Plastering equipment for house building construction

By using technologies such as universal wheels, lifting grooves and spiral motors in plastering equipment, the problem of inefficient collection of mud and unadjustable equipment height is solved, and efficient plastering construction and mud circulation in buildings of different heights is realized. Utilization improves construction efficiency and equipment applicability.

CN221941840UActive Publication Date: 2024-11-01贾从贵 +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323394410.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-13
Publication Date
2024-11-01
Estimated Expiration
2033-12-13

AI Technical Summary

Technical Problem

The existing plastering machinery and equipment cannot be efficiently collected and utilized during construction, and the preset height of the plastering equipment cannot be adjusted, resulting in inefficient construction inside buildings of different heights.

Method used

A plastering equipment for building construction was designed, using components such as universal wheels, lifting grooves, screws and spiral motors to realize the height adjustment of the equipment and the recycling of mud mortar. Through the design of lifting plates and mortar boxes, the mud mortar is realized. efficient collection and reuse.

Benefits of technology

The continuous construction of plastering equipment in buildings with different heights is realized, avoiding waste of mortar, and improving construction efficiency and equipment usage scenarios.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221941840U_ABST
    Figure CN221941840U_ABST
Patent Text Reader

Abstract

The utility model relates to the field of building construction, in particular to house building construction plastering equipment which comprises a bottom plate, a main side plate is arranged on the top of the bottom plate, a telescopic auxiliary side plate is arranged in the bottom plate, and therefore a lifting motor is driven to be heightened through lifting of the auxiliary side plate. A lifting plate is mounted on the outer side of the lifting screw, so that the lifting plate is pushed to ascend and descend along the lifting screw when the lifting motor rotates, and the lifting height of the lifting plate is also changed along with the increase of the distance of the lifting screw; the plastering equipment can adapt to plastering projects in buildings with different heights after the height of the plastering equipment is adjusted, the plastering box is connected to one side of the lifting plate, and the plastering equipment can be attached to the wall surface for plastering construction; and one end of the spiral motor is mounted in the plastering box, so that redundant marl can be efficiently and repeatedly utilized during plastering, and waste and influence on construction efficiency are avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of building construction, in particular to a plastering device for house building construction. Background Art

[0002] The construction process of house buildings is very complicated. Generally, after the main frame structure of the house is built, it is necessary to plaster the concrete or brick walls to improve the overall flatness and aesthetics of the wall. However, in the current plastering construction process, most of them adopt manual plastering process, which is extremely inefficient. Therefore, in order to improve the efficiency of plastering, a plastering equipment has been derived to improve the construction efficiency.

[0003] With respect to the above-mentioned related technologies, the inventors believe that the following defects exist: the existing plastering machinery and equipment transports mud and plaster to the trowel plate during the plastering process, and achieves plastering construction through the vertical up and down movement of the trowel plate. However, during the plastering construction process, excess mud and plaster on the existing trowel plate will fall directly from the edge, resulting in the inability to efficiently collect and utilize the mud and plaster, causing waste of mud and plaster. At the same time, the preset plastering height of the existing plastering equipment is fixed. When encountering a taller building, the height of the plastering equipment cannot be adjusted without affecting the continuity of the plastering construction, and it cannot be lowered at any time when moved to a shorter building, resulting in a single use scenario for the plastering equipment. Utility Model Content

[0004] In order to improve the problem that fallen plaster cannot be efficiently collected and utilized and the preset height of the plastering board cannot be adjusted, the present application provides a plastering equipment for house construction.

[0005] The present application provides a house construction plastering equipment adopting the following technical scheme: a house construction plastering equipment, comprising a bottom plate, the bottom four corners of the bottom plate are all equipped with universal wheels, the top of the bottom plate is provided with a rotation groove, the top two sides of the bottom plate are provided with main side plates, the inside of the main side plates are provided with lifting grooves, the inside of the lifting grooves are slidably equipped with secondary side plates, the top of the secondary side plates is equipped with a lifting motor, one end of the lifting motor is fixedly equipped with a lifting screw, and one end of the lifting screw is connected to the inside of the bottom plate;

[0006] A lifting plate is installed on the outside of the lifting screw, and both ends of the lifting plate are slidably connected to the inside of the main side plate and the auxiliary side plate. A plastering box is connected to one side of the lifting plate, and one side of the plastering box can be in close contact with the wall surface. A spiral motor is installed inside the plastering box, and a ash storage box is provided on the top of the bottom plate;

[0007] By adopting the above technical solution, the whole device can be moved and fixed arbitrarily through the setting of universal wheels.

[0008] It is further provided that a main slide groove is provided in the middle of one side of the lifting groove, symmetrical main limit holes are provided at the tops of both sides of the main side plates, a secondary slide groove is provided in the inner side of the secondary side plates, the secondary slide groove is horizontally aligned with the main slide groove, and symmetrical secondary limit holes are provided at both upper and lower ends of both sides of the secondary side plates, a short bolt is installed inside the secondary limit hole at one end, and one end of the short bolt can pass through the main limit hole and then be movably connected with the inside of the secondary limit hole;

[0009] By adopting the above technical solution, the auxiliary side plate can be slid and raised through the lifting groove, and after lifting, the auxiliary side plate can be fixed by connecting the main limit hole with the auxiliary limit hole at the specified position through the short bolt.

[0010] It is further provided that the lifting screw comprises a main screw, a secondary screw, a connector and a long bolt, the secondary screw is arranged inside the main screw, one end of the secondary screw is connected to one end of the lifting motor, a lower screw hole is arranged outside one end of the main screw, an upper screw hole is arranged outside the other end of the main screw, a fixing hole is arranged at one end of the secondary screw, one end of the long bolt can pass through the inner side of the lower screw hole and then be movably connected with the inner side of the fixing hole, and one end of the long bolt can also pass through the inner side of the upper screw hole and then be movably connected with the inner side of the fixing hole;

[0011] By adopting the above technical solution, it is convenient to connect the plastering equipment with the long bolts after adjusting the height through the setting of the lower screw hole and the upper screw hole, so that the auxiliary screw can be quickly fixed after lifting and lowering without affecting the overall rotation of the lifting screw driven by the lifting motor.

[0012] It is further provided that a rotating disk is provided at one end of the main screw, the outer side of the rotating disk is rotatably engaged with the inner side of the rotating groove, a screw groove is provided inside the connector, and the inner side of the screw groove cooperates with the outer side thread of the auxiliary screw;

[0013] By adopting the above technical solution, the lifting screw can be ensured to rotate in place when rotating through the clamping connection between the turntable and the rotating groove, and the connector can be vertically lifted and lowered by the rotation of the auxiliary screw through the setting of the screw groove.

[0014] It is further configured that both ends of the lifting plate are provided with sliders, the outer sides of the sliders can be slidably engaged with the inner sides of the main slide groove and the auxiliary slide groove, the top of the lifting plate is provided with a slot, the inner side of the slot can be engaged with the outer side of the connector, the bottom of the slot is provided with an inner screw hole, the inner side of the inner screw hole cooperates with the outer thread of the main screw, and through holes are provided on both sides of one side of the lifting plate;

[0015] By adopting the above technical solution, the lifting plate can be moved to the connector through the card slot and can be engaged with the connector, and the lifting plate can be vertically lifted and lowered along the auxiliary screw rod through the connector.

[0016] It is further provided that a plastering plate groove is provided on one side of the plastering plate groove, a plurality of feed holes are arranged equidistantly on one side of the plastering plate groove, a plurality of discharge grooves are provided on the top of the plastering plate groove, an inner cavity is provided inside the plastering box, the discharge groove can be communicated with the inner cavity, a mounting hole is provided on one side of the inner cavity, a fixture is provided on one side of the outside of the plastering box, the interior of the fixture is communicated with the mounting hole, and one side of the fixture is connected to the outer side of the through hole;

[0017] By adopting the above technical solution, the mud and mortar inside the inner cavity can be discharged through the feeding hole, and when plastering, if there is excess mud and mortar, it can re-enter the inner cavity from the discharge trough to form a circulation.

[0018] It is further configured that a spiral rod is provided at one end of the spiral motor, and the spiral rod is installed inside the inner cavity. Telescopic tubes are installed on both sides of the interior of the ash storage box, and a suction pump is provided at one end of the telescopic tube. The other end of the telescopic tube passes through the through hole and the interior of the fixer and is connected to the inner side of the mounting hole.

[0019] Compared with the related art, the plastering equipment for house construction provided by the utility model has the following beneficial effects:

[0020] The utility model provides a plastering device for house construction construction, by providing a lifting groove inside the main side plate, a lifting side plate that can be lifted and lowered can be installed inside the main side plate, and a set of lifting side plates are formed by the main side plate and the secondary side plate, so that the position of the lifting motor is increased, and the secondary screw rod is pulled out from the inside of the main screw rod, so that the length of the lifting screw rod is increased, and a long bolt is provided, which can pass through the lower screw hole or the upper screw hole when needed and then be connected with the fixing hole, so that the lifting screw length can be increased or decreased without affecting the rotation of the lifting screw rod driven by the lifting motor, and the screw groove cooperates with the outer thread of the secondary screw rod, so that after the lifting plate is lifted and lowered to the connector along the main screw rod, the secondary screw rod can be driven to continue to lift and lower along the secondary screw rod through the action of the connector when the secondary screw rod rotates, and at the same time drive the lifting plate to continue to lift and lower along the secondary screw rod, so that after the length of the lifting screw rod changes, the lifting plate can continue to lift and lower vertically to drive the plastering height change of the plastering box, and at the same time does not affect the coherent construction during the plastering construction process, so that the plastering device can be constructed inside low or tall buildings, thereby increasing the use scenarios.

[0021] The utility model provides a plastering device for house construction, in which a spiral rod is installed inside an inner cavity, and when the mud and plaster enter the inner cavity, the mud and plaster will be pushed through the feed hole and enter the inside of the plastering plate groove through the rotation of the spiral rod to complete the plastering construction, and when excess mud and plaster are squeezed inside the plastering plate groove during the plastering construction, the mud and plaster will flow back into the inner cavity from the discharge chute, and the mud and plaster will contact the outer side of the spiral rod again and be pushed through the feed hole and enter the inside of the plastering plate groove by the rotation to complete the repetitive plastering construction process, thereby avoiding the problem of mud and plaster falling during the plastering construction and causing waste, and at the same time, the mud and plaster can efficiently and repeatedly complete the plastering construction through the discharge chute and the spiral rod, without the need to flow back to the container for storing the mud and plaster, thereby achieving the purposes of efficient mud collection and efficient plastering. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 A structural schematic diagram of a preferred embodiment of a house construction plastering device provided by the utility model;

[0023] Figure 2 This is a schematic diagram of the main side plate structure of the utility model;

[0024] Figure 3 This is a schematic diagram of the auxiliary side plate structure of the utility model;

[0025] Figure 4 This is a schematic diagram of the lifting screw structure of the utility model;

[0026] Figure 5 This is a schematic diagram of the structure of the connector of the utility model;

[0027] Figure 6 This is a schematic diagram of the lifting plate structure of the utility model;

[0028] Figure 7 This is a schematic cross-sectional view of the structure of the plastering box of the utility model;

[0029] Figure 8 This is a schematic diagram of the structure of the spiral motor of the utility model;

[0030] Fig. 9 This is a schematic diagram of the structure of the ash storage box of the utility model.

[0031] Numbers in the figure: 1, bottom plate; 101, universal wheel; 102, rotating groove; 2, main side plate; 201, lifting groove; 202, main slide; 203, main limit hole; 3, auxiliary side plate; 301, auxiliary slide; 302, auxiliary limit hole; 303, short bolt; 4, lifting motor; 5, lifting screw; 501, main screw; 5011, turntable; 5012, lower screw hole; 5013, upper screw hole; 502, auxiliary screw; 5021, fixing hole; 50 3. Connector; 5031. Screw groove; 504. Long bolt; 6. Lifting plate; 601. Slider; 602. Slot; 6021. Screw hole in the groove; 603. Through hole; 7. Plastering box; 701. Plastering board groove; 7011. Feed hole; 7012. Discharge trough; 702. Inner cavity; 7021. Mounting hole; 703. Fixer; 8. Screw motor; 801. Screw rod; 9. Ash storage box; 901. Telescopic tube; 902. Suction pump. DETAILED DESCRIPTION

[0032] In order to facilitate the understanding of the present invention, the present invention will be described more comprehensively below with reference to the accompanying drawings, in which typical embodiments of the present invention are shown.

[0033] Embodiment 1:

[0034] like Figure 1 As shown, a plastering device for house construction of the utility model comprises a base plate 1. By installing a universal wheel 101 at the bottom of the base plate 1, the device can be moved as a whole. Then, a main side plate 2 is provided on the top of the base plate 1 and a secondary side plate 3 with a retractable height distance is provided inside the main side plate 2. Thus, the lifting motor 4 is driven to increase in height by lifting the secondary side plate 3, thereby driving the lifting screw 5 connected to one end of the lifting motor 4 to be stretched to change its length. By installing a lifting plate 6 on the outside of the lifting screw 5, the lifting motor 4 will be driven to move along the lifting plate 6 when it rotates. The screw rod 5 is raised and lowered, and as the distance of the lifting screw rod 5 becomes longer, the lifting height of the lifting plate 6 also changes, so that the plastering equipment can adapt to the internal plastering projects of buildings of different heights after adjusting the height. A plastering box 7 is connected to one side of the lifting plate 6, and the plastering box 7 can be fitted with the wall surface for plastering construction. By installing one end of the spiral motor 8 inside the plastering box 7, the excess plaster during plastering can be efficiently reused to avoid waste and affect the construction efficiency. Finally, a ash storage box 9 is placed on the top of the base plate 1 to transport plaster to the inside of the plastering box 7.

[0035] like Figure 2 , Figure 3 and Figure 6As shown, by providing a lifting groove 201, the secondary side plate 3 can be extended and retracted inside it to achieve the purpose of lifting. By providing a main slide groove 202 and a secondary slide groove 301 and aligning the two, the two ends of the slider 601 can be connected with the secondary slide groove 301 after passing through the main slide groove 202, so that the lifting plate 6 is limited when it is lifted or lowered. By providing a secondary limiting hole 302, a short bolt 303 and a main limiting hole 203, the short bolt 303 can be passed through the main limiting hole 203 to connect with the secondary limiting holes 302 at different positions, so that the secondary side plate 3 can be fixed after being lifted or lowered.

[0036] like Figure 2 and Figure 4 As shown, by setting the lifting screw 5 to include multiple parts including a main screw 501, a secondary screw 502, a connector 503 and a long bolt 504, the main screw 501 can be used to lift the lifting plate 6 to a relatively low height, and after the secondary screw 502 is connected to the lifting motor 4, the secondary screw 502 can be used to stretch the lifting screw 5 from the inside of the main screw 501 to lengthen the overall length of the lifting screw 5, and the connector 503 installed at one end of the main screw 501 can be used to lift the lifting plate 6 to this position. It can continue to be lifted and lowered along the outer side of the secondary screw 502, and can be connected to the inside of the rotating groove 102 through the turntable 5011 to rotate the lifting screw 5 in its original position. When the long bolt 504 passes through the lower screw hole 5012 and is connected to the fixing hole 5021, the lifting screw 5 can be made shorter and the main screw 501 and the secondary screw 502 can be rotated at the same time. When the long bolt 504 passes through the upper screw hole 5013 and is connected to the fixing hole 5021, the lifting screw 5 can be made longer and the main screw 501 and the secondary screw 502 can be rotated at the same time.

[0037] like Figure 4 , Figure 5 and Figure 6 As shown, the screw groove 5031 can cooperate with the outer thread of the auxiliary screw 502, and the card slot 602 can be clamped with the connector 503, so that the lifting plate 6 and the connector 503 form a whole, and the screw hole 6021 in the groove can be configured to cooperate with the outer thread of the main screw 501.

[0038] During implementation, by providing a lifting groove 201 inside the main side panel 2, a lifting auxiliary side panel 3 can be installed inside it. When it is necessary to carry out plastering work inside a high building, the auxiliary side panel 3 can be raised and connected to the auxiliary limiting hole 302 at the corresponding position through the short bolt 303 passing through the main limiting hole 203, so that the raised auxiliary side panel 3 can be fixed, thereby forming a set of lifting side panels through the main side panel 2 and the auxiliary side panel 3, and at the same time making the position of the lifting motor 4 higher. During the process, the auxiliary screw 502 can be pulled out from the inside of the main screw 501, so that the length of the lifting screw 5 is lengthened, and by providing a long bolt 504, it can pass through the lower screw hole 5012 or the upper screw hole 5013 when needed and then be connected to the fixing hole 5021, so that the length of the lifting screw 5 can be lengthened or shortened without affecting the lifting motor 4 and driving the main screw 501 and the auxiliary screw 502 to rotate together, and through The screw groove 5031 and the outer side thread of the auxiliary screw 502 cooperate with each other, so that when the outer side of the main screw 501 rotates on the inner side of the screw hole 6021 in the groove, the lifting plate 6 can be continuously lifted and lowered through the mutual cooperation between the threads, and after being lifted and lowered to the connector 503, the lifting plate 6 and the connector 503 can be formed into a whole through the clamping connection between the clamping groove 602 and the connector 503. When the auxiliary screw 502 rotates inside the screw groove 5031, the lifting plate 6 can continue to be lifted and lowered along the auxiliary screw 502 due to the action of the connector 503 through the mutual cooperation between the threads, so that after the length of the lifting screw 5 changes, the lifting plate 6 can continue to be lifted and lowered vertically, driving the plastering height change of the plastering box 7. In addition, due to the existence of the connector 503, the continuity of the plastering construction process is not affected, so that the plastering equipment can be constructed inside low or tall buildings, which increases the usage scenarios.

[0039] Embodiment 2:

[0040] like Figure 7 As shown, on the basis of the first embodiment, the utility model provides a technical solution: by providing a plastering plate groove 701, the plaster can be transported here for plastering construction, by providing a feeding hole 7011, the internal plaster can be evenly transported out, by providing an inner cavity 702 and providing a discharge groove 7012 inside the plastering plate groove 701, it can communicate with the inner cavity 702, by providing an installation hole 7021 to align with the fixer 703, the plaster can be transported from the inside of the fixer 703 to the inner cavity 702, and the plastering box 7 is fixed on one side of the lifting plate 6 through the fixer 703 and rises and falls with the lifting plate 6.

[0041] like Figure 8 and Figure 7As shown, a spiral motor 8 and a spiral rod 801 are provided, and the spiral rod 801 is installed in the inner cavity 702. When the mud enters the inner cavity 702, it will be stirred by the spiral rod 801 and driven to the feed hole 7011 and then discharged. At the same time, the spiral rod 801 will also contact the mud entering the inner cavity 702 from the discharge trough 7012.

[0042] like Fig. 9 and Figure 6 As shown, a ash storage box 9 is provided for storing mud and ash for construction, and the mud and ash are sucked into the telescopic tube 901 by a suction pump 902. The telescopic tube 901 is configured to be telescopic and at the same time, one end of the telescopic tube is transported into the inner cavity 702 through the through hole 603.

[0043] In practice, a spiral rod 801 is installed inside the inner cavity 702. When the mortar is sucked into the telescopic tube 901 by the suction pump 902, it will enter the inner cavity 702, and then it will be pushed through the feed hole 7011 and enter the inside of the plastering plate groove 701 through the rotation of the spiral rod 801. The lifting of the lifting plate 6 drives the outer side of the plastering plate groove 701 to contact the wall to complete the plastering construction. In the process of plastering construction, excess mortar will be squeezed inside the plastering plate groove 701 and will be discharged from the outlet. The groove 7012 flows back into the inner cavity 702, and makes the mud and plaster contact the outer side of the spiral rod 801 again, and is pushed by its rotation again through the feed hole 7011 and enters the plastering board groove 701 to complete the repetitive plastering construction process, thereby avoiding the problem of mud and plaster falling during plastering construction and causing waste. At the same time, the mud and plaster can efficiently and repeatedly complete the plastering construction through the discharge groove 7012 and the spiral rod 801, without the need to flow back into the container for storing mud and plaster, thereby achieving the purpose of efficient collection of mud and plastering.

[0044] The advantages of this technical solution in practical applications include but are not limited to the following:

[0045] 1. The construction height of the plastering equipment can be changed by providing the main side plate 2 and the auxiliary side plate 3 that can be lifted and lowered. At the same time, the main screw 501, the auxiliary screw 502 and the connector 503 are provided to ensure the continuity of the plastering construction process, which can be more suitable for the plastering construction inside high buildings.

[0046] 2. The inner cavity 702 and the discharge chute 7012 are provided to make them connected, and the spiral rod 801 installed inside the inner cavity 702 can allow the mud to enter and be pushed to the inside of the plastering board groove 701 for plastering. During the process, the excess mud will re-enter the inner cavity 702 through the discharge chute 7012, achieving a repeated cycle of plastering construction, avoiding waste of mud and achieving the purpose of efficient plastering construction.

[0047] When it is necessary to carry out plastering work inside a high building, the technical solution can raise the secondary side panel 3 and connect it with the secondary limit hole 302 at the corresponding position through the short bolt 303 passing through the main limit hole 203, so that the raised secondary side panel 3 can be fixed, so that a set of lifting side panels is formed through the main side panel 2 and the secondary side panel 3, and at the same time, the position of the lifting motor 4 is raised. During the process, the secondary screw rod 502 is pulled out from the inside of the main screw rod 501, so that the length of the lifting screw 5 is lengthened, and the long bolt 504 can be passed through the lower screw hole 5012 or the upper screw hole 5013 when needed and then connected to the fixing hole 5021, so that the length of the lifting screw 5 is lengthened or shortened without affecting the lifting motor 4 and driving the main screw rod 5 at the same time. The screw rod 501 and the auxiliary screw rod 502 rotate together, and the connector 503 is rotated around the outside of the auxiliary screw rod 502 to one end of the main screw rod 501 to move it to the initial position before the main screw rod 501 and the auxiliary screw rod 502 are extended and retracted, and the screw groove 5031 cooperates with the outer thread of the auxiliary screw rod 502, so that when the main screw rod 501 rotates on the inner side of the screw hole 6021 in the groove, the lifting plate 6 is continuously lifted and lowered through the mutual cooperation between the threads, and after lifting and lowering to the connector 503, the lifting plate 6 and the connector 503 can be clamped through the clamping groove 602 to form a whole with the connector 503. When the auxiliary screw 502 continues to rotate inside the screw groove 5031, the mutual cooperation between the threads is also The lifting plate 6 will continue to lift and lower along the auxiliary screw 502 due to the action of the connector 503, so that after the length of the lifting screw 5 changes, the lifting plate 6 can continue to lift and lower vertically to drive the plastering height of the plastering box 7 to change, and the existence of the connector 503 does not affect the continuity of the plastering construction process, so that the plastering equipment can be constructed inside low or tall buildings, increasing the use scenarios, and then by installing a spiral rod 801 inside the inner cavity 702, when the mortar is sucked into the telescopic tube 901 through the suction pump 902, it will enter the inner cavity 702, and then it will be pushed through the feed hole 7011 into the inside of the plastering plate groove 701 through the rotation of the spiral rod 801, The lifting of the lifting plate 6 drives the outer side of the plastering plate groove 701 to contact the wall to complete the plastering construction. During the plastering construction process, when there is excess mud and plaster squeezed inside the plastering plate groove 701, it will flow back into the inner cavity 702 from the discharge trough 7012, and the mud and plaster will contact the outer side of the spiral rod 801 again and be pushed by its rotation through the feed hole 7011 to enter the plastering plate groove 701 to complete the repetitive plastering construction process, thereby avoiding the problem of mud and plaster falling during plastering construction and causing waste. At the same time, the mud and plaster can efficiently and repeatedly complete the plastering construction through the discharge trough 7012 and the spiral rod 801 without flowing back into the container for storing mud and plaster, thereby achieving the purpose of efficient collection of mud and plastering.

[0048] The above are only exemplary embodiments of the present disclosure, and the scope of the present disclosure cannot be limited thereto. That is, any equivalent changes and modifications made according to the teachings of the present disclosure are still within the scope of the present disclosure. After considering the disclosure of the specification and the truth of practice, it will be easy for those skilled in the art to think of other embodiments of the present disclosure. This application is intended to cover any variation, use or adaptive change of the present disclosure, which follows the general principles of the present disclosure and includes common knowledge or customary technical means in the technical field not recorded in the present disclosure.

Claims

1. A plastering device for house construction, comprising a base plate (1), characterized in that: Universal wheels (101) are installed at the four corners of the bottom of the bottom plate (1), a rotating groove (102) is provided at the top of the bottom plate (1), main side plates (2) are provided on both sides of the top of the bottom plate (1), a lifting groove (201) is provided inside the main side plate (2), a secondary side plate (3) is slidably installed inside the lifting groove (201), a lifting motor (4) is installed on the top of the secondary side plate (3), a lifting screw (5) is fixedly installed at one end of the lifting motor (4), and one end of the lifting screw (5) is connected to the inside of the bottom plate (1); A lifting plate (6) is installed on the outer side of the lifting screw (5), and both ends of the lifting plate (6) are slidably connected to the inside of the main side plate (2) and the auxiliary side plate (3). One side of the lifting plate (6) is connected to a plastering box (7), and one side of the plastering box (7) can be in close contact with the wall surface. A spiral motor (8) is installed inside the plastering box (7), and a ash storage box (9) is provided on the top of the bottom plate (1).

2. A plastering equipment for house construction according to claim 1, characterized in that: A main slide groove (202) is provided in the middle of one side of the lifting groove (201), symmetrical main limit holes (203) are provided on the top of both sides of the main side plate (2), and a secondary slide groove (301) is provided in the inner side of the secondary side plate (3), and the secondary slide groove (301) is horizontally aligned with the main slide groove (202), and symmetrical secondary limit holes (302) are provided at both upper and lower ends of both sides of the secondary side plate (3), and a short bolt (303) is installed inside the secondary limit hole (302) at one end, and one end of the short bolt (303) can pass through the main limit hole (203) and be movably connected with the inside of the secondary limit hole (302).

3. A plastering equipment for house construction according to claim 1, characterized in that: The lifting screw rod (5) comprises a main screw rod (501), a secondary screw rod (502), a connector (503) and a long bolt (504). The secondary screw rod (502) is arranged inside the main screw rod (501). One end of the secondary screw rod (502) is connected to one end of the lifting motor (4). A lower screw hole (5012) is arranged on the outer side of one end of the main screw rod (501). An upper screw hole (5013) is arranged on the outer side of the other end of the main screw rod (501). A fixing hole (5021) is arranged on one end of the secondary screw rod (502). One end of the long bolt (504) can pass through the inner side of the lower screw hole (5012) and then be movably connected to the inner side of the fixing hole (5021). One end of the long bolt (504) can also pass through the inner side of the upper screw hole (5013) and then be movably connected to the inner side of the fixing hole (5021).

4. A plastering equipment for house construction according to claim 3, characterized in that: A turntable (5011) is provided at one end of the main screw (501), and the outer side of the turntable (5011) is rotatably engaged with the inner side of the rotating groove (102). A screw groove (5031) is provided inside the connector (503), and the inner side of the screw groove (5031) cooperates with the outer side thread of the auxiliary screw (502).

5. The plastering equipment for house construction according to claim 1, characterized in that: Both ends of the lifting plate (6) are provided with sliders (601), and the outer side of the slider (601) can be slidably engaged with the inner side of the main slide groove (202) and the auxiliary slide groove (301). The top of the lifting plate (6) is provided with a slot (602), and the inner side of the slot (602) can be engaged with the outer side of the connector (503). The bottom of the slot (602) is provided with an inner screw hole (6021), and the inner side of the inner screw hole (6021) cooperates with the thread on the outer side of the main screw rod (501). Through holes (603) are provided on both sides of one side of the lifting plate (6).

6. A plastering equipment for house construction according to claim 1, characterized in that: A plastering plate groove (701) is provided on one side of the plastering plate groove (701), and a plurality of feed holes (7011) are arranged at equal intervals on one side of the plastering plate groove (701). A plurality of discharge grooves (7012) are provided on the top of the plastering plate groove (701). An inner cavity (702) is provided inside the plastering box (7), and the discharge grooves (7012) can be connected with the inner cavity (702). A mounting hole (7021) is provided on one side of the inner cavity (702). A fixer (703) is provided on one side of the outside of the plastering box (7), and the inside of the fixer (703) is connected with the mounting hole (7021), and one side of the fixer (703) is connected with the outer side of the through hole (603).

7. The plastering equipment for house construction according to claim 1, characterized in that: A spiral rod (801) is provided at one end of the spiral motor (8), and the spiral rod (801) is installed inside the inner cavity (702). Telescopic tubes (901) are installed on both sides of the interior of the ash storage box (9), and a suction pump (902) is provided at one end of the telescopic tube (901). The other end of the telescopic tube (901) passes through the through hole (603) and the interior of the fixer (703) and is connected to the inner side of the mounting hole (7021).