Deep-buried water-rich soft zone surrounding rock forepoling structure
By adopting a double-layer diagonal advanced small conduit structure and grouting treatment in the surrounding rock strata of the deep water-rich weak zone, the problem of insufficient support effect of a single-layer advanced small conduit is solved, and a wider support scope and Higher support reliability ensures the safety and efficiency of tunnel construction.
Patent Information
- Application Number
- CN202420313911.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-20
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2034-02-20
AI Technical Summary
In the surrounding rock formations in deep water-rich weak zones, existing advanced support mostly uses single-layer advanced small conduits, resulting in a small support area and weak support effect, which affects the safety and efficiency of tunnel construction.
It adopts a double-layer diagonal advanced small duct structure. The first and second rows of advanced small ducts are obliquely intersecting. Seamless steel pipes are used. Grouting sections and grouting holes are reserved, cement-water glass slurry is injected, and the angles are crossed. Connect to expand the support range and enhance the support effect.
Through the double-layer oblique advanced small duct structure and grouting treatment, the reliability and support effect of the advanced support structure are improved, ensuring the stability of the surrounding rock and construction safety.
Smart Images

Figure CN221920964U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of tunnel engineering advance support, in particular to an advance support structure for surrounding rock in a deep-buried water-rich weak zone. Background Art
[0002] In the process of tunnel excavation in highway engineering in my country, the advanced small-duct support technology has been widely used in my country's tunnel engineering construction projects as an auxiliary construction method to strengthen soft strata, reduce stratum settlement, and protect tunnel support structures. Especially in deep buried water-rich soft rock formations, advanced support directly affects the safety and efficiency of tunnel construction and has a great impact on the quality of tunnel engineering.
[0003] At present, advance support mostly adopts single-layer advance small guide tube for support, and the angle of the guide tube entering the rock is roughly the same as the tunnel progress, which has problems such as small support area and weak support effect. Utility Model Content
[0004] Therefore, in order to solve the above-described problems and ensure that the advance support structure for water-rich soft surrounding rock has sufficient stability, the utility model specially provides a deep-buried water-rich soft zone surrounding rock advance support structure with a wide support area and safety and reliability.
[0005] The utility model is implemented in this way, constructing a deep-buried water-rich weak zone surrounding rock advance support structure, which is characterized by comprising a first row of advance small conduits and a second row of advance small conduits, and the first row of advance small conduits and the second row of advance small conduits are in an oblique shape.
[0006] Furthermore, the small advance guide tube is made of seamless steel pipe, the reserved grouting section is 50cm, the grouting holes are spaced 15cm apart, and are arranged in a plum blossom shape.
[0007] Furthermore, the first row of 35 advance small guide tubes are driven into the surrounding rock at an angle of 30° to the left along the center line of the tunnel, and the second row of 34 advance small guide tubes are driven into the surrounding rock at an angle of 30° to the right along the center line of the tunnel. The rock holes of the second row of advance small guide tubes are distributed in the interval areas of the first row of advance small guide tubes.
[0008] Furthermore, the small catheters are cross-connected at angles ranging from 20° to 45°.
[0009] The utility model has the following advantages: the application adopts a double-layer oblique advance small conduit and uses the advance small conduit for grouting, thereby expanding the advance support range and enhancing the support effect, thereby improving the reliability of the advance support structure. Therefore, the patent has the advantages of simple structure, stability and reliability. BRIEF DESCRIPTION OF THE DRAWINGS
[0010] Figure 1This is a schematic diagram of the existing advance support that mostly uses a single-layer advance small conduit for support;
[0011] Figure 2 yes Figure 1 Middle II section;
[0012] Figure 3 This is a schematic diagram of the double-layer oblique advance small guide tube advance support structure of the present application;
[0013] Figure 4 This is a diagram of the small catheter structure (with a cone head);
[0014] Figure 5 It is a cross-sectional view of the small duct;
[0015] Figure 6 Schematic diagram of the snap ring.
[0016] Among them: the first row of advance small ducts 1, the second row of advance small ducts 2, the clamping rings 3, the secondary lining 4, the steel frame 5, the sprayed concrete 6, the single-layer advance support (small ducts or anchor rods) 7, the reserved grouting section 8, the grouting holes 9, and the steel pipe 10. DETAILED DESCRIPTION
[0017] The following will be combined with the attached Figure 1-Figure 6 The utility model is described in detail, and the technical solutions in the embodiments of the utility model are clearly and completely described. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of them. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0018] The utility model provides an embodiment of a deep-buried water-rich weak zone surrounding rock advance support structure, comprising a first row of advance small pipes 1, a second row of advance small pipes 2, and grouting materials. The first row of advance small pipes 1 and the second row of advance small pipes 2 are obliquely crossed, and the grouting materials are injected into the advance support surrounding rock area through the advance small pipes.
[0019] When this application is implemented; the small advance conduits are seamless steel pipes, with a reserved grouting section of 50 cm, and grouting holes spaced 15 cm apart, arranged in a plum blossom shape. The first row of small advance conduits consists of 35 conduits, which are driven into the surrounding rock at an angle of 30° to the left along the center line of the tunnel; the second row of small advance conduits consists of 34 conduits, which are driven into the surrounding rock at an angle of 30° to the right along the center line of the tunnel. The rock holes of the second row of small advance conduits are distributed in the interval area of the first row of small advance conduits. After the construction is completed, the two layers of small advance conduits intersect at an angle of 60°.
[0020] When this application is implemented, after the first row of advance small ducts and the second row of advance small ducts are trial-made, pressure-controlled grouting materials are injected. The grouting material uses cement-water glass slurry, and its initial parameters are: cement slurry / water glass = 1:0.2 (volume ratio), water glass concentration = 35~40°Be, water glass modulus m = 2.6, sodium hydrogen phosphate content 2%, and the strength grade of grouting cement is 42.5.
[0021] In the present application, the small conduits are cross-connected at an angle between 20° and 45°; the small conduits are grouting-treated.
[0022] Figure 6 In the middle, the bottom plate of the clamp ring 3 is made of 8mm steel plate, and the outer wall of the small catheter is cut at the buckle (it can meet the inner circle of the small catheter).
[0023] The advantages and beneficial effects of the present application are: by adopting double-layer oblique advanced small pipes and using the advanced small pipes for grouting, the advanced support range is expanded, the support effect is enhanced, and the reliability of the advanced support structure is improved. Therefore, the present patent has the advantages of simple structure, stability and reliability.
[0024] The above description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A deep buried water-rich weak zone surrounding rock advance support structure, It is characterized by: It comprises a first row of advanced small pipes (1) and a second row of advanced small pipes (2), wherein the first row of advanced small pipes (1) and the second row of advanced small pipes (2) are in an oblique shape, and the grouting material is injected into the advanced support surrounding rock area through the advanced small pipes; The small advance guide tube is made of seamless steel pipe, with a reserved grouting section of 50 cm, and grouting holes spaced 15 cm apart, arranged in a plum blossom shape; The first row of small advance pipes (1) consists of 35 pipes, which are driven into the surrounding rock at an angle of 30° to the left along the tunnel centerline. The second row of small advance pipes (2) consists of 34 pipes, which are driven into the surrounding rock at an angle of 30° to the right along the tunnel centerline. The rock holes of the second row of small advance pipes are distributed in the interval area of the first row of small advance pipes. After the construction is completed, the two layers of small advance pipes intersect at an angle of 60°. The small catheters are inserted at cross angles ranging from 20° to 45°.