Concrete-filled steel tube arch rib low-position assembly temporary tie bar cable installation system

By adopting a low-level assembly temporary tether cable installation system in the construction of steel pipe concrete arch bridges, and using sling truss wheel sets and bracket wheel sets to lift the tether cable, the problem of temporary tether cable sag control is solved and the structure is stable and construction safety improve construction quality.

CN221941131UActive Publication Date: 2024-11-01GUANGXI ROAD CONSTR ENG GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420207519.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-29
Publication Date
2024-11-01
Estimated Expiration
2034-01-29

AI Technical Summary

Technical Problem

In the construction of steel pipe concrete arch bridges, the uncontrolled sag of the temporary tether cable may cause the arch rib structure to exceed the design limit, affecting stability and safety, and affecting construction quality.

Method used

The temporary tether cable installation system is adopted for low-level assembly of steel pipe concrete arch ribs. Through the combination of large sections of arch ribs, vertical tether brackets, lifting towers and temporary tether fixed steel strand cables, the uniform distribution and stability of the tether cables are ensured. Installation, use the sling wheel set and the bracket wheel set to lift the tie rope to reduce the installation sag.

Benefits of technology

The smooth installation of temporary ties and structural stress are achieved, the construction quality is improved, the workload of later adjustment is reduced, and the risk of structural stress is reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221941131U_ABST
    Figure CN221941131U_ABST
Patent Text Reader

Abstract

The utility model relates to a concrete filled steel tube arch rib low-position assembly temporary tie bar cable installation system which comprises arch rib large sections, a vertical assembly support, a lifting tower, a temporary tie bar cable and temporary tie bar fixing steel strand slings. The two ends of the arch rib large section penetrate through the lifting towers respectively and are supported by the lifting towers through lifting suspension points; the bottom of the large arch rib section is connected with and supports a plurality of vertically-spliced brackets which are arranged at intervals; two ends of the temporary tie-rod cable are fixed on two anchoring points, close to the tail end, of the arch rib large section, and the temporary tie-rod cable is arranged in an upper layer and a lower layer; temporary tie bar fixing steel strand slings are lowered from the arch rib large section according to the arrangement rule that one position is arranged in the center of each interval between every two adjacent vertically-spliced supports and between the lifting tower and the vertically-spliced supports, sling riding wheel sets are installed at the lower ends of the temporary tie bar fixing steel strand slings in a suspended mode, and support riding wheel sets are installed on the vertically-spliced supports. The sling riding wheel set and the support riding wheel set support the temporary tie-rod cable. The system can ensure smooth installation of the temporary tie bar cable, and ensures the stress safety and stability of the structure in the installation process.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of bridge construction, in particular to a temporary tie cable installation system for low-position assembly of steel tube concrete arch ribs. Background Art

[0002] With the economic progress of our country, the construction of steel tube concrete arch bridges has become more and more popular in China. The overall lifting construction of steel tube concrete arch bridges is a relatively new construction technology in bridge construction. This method first prefabricates the various segments of the arch ribs beside the arch bridge or other appropriate locations, and then uses lifting equipment such as lifting vehicles and crawler cranes to lift the prefabricated arch rib segments to the designated location, and connects each segment into a large integral segment by bolting and welding, and then uses a continuous jack to lift it to the predetermined position at one time, and then completes the joint with the arch foot side segment.

[0003] Temporary tie cables play a key role in overall lifting construction. They are designed to balance the tension generated by the arch ribs during the lifting process. One of the key links in overall lifting construction is how to control the temporary tie cables to be balanced, stable and accurate. If appropriate measures are not taken to assist in the installation of these tie cables, a variety of adverse phenomena may occur.

[0004] This is mainly because the temporary tie cables have a large sag, which refers to the bending or sagging of the tie cables under the action of their own weight, which is the result of the combined effect of factors such as cable length, deadweight and prestress. When the sag is too large, the weight of the tie cables is no longer evenly distributed, but concentrated in some specific locations, which will cause the arch rib structure to bear additional bending moments and axial forces, which may cause the arch rib structure to be subjected to forces exceeding the design limit, thus affecting its stability and safety. If the arch rib structure continues to be constructed in this state, it may cause deformation or even collapse. In addition, if the sag of the tie cables is not controlled, its position may deviate from the design, thereby affecting the geometry of the arch rib and the balance of the structure, increasing the workload of later adjustments, and leading to construction quality problems.

[0005] In summary, the uncontrolled installation of temporary tie cables may bring about a variety of structural and construction risks. In order to ensure the stability and safety of the arch rib structure, the temporary tie cables should be pre-installed before the arch rib is lifted, and the temporary tie cables should be installed smoothly to reduce the installation sag of the temporary tie cables and ensure the safety and stability of the structure during its installation. Summary of the invention

[0006] The utility model aims to provide a temporary tie cable installation system for low-position assembly of steel tube concrete arch ribs, which can ensure smooth installation of temporary tie cables and ensure the safety and stability of the force of the structure during its installation.

[0007] The utility model is realized by the following technical solutions:

[0008] A temporary tie-rope installation system for low-position assembly of steel tube concrete arch ribs, comprising a large arch rib segment, a vertical assembly bracket, a lifting tower, a temporary tie-rope and a temporary tie-rope fixed steel strand sling; the two ends of the large arch rib segment respectively pass through the lifting tower and are supported by the lifting tower to lift the lifting point; the bottom of the large arch rib segment is connected to support a plurality of vertical assembly brackets arranged at intervals; the two ends of the temporary tie-rope are fixed to two anchor points close to the ends of the large arch rib segment, and the temporary tie-rope is arranged in two layers, upper and lower; the temporary tie-rope fixed steel strand sling is lowered from the large arch rib segment according to the arrangement rule of setting one point in the center of each interval between two adjacent vertical assembly brackets and between the lifting tower and the vertical assembly bracket, the lower end of the temporary tie-rope fixed steel strand sling is suspended with a sling support wheel group, the vertical assembly bracket is installed with a support support wheel group, the sling support wheel group and the support support wheel group are fixed at the design height position of the temporary tie-rope, and the temporary tie-rope is supported.

[0009] Further preferred: the sling supporting wheel group includes an upper sling supporting wheel group and a lower sling supporting wheel group, and the upper sling supporting wheel group and the lower sling supporting wheel group are fixedly installed on the temporary tie rod fixed steel strand sling in an upper and lower structure; the upper sling supporting wheel group and the lower sling supporting wheel group respectively include a rolling supporting wheel, a roller, a supporting wheel frame and an I-beam; the rolling supporting wheel is rotatably installed on the roller, the roller is installed on the supporting wheel frame, the supporting wheel frame is welded to the I-beam, and the rolling supporting wheel supports the temporary tie rod for installation; the I-beam and the temporary tie rod fixed steel strand sling are fixed at the designed height position of supporting the temporary tie rod by a bolted anchor.

[0010] Further preferred: channel steels extending outwards are welded on the upper parts of both sides of the supporting wheel frame respectively, and temporary tie rods are used to fix the steel strand slings and then pass through the channel steels and then connect to the I-beams.

[0011] Further preferably, the temporary tie rod fixing steel strand sling adopts Strand 1860 steel strand with a diameter of 15.2.

[0012] Further preferred: the support wheel group includes an upper support wheel group and a lower support wheel group, and the upper support wheel group and the lower support wheel group are fixedly installed on the vertical support in an upper and lower structure; the upper support wheel group and the lower support wheel group respectively include rolling wheels, rollers, wheel frames and I-beams; the rolling wheels are rollingly installed on the rollers, the rollers are installed on the wheel frames, the wheel frames are welded to the I-beams, and the rolling wheels support the temporary tie rods for installation; the I-beams and the vertical support are welded and fixed at the designed height position for supporting the temporary tie rods.

[0013] The fixed height of the I-beam enables the rolling wheels of the upper suspension cable wheel group and the upper support wheel group to support the upper temporary tie rod cable, and the rolling wheels of the lower suspension cable wheel group and the lower support wheel group to support the lower temporary tie rod cable.

[0014] The temporary tie cable installation system for low-position assembly of steel tube concrete arch ribs is simple in structure, efficient and practical; the two ends of the temporary tie cable are fixed on the two anchor points close to the ends of the large arch rib segment, and the temporary tie cable is arranged in upper and lower layers, and then the temporary tie cable is lowered from the large arch rib segment according to the arrangement rule between two adjacent vertical assembly brackets and between the lifting tower and the vertical assembly bracket, and the lower end of the temporary tie cable is suspended and installed by the cable support wheel group to support the upper and lower layers of temporary tie cables, and the bracket support wheel group fixed on the vertical assembly bracket is also used to support the upper and lower layers of temporary tie cables, thereby ensuring the smooth installation of the temporary tie cable and ensuring the safety and stability of the structure during the installation process, which is better than the force stability of using a single layer of temporary tie cable. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a schematic diagram of the connection arrangement of the temporary tie cable installation system for the low-position assembly of the steel tube concrete arch rib;

[0016] Figure 2 It is a structural schematic diagram of the sling supporting wheel assembly;

[0017] Figure 3 yes Figure 2 Schematic diagram of the left side;

[0018] Figure 4 This is the structural diagram of the bracket supporting wheel assembly;

[0019] The names corresponding to the numbers in the figure are:

[0020] 1. Large section of arch rib; 2. Vertical support; 3. Lifting tower; 4. Temporary tie rope; 5. Temporary tie to fix the steel strand sling; 6. Sling supporting wheel group; 61. Upper sling supporting wheel group; 62. Lower sling supporting wheel group; 7. Support supporting wheel group; 71. Upper support supporting wheel group; 72. Lower support supporting wheel group; 8. Rolling supporting wheel; 9. Roller; 10. Supporting wheel frame; 11. I-beam; 12. Channel steel; 13. Anchor. DETAILED DESCRIPTION

[0021] In order to describe the present technology more clearly, the present technology is further described in detail below with reference to the accompanying drawings and embodiments. Example

[0022] A temporary tie cable installation system for low-position assembly of steel tube concrete arch ribs, comprising a large arch rib segment 1, a vertical assembly bracket 2, a lifting tower 3, a temporary tie cable 4 and a temporary tie-fixing steel strand sling 5; the two ends of the large arch rib segment 1 pass through the lifting tower 3 respectively, and are supported by the lifting tower 3 to lift the lifting point; the bottom of the large arch rib segment 1 is connected to support a plurality of vertical assembly brackets 2 arranged at intervals; the two ends of the temporary tie cable 4 are fixed to the anchor points near the two ends of the large arch rib segment 1, and the temporary tie cable 4 is fixed to the anchor points near the two ends of the large arch rib segment 1. The rod cables 4 are arranged in two layers, upper and lower. The temporary tie-rod fixed steel strand sling cable 5 is lowered from the arch rib large section 1 according to the arrangement rule that one place is set in the center of each interval between two adjacent vertical brackets 2 and between the lifting tower 3 and the vertical bracket 2. The lower end of the temporary tie-rod fixed steel strand sling cable 5 is suspended with a sling wheel group 6, and the vertical bracket 2 is equipped with a bracket wheel group 7. The sling wheel group 6 and the bracket wheel group 7 are fixed at the design height position of the temporary tie-rod cable 4 and hold up the temporary tie-rod cable 4. The temporary tie-rod fixed steel strand sling cable 5 adopts Strand 1860 steel strand with a diameter of 15.2.

[0023] The sling cable supporting wheel group 6 includes an upper sling cable supporting wheel group 61 and a lower sling cable supporting wheel group 62, and the upper sling cable supporting wheel group 61 and the lower sling cable supporting wheel group 62 are fixedly installed on the temporary tie rod fixed steel strand sling 5 in an upper and lower structure; the upper sling cable supporting wheel group 61 and the lower sling cable supporting wheel group 62 respectively include a rolling supporting wheel 8, a roller 9, a supporting wheel frame 10 and an I-beam 11; the rolling supporting wheel 8 is rollingly installed on the roller 9, the roller 9 is installed on the supporting wheel frame 10, the supporting wheel frame 10 is welded on the I-beam 11, and the rolling supporting wheel 8 supports the temporary tie rod cable 4 for installation; the I-beam 11 and the temporary tie rod fixed steel strand sling 5 are fixed at the designed height position of supporting the temporary tie rod cable 4 in the form of a bolt connection anchor 13.

[0024] The upper parts of both sides of the supporting wheel frame 10 are respectively welded with outwardly extending channel steels 12, and the temporary tie rod fixing steel strand sling 5 passes through the channel steels 12 and then is connected to the I-beam 11.

[0025] The support wheel group 7 includes an upper support wheel group 71 and a lower support wheel group 72, and the upper support wheel group 71 and the lower support wheel group 72 are fixedly installed on the vertical support 2 in an upper and lower structure; the upper support wheel group 71 and the lower support wheel group 72 respectively include a rolling wheel 8, a roller 9, a wheel frame 10 and an I-beam 11; the rolling wheel 8 is rollingly installed on the roller 9, the roller 9 is installed on the wheel frame 10, the wheel frame 10 is welded on the I-beam 11, and the rolling wheel 8 supports the temporary tie rod 4 for installation; the I-beam 11 is welded to the vertical support 2 and fixed at the designed height position for supporting the temporary tie rod 4. The fixed position of the I-beam 11 enables the rolling wheel 8 of the upper suspension cable wheel group 61 and the upper support wheel group 71 to support the upper temporary tie rod 4, and the rolling wheel 8 of the lower suspension cable wheel group 62 and the lower support wheel group 72 to support the lower temporary tie rod 4.

[0026] The above description is not a limitation of the present application, and the present application is not limited to the above examples. Any changes, modifications, additions or substitutions made by ordinary technicians in this technical field within the essential scope of the present application should fall within the scope of protection of the present application.

Claims

1. A temporary tie-rod installation system for low-position assembly of steel tube concrete arch ribs, characterized in that: The invention comprises a large arch rib segment (1), a vertical assembly support (2), a lifting tower (3), a temporary tie rod cable (4) and a temporary tie rod fixing steel strand sling cable (5); the two ends of the large arch rib segment (1) respectively pass through the lifting tower (3) and are supported by the lifting tower (3) at a lifting point; the bottom of the large arch rib segment (1) is connected to support a plurality of vertical assembly supports (2) arranged at intervals; the two ends of the temporary tie rod cable (4) are fixed to two anchor points close to the end of the large arch rib segment (1), and the temporary tie rod cable (4) is arranged in two layers; The temporary tie-rod fixed steel strand sling (5) is lowered from the arch rib large section (1) according to the arrangement rule between two adjacent vertical support frames (2) and between the lifting tower (3) and the vertical support frame (2), with one sling being set in the center of each interval. A sling wheel assembly (6) is suspended and installed at the lower end of the temporary tie-rod fixed steel strand sling (5), and a support wheel assembly (7) is installed on the vertical support frame (2). The sling wheel assembly (6) and the support wheel assembly (7) are fixed at the designed height position of the temporary tie-rod rope (4) and support the temporary tie-rod rope (4).

2. The temporary tie-rod installation system for low-position assembly of steel tube concrete arch ribs according to claim 1 is characterized in that: The sling cable wheel assembly (6) comprises an upper sling cable wheel assembly (61) and a lower sling cable wheel assembly (62), the upper sling cable wheel assembly (61) and the lower sling cable wheel assembly (62) being fixedly mounted on a temporary tie rod fixed steel strand sling cable (5) in an upper and lower structure; the upper sling cable wheel assembly (61) and the lower sling cable wheel assembly (62) respectively comprise a rolling wheel (8), a roller (9), a wheel support (10) and an I-beam (11); the rolling wheel (8) is rollingly mounted on the roller (9), the roller (9) is mounted on the wheel support (10), the wheel support (10) is welded to the I-beam (11), and the rolling wheel (8) supports the temporary tie rod cable (4) for installation; the I-beam (11) and the temporary tie rod fixed steel strand sling cable (5) are fixed at a designed height position for supporting the temporary tie rod cable (4) in the form of a bolt connection anchor (13).

3. The temporary tie cable installation system for low-position assembly of steel tube concrete arch ribs according to claim 2 is characterized in that: Outwardly extending channel steels (12) are welded to the upper parts of both sides of the wheel support frame (10), and the temporary tie rod fixing steel strand sling (5) passes through the channel steels (12) and is then connected to the I-beam (11).

4. The temporary tie-rod installation system for low-position assembly of steel tube concrete arch ribs according to claim 1 is characterized in that: The support wheel assembly (7) comprises an upper support wheel assembly (71) and a lower support wheel assembly (72), the upper support wheel assembly (71) and the lower support wheel assembly (72) being fixedly mounted on the vertical support (2) in an upper and lower structure; the upper support wheel assembly (71) and the lower support wheel assembly (72) respectively comprise a rolling wheel (8), a roller (9), a wheel frame (10) and an I-beam (11); the rolling wheel (8) is rollingly mounted on the roller (9), the roller (9) is mounted on the wheel frame (10), the wheel frame (10) is welded to the I-beam (11), and the rolling wheel (8) supports the temporary tie rod (4) for installation; the I-beam (11) and the vertical support (2) are welded and fixed at a designed height position for supporting the temporary tie rod (4).