Concrete pouring and vibrating equipment
By designing concrete pouring equipment that supports components and vibration mechanisms, workers are allowed to vibrate in non-cast areas, solving the problem of limited operation of traditional equipment, improving construction efficiency and safety, and reducing the work burden of workers.
Patent Information
- Application Number
- CN202420499466.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-14
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2034-03-14
AI Technical Summary
The operation of traditional concrete pouring vibration equipment is limited, resulting in workers having to frequently move and adjust the equipment position, increasing construction complexity, affecting efficiency, and posing safety risks.
Design a concrete pouring vibration equipment including telescopic rods, support components, connecting frames, casting pipes and vibration mechanisms. The telescopic rods are supported by hydraulic cylinders and U-shaped frames, combined with guide rods and elastic parts to absorb shock, and the anti-slip sleeve is improved. Holding stability allows workers to vibrating in non-cast areas.
It has achieved a large-scale workability, reduced work intensity for workers, improved construction efficiency, reduced safety risks, and reduced arm fatigue and equipment vibration burden on the body through shock absorption and enhanced grip stability.
Smart Images

Figure CN221941964U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of construction engineering equipment, in particular to a concrete pouring and vibrating device. Background Art
[0002] Vibration is one of the important steps in concrete pouring. Concrete vibration refers to a process of vibrating and compacting concrete using vibration equipment during the concrete pouring process. The purpose of this process is to improve the density and uniformity of concrete, better combine concrete with steel bars, and thus improve the seismic resistance and durability of concrete. Insertion vibration is one of the most widely used vibration methods. Its working principle is to transmit vibration waves directly to concrete through a vibrating rod, so that a tighter structure is formed inside the concrete. The traditional pouring vibration method requires workers to operate the vibration equipment by hand and vibrate in the pouring area.
[0003] The operation of the vibrating equipment in the prior art is limited by the pouring area, and workers need to frequently move and adjust the position of the vibrating equipment, which not only increases the complexity of construction and affects work efficiency, but also causes a greater burden on the workers' bodies due to the vibration of the vibrating equipment. In addition, since workers need to operate in the pouring area, there are certain safety risks. Therefore, it is necessary to design a new pouring vibrating equipment to solve the deficiencies in the prior art. Utility Model Content
[0004] In order to overcome the shortcomings in the prior art that the operation of the vibrating equipment is limited by the pouring area and workers need to frequently move and adjust the position of the vibrating equipment, the utility model provides a concrete pouring and vibrating equipment, which enables workers to perform pouring and vibrating work in non-pouring areas.
[0005] A concrete pouring and vibrating device comprises a telescopic rod, a supporting assembly, a connecting frame one, a pouring wall pipe, a connecting frame two and a vibrating mechanism. A supporting assembly is arranged at the bottom right of the telescopic rod for supporting the telescopic rod. The left end of the telescopic rod is fixedly connected to the connecting frame one. The left end of the connecting frame one is connected to the pouring wall pipe. The pouring wall pipe is connected to the vibrating mechanism through the connecting frame two for vibrating concrete. The connecting frame two is located above the connecting frame one.
[0006] As an improvement of the above solution, the support assembly includes a tripod, a hydraulic cylinder and a U-shaped frame. The top of the tripod is provided with a hydraulic cylinder, the top of the hydraulic cylinder is rotatably provided with a U-shaped frame, and the telescopic rod is located in the U-shaped frame.
[0007] As an improvement of the above scheme, the vibration mechanism includes a vibrating rod, a connecting rod and a vibration motor. Two vibrating rods are connected to the end of the connecting frame away from the casting wall pipe. A connecting rod is arranged between the upper sections of the vibrating rods. The connecting rod is located above the telescopic rod, and a vibration motor is installed on the left side of the connecting rod.
[0008] As an improvement of the above scheme, it also includes a guide rod and an elastic member. The top of the telescopic rod is fixedly connected to the guide rod near the top of the connecting frame 1. The top of the guide rod is slidably connected to the connecting frame 2, and the elastic member is sleeved on the guide rod.
[0009] As an improvement of the above solution, an anti-slip cover is also included. The right end of the telescopic rod is provided with an anti-slip cover.
[0010] As an improvement of the above solution, a rubber pad is also included. The bottoms of the three legs of the tripod are all provided with rubber pads.
[0011] The beneficial effects of the utility model are:
[0012] 1. The utility model supports the telescopic rod by arranging a supporting assembly, and is connected to the casting wall pipe through the telescopic rod. The casting wall pipe is connected with a vibrating mechanism, which provides a wider range of workability, allowing workers to perform casting and vibration work in non-casting areas, which can greatly reduce the work intensity of the workers, improve construction efficiency, and reduce safety risks.
[0013] 2. The utility model can reduce the vibration of the telescopic rod when the vibrating mechanism is working through the cooperation of the guide rod and the elastic member, thereby reducing the fatigue of the worker's arm caused by vibration. The anti-slip sleeve can increase the friction of the contact surface of the worker holding the telescopic rod and improve the stability of holding. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a three-dimensional structural schematic diagram of the utility model.
[0015] Figure 2 It is a schematic diagram of the installation structure of the telescopic rod and the supporting assembly of the utility model.
[0016] Figure 3 The utility model is a schematic diagram of the installation structure of the vibrating mechanism, the guide rod and the elastic member.
[0017] The reference numbers in the figure are: 1. telescopic rod, 2. supporting assembly, 201. tripod, 202. hydraulic cylinder, 203. U-shaped frame, 3. connecting frame one, 4. casting wall pipe, 5. connecting frame two, 6. vibrating mechanism, 601. vibrating rod, 602. connecting rod, 603. vibration motor, 7. guide rod, 8. elastic part, 9. anti-slip sleeve, 10. rubber pad. DETAILED DESCRIPTION
[0018] The above scheme is further described below in conjunction with specific examples. It should be understood that these examples are used to illustrate the present application and are not limited to the scope of the present application. The implementation conditions adopted in the examples can be further adjusted according to the conditions of the specific manufacturer, and the implementation conditions not specified are usually the conditions in conventional experiments.
[0019] Embodiment: A concrete pouring and vibrating device, such as Figure 1-Figure 3 As shown, it includes a telescopic rod 1, a supporting assembly 2, a connecting frame 1 3, a casting wall pipe 4, a connecting frame 2 5 and a vibrating mechanism 6. A supporting assembly 2 for supporting the telescopic rod 1 is arranged at the bottom of the right side of the telescopic rod 1. The left end of the telescopic rod 1 is fixedly connected to the connecting frame 1 3 by welding. The left end of the connecting frame 1 3 is connected to the casting wall pipe 4 by bolts. One end of the connecting frame 2 5 is connected to the casting wall pipe 4 by bolts, and the other end is connected to the vibrating mechanism 6 for vibrating concrete by bolts. The connecting frame 2 5 is located above the connecting frame 1 3.
[0020] like Figure 1 and Figure 2 As shown, the support assembly 2 includes a tripod 201, a hydraulic cylinder 202 and a U-shaped frame 203. The hydraulic cylinder 202 is welded to the top of the tripod 201, and the U-shaped frame 203 is rotatably arranged on the top of the hydraulic cylinder 202. The telescopic rod 1 is installed on the U-shaped frame 203 through a screw and can rotate inside the U-shaped frame 203.
[0021] like Figure 1 and Figure 3 As shown, the vibrating mechanism 6 includes a vibrating rod 601, a connecting rod 602 and a vibration motor 603. The end of the connecting frame 2 5 away from the casting wall tube 4 is connected with two vibrating rods 601 by bolts. A connecting rod 602 is arranged between the upper sections of the vibrating rods 601 by welding. The connecting rod 602 is located above the telescopic rod 1, and the vibration motor 603 is installed on the left side of the connecting rod 602 by bolts.
[0022] When in use, the worker places the tripod 201 of the device in the non-casting area, starts the hydraulic cylinder 202, moves the telescopic rod 1 upward to a suitable height, closes the hydraulic cylinder 202, connects the connecting frame 1 3 and the connecting frame 2 5 to the casting wall pipe 4, and installs the vibrating mechanism 6 at the end of the connecting frame 2 5 away from the casting wall pipe 4. When the casting wall pipe 4 is driven to move to the casting area by the pumping wall of the external pump truck, the casting wall pipe 4 will drive the telescopic rod 1 to extend through the connecting frame 1 3, and then the pump truck pumps concrete to the casting wall pipe 4, and flows out from the pipe mouth to the casting area. The worker then starts the vibration motor 603, and the vibration motor 603 vibrates the two vibrating rods 601. The worker in the non-casting area rotates the telescopic rod 1 up and down on the U-shaped frame 203 by hand, thereby moving the casting wall pipe 4 up and down, and then moving the vibrating rod 601 up and down, inserting it into the concrete to directly transmit the vibration wave to the concrete, so that a tighter structure is formed inside the concrete. When the casting wall pipe 4 moves to different areas on the horizontal plane, the casting wall pipe 4 can not only drive the telescopic rod 1 to extend or contract, but also make the U-shaped frame 203 rotate on the top of the hydraulic cylinder 202 through the telescopic rod 1, so as to maintain a larger working range and reduce the number of times the workers move during the operation, which can greatly reduce the workers' work intensity, improve construction efficiency, and reduce safety risks. After the casting construction is completed, the staff will turn off the vibration motor 603 to end the operation.
[0023] like Figure 3 As shown, it also includes a guide rod 7 and an elastic member 8. The telescopic rod 1 is fixedly connected to the guide rod 7 near the top of the connecting frame 1 3 by welding. The connecting frame 2 5 has a through opening. The top of the guide rod 7 passes through the square opening and is slidably connected to the connecting frame 2 5. The elastic member 8 is sleeved on the guide rod 7. One end of the elastic member 8 is connected to the telescopic rod 1, and the other end is connected to the connecting frame 2 5.
[0024] like Figure 1 and Figure 2 As shown, an anti-slip cover 9 is also included. The right end of the telescopic rod 1 is provided with the anti-slip cover 9.
[0025] like Figure 1 and Figure 2 As shown, a rubber pad 10 is also included. The bottoms of the three legs of the tripod 201 are all provided with a rubber pad 10 .
[0026] When the vibrating mechanism 6 is working, the guide rod 7 and the elastic member 8 cooperate to reduce the vibration of the telescopic rod 1, thereby reducing the fatigue of the worker's arm caused by the vibration. The anti-slip sleeve 9 can increase the friction of the contact surface of the worker holding the telescopic rod 1, thereby improving the grip stability. The rubber pad 10 can increase the friction between the tripod 201 and the ground surface, thereby enhancing the stability of the device when working.
[0027] The above embodiments are only preferred embodiments of the present invention and are not intended to limit the scope of implementation of the present invention. Therefore, any equivalent changes made to the contents described in the claims of the present invention should be included in the scope of the claims of the present invention.
Claims
1. A concrete pouring and vibrating device, characterized in that: The invention comprises a telescopic rod (1), a support assembly (2) is arranged at the bottom right of the telescopic rod (1) for supporting the telescopic rod (1), a connecting frame 1 (3) is fixedly connected to the left end of the telescopic rod (1), a casting wall pipe (4) is connected to the left end of the connecting frame 1 (3), the casting wall pipe (4) is connected to a vibrating mechanism (6) via a connecting frame 2 (5) for vibrating concrete, and the connecting frame 2 (5) is located above the connecting frame 1 (3).
2. A concrete pouring and vibrating device as claimed in claim 1, characterized in that: The support assembly (2) comprises a tripod (201), a hydraulic cylinder (202) is arranged on the top of the tripod (201), a U-shaped frame (203) is rotatably arranged on the top of the hydraulic cylinder (202), and the telescopic rod (1) is located in the U-shaped frame (203).
3. A concrete pouring and vibrating device as claimed in claim 2, characterized in that: The vibrating mechanism (6) comprises a vibrating rod (601), two vibrating rods (601) are connected to one end of the second connecting frame (5) away from the casting wall pipe (4), a connecting rod (602) is arranged between the upper sections of the vibrating rods (601), the connecting rod (602) is located above the telescopic rod (1), and a vibration motor (603) is installed on the left side of the connecting rod (602).
4. A concrete pouring and vibrating device as claimed in claim 3, characterized in that: It also includes a guide rod (7) and an elastic member (8). The guide rod (7) is fixedly connected to the top of the telescopic rod (1) near the first connecting frame (3). The top of the guide rod (7) is slidably connected to the second connecting frame (5). The elastic member (8) is sleeved on the guide rod (7).
5. A concrete pouring and vibrating device as claimed in claim 4, characterized in that: It also includes an anti-slip sleeve (9), which is arranged on the right end of the telescopic rod (1).
6. A concrete pouring and vibrating device as claimed in claim 5, characterized in that: It also includes a rubber pad (10), and the bottoms of the three legs of the tripod (201) are all provided with a rubber pad (10).
Citation Information
Cited By
Concrete pouring and vibrating equipment
CN121321800A