Bridge support replacing device
By designing the bridge support replacement device, the jacking mechanism and the stabilization mechanism are used to solve the problem of jack pressure concentration and slippage, the safety and stability of the replacement process are improved, and the jack and beam body structure is protected.
Patent Information
- Application Number
- CN202420542784.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-20
- Publication Date
- 2024-11-01
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
During the replacement of bridge support, the jack is subjected to concentrated pressure, which leads to easy damage, and there is a risk of slippage during the hoisting process, which is a high risk.
A bridge support replacement device is designed, including a hoisting mechanism and a stabilizing mechanism. By setting up a base, a roof, a jack, a hoisting telescopic column and an adjustable connecting rod and clamp, the contact area between the jack and the beam body is increased, and the contact area between the jack and the beam body is increased. Support capacity and fixing device through clamps and adjusting bolts to avoid slippage.
Effectively disperse the stress of the jack, protect the jack and beam body structure, improve the safety and stability of the bridge support replacement process, and facilitate movement and storage.
Smart Images

Figure CN221941154U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of bridges, and in particular to a bridge support replacement device. Background Art
[0002] The bridge bearing is an important structural component connecting the superstructure and substructure of the bridge. It is located between the bridge and the pad stone. It can reliably transmit the load, deformation displacement and rotation angle borne by the superstructure of the bridge to the substructure of the bridge. It is an important force transmission device of the bridge. In order to ensure the safety of the bridge, the bridge bearing needs to be replaced regularly, which requires the use of jacks to lift the superstructure of the bridge, so as to replace the bridge bearing between the superstructure and the substructure of the bridge.
[0003] At present, in the process of replacing the bearings, after the bridge is lifted up, the bearings are no longer subjected to stress, and all the force at the bearings is borne by the jacks. At this time, the lifting part of the jack is subjected to great stress. If the pressure on the jack cannot be dispersed and its stress area cannot be increased, it is easy to cause damage to the beam and the jack. At the same time, since the jacks are directly pressed against the box beam and the pier top caps, there is a great possibility of slippage during the lifting process, which is extremely dangerous.
[0004] In summary, there is an urgent need to design a bridge bearing replacement device that overcomes the above-mentioned problems. Utility Model Content
[0005] The utility model aims to provide a bridge bearing replacement device which overcomes the above problems.
[0006] In order to achieve the above purpose, the technical solution adopted by the utility model is: a bridge bearing replacement device, comprising:
[0007] A lifting mechanism, comprising a base, a top plate, and a jack and a lifting telescopic column arranged between the base and the top plate, wherein the lifting telescopic columns are evenly arranged on both sides of the jack, and a fastening assembly is also provided on the lifting telescopic column;
[0008] The stabilizing mechanism comprises connecting rods respectively arranged on both sides of the base and a clamping block arranged at one end of the connecting rod away from the base, wherein the connecting rod is an adjustable telescopic rod.
[0009] The purpose of the utility model and the solution to its technical problems can also be further achieved by adopting the following technical measures.
[0010] Furthermore, the lifting telescopic column comprises a first sleeve and a first sleeve rod slidably sleeved inside the upper end of the first sleeve, the lower end outer wall of the first sleeve rod is provided with a first external thread, and the upper end outer wall of the first sleeve is provided with a second external thread;
[0011] The fastening assembly includes a cap disposed on the first sleeve rod, a first internal thread matching the first external thread is provided in the middle of the top wall of the cap, and a second internal thread matching the second external thread is provided on the inner side wall of the cap.
[0012] Furthermore, the outer wall of the cap is provided with anti-slip grooves.
[0013] Furthermore, the connecting rod includes a second sleeve connected to the base and a second sleeve rod slidably sleeved inside the other end of the second sleeve, and a fastening bolt is penetrated through the side wall of the second sleeve at one end away from the base.
[0014] Furthermore, an adjusting bolt is threadedly penetrated on one side of the clamping block away from the connecting rod, and a tightening block is provided on one side of the clamping block close to the connecting rod. One end of the tightening block close to the adjusting bolt is rotatably connected to the adjusting bolt.
[0015] Furthermore, a columnar block is provided at the end of the adjusting bolt, and a convex groove matching the columnar block and the end of the adjusting bolt is formed at one end of the tightening block close to the adjusting bolt.
[0016] Furthermore, anti-slip teeth are provided on one side of the tightening block close to the connecting rod.
[0017] Furthermore, connecting ears are fixedly provided on the base on both sides of the connecting rod, and the connecting ears are rotatably connected to the connecting rod through a rotating shaft. The outer wall of the rotating shaft is also sleeved with a torque spring, and the two ends of the torque spring are fixedly connected to the base and the connecting rod respectively.
[0018] Furthermore, threaded blind holes are respectively opened on both sides of the top plate, fixing bolts are threadedly connected to the threaded blind holes, and threaded holes matching the fixing bolts are provided on the connecting rod.
[0019] Furthermore, the top plate and the base are both of the same shape.
[0020] Compared with the prior art, the beneficial effects of the utility model are:
[0021] 1. The utility model provides a bridge support replacement device, which is provided with a base, a top plate, a jack and a lifting telescopic column. The top plate can increase the contact area between the jack and the beam body, and the lifting telescopic column and the fastening components on the lifting telescopic column can enhance the supporting capacity of the jack, so that the force on the lifting part of the jack can be effectively dispersed, which can effectively protect the jack and the beam structure and avoid damage to the beam body and the jack.
[0022] 2. The utility model provides a bridge bearing replacement device, which is provided with connecting rods and clamping blocks on both sides of the base, wherein the connecting rods are adjustable telescopic rods. When the bearing needs to be replaced, the device is placed on the pier, and then the length of the connecting rods is adjusted to clamp the clamping blocks on both sides of the pier respectively, thereby fixing the jacking mechanism in the device. When the jacking mechanism is in the jacking process, it can effectively prevent it from slipping on the box girder and the pier top cap, making the device more stable when used, and effectively improving the safety during the bridge bearing replacement process.
[0023] 3. The utility model provides a bridge support replacement device, which is connected to the base by rotating the connecting rod, so that the position of the connecting rod can be adjusted according to needs. When the stabilizing mechanism needs to be used, the fixing bolt is unscrewed, the connecting rod is rotated to make it horizontal, and then the clamping blocks are clamped on both sides of the pier; when it is not needed, the connecting rod automatically becomes vertical under the action of the torque spring and fits with the side wall of the top plate, and it can be fixed to the side wall of the top plate by fixing bolts, which makes it easy to move and store the device, thereby improving the practicality of the device. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 It is a schematic diagram of the overall structure of the bridge bearing replacement device provided by the utility model;
[0025] Figure 2 It is a cross-sectional schematic diagram of a stabilizing mechanism in an embodiment of the utility model;
[0026] Figure 3 It is a cross-sectional schematic diagram of a lifting telescopic column and a fastening assembly in an embodiment of the utility model;
[0027] Description of reference numerals:
[0028] 1. Lifting mechanism; 11. Base; 12. Top plate; 121. Threaded blind hole; 122. Fixing bolt; 123. Rubber anti-skid pad; 13. Jack; 14. Lifting telescopic column; 141. First sleeve; 142. First set of rods; 143. First external thread; 144. Second external thread; 15. Fastening assembly; 151. Cover cap; 152. First internal thread; 153. Second internal thread; 154. Anti-skid pattern; 16. Connecting ear; 17. Rotating shaft; 18. Torque spring;
[0029] 2. Stabilizing mechanism; 21. Connecting rod; 211. Second sleeve; 212. Second sleeve rod; 213. Fastening bolt; 214. Threaded hole; 22. Clamping block; 23. Adjusting bolt; 24. Tightening block; 241. Convex groove; 242. Anti-skid teeth; 25. Columnar block. DETAILED DESCRIPTION
[0030] In order to make the purpose, technical solution and advantages of the utility model more clear, the utility model is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the utility model and are not used to limit the utility model.
[0031] See also Figures 1 to 3 , a bridge bearing replacement device, comprising:
[0032] The jacking mechanism 1 comprises a base 11, a top plate 12, and a jack 13 and a jacking telescopic column 14 arranged between the base 11 and the top plate 12. The jacking telescopic column 14 is evenly arranged on both sides of the jack 13. The jacking telescopic column 14 is also provided with a fastening assembly 15. When the jack 13 jacks up the bridge, the fastening assembly 15 can fix the jacking telescopic column 14 so that its height does not change, thereby improving its supporting performance. The contact area between the jack 13 and the beam body can be increased by the top plate 12, and the supporting capacity of the jack 13 can be improved by the jacking telescopic column 14 and the fastening assembly 15 on the jacking telescopic column 14, so that the force of the jacking part of the jack 13 is effectively dispersed, which can effectively protect the jack 13 and the beam structure and avoid damage to the beam body and the jack 13.
[0033] The stabilizing mechanism 2 comprises connecting rods 21 respectively arranged on both sides of the base 11 and a clamping block 22 arranged at one end of the connecting rod 21 away from the base 11. The connecting rod 21 is an adjustable telescopic rod.
[0034] When the bridge bearing needs to be replaced, the device is placed on the pier, and then the length of the connecting rod 21 is adjusted so that the clamping blocks 22 are clamped on both sides of the pier respectively, thereby fixing the jacking mechanism 1 in the device. When the jacking mechanism 1 is in the jacking process, it can effectively prevent it from slipping on the box girder and the pier top cap, making the device more stable when used, and effectively improving the safety during the replacement of the bridge bearing.
[0035] Preferably, the lifting telescopic column 14 includes a first sleeve 141 and a first sleeve rod 142 slidably sleeved inside the upper end of the first sleeve 141, the lower end outer wall of the first sleeve rod 142 is provided with a first external thread 143, and the upper end outer wall of the first sleeve 141 is provided with a second external thread 144;
[0036] The fastening assembly 15 includes a set of caps 151 arranged on the first sleeve rod 142, a first internal thread 152 matching the first external thread 143 is provided in the middle of the top wall of the cap 151, and a second internal thread 153 matching the second external thread 144 is provided on the inner side wall of the cap 151. In the process of lifting the bridge by the jacking mechanism, the cap 151 is only screwed on the first sleeve rod 142, and is not connected to the first sleeve 141, which does not affect the jacking operation of the jack 13. After the jack 13 props up the bridge, the cap 151 is screwed downward on the first sleeve rod 142 and connected to the first sleeve 141, ensuring that the first sleeve rod 142 is no longer telescopic, thereby improving the supporting performance of the jacking telescopic column, making it more stable, and effectively dispersing the force of the jack 13.
[0037] For ease of operation, the outer wall of the cap 151 is provided with anti-slip grooves 154 .
[0038] Preferably, the connecting rod 21 includes a second sleeve 211 connected to the base 11 and a second sleeve rod 212 slidably sleeved inside the other end of the second sleeve 211, and a fastening bolt 213 is penetrated through the side wall of the second sleeve 211 at one end away from the base 11. The length of the connecting rod 21 is adjustable, which is not only convenient for clamping by the clamping block 22, but also suitable for bridges of different widths, thereby improving the practicality of the device.
[0039] Preferably, in order to make the clamping block 22 clamp more tightly on both sides of the pier and facilitate operation, an adjusting bolt 23 is threadedly penetrated on the side of the clamping block 22 away from the connecting rod 21, and a tightening block 24 is provided on the side of the clamping block 22 close to the connecting rod 21, and the end of the tightening block 24 close to the adjusting bolt 23 is rotatably connected to the adjusting bolt 23.
[0040] Preferably, a columnar block 25 is provided at the end of the adjusting bolt 23 , and a convex groove 241 matching the columnar block 25 and the end of the adjusting bolt 23 is formed at one end of the tightening block 24 close to the adjusting bolt 23 .
[0041] In order to increase the friction between the tightening block 24 and the bridge pier, an anti-slip tooth 242 is provided on one side of the tightening block 24 close to the connecting rod 21 .
[0042] Preferably, connecting ears 16 are fixedly provided on the base 11 on both sides of the connecting rod 21, and the connecting ears 16 are rotatably connected to the connecting rod 21 through a rotating shaft 17. The outer wall of the rotating shaft 17 is also sleeved with a torque spring 18, and the two ends of the torque spring 18 are fixedly connected to the base 11 and the connecting rod 21 respectively.
[0043] Preferably, threaded blind holes 121 are respectively formed on both sides of the top plate 12, a fixing bolt 122 is threadedly connected to the threaded blind hole 121, and a threaded hole 214 matching the fixing bolt 122 is provided on the connecting rod 21.
[0044] Specifically, when the stabilizing mechanism 2 needs to be used, the fixing bolt 122 is unscrewed, the connecting rod 21 is rotated to a horizontal state, and then the clamping blocks 22 are clamped on both sides of the bridge pier; when not in use, the connecting rod 21 automatically assumes a vertical state and fits against the side wall of the top plate 12 under the action of the torsion spring 18, and it can be fixed to the side wall of the top plate 12 through the fixing bolt 122, which is convenient for moving and storing the device and improves the practicability of the device.
[0045] Preferably, both the top plate 12 and the base 11 are in the shape of a U-shaped with the same shape. The opening of the U-shaped facilitates surrounding the顶升机构 on both sides of the bridge bearing and also facilitates removing the old bridge bearing from the opening or inserting a new bridge bearing through the opening.
[0046] Preferably, a rubber anti-slip pad 123 is provided on the top plate 12, which can prevent slipping and also contact the bottom surface of the beam body with an inclination.
[0047] The above describes the present utility model in further detail with reference to the embodiments, but the present utility model is not limited to the above embodiments. Within the scope of knowledge possessed by those of ordinary skill in the art, various changes can be made without departing from the gist of the present utility model. It should be noted that there is an unclear expression "顶升机构" in the original text which is retained as it is in the translation. You may need to check and correct it according to the actual content.
Claims
1. A bridge bearing replacement device, characterized in that: include: A lifting mechanism (1) comprises a base (11), a top plate (12), and a jack (13) and a lifting telescopic column (14) arranged between the base (11) and the top plate (12); the lifting telescopic column (14) is evenly arranged on both sides of the jack (13); and a fastening assembly (15) is also provided on the lifting telescopic column (14); The stabilizing mechanism (2) comprises connecting rods (21) respectively arranged on both sides of the base (11) and a clamping block (22) arranged at one end of the connecting rod (21) away from the base (11); the connecting rod (21) is an adjustable telescopic rod.
2. A bridge bearing replacement device according to claim 1, characterized in that: The lifting telescopic column (14) comprises a first sleeve (141) and a first sleeve rod (142) slidably sleeved inside the upper end of the first sleeve (141); the outer wall of the lower end of the first sleeve rod (142) is provided with a first external thread (143); and the outer wall of the upper end of the first sleeve (141) is provided with a second external thread (144); The fastening assembly (15) comprises a cover cap (151) arranged on the first sleeve rod (142), a first internal thread (152) matching the first external thread (143) being provided in the middle of the top wall of the cover cap (151), and a second internal thread (153) matching the second external thread (144) being provided on the inner side wall of the cover cap (151).
3. A bridge bearing replacement device according to claim 2, characterized in that: The outer wall of the cover cap (151) is provided with anti-slip grooves (154).
4. A bridge bearing replacement device according to claim 1, characterized in that: The connecting rod (21) comprises a second sleeve (211) connected to the base (11) and a second sleeve rod (212) slidably sleeved inside the other end of the second sleeve (211), and a fastening bolt (213) is penetrated through the side wall of the second sleeve (211) at one end away from the base (11).
5. A bridge bearing replacement device according to claim 1 or 4, characterized in that: An adjusting bolt (23) is threadedly penetrated on one side of the clamping block (22) away from the connecting rod (21), and a tightening block (24) is provided on one side of the clamping block (22) close to the connecting rod (21). One end of the tightening block (24) close to the adjusting bolt (23) is rotatably connected to the adjusting bolt (23).
6. A bridge bearing replacement device according to claim 5, characterized in that: A columnar block (25) is provided at the end of the adjusting bolt (23), and a convex groove (241) matching the columnar block (25) and the end of the adjusting bolt (23) is provided at one end of the tightening block (24) close to the adjusting bolt (23).
7. A bridge bearing replacement device according to claim 6, characterized in that: The side of the tightening block (24) close to the connecting rod (21) is provided with anti-slip teeth (242).
8. A bridge bearing replacement device according to claim 1 or 4, characterized in that: Connecting ears (16) are fixedly provided on the base (11) at both sides of the connecting rod (21), and the connecting ears (16) are rotatably connected to the connecting rod (21) via a rotating shaft (17). A torque spring (18) is also sleeved on the outer wall of the rotating shaft (17), and two ends of the torque spring (18) are fixedly connected to the base (11) and the connecting rod (21) respectively.
9. A bridge bearing replacement device according to claim 8, characterized in that: Threaded blind holes (121) are respectively provided on both sides of the top plate (12), fixing bolts (122) are threadedly connected to the threaded blind holes (121), and threaded holes (214) matching the fixing bolts (122) are provided on the connecting rod (21).
10. The bridge bearing replacement device according to claim 1, characterized in that: The top plate (12) and the base (11) are both of the same shape.