Positioning scaffold for building wall
By designing an adjustable positioning construction frame for building walls, automatic height and angle adjustment is achieved using hydraulic cylinders and suction cups, the limitations of construction operations caused by fixed structures are solved, construction efficiency and safety are improved, and more stable Positioning effect and stronger applicability.
Patent Information
- Application Number
- CN202323585782.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-27
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2033-12-27
AI Technical Summary
The existing positioning construction frames for building walls are usually set up with fixed structures and are not easy to adjust according to the actual situation of the construction site, resulting in limited operation during construction.
A positioning construction frame including a mounting frame, an adjustment component, a construction component, a first support component, a balance component and a pulley are designed. Through the adjustment component, the height and angle adjustment are adjusted by automatically moving up and down, and the hydraulic cylinder and suction cup are used to adjust the height and angle to enhance the Stability and applicability of the mounting frame.
Improve construction efficiency and safety, and through the synergy of multiple support components, a more stable positioning effect and stronger applicability are achieved, avoiding the danger of construction workers.
Smart Images

Figure CN221941865U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of building construction, in particular to a positioning construction frame for building walls. Background Art
[0002] Building walls are an important part of buildings, and they mainly serve as enclosures and space partitions. There are many types of walls, including walls made of a single material and walls made of composite materials. The functions of walls are thermal insulation, heat insulation, sound insulation, fire prevention and waterproofing. The positioning construction frame is a frame structure used for positioning construction of building walls, and is mainly composed of scaffolding, scaffolding pipes, fasteners, bases and protective nets. The function of the positioning construction frame is to support and fix the building walls to ensure the position and stability of the walls. At the same time, it can also protect construction personnel and materials from falling and sliding. Existing positioning construction frames for building walls are usually fixed structures, which are not easy to adjust according to the actual conditions of the construction site, which makes the operation during the construction process limited. Utility Model Content
[0003] In order to overcome the existing positioning construction frames for building walls, they are usually fixed structures, which are not easy to adjust according to the actual situation of the construction site, resulting in limitations in operation during the construction process.
[0004] The technical solution of the utility model is: a positioning construction frame for a building wall, comprising a mounting frame, an adjustment component, a construction component, a first support component, a balance component, a second support component and a pulley, the construction component and the mounting frame are adjusted and connected by the adjustment component, two groups of balance components for increasing stability are symmetrically provided at the middle part of the upper end of the mounting frame, the first support component for supporting the wall is provided at one end of the mounting frame close to the wall, the second support component for keeping the mounting frame balanced is provided at one end of the mounting frame away from the wall, and pulleys for facilitating the movement of the mounting frame are provided around the four corners of the lower end of the mounting frame.
[0005] Preferably, by setting up a construction component that can automatically move up and down to adjust the position under the control of an adjustment component, corresponding adjustments can be made according to the height of the wall and the construction conditions. There is no need to adjust the height manually, which is simple and quick, and greatly improves work efficiency. By setting up a balancing component, the stability of the mounting frame can be increased. By setting up a first support component, an auxiliary support can be provided. By setting the first connecting block and the second connecting block of the second support component to be rotatably connected with the support column, the angle of the support seat can be appropriately adjusted according to the environmental conditions of the construction site, thereby achieving better support effect. Under the multiple effects of the first support component, the second support component and the balancing component, the mounting frame is more stable and the positioning effect is better, thereby ensuring the safe and orderly progress of the construction work.
[0006] Preferably, the adjustment component includes a hydraulic cylinder, a hydraulic rod, a support frame, a support block and a connecting plate. The hydraulic rod is arranged at the corners around the lower end of the construction component. The hydraulic cylinder is provided with an output shaft. The hydraulic cylinder controls the up and down movement of the hydraulic cylinder by controlling the output shaft. The left and right sides of the hydraulic rod are symmetrically provided with support frames for support. The lower end of the support frame is provided with a support block for increasing stability. The first mounting holes for installing and fixing the support block are opened around the four corners of the upper end of the support block. The two groups of hydraulic rods in the same row are fixedly connected by a connecting plate. The stability of the hydraulic rod can be increased by connecting the two groups of hydraulic rods using the connecting plate.
[0007] Preferably, the construction assembly includes a construction platform, a protective frame and a protective door. A protective frame is provided on the upper side of the construction platform to increase safety. A plurality of groups of second mounting holes for installing related auxiliary support structures are linearly distributed on the surface of the protective frame. A protective door for opening and closing is provided at one end of the construction platform away from the wall. The protective frame and the protective door can protect the safety of workers on the construction platform.
[0008] Preferably, the first support assembly includes a support plate, a connecting column and a first suction cup. A plurality of groups of first suction cups for sucking to the wall surface are linearly distributed at one end of the support plate close to the wall. The first suction cup is fixedly connected to the support plate through the connecting column. The first suction cup can suck the wall surface, thereby increasing the stability of the mounting frame.
[0009] Preferably, the balancing assembly includes an adjusting bolt and a second suction cup, the adjusting bolt extending through the upper end of the mounting frame to the lower end to adjust the position of the second suction cup, the adjusting bolt is threadedly connected to the mounting frame, and the position of the second suction cup can be controlled by turning the adjusting bolt, so that during operation, the adjusting bolt can be turned to move the suction cup downward and suck the ground.
[0010] Preferably, the second support assembly includes a first connecting block, a support column, a second connecting block, a support seat and a drive motor. The first connecting block and the second connecting block are rotatably connected via the support column. The lower end of the second connecting block is provided with a support seat for increasing stability. The upper end of the support seat is surrounded by four corners with third mounting holes for installing and fixing the support seat for related auxiliary support structures. By opening the third mounting holes, some auxiliary support structures can be appropriately added according to different construction site environments, thereby making the construction frame more applicable.
[0011] Preferably, an output shaft is provided on the driving motor, and the output shaft of the driving motor extends through the outer sides of the first connecting block and the second connecting block to the inner sides to drive the support column and the second connecting block to rotate. By driving the support column and the second connecting block to rotate by the driving motor, the angle of the support seat can be adjusted to adapt to the environment of the construction site.
[0012] Beneficial effects of the utility model:
[0013] 1. Compared with the traditional positioning construction frame for building walls, which is usually a fixed structure, it is not easy to adjust it according to the actual situation of the construction site, which makes the operation during the construction process limited. By setting up a construction component that can automatically move up and down to adjust the position using an adjustment component, it can be adjusted accordingly according to the height of the wall and the construction situation. There is no need to adjust the height manually, which is simple and fast, and greatly improves the work efficiency. By setting up a hydraulic cylinder, the hydraulic rod can be controlled to move up and down, thereby driving the construction platform to move up and down, and walls of different heights can be constructed. By setting up a balancing component, the stability of the mounting frame can be increased. By turning the adjusting bolt, the second suction cup can be controlled to move up and down. During the construction process, the suction cup tightly adheres to the ground, which makes it difficult for the mounting frame to shift, thereby ensuring the safety of the construction workers.
[0014] 2. The first support assembly can be provided to play an auxiliary support role. By providing multiple groups of first suction cups on the support plate to suck the wall, the mounting frame can be made more stable. By providing the second support assembly to provide support on the other side, the first suction cup can be more firmly sucked. By providing the first connecting block and the second connecting block of the second support assembly to be rotatably connected with the support column, the angle of the support seat can be appropriately adjusted according to the environmental conditions of the construction site, so as to achieve better support effect. Under the multiple effects of the first support assembly, the second support assembly and the balancing assembly, the mounting frame is more stable and has better positioning effect, thereby ensuring the safe and orderly progress of the construction work. The protection frame can be provided to protect the construction personnel. The shielding effect of the protection frame can prevent the staff from accidentally stepping on the air and slipping to cause danger. By opening multiple groups of second mounting holes on the protection frame, some auxiliary support structures can be installed, which is convenient for appropriate adjustment according to different construction scenes and has stronger applicability. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 What is shown is the overall schematic diagram of the positioning construction frame for the building wall of the utility model;
[0016] Figure 2 Shown is a schematic diagram of another angle of the positioning construction frame for the building wall of the utility model;
[0017] Figure 3 Shown is a schematic diagram of an adjustment component in a positioning construction frame for a building wall of the utility model;
[0018] Figure 4 Shown is a schematic diagram of the first supporting assembly in the positioning construction frame for the building wall of the utility model;
[0019] Figure 5Shown is a schematic diagram of the second supporting assembly in the positioning construction frame for the building wall of the utility model.
[0020] Explanation of the accompanying drawings: 1. mounting frame; 2. adjustment assembly; 3. construction assembly; 4. first support assembly; 5. balancing assembly; 6. second support assembly; 7. pulley; 201. hydraulic cylinder; 202. hydraulic rod; 203. support frame; 204. support block; 205. first mounting hole; 206. connecting plate; 301. construction platform; 302. protective frame; 303. second mounting hole; 304. protective door; 401. support plate; 402. connecting column; 403. first suction cup; 501. adjustment bolt; 502. second suction cup; 601. first connecting block; 602. support column; 603. second connecting block; 604. support seat; 605. drive motor; 606. third mounting hole. Implementation
[0021] The utility model is further described below in conjunction with the accompanying drawings and embodiments.
[0022] See also Figure 1-2 The utility model provides an embodiment: a positioning construction frame for a building wall, comprising a mounting frame 1, an adjustment component 2, a construction component 3, a first support component 4, a balance component 5, a second support component 6 and a pulley 7. The construction component 3 is connected to the mounting frame 1 by adjustment through the adjustment component 2. Two groups of balance components 5 for increasing stability are symmetrically arranged in the middle of the upper end of the mounting frame 1. The first support component 4 for supporting the wall is arranged at one end of the mounting frame 1 close to the wall. The second support component 6 for keeping the mounting frame 1 balanced is arranged at one end of the mounting frame 1 away from the wall. Pulleys 7 for facilitating the movement of the mounting frame 1 are arranged around the four corners of the lower end of the mounting frame 1.
[0023] See also Figure 3In this embodiment, the adjustment component 2 includes a hydraulic cylinder 201, a hydraulic rod 202, a support frame 203, a support block 204 and a connecting plate 206. The hydraulic rod 202 is arranged at the corners around the lower end of the construction component 3. The hydraulic cylinder 201 is provided with an output shaft. The hydraulic cylinder 201 controls the hydraulic cylinder 201 to move up and down by controlling the output shaft. The left and right sides of the hydraulic rod 202 are symmetrically provided with support frames 203 for support. The lower end of the support frame 203 is provided with a support block 204 for increasing stability. The upper four corners of the support block 204 are surrounded by first mounting holes 205 for mounting and fixing the support block 204. The two groups of hydraulic The pressure rod 202 is fixedly connected by a connecting plate 206. Using the connecting plate 206 to connect the two groups of hydraulic rods 202 can increase the stability of the hydraulic rods 202. The construction component 3 includes a construction platform 301, a protective frame 302 and a protective door 304. The upper side of the construction platform 301 is provided with a protective frame 302 for increasing safety. The surface of the protective frame 302 is linearly distributed and has multiple groups of second mounting holes 303 for installing related auxiliary support structures. A protective door 304 for opening and closing is provided at one end of the construction platform 301 away from the wall. The protective frame 302 and the protective door 304 can protect the safety of the workers on the construction platform 301.
[0024] See also Figure 4 In this embodiment, the first support assembly 4 includes a support plate 401, a connecting column 402 and a first suction cup 403. The support plate 401 has a plurality of first suction cups 403 linearly distributed at one end close to the wall and used to be sucked together with the wall surface. The first suction cups 403 are fixedly connected to the support plate 401 through the connecting column 402. The first suction cups 403 can suck the wall surface, thereby increasing the stability of the mounting frame 1. The balancing assembly 5 includes an adjusting bolt 501 and a second suction cup 502. The adjusting bolt 501 passes through the upper end of the mounting frame 1 and extends to the lower end to adjust the position of the second suction cup 502. The adjusting bolt 501 is threadedly connected to the mounting frame 1. The position of the second suction cup 502 can be controlled by screwing the adjusting bolt 501, so that the adjusting bolt 501 can be screwed during work to make the suction cup move downward and suck the ground.
[0025] See also Figure 5In this embodiment, the second support assembly 6 includes a first connecting block 601, a support column 602, a second connecting block 603, a support seat 604 and a driving motor 605. The first connecting block 601 and the second connecting block 603 are rotatably connected through the support column 602. The lower end of the second connecting block 603 is provided with a support seat 604 for increasing stability. The upper end of the support seat 604 is surrounded by four corners with third mounting holes 606 for installing and fixing the support seat 604 for related auxiliary supporting structures. By opening the third mounting holes 606, some auxiliary supporting structures can be appropriately added according to different construction site environments, thereby making the construction frame more applicable.
[0026] When working, first push the construction frame, use the pulley 7 to drive the installation frame 1 to move, and push the installation frame 1 to the corresponding construction site, so that the first suction cup 403 is tightly attached to the wall;
[0027] Then, the driving motor 605 is used to drive the support column 602 and the second connecting block 603 to rotate, and the support base 604 is adjusted to make it fit the ground to support the mounting frame 1, and then the support base 604 is installed and fixed through the third mounting hole 606;
[0028] Then, the adjusting bolt 501 on the balancing assembly 5 is screwed to move the second suction cup 502 downward until it is tightly attached to the ground.
[0029] After the mounting frame 1 remains stable, the hydraulic cylinder 201 is used to control the hydraulic rod 202 to move downward, and the construction platform 301 is adjusted to the lowest position. The worker opens the protective door 304 and then goes onto the construction platform 301, and then closes the protective door 304.
[0030] Finally, the hydraulic cylinder 201 is used to control the hydraulic rod 202 to move upward to move the construction platform 301 to a suitable height, and the staff carry out construction work. During the work process, the hydraulic cylinder 201 is used to control the hydraulic rod 202 to appropriately adjust the external position of the construction platform 301. After the work is completed, the construction platform 301 is adjusted to a suitable position and the staff can get down.
[0031] Through the above steps, the staff first pushes the construction frame, uses the pulley 7 to drive the installation frame 1 to move, and pushes the installation frame 1 to the corresponding construction site, so that the first suction cup 403 is tightly attached to the wall, and then uses the driving motor 605 to drive the support column 602 and the second connecting block 603 to rotate, adjusts the support seat 604 to make it fit with the ground to support the installation frame 1, and then installs and fixes the support seat 604 through the third mounting hole 606, and then screws the adjusting bolt 501 on the balancing component 5 to make the second suction cup 502 move downward until it is tightly attached to the ground. Under the multiple effects of the first supporting component 4, the second supporting component 6 and the balancing component 5, the installation frame 1 is more stable and the positioning effect is better, thereby ensuring the safe and orderly progress of the construction work. After the installation frame 1 remains stable, use The hydraulic cylinder 201 is used to control the hydraulic rod 202 to move downward, and the construction platform 301 is adjusted to the lowest position. The worker opens the protective door 304 and then goes onto the construction platform 301, then closes the protective door 304, and finally uses the hydraulic cylinder 201 to control the hydraulic rod 202 to move upward to move the construction platform 301 to a suitable height. The worker performs construction work and uses the hydraulic cylinder 201 to control the hydraulic rod 202 to appropriately adjust the external position of the construction platform 301 during the work process. After the work is completed, the construction platform 301 is adjusted to a suitable position and the worker can get off. By setting up a construction component 3 that can automatically move up and down and adjust the position using the adjustment component 2, corresponding adjustments can be made according to the height of the wall and the construction situation. There is no need for manual operation to adjust the height, which is simple and quick, and greatly improves work efficiency.
[0032] The embodiments of the present invention are described in detail above in conjunction with the accompanying drawings, but the present invention is not limited to the above embodiments, and various changes can be made within the knowledge scope of those skilled in the art without departing from the purpose of the present invention.
Claims
1. A positioning construction frame for a building wall, comprising a mounting frame (1); characterized in that: The invention also comprises an adjustment component (2), a construction component (3), a first support component (4), a balance component (5), a second support component (6) and a pulley (7); the construction component (3) is connected to the mounting frame (1) by adjustment via the adjustment component (2); two groups of balance components (5) for increasing stability are symmetrically arranged at the middle of the upper end of the mounting frame (1); the first support component (4) for supporting the wall is arranged at one end of the mounting frame (1) close to the wall; the second support component (6) for keeping the mounting frame (1) balanced is arranged at one end of the mounting frame (1) away from the wall; and pulleys (7) for facilitating the movement of the mounting frame (1) are arranged around the four corners of the lower end of the mounting frame (1).
2. A positioning construction frame for a building wall according to claim 1, characterized in that: The adjustment component (2) comprises a hydraulic cylinder (201), a hydraulic rod (202), a support frame (203), a support block (204) and a connecting plate (206); the hydraulic rod (202) is arranged at the corners around the lower end of the construction component (3); an output shaft is arranged on the hydraulic cylinder (201); the hydraulic cylinder (201) controls the hydraulic cylinder (201) to move up and down by controlling the output shaft; support frames (203) for supporting are symmetrically arranged on the left and right sides of the hydraulic rod (202); a support block (204) for increasing stability is arranged at the lower end of the support frame (203); first mounting holes (205) for mounting and fixing the support block (204) are arranged around the four corners of the upper end of the support block (204); and two groups of hydraulic rods (202) located in the same row are fixedly connected by a connecting plate (206).
3. A positioning construction frame for a building wall according to claim 1, characterized in that: The construction assembly (3) comprises a construction platform (301), a protection frame (302) and a protection door (304); the protection frame (302) for increasing safety is provided on the upper side of the construction platform (301); a plurality of groups of second mounting holes (303) for mounting related auxiliary support structures are linearly distributed on the surface of the protection frame (302); and a protection door (304) for opening and closing is provided at one end of the construction platform (301) away from the wall.
4. A positioning construction frame for a building wall according to claim 1, characterized in that: The first support assembly (4) comprises a support plate (401), a connecting column (402) and a first suction cup (403); a plurality of groups of first suction cups (403) for sucking together with the wall surface are linearly distributed at one end of the support plate (401) close to the wall; the first suction cups (403) are fixedly connected to the support plate (401) via the connecting column (402).
5. The positioning construction frame for building wall according to claim 1, characterized in that: The balancing assembly (5) comprises an adjusting bolt (501) and a second suction cup (502); the adjusting bolt (501) passes through the upper end of the mounting frame (1) and extends to the lower end to adjust the position of the second suction cup (502); the adjusting bolt (501) is threadedly connected to the mounting frame (1).
6. A positioning construction frame for a building wall according to claim 1, characterized in that: The second support assembly (6) comprises a first connection block (601), a support column (602), a second connection block (603), a support seat (604) and a drive motor (605); the first connection block (601) and the second connection block (603) are rotatably connected via the support column (602); a support seat (604) for increasing stability is provided at the lower end of the second connection block (603); and third mounting holes (606) for mounting and fixing the support seat (604) and for related auxiliary support structures are provided around the four corners of the upper end of the support seat (604).
7. A positioning construction frame for a building wall according to claim 6, characterized in that: An output shaft is provided on the driving motor (605), and the output shaft of the driving motor (605) passes through the outer sides of the first connecting block (601) and the second connecting block (603) respectively and extends to the inner sides to drive the supporting column (602) and the second connecting block (603) to rotate.