wall reserved reinforcement 7 is arranged at the position of the step slope 9 of the precast partition wall 5 and extends vertically downward for a distance, and the distance refers to being close to or in contact with the surface of the cast-in-place bottom plate 6; similarly, the cast-in-place bottom plate reserved reinforcement 8 is arranged at the position corresponding to the step slope 9 of the precast partition wall 5 and extends vertically upward for a distance to be close to or in contact with the step slope 9.

[0024] In this embodiment, if Figure 2 As shown, a plurality of prefabricated partition wall reserved ribs 7 and a plurality of cast-in-place bottom slab reserved ribs 8 are arranged in an array along the extension direction of the prefabricated partition wall 5, and are arranged at equal intervals and staggered in the same plane, that is, a certain spacing distance is reserved between the prefabricated partition wall reserved ribs 7 and the cast-in-place bottom slab reserved ribs 8. Figure 2 The reserved reinforcement bars 7 of the prefabricated partition walls on the left are for illustration, and the remaining positions on the same side are reserved reinforcement bars 8 of the cast-in-place floor slab, thereby forming a staggered arrangement. In this way, the integrity and safety of the UHPC wet joint 3 are improved while omitting a large number of welding operations.

[0025] like Figure 1 As shown, a UHPC wet joint 3 is formed by pouring UHPC below the step slope 9 of the prefabricated partition wall 5, a socket slot fitted to the tenon structure 1 is formed between the UHPC wet joints 3 on both sides, and the outer side surfaces of the UHPC wet joints 3 on both sides are located outside the outer side surfaces of the prefabricated partition wall 5.

[0026] At this time, the mortise and tenon structure 1 is inserted into the socket formed between the UHPC wet joints 3 on both sides in a socket-and-spigot manner, so as to achieve the effect of limiting and fixing the prefabricated partition wall 5; and the step slope 9 of the prefabricated partition wall 5 is directly supported on the surface of the UHPC wet joint 3, so that the prefabricated partition wall 5 can be stably supported by the UHPC wet joint 3. At the same time, the UHPC wet joint 3 covers the prefabricated partition wall reserved ribs 7 and the cast-in-place bottom plate reserved ribs 8, so that the prefabricated partition wall 5 is connected to the cast-in-place bottom plate 6 through the UHPC wet joint 3 to form an integral structure, ensuring integrity and safety.

[0027] like Figure 1As shown, a plurality of height adjustment steel washers 4 are arranged between the bottom surface of the tenon structure 1 and the surface of the cast-in-place bottom plate 6, and the height adjustment steel washers 4 are used to adjust the height and flatness of the prefabricated partition wall 5 when it is installed, thereby improving the installation accuracy of the prefabricated partition wall 5. In some cases, some holes can be reserved on the bottom surface of the tenon structure 1, and then plug-ins are installed on the height adjustment steel washers 4, and the plug-ins are inserted into the reserved holes, so that the tenon structure 1 and the height adjustment steel washers 4 also form an integral structure to ensure integrity.

[0028] When used, this embodiment includes the following construction steps:

[0029] (1) Before the prefabricated partition wall 5 is hoisted, the cast-in-place base plate 6 is roughened and cleaned.

[0030] (2) Carry out measurement and layout, and control the elevation and flatness of the prefabricated partition wall 5 by adjusting the elevation adjustment steel gasket 4.

[0031] (3) When hoisting components, the reserved reinforcement 2 of the prefabricated components and the cast-in-place base plate are staggered, and the spacing between the reinforcements of the two is 150 mm.

[0032] (4) Install the casting formwork that matches the UHPC wet joint 3. The specific requirements are: the elevation and position design of the formwork meet the requirements, and the formwork positioning reinforcement is accurate; the outer support and fixation of the formwork should be firm; the tightness of the formwork meets the requirements, and if leakage occurs, it should be sealed in time.

[0033] (5) Mixing and pouring UHPC wet joint 3: UHPC integrated mixing and pumping equipment can be used. This equipment is a multifunctional integrated equipment with a small size and continuous working ability. The equipment uses hydraulic power for traveling, mixing, conveying and lifting. When pouring UHPC wet joint 3, the integrity is better and the quality is higher.

[0034] (6) After pouring the UHPC wet joint 3, it is immediately covered with a film for curing and continuously watered for 24 hours. After 24 hours, the strength of the UHPC is measured using an ultra-high performance concrete (UHPC) rebound hammer. The formwork is removed when it meets the design requirements.

[0035] (7) The UHPC wet joint 3 was subsequently maintained for 14 days.

[0036] In the specific implementation of this embodiment: when the cast-in-place base plate 6 is also prefabricated, it is necessary to embed reserved reinforcement during prefabrication, and the position of the reserved reinforcement should be strictly positioned.

[0037] Although the above embodiments have described the concepts and embodiments of the purpose of the utility model in detail with reference to the accompanying drawings, ordinary technicians in this field can recognize that various improvements and modifications can still be made to the utility model without departing from the scope of the claims, so they are not described one by one here.

Claims

1. A connection structure of a wet joint at the bottom of a large prefabricated component, used for connecting a prefabricated partition wall with a cast-in-place bottom plate, characterized in that: The bottom of the prefabricated partition wall is arranged as a mortise and tenon structure, and the bottom of the prefabricated partition wall and the top of the cast-in-place base plate are both provided with reserved ribs, and wet joints are formed on both sides of the mortise and tenon structure by casting, and the reserved ribs are covered in the wet joints; a socket slot matching the mortise and tenon structure is formed between the wet joints on both sides, and the mortise and tenon structure is integrally inserted into the socket slot.

2. The connection structure of the bottom wet joint of a large prefabricated component according to claim 1, characterized in that: The reserved reinforcement at the bottom of the prefabricated partition wall and the reserved reinforcement at the top of the cast-in-place bottom plate are staggered, and a certain distance is spaced between the reserved reinforcements of the two.

3. The connection structure of the bottom wet joint of a large prefabricated component according to claim 1, characterized in that: A height adjustment gasket is arranged between the bottom surface of the tenon structure and the top surface of the cast-in-place base plate.

4. The connection structure of the bottom wet joint of a large prefabricated component according to claim 1, characterized in that: The step surface formed between the tenon structure and the prefabricated partition wall is an inclined surface.

5. The connection structure of the bottom wet joint of a large prefabricated component according to claim 1, characterized in that: The wet joint is a UHPC wet joint.