Anti-deviation auxiliary device for pile foundation construction for foundation engineering

By designing pile foundation construction anti-offset auxiliary devices for supporting frames, limit rods, guide frames and other components, the problem of inconvenient change in pile foundation installation direction in the existing technology is solved, rapid disassembly and fine adjustment is achieved, and construction is improved efficiency.

CN221941341UInactive Publication Date: 2024-11-01HEBEI SHIDA CONSTR GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420567198.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-22
Publication Date
2024-11-01
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing anti-offset pile foundation construction device is inconvenient when changing the pile foundation installation direction, and it is necessary to loosen the movable plate and adjust the overall position.

Method used

A pile foundation construction anti-offset auxiliary device including support frame, limit rod, guide frame, slide chute, adjustment frame, deviation correction frame and hoisting ring is designed, and the limit disassembly and assembly mechanism, auxiliary anti-offset mechanism and direction adjustment are adjusted. mechanism to realize rapid disassembly, correct deviation and direction adjustment.

Benefits of technology

It improves the flexibility and precision of the pile foundation installation direction, simplifies the installation and deviation correction process of the pile foundation, and improves construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221941341U_ABST
    Figure CN221941341U_ABST
Patent Text Reader

Abstract

The utility model discloses a pile foundation construction anti-deviation auxiliary device for foundation engineering, which belongs to the technical field of pile foundations and comprises a support frame, a plurality of limit rods, guide frames, chutes C, an adjusting frame, a deviation rectifying frame and a hanging ring, the limit rods are fixedly mounted below the support frame and are equidistantly arranged in a surrounding manner, the guide frames are arranged on two sides above the limit rods, and the chutes C are arranged on the guide frames. Sliding grooves C are oppositely embedded in the sides of the guide frames, and adjusting frames are slidably arranged on the sides of the interiors of the sliding grooves C. The hydraulic rods B are controlled to contract the deviation rectifying plates, so that the four deviation rectifying plates are in extrusion contact with the front side and the rear side of the square precast pile foundation respectively, the square precast pile foundation is subjected to complete deviation rectifying treatment, and after the square precast pile foundation horizontally and slowly descends into a foundation pit, a worker pours concrete into the foundation pit; and other supporting frames and guide frames are used in the same mode to conduct auxiliary deviation correction on construction of the remaining prefabricated square pile foundations, the stable deviation prevention effect on the prefabricated square pile foundations is improved, and the deviation correction efficiency of the prefabricated square pile foundations is higher.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of pile foundations, in particular to a pile foundation construction anti-deviating auxiliary device for foundation engineering. Background Art

[0002] Pile foundation is the use of piles to transfer all or part of the weight of the building to the deeper part of the foundation soil layer to bear the weight of the building. It is composed of foundation piles and a cap connected to the top of the piles. Precast piles are piles pre-made in a factory or construction site, and then driven or pressed into the soil using equipment such as pile drivers. Cast-in-place piles are made by digging holes in the foundation directly at the construction site through drilling or other methods, and then pouring concrete and other materials into the holes, and then forming piles after they solidify.

[0003] Among them, after searching, it was found that the application number is CN202023059162.2, an anti-deviating pile foundation construction device, which has the function of adjusting the angle of the support rod by adjusting the screw rod to drive the screw rod ring to move, so as to facilitate the propping up of the movable plate for subsequent pile foundation construction, and when adjusting the movable plate, under the elastic action of the elastic pull rope, it can avoid the single movable plate from tipping over after being adjusted to a certain angle, thereby preventing the normal use of the equipment from being affected, and at the same time avoiding affecting the efficiency of the pile foundation construction; among them, the shortcomings are as follows:

[0004] When the staff needs to use this kind of anti-drift pile foundation construction device to carry out anti-drift treatment on the constructed pile foundation, the adjusting screw rod drives the screw rod ring to move to adjust the angle of the support rod, and the movable plate is propped up under the elastic action of the elastic pull rope to avoid tilting of the single movable plate when adjusted to a certain angle, and the constructed pile foundation is supported to prevent drift. When the pile foundation is carried out anti-drift treatment, since the position of the fixed top plate is fixed and cannot be rotated, when the staff needs to adjust the installation direction of the pile foundation, they need to loosen the movable plate and change the position of the whole to change the installation direction of the pile foundation, which makes this kind of anti-drift pile foundation construction device slightly inconvenient to change the installation direction of the pile foundation. Utility Model Content

[0005] The purpose of the utility model is to provide an anti-deviation auxiliary device for pile foundation construction for foundation engineering in order to solve the problem that the above-mentioned anti-deviation pile foundation construction device is slightly inconvenient when the installation direction of the pile foundation is changed.

[0006] The technical scheme adopted by the utility model is as follows: an anti-deviation auxiliary device for pile foundation construction for foundation engineering, comprising a support frame, a limit rod, a guide frame, a slide groove C, an adjustment frame, a deviation correction frame and a lifting ring, a limit rod is fixedly installed under the support frame, there are several limit rods, and they are equidistantly arranged around, guide frames are arranged on both sides above the limit rod, the guide frame is relatively embedded with slide grooves C on the side, the adjustment frame is slidingly arranged inside the slide groove C, the adjustment frame is relatively rotated on the side of the adjustment frame through a rotating shaft, a lifting ring is fixedly installed above the guide frame, and a limit disassembly and assembly mechanism for convenient disassembly and assembly is arranged under the guide frame, an auxiliary anti-deviation mechanism for quickly correcting the deviation of a square pile foundation is arranged on the outside of the deviation correction frame, and a direction adjustment mechanism for conveniently changing the installation direction of the square pile foundation is arranged on the outside of the guide frame.

[0007] Among them, the limit disassembly and assembly mechanism is composed of a slide groove A, a sliding frame, a roller, a limit groove, an installation groove, a slide groove B and a limit card frame. The slide groove A is embedded on the top of the support frame, and the slide groove A is set in a ring shape. Sliding frames are slidably arranged on both sides above the inside of the slide groove A through sliders, and rollers are rotatably arranged on the front and back sides of the bottom of the sliding frame through bearings. The limit groove is embedded on the side of the sliding frame, and the limit groove is set in an "L" shape. The installation groove is embedded under the guide frame, and the installation groove fits and slides above the outside of the sliding frame. The slide groove B is embedded on the side of the guide frame near the side of the installation groove. A limit card frame is slidably arranged between the slide groove B and the inner side of the limit groove, and the limit card frame is set in an "L" shape.

[0008] Among them, the auxiliary anti-deviation mechanism is composed of a hydraulic rod A, a guide roller, a protrusion, a silk thread, a horizontal cone, a hydraulic rod B and a correction plate. The hydraulic rod A is fixedly installed between the inner wall side of the adjustment frame and the inner wall side of the slide groove C. A guide roller is rotatably arranged on the side of the correction frame through a bearing. There are several guide rollers, which are arranged in parallel at equal distances, and the outer surface material of the guide roller is butadiene rubber. A protrusion is fixedly installed on the top of the correction frame near the top of the adjustment frame, and the protrusion is arranged in a cone shape. A silk thread is fixedly installed on the top of the correction frame near the top of the protrusion, and a horizontal cone is fixedly installed below the end of the silk thread. Hydraulic rods B are fixedly installed relatively to each other at the front and rear of the correction frame, and a correction plate is fixedly installed between the ends of the two parallel hydraulic rods B.

[0009] Among them, the direction adjustment mechanism is composed of a groove, teeth, a servo motor, a gear, a dial and a magnetic needle. A groove is embedded on the top of the support frame, and the groove is arranged in a ring shape. Teeth are fixedly installed below the inner wall of the groove. There are several teeth, which are arranged equidistantly in a trapezoidal shape. A servo motor is fixedly installed on the side of the inner wall of the guide frame. The servo motor is connected to a gear through an output shaft, and the gear and the several teeth are arranged in a bite transmission. A dial is fixedly installed on the top of the guide frame near the side of the hanging ring, and a magnetic needle is rotatably arranged on the top of the guide frame near the middle of the dial through a bearing, and there is a one-millimeter interval between the bottom of the magnetic needle and the top of the dial.

[0010] In summary, due to the adoption of the above technical solution, the beneficial effects of the utility model are:

[0011] 1. This kind of pile foundation construction anti-deviation auxiliary device for foundation engineering is provided with a limited disassembly and assembly mechanism, which enables the staff to cooperate between the slide groove A, the sliding frame, the roller, the limit groove, the installation groove, the slide groove B and the limit bracket, and utilizes the limit bracket to freely slide and limit between the slide groove B and the inner side of the limit groove, so as to facilitate the staff to quickly disassemble and assemble the guide frame.

[0012] 2. The auxiliary device for pile foundation construction anti-deviation of this type of foundation engineering is provided with an auxiliary anti-deviation mechanism, which enables the staff to coordinate the hydraulic rod A, guide rollers, bumps, wires, horizontal cones, hydraulic rods B and the correction plate, and use the correction frame to rotate through the rotating shaft to make several guide rollers on the side of the correction frame completely squeeze and contact the surfaces on both sides of the square prefabricated pile foundation. At the same time, one hydraulic rod A is controlled to extend and the other hydraulic rod A is contracted to slide the adjustment frame inside the slide groove C, pushing the suspended square prefabricated pile foundation to adjust the falling position. Whether the horizontal cone of the wire swings relative to the bump is improved to improve the effect of stabilizing and preventing the prefabricated square pile foundation from deflection, and the correction efficiency of the prefabricated square pile foundation is higher.

[0013] 3. The pile foundation construction anti-deviating auxiliary device for this type of foundation engineering is provided with a direction adjustment mechanism, which enables the staff to coordinate the grooves, teeth, servo motors, gears, dials and magnetic needles, and utilize the gears and a number of teeth to engage in transmission, so as to drive the guide frame to move inside the slide groove A through the rollers below the sliding frame, and drive the guide frame to push the square precast pile to rotate above the support frame. The magnetic needle rotates above the dial through the bearing, which facilitates the staff to quickly and finely adjust the burying direction of the precast pile. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 This is a schematic diagram of the front view of the three-dimensional structure of the anti-deviation auxiliary device of the utility model;

[0015] Figure 2This is a schematic diagram of the structure of the anti-deviation auxiliary device of the utility model in a front cross-sectional view in a use state;

[0016] Figure 3 For the utility model Figure 2 The enlarged schematic diagram of the structure at A in the middle;

[0017] Figure 4 For the utility model Figure 2 The enlarged schematic diagram of the structure at B in the middle;

[0018] Figure 5 This is a schematic diagram of the cross-sectional structure of the top surface of the guide frame in the utility model;

[0019] Figure 6 For the utility model Figure 2 A in the middle is a schematic diagram of the enlarged structure of Example 2.

[0020] Markings in the figure: 1. Support frame; 101. Limit rod; 102. Slide A; 103. Sliding frame; 104. Roller; 105. Limit slot; 2. Guide frame; 201. Mounting slot; 202. Slide B; 203. Limit bracket; 204. Slide C; 205. Adjustment frame; 206. Hydraulic rod A; 207. Correction frame; 208. Guide roller; 209. Bump; 3. Silk thread; 301. Horizontal cone; 4. Groove; 401. Teeth; 5. Servo motor; 501. Gear; 6. Lifting ring; 7. Dial; 701. Magnetic needle; 8. Hydraulic rod B; 801. Correction plate. DETAILED DESCRIPTION

[0021] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0022] In the utility model:

[0023] Example 1: Reference Figure 1-5, an anti-deviation auxiliary device for pile foundation construction for foundation engineering, comprising a support frame 1, a limit rod 101, a guide frame 2, a slide groove C204, an adjustment frame 205, a deviation correction frame 207 and a lifting ring 6, a limit rod 101 is fixedly installed below the support frame 1, a plurality of limit rods 101 are arranged around at equal intervals, guide frames 2 are arranged on both sides above the limit rod 101, slide grooves C204 are relatively embedded on the sides of the guide frame 2, an adjustment frame 205 is slidingly arranged inside the slide groove C204, a deviation correction frame 207 is arranged on the sides of the adjustment frame 205 for relative rotation through a rotating shaft, a lifting ring 6 is fixedly installed above the guide frame 2, a limit disassembly and assembly mechanism for convenient disassembly and assembly is arranged below the guide frame 2, an auxiliary anti-deviation mechanism for quickly correcting the square pile foundation is arranged on the outside of the deviation correction frame 207, and a direction adjustment mechanism for conveniently changing the installation direction of the square pile foundation is arranged on the outside of the guide frame 2.

[0024] Reference Figure 1-3 , further, the limiting disassembly and assembly mechanism is composed of a slide groove A102, a sliding frame 103, a roller 104, a limiting groove 105, a mounting groove 201, a slide groove B202 and a limiting bracket 203;

[0025] A slide groove A102 is embedded on the top of the support frame 1, and the slide groove A102 is set in a ring shape. Slide frames 103 are slidably set on both sides of the top of the slide groove A102 through sliders. Rollers 104 are rotatably set on the front and back sides of the bottom of the slide frame 103 through bearings. A limiting groove 105 is embedded on the side of the slide frame 103, and the limiting groove 105 is set in an "L" shape. An installation groove 201 is embedded below the guide frame 2, and the installation groove 201 is fitted and slidably set above the outside of the slide frame 103. The side of the guide frame 2 is embedded near the side of the installation groove 201. There is a slide groove B202, and a limit bracket 203 is slidably arranged between the slide groove B202 and the inner side of the limit groove 105, and the limit bracket 203 is arranged in an "L" shape. When the staff needs to perform auxiliary deviation correction on the square prefabricated pile foundation under construction, the support frame 1 is placed around the surface of the foundation pit, and the limit rod 101 under the support frame 1 is inserted into the soil and fixed, and one of the guide frames 2 is placed above the support frame 1 and above one of the sliding frames 103 by a crane, so that the guide frame 2 slides to the outside of the sliding frame 103 through the installation groove 201, and the staff pushes the limit After the bracket 203 slides out of the slide slot B202 and makes the slide slot B202 and the limit slot 105 face each other, the limit bracket 203 is pushed to slide between the slide slot B202 and the inner side of the limit slot 105, and after the guide frame 2 passes through the installation slot 201 and completely slides to the outside of the sliding frame 103, the slide slot B202 presses the limit bracket 203 downward on the inner side of the limit slot 105, and completely fits and is limited on the inner side of the limit slot 105, completing the installation and fixation of the guide frame 2, and then another guide frame 2 is installed in the same way, and after the guide frame 2 is used later, the staff passes The crane lifts the lifting ring 6 above the guide frame 2, lifts the guide frame 2, drives the limit bracket 203 to loosen the inner side of the limit groove 105, and then the staff member releases the guide frame 2 by sliding the limit bracket 203 out of the slide groove B202 and the inner side of the limit groove 105. Then, the guide frame 2 is lifted to drive the installation groove 201 to be completely removed from the top of the sliding frame 103, and the guide frame 2 is disassembled. After the support frame 1 is lifted from the ground, the staff member can quickly install it in the same way and assist in correcting the construction of other square prefabricated pile foundations, which is convenient for the staff member to quickly disassemble and use the guide frame 2.

[0026] Reference Figure 1 , 2 , 4, 5, further, the auxiliary anti-deviation mechanism is composed of a hydraulic rod A206, a guide roller 208, a bump 209, a wire 3, a horizontal cone 301, a hydraulic rod B8 and a deviation correction plate 801;

[0027] A hydraulic rod A206 is fixedly installed between the inner wall side of the adjusting frame 205 and the inner wall side of the slide groove C204. A guide roller 208 is rotatably arranged on the side of the correcting frame 207 through a bearing. There are several guide rollers 208, which are arranged in parallel at equal distances. The outer surface material of the guide rollers 208 is butadiene rubber. A convex block 209 is fixedly installed above the correcting frame 207 near the upper part of the adjusting frame 205, and the convex block 209 is arranged in a conical shape. A wire 3 is fixedly installed above the correcting frame 207 near the upper part of the convex block 209, and a wire 3 is fixedly installed below the end of the wire 3. The horizontal cone 301, the hydraulic rod B8 is relatively fixedly installed in the front and rear of the correcting frame 207, and the correcting plate 801 is fixedly installed between the ends of the two parallel hydraulic rods B8. When the staff installs the two guide frames 2, they drive the crane to lift one of the square prefabricated pile foundations and place it in the foundation pit between the guide frames 2. At the same time, the staff controls the two hydraulic rods A206 to shrink the adjustment frame 205 and slide it in the opposite direction on the inner side of the slide groove C204, driving the guide rollers 208 on the sides of the two correcting frames 207 to contact the square prefabricated pile foundations. At the same time, the deflection correction frame 207 is squeezed and rotated by the rotating shaft, so that the guide rollers 208 on the side of the deflection correction frame 207 are completely squeezed and contacted with the surfaces of both sides of the square prefabricated pile foundation. At the same time, the staff controls a hydraulic rod A206 to extend the other hydraulic rod A206 to retract the adjustment frame 205 to slide inside the slide groove C204, pushing the suspended square prefabricated pile foundation to adjust the falling position. While correcting the deflection of the square prefabricated pile foundation, the staff observes whether the horizontal cone 301 swinging through the silk thread 3 is opposite to the protrusion 209, and After the deviation correction in one direction of the square prefabricated pile foundation is completed, the hydraulic rod B8 is controlled to retract the deviation correction plate 801 so that the four deviation correction plates 801 are respectively squeezed and contacted on the front and rear sides of the square prefabricated pile foundation, and the square prefabricated pile foundation is completely corrected. After it is slowly lowered horizontally into the foundation pit, the staff pours concrete into the foundation pit and uses other support frames 1 and guide frames 2 in the same way to assist in the deviation correction of the remaining prefabricated square pile foundations, thereby improving the effect of stabilizing and preventing the deviation of the prefabricated square pile foundation and making the deviation correction efficiency of the prefabricated square pile foundation higher.

[0028] Reference Figure 1 , 2 , 3, 5, further, the direction adjustment mechanism is composed of a groove 4, a tooth 401, a servo motor 5, a gear 501, a dial 7 and a magnetic needle 701;

[0029] A groove 4 is embedded on the top of the support frame 1, and the groove 4 is arranged in a ring shape. A tooth 401 is fixedly installed at the bottom of the inner wall of the groove 4. There are several teeth 401, which are arranged equidistantly in a trapezoidal shape. A servo motor 5 is fixedly installed on the side of the inner wall of the guide frame 2. The servo motor 5 is connected to a gear 501 through an output shaft, and the gear 501 and the several teeth 401 are arranged in a bite transmission. A dial 7 is fixedly installed on the side of the guide frame 2 near the hanging ring 6. A magnetic needle 701 is rotatably arranged on the top of the guide frame 2 near the middle of the dial 7 through a bearing, and there is a one-millimeter interval between the bottom of the magnetic needle 701 and the top of the dial 7. When the staff is checking the square pre- When the pile making is corrected, if it is necessary to adjust the buried direction of the square precast pile, the staff turns on the two servo motors 5 to drive the gear 501 to rotate, so that the gear 501 and a plurality of teeth 401 are engaged for transmission, and the guide frame 2 is pushed to move inside the slide groove A102 through the roller 104 below the sliding frame 103, and the guide frame 2 is driven to push the square precast pile to rotate above the support frame 1. At the same time, the magnetic needle 701 will rotate through the bearing, and after the staff observes that the magnetic needle 701 points to the specified scale position, the servo motor 5 is turned off to complete the adjustment of the buried direction of the square precast pile, which is convenient for the staff to quickly and finely adjust the buried direction of the precast pile.

[0030] Reference Figure 2 , 3 , 5. Further, the hydraulic rod A206 and the hydraulic rod B8 are electrically connected to the battery through the matching hydraulic pump and control panel, and the servo motor 5 is electrically connected to the battery through the matching control panel.

[0031] Embodiment 2:

[0032] like Figure 3 , 6As shown, in the utility model, in addition to the embodiment in which the limiting groove 105 is embedded on the side of the sliding frame 103, and the limiting groove 105 is set in an "L" shape, a mounting groove 201 is embedded below the guide frame 2, and the mounting groove 201 is slidably arranged above the outside of the sliding frame 103, a sliding groove B202 is embedded on the side of the guide frame 2 near the mounting groove 201, a limiting card frame 203 is slidably arranged between the sliding groove B202 and the inner side of the limiting groove 105, and the limiting card frame 203 is set in an "L" shape, there is another embodiment in which the limiting groove 105 is embedded on the side of the sliding frame 103, and the limiting groove 105 is set in a "J" shape, a mounting groove 201 is embedded below the guide frame 2, and the mounting groove 201 is slidably arranged on the sliding frame 1 03, a slide groove B202 is embedded on the side of the guide frame 2 near the installation groove 201, and a limit bracket 203 is slidably set between the slide groove B202 and the inner side of the limit groove 105, and the limit bracket 203 is set in a "J" shape. When the guide frame 2 slides to the outside of the sliding frame 103 through the installation groove 201, the staff pushes the limit bracket 203 to slide out of the slide groove B202, so that the slide groove B202 and the limit groove 105 are opposite, and then push the limit bracket 203 to slide between the slide groove B202 and the inner side of the limit groove 105, and after the guide frame 2 is slowly lowered again by a small distance, the limit bracket 203 is pulled to completely fit the inside of the limit groove 105 to limit the position, and the installation and fixation of the guide frame 2 is completed. Compared with the first embodiment, the limiting effect is better.

[0033] Working principle: First, the staff needs to carry out auxiliary correction processing on the square prefabricated pile foundation under construction, place the support frame 1 around the surface of the foundation pit, and insert the limit rod 101 under the support frame 1 into the soil to fix it, then place one of the guide frames 2 above one of the sliding frames 103 above the support frame 1 through a crane, so that the guide frame 2 slides to the outside of the sliding frame 103 through the installation groove 201, and the staff pushes the limit bracket 203 to slide out of the slide groove B202, so that the slide groove B202 and the limit groove 105 are opposite, and then push the limit bracket 203 to slide between the slide groove B202 and the inner side of the limit groove 105, and after the guide frame 2 completely slides to the outside of the sliding frame 103 through the installation groove 201, the slide groove B202 presses the limit bracket 203 in the limit groove 1 05 slides downward on the inside and completely fits in the limit groove 105 to complete the installation and fixation of the guide frame 2, and then installs another guide frame 2 in the same way. Then, the staff drives the crane to lift one of the square prefabricated pile foundations and place it in the foundation pit between the guide frames 2. At the same time, the staff controls two hydraulic rods A206 to retract the adjustment frame 205 and slide in opposite directions on the inside of the slide groove C204, driving the guide rollers 208 on the sides of the two deviation correcting frames 207 to contact the two sides of the square prefabricated pile foundation respectively. At the same time, the deviation correcting frame 207 is squeezed and rotated through the rotating shaft, so that the guide rollers 208 on the sides of the deviation correcting frame 207 are completely squeezed and contacted with the surfaces on both sides of the square prefabricated pile foundation. Then, the staff controls a hydraulic rod A206 to extend Another hydraulic rod A206 is extended to retract the adjustment frame 205 and slide inside the slide groove C204, pushing the suspended square precast pile foundation to adjust the falling position. While correcting the square precast pile foundation, the staff observes whether the horizontal cone 301 swinging through the wire 3 is opposite to the protrusion 209, and after the correction of one direction of the square precast pile foundation is completed, the hydraulic rod B8 is controlled to retract the correction plate 801, so that the four correction plates 801 are respectively squeezed and contacted on the front and rear sides of the square precast pile foundation, and the square precast pile foundation is completely corrected. Finally, if the burying direction of the square precast pile needs to be adjusted, the staff turns on the two servo motors 5 to drive the gear 501 to rotate, so that the gear 501 and a plurality of teeth 401 are engaged for transmission, and the guide frame 2 is pushed through The roller 104 below the sliding frame 103 moves inside the slide groove A102, driving the guide frame 2 to push the square precast pile to rotate above the support frame 1. At the same time, the magnetic needle 701 will rotate through the bearing, and after the staff observes that the magnetic needle 701 points to the specified scale position, the servo motor 5 is turned off to complete the adjustment of the buried direction of the square precast pile, and the square precast pile foundation is slowly lowered into the foundation pit horizontally. The staff then pours concrete into the foundation pit and uses other support frames 1 and guide frames 2 in the same way to assist in the construction of the remaining precast square pile foundations. After the guide frame 2 is used later, the staff lifts the lifting ring 6 above the guide frame 2 by a crane, lifts the guide frame 2, and drives the limit clamping frame 203 to loosen the inner side of the limit groove 105.After the staff member slides the limit bracket 203 out of the slide slot B202 and the inner side of the limit slot 105 to release the guide frame 2, the staff member lifts the guide frame 2 to drive the installation slot 201 to be completely removed from the top of the sliding frame 103, and after the guide frame 2 is disassembled and the support frame 1 is lifted from the ground, the staff member performs auxiliary deviation correction processing on the construction of other square prefabricated pile foundations in the same way.

[0034] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A pile foundation construction anti-deviation auxiliary device for foundation engineering, comprising a support frame (1), a limit rod (101), a guide frame (2), a slide groove C (204), an adjustment frame (205), a deviation correction frame (207) and a lifting ring (6), wherein a limit rod (101) is fixedly installed below the support frame (1), a plurality of limit rods (101) are arranged equidistantly around, guide frames (2) are arranged on both sides above the limit rod (101), a slide groove C (204) is relatively embedded on the side of the guide frame (2), an adjustment frame (205) is slidably arranged on the side of the slide groove C (204), a deviation correction frame (207) is relatively rotated on the side of the adjustment frame (205) through a rotating shaft, and a lifting ring (6) is fixedly installed above the guide frame (2), characterized in that: A position limiting disassembly and assembly mechanism is arranged below the guide frame (2) for easy disassembly and assembly, an auxiliary anti-deviation mechanism is arranged outside the deviation correction frame (207) for rapid deviation correction of the square pile foundation, and a direction adjustment mechanism is arranged outside the guide frame (2) for easy change of installation direction of the square pile foundation.

2. The anti-deviating auxiliary device for pile foundation construction for foundation engineering as claimed in claim 1, characterized in that: The position limiting and disassembling mechanism is composed of a slide groove A (102), a sliding frame (103), a roller (104), a position limiting groove (105), a mounting groove (201), a slide groove B (202) and a position limiting bracket (203); A slide groove A (102) is embedded on the top of the support frame (1), and the slide groove A (102) is arranged in a ring shape. Slide frames (103) are slidably arranged on both sides of the top of the slide groove A (102) through sliders. Rollers (104) are rotatably arranged on the front and rear sides of the bottom of the slide frame (103) through bearings. A limiting groove (105) is embedded on the side of the slide frame (103). An installation groove (201) is embedded on the bottom of the guide frame (2), and the installation groove (201) is slidably arranged on the top of the outside of the slide frame (103). A slide groove B (202) is embedded on the side of the guide frame (2) close to the side of the installation groove (201). A limiting bracket (203) is slidably arranged between the slide groove B (202) and the inner side of the limiting groove (105).

3. The anti-deviating auxiliary device for pile foundation construction for foundation engineering as claimed in claim 1, characterized in that: The auxiliary anti-deviation mechanism is composed of a hydraulic rod A (206), a guide roller (208), a convex block (209), a wire (3), a horizontal cone (301), a hydraulic rod B (8) and a deviation correction plate (801); A hydraulic rod A (206) is fixedly installed between the inner wall side of the adjustment frame (205) and the inner wall side of the slide groove C (204); a guide roller (208) is rotatably arranged on the side of the deflection correcting frame (207) through a bearing; a protrusion (209) is fixedly installed on the upper part of the deflection correcting frame (207) near the upper part of the adjustment frame (205); a wire (3) is fixedly installed on the upper part of the deflection correcting frame (207) near the upper part of the protrusion (209); a horizontal cone (301) is fixedly installed below the end of the wire (3); hydraulic rods B (8) are relatively fixedly installed on the upper and lower sides of the deflection correcting frame (207); a deflection correcting plate (801) is fixedly installed between the ends of two parallel hydraulic rods B (8).

4. The anti-deviating auxiliary device for pile foundation construction for foundation engineering as claimed in claim 1, characterized in that: The direction adjustment mechanism is composed of a groove (4), teeth (401), a servo motor (5), a gear (501), a dial (7) and a magnetic needle (701); A groove (4) is embedded on the upper part of the support frame (1), and teeth (401) are fixedly installed on the lower part of the inner wall of the groove (4). A servo motor (5) is fixedly installed on the side of the inner wall of the guide frame (2). The servo motor (5) is connected to a gear (501) via an output shaft, and the gear (501) and the plurality of teeth (401) are arranged in a meshing transmission. A dial (7) is fixedly installed on the upper part of the guide frame (2) near the side of the hanging ring (6), and a magnetic needle (701) is rotatably arranged on the upper part of the guide frame (2) near the middle of the dial (7) via a bearing.

5. The anti-deviating auxiliary device for pile foundation construction for foundation engineering as claimed in claim 2, characterized in that: The limiting groove (105) is arranged in an "L" shape, and the limiting bracket (203) is arranged in an "L" shape.

6. The anti-deviating auxiliary device for pile foundation construction for foundation engineering as claimed in claim 3, characterized in that: There are a plurality of guide rollers (208) which are arranged in parallel at equal distances, and the outer surface material of the guide rollers (208) is butadiene rubber, and the protrusions (209) are arranged in a conical shape.

7. The anti-deviating auxiliary device for pile foundation construction for foundation engineering as claimed in claim 4, characterized in that: The groove (4) is arranged in a ring shape, and there are a plurality of teeth (401) which are arranged in a trapezoidal shape at equal intervals. The interval between the bottom of the magnetic needle (701) and the top of the dial (7) is one millimeter.