Flue gas dehumidification electric precipitation system for small coal-fired boiler
By setting up a wet electrostatic precipitator outside the desulfurization tower outlet of the small coal-fired boiler, we use humidified medium and electric field to remove flue gas particulate matter, the problem of flue gas purification in small coal-fired boilers is solved, and efficient dust removal and stable system operation is achieved. .
Patent Information
- Application Number
- CN202323541978.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-25
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2033-12-25
AI Technical Summary
Small coal-fired boilers lack efficient and low-investment desulfurization and electro-dust removal systems in flue gas purification, making pollutant emissions difficult to control.
A wet electro-dust collector is designed, combining the wet medium and electric field to remove particles in the flue gas by setting up a wet electro-dust collector outside the outlet of the desulfurization tower by using the electric field of the anode tube and the cathode line, and through the spraying device and flushing system for cleaning and recycling.
The flue gas dust concentration is reduced to below 5mg/Nm3, effectively purifying the flue gas, the system is compact and stable in operation, and is suitable for small coal-fired boilers, saving land occupation and reducing operating costs.
Smart Images

Figure CN221934201U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of flue gas purification, in particular to a flue gas moisture removal electric precipitator system for a small coal-fired boiler. Background Art
[0002] Pulverized coal industrial boilers, especially small and medium-sized boilers, have the special characteristics of small combustion space and high water cooling. Stable combustion and burnout problems are prominent. They can only burn high-quality bituminous coal or lignite pulverized coal. In terms of pollutant emissions, although the dust treatment of large and medium-sized coal-fired boilers in the power generation units of major power plants has mature and reliable technical equipment to guarantee it, the enterprises that invest in the construction of small and medium-sized boilers are small in scale and investment, and the pulverized coal industrial boiler room is restricted by the system investment and operating costs. Therefore, it is impossible to match the complex flue gas ultra-low moisture removal electrostatic precipitator system like large coal-fired power boilers.
[0003] Based on the characteristics of my country's energy resources and the actual situation that there are many small-scale pulverized coal industrial boilers, it is very necessary to develop a simple desulfurization system with high desulfurization efficiency, low investment and stable operation. Utility Model Content
[0004] The utility model overcomes the shortcomings of the prior art and proposes a smoke dehumidification and electric dust removal system for a small coal-fired boiler.
[0005] In order to achieve the above purpose, the utility model is implemented through the following technical solutions.
[0006] A flue gas dehumidification electrostatic precipitator system for a small coal-fired boiler comprises a wet electrostatic precipitator, wherein the wet electrostatic precipitator is arranged outside the outlet of a desulfurization tower, a plurality of anode tubes are arranged inside the wet electrostatic precipitator, an insulating box is arranged outside the wet electrostatic precipitator, the insulating box is connected to a sealed fan, and an air heater is connected to the outlet of the sealed fan; the insulating box is connected to a high-frequency constant current power supply, and the high-frequency constant current power supply is connected to a plurality of cathode wires, the number of the cathode wires is the same as that of the anode tubes, each cathode wire extends into the anode tube, and the bottom of the cathode wire extends from the bottom of the anode tube, the bottom of the cathode wire is connected to a hanging hammer, and a grid plate is arranged below the hanging hammer; a spray device is arranged above the anode tube; a flue gas inlet is arranged at the top of the wet electrostatic precipitator, and a flue gas outlet is arranged at the bottom.
[0007] Furthermore, a wet electrostatic precipitator is arranged on the top of the desulfurization tower.
[0008] Furthermore, the insulation box is connected to the sealed fan through a sealed air duct, and a pressure transmitter is provided on the sealed air duct.
[0009] Furthermore, the flue gas inlet is provided with a pressure transmitter and a temperature sensor.
[0010] Furthermore, the smoke outlet is provided with a temperature sensor.
[0011] Furthermore, a water collecting tank is provided at the bottom of the wet electrostatic precipitator, and the water collecting tank is connected to the pit through a pipeline.
[0012] Furthermore, the spray device includes a process water tank and a flushing spray layer, the flushing spray layer is evenly distributed above the anode tube, the flushing spray layer is connected to the process water tank through a flushing pipeline, and the flushing pipeline is connected to a flushing water pump.
[0013] Furthermore, the flushing pipeline is connected with anode and cathode flushing electric valves and a pressure transmitter.
[0014] Furthermore, the insulation box is connected to a temperature sensor.
[0015] Furthermore, the anode tube is a glass fiber reinforced plastic tube with a regular hexagonal cross section, and a plurality of anode tubes form a tube bundle with a honeycomb cross section.
[0016] Wet electrostatic precipitators effectively remove particulate matter from the air by combining humidification media and electric field action. The working principle of wet electrostatic precipitators mainly includes several steps: humidification, collection, cleaning and discharge. First, the particulate matter in the air is humidified through the front-end wet desulfurization tower. The humidification effect can make the particulate matter combine with water molecules to form wet particles and increase the adhesion of the particulate matter. Next, the wet particles generated in the humidification process are collected through the electric field.
[0017] The electrodes in a wet electrostatic precipitator consist of a positive electrode and a negative electrode, as well as an adjustable voltage source. When the distance between the positively charged particles and the negative electrode approaches zero, the electric field takes effect. Under the action of the electric field, the charged particles are attracted and repelled by the electric force, causing the particles to move in the air. During the movement, the wet particles will be captured by the electrodes. This capture action allows the wet electrostatic precipitator to remove particles efficiently.
[0018] When the wet electrostatic precipitator collects a large amount of wet particles, it needs to be cleaned. The purpose of cleaning is to remove the wet particles from the electrodes and recover the water to keep the equipment working properly. A common cleaning method is to wash the electrodes with water. During the water washing process, the water flow will carry away the wet particles and guide them into the wastewater treatment system for treatment. This ensures that the wet electrostatic precipitator can work stably for a long time. After cleaning, the wet electrostatic precipitator will discharge air with high dust removal effect into the environment.
[0019] The beneficial effects of the utility model compared with the prior art are:
[0020] The wet electrostatic precipitator described in the utility model effectively removes particulate matter in the air by combining the humidification medium and the electric field. The system has a compact structure, low operating resistance, high efficiency, and stable system operation, and can be effectively applied to small coal-fired boilers.
[0021] The flue gas generated by a small coal-fired boiler comes out of the induced draft fan and enters the desulfurization tower through the original flue. After desulfurization, the wet flue gas enters the wet electrostatic precipitator installed separately outside the tower through the upper outlet of the absorption tower. In the wet electrostatic precipitator, the droplets and fine dust particles are charged and release electrons on the pole tube, so the particles are gathered and flow to the bottom slurry pool under the action of the flushing system and gravity. After the wet electrostatic precipitator treatment, the dust concentration of the flue gas is reduced to 5mg / Nm 3 The following can effectively purify the flue gas from small coal-fired boilers.
[0022] The utility model arranges the wet electrostatic precipitator at the very end of the flue gas purification process, which plays a very important role. The wet electrostatic precipitator is arranged separately from the desulfurization tower and arranged outside the desulfurization tower. If the on-site space is tight and the split arrangement cannot be met, the entire wet electrostatic system can be arranged on the top of the desulfurization tower, thereby saving most of the space. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 It is a structural schematic diagram of the flue gas dehumidification electrostatic precipitator system described in the utility model.
[0024] In the figure:
[0025] 1-sealed fan; 2-air heater; 3-insulation box; 4-high frequency constant current power supply; 5-flushing spray layer; 6-cathode wire; 7-anode tube; 8-hanging hammer; 9-grid plate; 10-wet electric cylinder; 11-water collecting tank; 12-flushing water pump; 13-process water tank; 14-sealed air duct; 15-pressure transmitter; 16-smoke inlet; 17-smoke outlet; 18-temperature sensor; 19-pit; 20-cathode and anode flushing electric valve. DETAILED DESCRIPTION
[0026] In order to make the technical problems, technical solutions and beneficial effects to be solved by the present invention more clearly understood, the present invention is further described in detail in combination with the embodiments and the accompanying drawings. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention. The technical solution of the present invention is described in detail below in combination with the embodiments and the accompanying drawings, but the scope of protection is not limited thereto.
[0027] like Figure 1As shown, this embodiment provides a flue gas dehumidification electrostatic precipitator system for a small coal-fired boiler, including two sealed fans 1; an air heater 2; an insulating box 3; a high-frequency constant current power supply 4; a flushing spray layer 5; a cathode wire 6; an anode tube 7; a hanging hammer 8; a grid plate 9; a wet electric cylinder 10; a water collection tank 11; a flushing water pump 12; and a process water tank 13.
[0028] The wet electrostatic precipitator is arranged outside the outlet of the desulfurization tower. If the space on site is tight and the split arrangement cannot be met, the entire wet electrostatic system can be arranged on the top of the desulfurization tower. A number of anode tubes 7 are arranged inside the wet electrostatic precipitator. The anode tubes 7 are glass fiber reinforced plastic tubes with a regular hexagonal cross section. A number of anode tubes 7 form a tube bundle with a honeycomb cross section. Its structural form is a FRP regular hexagonal honeycomb tube with an inscribed circle of Φ360mm, a wall thickness of 3mm, and a length of 6000mm: the material is conductive flame-retardant glass fiber reinforced plastic, and the resin is vinyl flame-retardant resin, forming a precipitation electrode honeycomb, which is suspended on the tube bundle support beam.
[0029] Two insulating boxes 3 are arranged outside the wet electrostatic precipitator, and the insulating boxes 3 are connected to a temperature sensor 18. The insulating boxes 3 are connected to the sealed fan 1 through a sealed air duct 14, and a pressure transmitter 15 is arranged on the sealed air duct 14. The outlet of the sealed fan 1 is connected to an air heater 2; the insulating box 3 is connected to a high-frequency constant current power supply 4, and the high-frequency constant current power supply 4 is connected to a plurality of cathode wires 6, the number of the cathode wires 6 is the same as that of the anode tube 7, each cathode wire 6 extends into an anode tube 7, the bottom of the cathode wire 6 extends from the bottom of the anode tube 7, the bottom of the cathode wire 6 is connected to a hanging hammer 8, and a grid plate 9 is arranged below the hanging hammer 8; a spray device is arranged above the anode tube 7; the spray device includes a process water tank 13 and a flushing spray layer 5, the flushing spray layer 5 is evenly distributed above the anode tube 7, the flushing spray layer 5 is connected to the process water tank 13 through a flushing pipeline, and the flushing pipeline is connected to a flushing water pump 12. The flushing pipeline is connected with an anode and cathode flushing electric valve 20 and a pressure transmitter 15 .
[0030] A water collecting tank 11 is provided at the bottom of the wet electrostatic precipitator, and the water collecting tank 11 is connected to a pit 19 through a pipeline. A flue gas inlet 16 is provided at the top of the wet electrostatic precipitator, and a flue gas outlet 17 is provided at the bottom. The flue gas inlet 16 is provided with a pressure transmitter 15 and a temperature sensor 18. The flue gas outlet 17 is provided with a temperature sensor 18.
[0031] Before the boiler is started, the wet electrostatic precipitator must be started first. First, the air heater 2 and the sealed fan 1 on the sealed air duct 14 are turned on, and dry hot air is blown into the insulation box 3. Since the insulation box 3 is connected with a high-voltage electrical connector, in order to prevent the air from being damp or condensed and causing electric shock and short-circuit penetration accidents, it is necessary to continuously blow dry hot air into the insulation box 3. When the air in the insulation box 3 is dry, the high-frequency constant current power supply 4 is turned on and energized. The high-voltage current charges the multiple cathode wires 6 of the lower branch, forming positive and negative electrodes with the anode tube 7. When the distance between the positively charged particles and the negative electrode approaches zero, the action of the electric field occurs. Under the action of the electric field, the charged particles are attracted and repelled by the electric force, so that the particles move in the air. When the particles contact the inner wall of the anode tube 7, they are effectively adsorbed, thereby efficiently removing the particles. Since the cathode wire 6 is arranged inside the anode tube 7 and is a thin strip with thorns, it is easy to bend and deform after being charged, resulting in contact with the inner wall of the anode tube 7 to cause a short circuit. Therefore, a hanging weight 8 is installed at the lower end of the cathode line 6 to straighten the cathode line 6 under the action of gravity. In order to prevent the cathode line 6 from accidentally disconnecting during long-term operation, causing the bottom hanging weight 8 to fall and damage the bottom equipment, a grid plate 9 is arranged at the lower end of the wet electric cylinder body 10 to effectively receive the falling hanging weight 8 and ensure the safety of the equipment.
[0032] After the boiler is running, the hot flue gas after wet desulfurization enters the wet electrostatic precipitator through the flue gas inlet 16. The pressure transmitter 15 and the temperature sensor 18 set at the flue gas inlet 16 can timely detect the inlet flue gas temperature and pressure to prevent damage to the equipment. After the wet electrostatic precipitator equipment has been operating normally for a period of time, a large amount of dust particles are accumulated and adsorbed on the inner wall. It is necessary to stop the high-frequency constant current power supply 4 and start the flushing water pump 12. The clean water in the process water tank 13 is used to flush the inner wall of the anode tube 7 through the flushing spray layer 5. The particles and water fall into the bottom sump 11 under the action of gravity and are drained into the pit with a conduit. After sedimentation, the clean water is recycled and the particle sediment is sent to the slag treatment system.
[0033] Finally, the flue gas that has been dusted and meets the standards by the wet electrostatic precipitator is returned to the chimney through the flue gas outlet 17 for discharge in compliance with the standards, thereby effectively ensuring that particulate matter in the air is effectively removed.
[0034] The above content is a further detailed description of the utility model in combination with a specific preferred implementation method. It cannot be determined that the specific implementation methods of the utility model are limited to this. For ordinary technicians in the technical field to which the utility model belongs, they can make several simple deductions or substitutions without departing from the utility model, which should be regarded as belonging to the utility model and the scope of patent protection determined by the submitted claims.
Claims
1. A flue gas dehumidification electrostatic precipitator system for a small coal-fired boiler, characterized in that: The invention comprises a wet electrostatic precipitator, wherein the wet electrostatic precipitator is arranged outside the outlet of a desulfurization tower, a plurality of anode tubes (7) are arranged inside the wet electrostatic precipitator, an insulating box (3) is arranged outside the wet electrostatic precipitator, the insulating box (3) is connected to a sealed fan (1), and the outlet of the sealed fan (1) is connected to an air heater (2); the insulating box (3) is connected to a high-frequency constant current power supply (4), the high-frequency constant current power supply (4) is connected to a plurality of cathode wires (6), the number of the cathode wires (6) is the same as the number of the anode tubes (7), each cathode wire (6) extends into an anode tube (7), and the bottom of the cathode wire (6) extends from the bottom of the anode tube (7), the bottom of the cathode wire (6) is connected to a hanging weight (8), and a grid plate (9) is arranged below the hanging weight (8); a spray device is arranged above the anode tube (7); a flue gas inlet (16) is arranged at the top of the wet electrostatic precipitator, and a flue gas outlet (17) is arranged at the bottom.
2. The flue gas dehumidification electrostatic precipitator system for a small coal-fired boiler according to claim 1, characterized in that: The wet electrostatic precipitator is arranged at the top of the desulfurization tower.
3. The flue gas dehumidification electrostatic precipitator system for a small coal-fired boiler according to claim 1, characterized in that: The insulating box (3) is connected to the sealed air fan (1) via a sealed air duct (14), and a pressure transmitter (15) is provided on the sealed air duct (14).
4. The flue gas dehumidification electrostatic precipitator system for a small coal-fired boiler according to claim 1, characterized in that: The flue gas inlet (16) is provided with a pressure transmitter (15) and a temperature sensor (18).
5. The flue gas dehumidification electrostatic precipitator system for a small coal-fired boiler according to claim 1, characterized in that: The smoke outlet (17) is provided with a temperature sensor (18).
6. The flue gas dehumidification electrostatic precipitator system for a small coal-fired boiler according to claim 1, characterized in that: A water collecting tank (11) is provided at the bottom of the wet electrostatic precipitator, and the water collecting tank (11) is connected to a ground pit (19) via a pipeline.
7. The flue gas dehumidification electrostatic precipitator system for a small coal-fired boiler according to claim 1, characterized in that: The spray device comprises a process water tank (13) and a flushing spray layer (5), wherein the flushing spray layer (5) is evenly distributed above the anode tube (7), and the flushing spray layer (5) is connected to the process water tank (13) via a flushing pipeline, and the flushing pipeline is connected to a flushing water pump (12).
8. The flue gas dehumidification electrostatic precipitator system for a small coal-fired boiler according to claim 7, characterized in that: The flushing pipeline is connected to an anode and cathode flushing electric valve (20) and a pressure transmitter (15).
9. The flue gas dehumidification electrostatic precipitator system for a small coal-fired boiler according to claim 1, characterized in that: The insulation box (3) is connected to a temperature sensor (18).
10. The flue gas dehumidification electrostatic precipitator system for a small coal-fired boiler according to claim 1, characterized in that: The anode tube (7) is a glass fiber reinforced plastic tube with a regular hexagonal cross section, and a plurality of anode tubes (7) form a tube bundle with a honeycomb cross section.