In the construction of cast-in piles, the pile top elevation is often higher than the design elevation, and the concrete pile heads that exceed the design elevation need to be chiseled. It is difficult to chisel piles, time-consuming and the piles are uneven.
Design a pre-cracking device for concrete pile heads in buildings, including pre-cracking mechanisms, which uses sleeves, air intake pipes, pressure cylinders and piston rods to push the piston rods into a longitudinal star cavity through high-pressure gas, so as to facilitate the removal of invalid pile heads and broken.
The rapid removal and breaking of invalid pile heads into multiple pieces is achieved, which is easy to clean and improves construction efficiency and flatness.
Smart Images

Figure CN221941309U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of pile foundation engineering, in particular to a pre-cracking device for a concrete pile head of a building. Background Art
[0002] As an important pile foundation structure, cast-in-place piles are widely used in foundation engineering. However, since cast-in-place piles are poured with concrete in the formed pile holes, in order to avoid the influence of factors such as sediment at the bottom of the pile hole and soil particles falling during the pouring process on the concrete strength of the pile body, during the construction of cast-in-place piles, the pile top elevation is often 0.5-1.0m higher than the design elevation. Therefore, after the concrete pile body is formed, it is necessary to chisel out the pile head that exceeds the design elevation. For invalid concrete pile heads that exceed the design elevation, electric picks, breaker hammers, hydraulic pile chiseling equipment and other related pile chiseling equipment are often used to chisel out the pile heads at this stage. Pile chiseling is difficult and time-consuming, and the pile chiseling surface is uneven after chiseling. Utility Model Content
[0003] The utility model aims to provide a building concrete pile head pre-splitting device, which can produce a star-shaped cavity in the longitudinal section inside the invalid pile head, so as to facilitate the removal of the invalid pile head and break it into multiple pieces for easy cleaning.
[0004] To achieve the above-mentioned purpose, a building concrete pile head pre-cracking device is provided, comprising: an invalid pile head and a pile foundation, wherein the invalid pile head is arranged at the upper end of the pile foundation, a plurality of longitudinal steel bars are arranged in the pile foundation, and the longitudinal steel bars extend into the invalid pile head, a pre-cracking mechanism is placed in the middle of the invalid pile head, and the pre-cracking mechanism is located at the bottom of the invalid pile head; the pre-cracking mechanism comprises a sleeve, an air intake pipe, a pressure cylinder and a piston rod, and a plurality of sleeves are provided, the pressure cylinder is placed in the middle of the invalid pile head, and the pressure cylinder is located at the lower end of the invalid pile head, a plurality of the sleeves are fixedly connected to the outer end of the pressure cylinder at equal distances and communicated with the pressure cylinder, and the cross-section of the sleeve and the pressure cylinder is star-shaped, the piston rod is arranged at one end of the sleeve, and the piston rod is away from the pressure cylinder, one end of the piston rod extends into the sleeve and is slidably connected with the sleeve, the air intake pipe is fixedly connected to the outer end of the pressure cylinder, and the air intake pipe is communicated with the pressure cylinder, and one end of the air intake pipe passes through the invalid pile head and extends to the outside of the invalid pile head. A cavity with a star-shaped longitudinal section can be manufactured inside the invalid pile head, which is convenient for dismantling the invalid pile head and breaking it into multiple pieces for easy cleaning.
[0005] According to the building concrete pile head pre-splitting device, a lifting rod is fixedly connected to the middle of the upper end of the pre-splitting mechanism, and the upper end of the lifting rod passes through the invalid pile head and extends to above the invalid pile head, and a handle is fixedly connected to the upper end of the lifting rod, which is used to manually assist in fixing the pre-splitting mechanism to prevent the pre-splitting mechanism from tilting.
[0006] According to the building concrete pile head pre-cracking device, the length of the lifting rod is 0.5m-1.0m, which is convenient for placing the pre-cracking mechanism at the bottom of the invalid pile head.
[0007] According to the device for pre-cracking concrete pile heads of buildings, a sealing ring is fixedly connected to the inner wall of the sleeve, and the sealing ring is away from the pressure cylinder, and the piston rod passes through the middle of the sealing ring and is slidably connected to the inner wall of the sealing ring, thereby improving the sealing performance between the sleeve and the piston rod.
[0008] According to the device for pre-cracking concrete pile heads of buildings, a blade is provided at one end of the piston rod away from the pressure cylinder, and a rounded corner is provided at the blade, so as to reduce the resistance encountered by the piston rod when it moves in the ineffective pile head.
[0009] According to the building concrete pile head pre-cracking device, the sleeve and the piston rod are made of stainless steel, which improves the structural strength and wear resistance and prolongs the service life of the device.
[0010] The beneficial effects of the utility model are as follows: high-pressure gas is input into the pressure cylinder through the air intake pipe, the pressure is used to push the piston rod out of the sleeve, and then the air in the pressure cylinder is extracted through the air intake pipe to form a negative pressure environment. After the piston rod is reset, multiple longitudinal cavities are formed in the invalid pile head, which is convenient for dismantling the invalid pile head and breaking it into multiple pieces for easy cleaning.
[0011] Additional aspects and advantages of the present invention will be given in part in the following description, and in part will become apparent from the following description, or will be learned through the practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] The utility model is further described below in conjunction with the accompanying drawings and embodiments;
[0013] Figure 1 This is a three-dimensional structural diagram of a building concrete pile head pre-cracking device of the utility model;
[0014] Figure 2 This is a cross-sectional structural diagram of a building concrete pile head pre-cracking device of the utility model;
[0015] Figure 3 It is a three-dimensional structural diagram of a pre-splitting mechanism of a building concrete pile head pre-splitting device of the utility model;
[0016] Figure 4 for Figure 3 Enlarged structural diagram of point A in the middle.
[0017] Legend:
[0018] 1. Handle; 2. Invalid pile head; 3. Pile foundation; 4. Lifting rod; 5. Pre-splitting mechanism; 6. Sleeve; 7. Inlet pipe; 8. Pressure cylinder; 9. Piston rod; 10. Sealing ring. DETAILED DESCRIPTION
[0019] This section will describe in detail the specific embodiments of the utility model. The preferred embodiments of the utility model are shown in the accompanying drawings. The purpose of the accompanying drawings is to supplement the description of the text part of the specification with graphics, so that people can intuitively and vividly understand each technical feature and the overall technical solution of the utility model, but it cannot be understood as a limitation on the protection scope of the utility model.
[0020] Reference Figure 1-4 The utility model embodiment is a building concrete pile head pre-splitting device, which includes: an invalid pile head 2 and a pile foundation 3, the invalid pile head 2 is arranged at the upper end of the pile foundation 3, a plurality of longitudinal steel bars are arranged in the pile foundation 3, and the longitudinal steel bars extend into the invalid pile head 2, a pre-splitting mechanism 5 is placed in the middle of the invalid pile head 2, and the pre-splitting mechanism 5 is located at the bottom of the invalid pile head 2; the pre-splitting mechanism 5 includes a sleeve 6, an air inlet pipe 7, a pressure cylinder 8 and a piston rod 9, and the sleeve 6 is provided with a plurality of them, the pressure cylinder 8 is placed in the middle of the invalid pile head 2, and the pressure The pressure cylinder 8 is located at the lower end of the invalid pile head 2, and several sleeves 6 are equidistantly fixedly connected to the outer end of the pressure cylinder 8 and communicated with the pressure cylinder 8, and the cross-section of the sleeve 6 and the pressure cylinder 8 is star-shaped. The piston rod 9 is arranged at one end of the sleeve 6, and the piston rod 9 is away from the pressure cylinder 8. One end of the piston rod 9 extends into the sleeve 6 and is slidably connected to the sleeve 6. The air intake pipe 7 is fixedly connected to the outer end of the pressure cylinder 8, and the air intake pipe 7 is communicated with the pressure cylinder 8. One end of the air intake pipe 7 passes through the invalid pile head 2 and extends to the outside of the invalid pile head 2.
[0021] A lifting rod 4 is fixedly connected to the middle of the upper end of the pre-splitting mechanism 5 , and the upper end of the lifting rod 4 passes through the invalid pile head 2 and extends to above the invalid pile head 2 , and the upper end of the lifting rod 4 is fixedly connected to the handle 1 .
[0022] The length of the lifting rod 4 is 0.5m-1.0m.
[0023] A sealing ring 10 is fixedly connected to the inner wall of the sleeve 6 , and the sealing ring 10 is away from the pressure cylinder 8 . The piston rod 9 passes through the middle of the sealing ring 10 and is slidably connected to the inner wall of the sealing ring 10 .
[0024] A blade is arranged at one end of the piston rod 9 away from the pressure cylinder 8, and a rounded corner is arranged at the blade.
[0025] The sleeve 6 and the piston rod 9 are made of stainless steel.
[0026] Working principle: When in use, hold the handle 1 to place the pre-splitting mechanism 5 on the upper end of the pile foundation 3, and then cast the invalid pile head 2. After the casting is completed, high-pressure gas is injected into the pressure cylinder 8 through the air inlet pipe 7. The high-pressure gas pushes the piston rod 9 to extend out of the sleeve 6 and extend into the invalid pile head 2. Then, the gas in the pressure cylinder 8 is extracted through the air inlet pipe 7, so that negative pressure is formed in the pressure cylinder 8, so that the piston rod 9 returns to the sleeve 6 and resets, thereby forming multiple longitudinal cavities in the invalid pile head 2.
[0027] The embodiments of the present invention are described in detail above in conjunction with the accompanying drawings, but the present invention is not limited to the above embodiments. Various changes can be made within the knowledge scope of ordinary technicians in the technical field without departing from the purpose of the present invention.
Claims
1. A building concrete pile head pre-cracking device, characterized in that: include: An invalid pile head (2) and a pile foundation (3), wherein the invalid pile head (2) is arranged at the upper end of the pile foundation (3), a plurality of longitudinal steel bars are arranged in the pile foundation (3), and the longitudinal steel bars extend into the invalid pile head (2), a pre-splitting mechanism (5) is arranged in the middle of the invalid pile head (2), and the pre-splitting mechanism (5) is located at the bottom of the invalid pile head (2); the pre-splitting mechanism (5) comprises a sleeve (6), an air intake pipe (7), a pressure cylinder (8) and a piston rod (9), and a plurality of sleeves (6) are arranged, the pressure cylinder (8) is arranged in the middle of the invalid pile head (2), and the pressure cylinder (8) is located at the lower end of the invalid pile head (2), A plurality of sleeves (6) are fixedly connected to the outer end of the pressure cylinder (8) at equal distances and are connected to the inside of the pressure cylinder (8), and the cross-section of the sleeve (6) and the pressure cylinder (8) is star-shaped. The piston rod (9) is arranged at one end of the sleeve (6), and the piston rod (9) is away from the pressure cylinder (8). One end of the piston rod (9) extends into the sleeve (6) and is slidably connected to the sleeve (6). The air intake pipe (7) is fixedly connected to the outer end of the pressure cylinder (8), and the air intake pipe (7) is connected to the pressure cylinder (8). One end of the air intake pipe (7) passes through the invalid pile head (2) and extends to the outside of the invalid pile head (2).
2. A building concrete pile head pre-splitting device according to claim 1, characterized in that: A lifting rod (4) is fixedly connected to the middle of the upper end of the pre-splitting mechanism (5), and the upper end of the lifting rod (4) passes through the invalid pile head (2) and extends to above the invalid pile head (2), and the upper end of the lifting rod (4) is fixedly connected to a handle (1).
3. A building concrete pile head pre-splitting device according to claim 2, characterized in that: The length of the lifting rod (4) is 0.5m-1.0m.
4. A building concrete pile head pre-splitting device according to claim 1, characterized in that: A sealing ring (10) is fixedly connected to the inner wall of the sleeve (6), and the sealing ring (10) is away from the pressure cylinder (8). The piston rod (9) passes through the middle of the sealing ring (10) and is slidably connected to the inner wall of the sealing ring (10).
5. A building concrete pile head pre-splitting device according to claim 1, characterized in that: A blade is arranged at one end of the piston rod (9) away from the pressure cylinder (8), and a rounded corner is arranged at the blade.
6. A building concrete pile head pre-splitting device according to claim 1, characterized in that: The sleeve (6) and the piston rod (9) are made of stainless steel.