Heavy-load overwater construction operation platform

By designing a modular heavy-load water construction platform, the problem of insufficient stability of ordinary temporary steel trests is solved, efficient demolition and maintenance is achieved, high-load operation needs are met, and construction efficiency and overall stability of the platform are improved. sex.

CN221941125UActive Publication Date: 2024-11-01ROAD & BRIDGE INT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323581425.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-27
Publication Date
2024-11-01
Estimated Expiration
2033-12-27

AI Technical Summary

Technical Problem

The existing ordinary temporary steel trestle has poor overall structural stability after repeated demolition and recovery, and cannot meet the needs of high-load operations such as water pile foundation drilling, water cofferdam steel pipe pile insertion and heavy gantry crane operation. Demolition and restoration are inconvenient.

Method used

A heavy-load water construction work platform was designed, including platform piles, beam frame support structure and platform panel, with drilling construction modules, plug-in cofferdam modules and gantry crane operation modules, and modular unit components are used for assembly. The support structure consists of Bere beam assembly and distribution beam assembly. The drilling construction module and the plug-in cofferdam module are located in the middle of the platform panel, and the gantry crane operation module is located on both sides to ensure structural stability and efficient removal.

Benefits of technology

It realizes efficient modular assembly and maintenance, reduces maintenance costs, improves the turnover efficiency and functional flexibility of the platform, and can change or increase functions without dismantling, avoids waste of materials, and improves construction efficiency and platform. Overall stability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221941125U_ABST
    Figure CN221941125U_ABST
Patent Text Reader

Abstract

The utility model provides a heavy-load overwater construction operation platform which comprises a platform pile, a beam frame supporting structure arranged on the platform pile in a supported mode and a platform panel laid on the beam frame supporting structure, and a drilling construction module, a cofferdam inserting and driving module and a gantry crane operation module are arranged on the platform panel. Wherein the drilling construction module and the cofferdam inserting and piling module are both arranged in the middle of the platform panel, and the gantry crane operation modules are arranged at the positions, close to the edges, of the two sides of the platform panel. The heavy-load overwater construction operation platform can solve the problem that an existing common temporary steel trestle is poor in overall structural stability after being dismantled and recovered for multiple times.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of large bridge construction, and more specifically, to a heavy-load water construction operation platform. Background Art

[0002] For large bridges, the water construction platform is the cornerstone of engineering construction within the water area. It is a temporary construction activity platform that integrates multiple functions such as personnel and material transportation channels, machinery and equipment layout platforms, and construction material storage sites.

[0003] Among the current water construction platforms, the most common one is the temporary steel trestles, which are mainly composed of steel pipe pile piers, Bailey trusses, I-beam distribution beams, bridge decks, etc. They mainly serve as temporary water traffic channels. They have simple and reliable structures, wide range of applications, and can be quickly erected to meet the needs of temporary structure construction during construction.

[0004] Then, the main function of the existing ordinary temporary steel trestles (i.e. the existing common water construction platforms) is a temporary water traffic channel. Its structural stability and bearing capacity cannot meet the needs of high-load operations such as water pile foundation drilling operations, water cofferdam steel pipe pile driving operations, and heavy gantry crane operation and construction operations.

[0005] In addition, for existing ordinary temporary steel trestles, due to the differences in time and space between various operations, the temporary steel trestles need to be repeatedly dismantled and restored; however, the high convenience of dismantling and restoring the trestles, and the high stability of the overall structure after multiple dismantling and restoration, are all requirements that are difficult for existing ordinary temporary steel trestles to meet.

[0006] Based on this, there is an urgent need for a heavy-loaded water platform that can carry out high-load operations such as water pile foundation drilling operations, water cofferdam steel pipe pile driving operations, and heavy gantry crane operation and construction operations without dismantling. Utility Model Content

[0007] In view of the above problems, the purpose of the utility model is to provide a heavy-loaded water construction work platform to solve the problem of poor overall structural stability of existing ordinary temporary steel trestles after multiple dismantling and restoration.

[0008] The utility model provides a heavy-loaded water construction work platform, including platform piles, a beam support structure supported on the platform piles and a platform panel laid on the beam support structure, wherein a drilling construction module, a cofferdam insertion module and a gantry crane operation module are arranged on the platform panel; wherein the drilling construction module and the cofferdam insertion module are both arranged in the middle of the platform panel, and the gantry crane operation module is arranged on both sides of the platform panel near the edge.

[0009] In addition, a preferred structure is that the beam frame supporting structure includes a Bailey beam assembly supported on the platform piles and a distribution beam assembly fixed on the Bailey beam, and the platform panel is fixedly laid on the distribution beam assembly.

[0010] In addition, a preferred structure is that the Bailey beam assembly includes at least two Bailey beam monomers, and a cross brace is fixedly connected between two adjacent Bailey beam monomers.

[0011] In addition, a preferred structure is that the distribution beam assembly includes a transverse distribution beam and a longitudinal distribution beam fixed on the Bailey beam assembly, and the platform panel is fixedly laid on the transverse distribution beam and the longitudinal distribution beam.

[0012] In addition, a preferred structure is that at least two platform piles are provided along the extension direction of the preset temporary bridge; and

[0013] A pile top bearing beam is fixed on each platform pile, and the top of each platform pile is connected to the Bailey beam assembly through the pile top bearing beam.

[0014] In addition, a preferred structure is that the drilling construction module includes a rotary drilling rig arranged on the platform panel, a drilling rod is arranged on the rotary drilling rig, and a drilling bit is arranged at the end of the drilling rod; wherein,

[0015] The drilling rig drill head avoids the Bailey beam and the distribution beam assembly and extends into a borehole of a preset pile foundation.

[0016] In addition, a preferred structure is that at least two preset pile foundations are provided; and

[0017] Temporary piles are set up between the preset pile foundations, and the temporary piles are fixed to the Bailey beams.

[0018] In addition, a preferred structure is that the cofferdam driving module includes a crawler crane and an exciting hammer arranged on the platform panel, and the crawler crane cooperates with the exciting hammer to drive the cofferdam piles around the periphery of the preset pile foundation.

[0019] In addition, a preferred structure is that the gantry crane operation module includes a gantry crane; and,

[0020] The Bailey beam monomer on the segment corresponding to the gantry crane operation module on the heavy-loaded water construction operation platform corresponds to the platform pile up and down.

[0021] In addition, a preferred structure is that guardrails are provided on both sides of the platform panel, and the drilling construction module, the cofferdam insertion module and the gantry crane operation module are all located between the two guardrails.

[0022] Compared with the prior art, the heavy-loaded water construction work platform provided by the utility model has the following beneficial effects:

[0023] The heavy-duty water construction work platform provided by the utility model has a high degree of modularization, and different functional structures are modularly assembled using standardized unit components, so the construction efficiency is high; secondly, when the entire heavy-duty water construction work platform is maintained and repaired, it is only necessary to repair or replace the old and damaged structural units (such as components, modules, individual parts, etc.), and the maintenance is convenient and fast, does not affect the overall structure of the platform, and the maintenance cost is low; in addition, after the use of the platform is over, the platform can be modularly dismantled, and the dismantled structural units (such as components, modules, individual parts, etc.) can be transported to the next construction site for assembly and splicing for continued use, which basically can achieve no material waste and high platform turnover efficiency; in addition, when changing or adding the platform's use function, it is sufficient to splice the corresponding functional modules in the functional use area, and there is no need to redesign the overall structure of the platform, thus saving time and energy. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] By referring to the following description in conjunction with the drawings and the contents of the claims, and with a more comprehensive understanding of the present invention, other objects and results of the present invention will become more apparent and easier to understand.

[0025] In the attached picture:

[0026] Figure 1 This is a front view of a section corresponding to the drilling construction module in the heavy-loaded water construction work platform provided by the utility model;

[0027] Figure 2 A side view of a section corresponding to the drilling construction module in the heavy-loaded water construction work platform provided by the utility model;

[0028] Figure 3 A top view of a section corresponding to a drilling construction module in a heavy-loaded water construction operation platform provided by the utility model after the platform panel is removed;

[0029] Figure 4 It is a top view of the segment corresponding to the gantry crane operation module in the heavy-load water construction operation platform provided by the utility model after the platform panel is removed;

[0030] Figure 5 A top view of a section corresponding to the cofferdam insertion module in the heavy-duty water construction operation platform provided by the utility model after the platform panel is removed (the relevant components in the cofferdam insertion module are also removed in this figure);

[0031] Figure numerals: platform panel 1, guardrail 2, longitudinal distribution beam 3, transverse distribution beam 4, Bailey beam assembly 5, pile top load-bearing beam 6, platform pile 7, cofferdam pile 8, rotary drilling rig 9, borehole 10, temporary pile 11, cross brace 12, diagonal brace 13, gantry crane 15, pile foundation 16.

[0032] The same reference numerals throughout the drawings indicate similar or corresponding features or functions. DETAILED DESCRIPTION

[0033] In the following description, for the purpose of illustration, in order to provide a comprehensive understanding of one or more embodiments, many specific details are set forth. However, it is apparent that these embodiments may also be implemented without these specific details. In other examples, for ease of describing one or more embodiments, known structures and devices are shown in the form of block diagrams.

[0034] In the description of the present utility model, it should be noted that the orientation or position relationship indicated by the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside", etc. is based on the orientation or position relationship shown in the drawings, and is only for the convenience of describing the present utility model and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation of the present utility model; the terms "first", "second", and "third" are only used for descriptive purposes and cannot be understood as indicating or implying relative importance; in addition, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be a communication between the two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present utility model can be understood according to specific circumstances.

[0035] Figure 1 The main structure of the section corresponding to the drilling construction module in the heavy-loaded water construction platform provided by the utility model is shown. Figure 2 The side view structure of the segment corresponding to the drilling construction module in the heavy-loaded water construction operation platform provided by the utility model is shown. Figure 3 The top view of the section corresponding to the drilling construction module in the heavy-loaded water construction platform provided by the utility model after the platform panel is removed is shown. Figure 4 The top view of the section corresponding to the gantry crane operation module in the heavy-loaded water construction operation platform provided by the utility model after the platform panel is removed is shown. Figure 5The figure shows a top view of a segment corresponding to the cofferdam insertion module in the heavy-duty water construction operation platform provided by the utility model after the platform panel is removed (the figure also removes the relevant components in the cofferdam insertion module).

[0036] Combination Figures 1 to 5 It can be seen that the heavy-loaded water construction work platform provided by the utility model includes a plurality of platform piles 7 fixed on the underwater ground. The platform piles 7 play the most basic role. The platform piles 7 are arranged in plurality (at least two) along the extension direction of the preset temporary bridge (that is, the heavy-loaded water construction work platform provided by the utility model) to stably support different sections of the preset temporary bridge; a beam support structure is fixedly supported on the platform piles 7, and the beam support structure is arranged along the extension direction of the preset temporary bridge, and different sections thereof are connected to different platform piles 7; a platform panel 1 is laid on the beam support structure, and the platform panel 1 is used to implement various different work activities.

[0037] Specifically, in order to realize operations such as drilling 10 of the pile foundation 16 on the water, driving of the cofferdam piles 8 on the water, and operation and construction of the heavy gantry crane 15 on the platform panel 1, a drilling 10 construction module, a cofferdam driving module and a gantry crane 15 operation module are provided on the platform panel 1; the drilling 10 construction module is used for the drilling 10 operation of the pile foundation 16 on the water, the cofferdam driving module is used for the driving of the cofferdam piles 8 on the water, and the gantry crane 15 operation module is used for the operation and construction of the heavy gantry crane 15.

[0038] It should be noted that since the preset pile foundation 16 generally corresponds to the middle part of the heavy-loaded water construction platform, the water cofferdam piles 8 are used to enclose the preset pile foundation 16; therefore, the drilling 10 construction module and the cofferdam insertion module need to be set in the middle part of the platform panel 1; and the gantry crane 15 is a heavy equipment with a large gravity. In order to ensure the stability of the entire device, the gantry crane 15 operation module needs to be set on both sides of the platform panel 1 near the edge. The support stability on both sides of the platform panel 1 near the edge is much higher than the support stability in the middle of the platform panel 1.

[0039] In a specific embodiment of the present invention, in order to provide the required support stability for the beam frame support structure, the beam frame support structure may include a Bailey beam assembly 5 supported on the platform piles 7 and a distribution beam assembly fixed on the Bailey beam assembly 5, and both the Bailey beam assembly 5 and the distribution beam assembly are arranged along the extension direction of the preset temporary bridge, and different sections at the bottom of the Bailey beam assembly 5 are connected to different platform assemblies, and the platform panel 1 is fixedly laid on the distribution beam assembly.

[0040] In addition, in order to improve the connection firmness between each platform pile 7 and the Bailey beam assembly, a pile top load-bearing beam 6 can also be fixed on each platform pile 7, and the top of each platform pile 7 is connected to different positions of the Bailey beam assembly 5 through the corresponding pile top load-bearing beam 6.

[0041] Further, the Bailey beam assembly 5 may include a plurality of (at least two) Bailey beam monomers, and two adjacent Bailey beam monomers are fixedly connected by a cross brace 12 to form the entire Bailey beam assembly 5, and a diagonal brace 13 is connected between each platform pile 7 and the Bailey beam assembly 5 to improve the support stability of the entire device. In addition, the distribution beam assembly may include a transverse distribution beam 4 and a longitudinal distribution beam 3 fixed on the Bailey beam assembly 5, and the platform panel 1 is fixedly laid on the transverse distribution beam 4 and the longitudinal distribution beam 3.

[0042] In another specific embodiment provided by the utility model, the drilling 10 construction module may include a rotary drilling rig 9 arranged on the platform panel 1, a drilling rig drill rod is arranged on the rotary drilling rig 9, and a drilling rig drill bit is arranged at the end of the drilling rig drill rod; wherein the drilling rig drill bit avoids the Bailey beam and the distribution beam assembly and extends into the borehole 10 of the preset pile foundation 16, and the preset pile foundation 16 is provided with multiple (at least two). It should be noted that for the drilling 10 construction module, in terms of the plane structure layout, temporary piles 11 need to be set up between each preset pile foundation 16 for support, and the temporary piles 11 are fixed to the Bailey beam assembly 5. The temporary piles 11 will be removed after the pile foundation 16 drilling 10 construction is completed to avoid affecting the construction of the cap and pier column; the Bailey beam assembly 5 and the distribution beam assembly thereon need to avoid the position directly opposite the pile foundation 16 when arranging, so that the drilling rig can extend the drill rod into the stratum at the position of the pile foundation 16 to drill 10.

[0043] In another specific embodiment provided by the utility model, the cofferdam insertion module may include heavy equipment such as a crawler crane and an exciting hammer set on the platform panel 1, and the crawler crane cooperates with the exciting hammer and other heavy equipment to insert the cofferdam pile 8 on the periphery of the preset pile foundation 16; wherein the cofferdam pile 8 is based on Figure 1 It should be noted that for the cofferdam module, it has high requirements for the load capacity and stability of the platform. Therefore, for the section corresponding to the cofferdam module on the heavy-loaded water construction platform, it is necessary to encrypt the Bailey beam assembly 5 and the distribution beam assembly to improve the support stability of this section of the heavy-loaded water construction platform.

[0044] In the last specific embodiment provided by the utility model, the gantry crane 15 operation module may include a gantry crane 15 (heavy gantry crane 15); and the Bailey beam monomer on the segment corresponding to the gantry crane 15 operation module on the heavy-loaded water construction platform needs to correspond to the platform pile 7 up and down. It should be noted that in actual use, the gantry crane 15 needs to lift a large segment steel box beam of about 400 tons and run it, and the gantry crane 15 needs to be set with a track. In order to improve the support stability of the gantry crane 15, the track of the gantry crane 15 needs to be laid near the edge on both sides of the platform, and the load will directly act on both sides of the platform. In addition, the load capacity and stability of the platform at this location are crucial to the lifting operation of the steel box girder of the main bridge. Therefore, in order to meet the high load capacity and high stability requirements of the gantry crane 15 during operation, the Bailey beam assemblies 5 on both sides of the platform also need to be encrypted. At the same time, the Bailey beam units need to be arranged at the top of the platform piles 7 as much as possible so that the platform piles 7 can directly bear the load, thereby avoiding the problem of the load-bearing beam 6 being bent and deformed after the load is transferred to the top of the pile, causing the gantry crane 15 track to sink.

[0045] Preferably, in order to prevent the components in each module from falling underwater, guardrails 2 can also be set on both sides of the platform panel 1. Modules such as the drilling 10 construction module, the cofferdam insertion module and the gantry crane 15 operation module need to be between the two guardrails 2 to improve safety.

[0046] In addition, it should be noted that in order to improve the supporting performance of each supporting pile structure (such as platform piles 7, temporary piles 11 and cofferdam piles 8, etc.), each supporting pile structure can be made of steel pipes of different calibers; and, in order to facilitate the running parts in each module (such as rotary drilling rigs 9, crawler cranes, gantry cranes 15, etc.) to walk on the platform panel 1, the running parts in each module can use crawlers to drive the front and rear wheels.

[0047] As above Figures 1 to 5 The heavy-loaded water construction work platform according to the utility model is described by way of example. However, those skilled in the art should understand that various improvements can be made to the heavy-loaded water construction work platform proposed by the utility model without departing from the content of the utility model. Therefore, the protection scope of the utility model should be determined by the content of the attached claims.

Claims

1. A heavy-loaded water construction work platform; characterized in that: It includes platform piles, a beam support structure supported on the platform piles, and a platform panel laid on the beam support structure, and a drilling construction module, a cofferdam insertion module, and a gantry crane operation module are arranged on the platform panel; wherein, The drilling construction module and the cofferdam insertion module are both arranged in the middle of the platform panel, and the gantry crane operation module is arranged on both sides of the platform panel near the edge.

2. The heavy-loaded water construction platform according to claim 1, characterized in that: The beam frame supporting structure comprises a Bailey beam assembly supported on the platform piles and a distribution beam assembly fixed on the Bailey beam assembly, and the platform panel is fixedly laid on the distribution beam assembly.

3. The heavy-loaded water construction platform according to claim 2, characterized in that: The Bailey beam assembly comprises at least two Bailey beam monomers, and a cross brace is fixedly connected between two adjacent Bailey beam monomers.

4. The heavy-loaded water construction work platform according to claim 3, characterized in that: The distribution beam assembly comprises a transverse distribution beam and a longitudinal distribution beam fixed on the Bailey beam assembly, and the platform panel is fixedly laid on the transverse distribution beam and the longitudinal distribution beam.

5. The heavy-loaded water construction work platform according to claim 4, characterized in that: At least two platform piles are arranged along the extension direction of the preset temporary bridge; and A pile top bearing beam is fixed on each platform pile, and the top of each platform pile is connected to the Bailey beam assembly through the pile top bearing beam.

6. The heavy-loaded water construction work platform according to claim 5, characterized in that: The drilling construction module comprises a rotary drilling rig arranged on the platform panel, a drilling rod is arranged on the rotary drilling rig, and a drilling bit is arranged at the end of the drilling rod; wherein, The drilling rig drill head avoids the Bailey beam and the distribution beam assembly and extends into a borehole of a preset pile foundation.

7. The heavy-loaded water construction work platform according to claim 6, characterized in that: There are at least two preset pile foundations; and Temporary piles are set up between the preset pile foundations, and the temporary piles are fixed to the Bailey beam assembly.

8. The heavy-loaded water construction platform according to claim 6, characterized in that: The cofferdam driving module includes a crawler crane and an exciting hammer arranged on the platform panel. The crawler crane cooperates with the exciting hammer to drive the cofferdam piles around the preset pile foundation.

9. The heavy-loaded water construction work platform according to claim 5, characterized in that: The gantry crane operation module includes a gantry crane; and, The Bailey beam monomer on the segment corresponding to the gantry crane operation module on the heavy-loaded water construction operation platform corresponds to the platform pile up and down.

10. The heavy-loaded water construction work platform according to any one of claims 1 to 9, characterized in that: Guardrails are arranged on both sides of the platform panel, and the drilling construction module, the cofferdam insertion module and the gantry crane operation module are all located between the two guardrails.