Tunnel construction system

By introducing detachable sub-gantry sets and adjustment components into the tunnel construction system, adjusting the angle of the arc top mold, the time-consuming and labor-consuming problem of disassembly and assembly when the tunnel cross-section changes is solved, and the convenience of disassembly and assembly of the tunnel construction system is achieved The diversified demand for grouting and supporting molds has improved construction efficiency.

CN221942450UActive Publication Date: 2024-11-01THE FIFTH ENG CO LTD OF CHINA TIESIJU CIVIL ENG GRP +6
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420022342.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-04
Publication Date
2024-11-01
Estimated Expiration
2034-01-04

AI Technical Summary

Technical Problem

In the prior art, the second lining trolley needs to be redisassembled and installed when the tunnel cross-section changes, which makes it time-consuming and labor-consuming to disassemble and install, and it is difficult to meet the needs of convenient disassembly and assembly, load-bearing requirements and diversified functions.

Method used

A tunnel construction system was designed, including a detachable sub-gantry group and adjustment components. By adjusting the angle and telescopic components of the arc top mold, the grouting support mold requirements after the tunnel cross-section change are achieved, and the second lining trolley is avoided to re-disassemble the second lining trolley. , it is only necessary to remove the secondary gantry group and top mold system to achieve convenient disassembly and assembly.

Benefits of technology

It realizes the convenience of disassembly and assembly when the tunnel cross-section changes, meets the diversified needs of grouting and supporting molds, reduces the disassembly and assembly time and labor, and improves construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221942450U_ABST
    Figure CN221942450U_ABST
Patent Text Reader

Abstract

The utility model provides a tunnel construction system which comprises a secondary lining trolley, the secondary lining trolley comprises a main portal frame, an auxiliary portal frame set and a formwork structure, the formwork structure comprises a first side formwork system and a top formwork system, and the first side formwork system comprises a plurality of first arc-shaped side formworks and a first telescopic assembly connected with the first arc-shaped side formworks and the auxiliary portal frame set. The top formwork system comprises a supporting assembly, a plurality of arc-shaped top formworks located above the supporting assembly and an adjusting assembly connected with the supporting assembly and the arc-shaped top formworks, the main portal and the auxiliary portal set are connected with the supporting assembly through a jacking assembly, and the supporting assembly comprises a first supporting frame body located above the main portal and a second supporting frame body located above the auxiliary portal set; the two ends of the adjusting assembly are connected with the supporting assembly and the arc-shaped top formwork in a rotating mode respectively, a secondary lining trolley does not need to be dismantled again, and only the auxiliary portal frame set needs to be dismantled and the top formwork system needs to be adjusted, so that the requirement for convenient disassembly and assembly can be met.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of tunnel engineering, in particular to a tunnel construction system. Background Art

[0002] There are two main types of tunnel cross-section structures in highway tunnels, one is the normal section (the tunnel cross-section radius does not change), and the other is the widened section (also called the emergency parking strip, where the tunnel cross-section radius becomes larger).

[0003] In the existing technology, a secondary lining trolley is usually used to carry out grouting and formwork support inside the tunnel. When the tunnel cross-section changes, the secondary lining trolley needs to be disassembled and reassembled. Since the secondary lining trolley is assembled from a large number of steel structures, it is very time-consuming and labor-intensive to disassemble and reassemble. Therefore, it is urgent to design a tunnel construction system to meet the needs of easy disassembly and assembly, sufficient bearing capacity and diversified functions. Utility Model Content

[0004] In view of the shortcomings of the prior art, the purpose of the utility model is to provide a tunnel construction system, aiming to solve the technical problem in the prior art that when the tunnel cross-section changes, the second lining trolley needs to be disassembled and reassembled, and since the second lining trolley is assembled from a large number of steel structures, it is very time-consuming and labor-intensive to disassemble and reassemble it.

[0005] In order to achieve the above purpose, the utility model is implemented through the following technical solutions:

[0006] A tunnel construction system, comprising a secondary lining trolley for grouting formwork, the secondary lining trolley comprising a main portal, a secondary portal assembly detachably arranged on a side of the main portal close to a tunnel cross-section change, and a template structure arranged around the main portal and the secondary portal assembly, the template structure comprising a first side formwork system arranged on a side of the secondary portal assembly away from the main portal, and a top formwork system located above the main portal and the secondary portal assembly, the first side formwork system comprising a plurality of first arc-shaped side forms hinged to each other, and a first telescopic assembly connecting the first arc-shaped side formwork and the secondary portal assembly, The top mold system includes a support assembly, a plurality of arc-shaped top molds hinged to each other and located above the support assembly, and an adjustment assembly connecting the support assembly and the arc-shaped top mold. The main portal and the auxiliary portal group are connected to the support assembly through a lifting assembly. The support assembly includes a first support frame body located above the main portal, and a second support frame body located above the auxiliary portal group. The second support frame body is slidably connected to the first support frame body through a second telescopic assembly, and both ends of the adjustment assembly are rotatably connected to the support assembly and the arc-shaped top mold respectively.

[0007] Compared with the prior art, the beneficial effects of the utility model are:

[0008] Firstly, a detachable sub-gantry group is arranged on the side of the main gantry close to the change of tunnel cross section, and the size of the sub-gantry group is arranged according to the actual situation. When the cross section of the tunnel becomes smaller, the sub-gantry group only needs to be removed to meet the tunnel size requirement. Then, a second telescopic assembly connected to the second support frame is arranged on the first support frame in the top formwork system. When the sub-gantry group is removed, the jacking assembly is removed together, and then the second telescopic assembly is started to pull the second support frame toward the first support frame. At the same time, a row of adjustment assemblies of the first support frame close to the second support frame and the arc top formwork connected to the row of adjustment assemblies are removed, and the second support frame drives the adjustment assembly and the arc top formwork thereon to move toward the first support frame. Since the arc top forms are hinged to each other, the angle between the arc top forms can be readjusted by the adjustment assembly to match the curvature of the tunnel after the cross-section change, so as to meet the grouting formwork requirement of the tunnel after the cross-section change. The utility model does not need to dismantle the second lining trolley again, and only needs to dismantle the sub-gantry group and adjust the top formwork system thereon to achieve the requirement of convenient disassembly and assembly.

[0009] Furthermore, the sub-gantry group is composed of a plurality of sub-gantry frames, and adjacent sub-gantry frames are detachably connected.

[0010] Furthermore, the first support frame includes a plurality of first main beams arranged at intervals along the extension direction of the tunnel, and a plurality of first beams arranged at intervals between the first main beams; the second support frame includes a plurality of second main beams arranged at intervals along the extension direction of the tunnel, and a plurality of second beams arranged at intervals between the second main beams; the second main beams are slidably connected to the first main beams.

[0011] Furthermore, the second telescopic assembly is fixedly connected to an end of the first supporting frame body away from the auxiliary door frame group, and the extended end of the second telescopic assembly is connected to the second supporting frame body.

[0012] Furthermore, the lifting assembly includes a plurality of jacks arranged in an array below the supporting assembly.

[0013] Furthermore, the adjustment assembly includes a plurality of oil cylinders arranged in an array above the support assembly, and each row of the plurality of oil cylinders arranged along the extension direction of the tunnel are connected to the same arc-shaped top mold.

[0014] Furthermore, the template structure also includes a second side mold system arranged on the side of the main portal away from the auxiliary portal, and the second side mold system includes a plurality of second arc-shaped side molds hinged to each other, and a third telescopic component connecting the second arc-shaped side mold and the main portal.

[0015] Furthermore, adjacent arc-shaped top molds are rotatably connected via detachable hinges.

[0016] Furthermore, it also includes a rail system located below the secondary lining trolley, and a walking system matching the rail system is provided below the main portal and the auxiliary portal assembly. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 This is a schematic diagram of the structure of the tunnel construction system in the embodiment of the utility model;

[0018] Figure 2 for Figure 1 Structural schematic diagram of the middle top mold system;

[0019] Figure 3 for Figure 2 A magnified view of part A;

[0020] Figure 4 for Figure 2 A schematic diagram of the structure of the middle arc top mold and the adjustment assembly when the arc top mold is in a first arc state;

[0021] Figure 5 for Figure 2 A schematic diagram of the structure of the middle arc top mold and the adjustment assembly when the arc top mold is in a second arc state;

[0022] Description of main component symbols:

[0023] Main gantry 10 The first mast 20 Second mast 30 Top mold system 40 The first curved side mold 51 First telescopic component 52 The second curved side mold 61 The third telescopic component 62 Lifting components 41 The first supporting frame 42 The second supporting frame 43 Second telescopic component 44 Adjustment components 45 Curved top mold 46 Mounting Plate 47 Chute 48

[0024] The following specific implementation manner will further illustrate the present utility model in conjunction with the above-mentioned drawings. DETAILED DESCRIPTION

[0025] In order to facilitate the understanding of the present invention, the present invention will be described more fully below with reference to the relevant drawings. Several embodiments of the present invention are given in the drawings. However, the present invention can be implemented in many different forms and is not limited to the embodiments described herein. On the contrary, the purpose of providing these embodiments is to make the disclosure of the present invention more thorough and comprehensive.

[0026] It should be noted that when an element is referred to as being "fixed to" another element, it may be directly on the other element or there may be a central element. When an element is considered to be "connected to" another element, it may be directly connected to the other element or there may be a central element at the same time. The terms "vertical", "horizontal", "left", "right" and similar expressions used herein are for illustrative purposes only.

[0027] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art in the technical field of the present invention. The terms used herein in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. The term "and / or" used herein includes any and all combinations of one or more related listed items.

[0028] See also Figures 1 to 5 , shown is a tunnel construction system in an embodiment of the utility model, including a secondary lining trolley for grouting formwork, the secondary lining trolley includes a main portal 10, a secondary portal group detachably arranged on the side of the main portal 10 close to the tunnel cross-section change, and a template structure arranged around the main portal 10 and the secondary portal group, the template structure includes a first side mold system arranged on the side of the secondary portal group away from the main portal 10, and a top mold system 40 located above the main portal 10 and the secondary portal group, the first side mold system includes a plurality of first arc-shaped side molds 51 hinged to each other, and a first telescopic assembly 5 connecting the first arc-shaped side mold 51 and the secondary portal group 2. The top mold system 40 includes a support assembly, a plurality of arc-shaped top molds 46 hinged to each other and located above the support assembly, and an adjustment assembly 45 connecting the support assembly and the arc-shaped top mold 46. The main portal 10 and the auxiliary portal assembly are connected to the support assembly through a lifting assembly 41. The support assembly includes a first support frame body 42 located above the main portal 10, and a second support frame body 43 located above the auxiliary portal assembly. The second support frame body 43 is slidably connected to the first support frame body 42 through a second telescopic assembly 44. The two ends of the adjustment assembly 45 are rotatably connected to the support assembly and the arc-shaped top mold 46, respectively.

[0029] It can be understood that, firstly, by arranging a detachable sub-gantry group on the side of the main gantry 10 close to the change of the tunnel cross section, the size of the sub-gantry group is set according to the actual situation. When the cross section of the tunnel becomes smaller, only the sub-gantry group needs to be removed to meet the tunnel size requirements. Then, a second telescopic assembly 44 connected to the second support frame 43 is arranged on the first support frame 42 in the top mold system 40. When the sub-gantry group is removed, the lifting assembly 41 is removed together, and then the second telescopic assembly 44 is started to pull the second support frame 43 toward the first support frame 42. At the same time, the first support frame 42 is moved close to the first support frame 42. A row of adjustment components 45 at the second support frame 43 and the arc-shaped top molds 46 connected to the row of adjustment components 45 are removed, and the second support frame 43 drives the adjustment components 45 and the arc-shaped top molds 46 thereon to move toward the first support frame 42. Since the arc-shaped top molds 46 are hinged to each other, the angles between the arc-shaped top molds 46 can be readjusted to match the curvature of the tunnel after the cross-section change, thereby meeting the grouting formwork requirements of the tunnel after the cross-section change. The utility model does not need to dismantle the second lining trolley again, but only needs to dismantle the sub-gantry group and adjust the top mold system 40 thereon to achieve the requirement of convenient disassembly and assembly.

[0030] It should be noted that the working principle of the second lining trolley in the utility model is:

[0031] Move the secondary lining trolley to the position where concrete needs to be poured, and then extend the first telescopic component 52 to prop up the first arc-shaped side form 51, so that it is close to the inner wall of the tunnel and acts as a formwork. At the same time, the jacking component 41 jacks up the supporting component and the arc-shaped top form 46, so that the arc-shaped top form 46 is close to the inner top wall of the tunnel and acts as a formwork.

[0032] In this embodiment, the adjusting assembly 45 includes a plurality of oil cylinders arranged in an array above the supporting assembly, and each row of the plurality of oil cylinders arranged along the extension direction of the tunnel are connected to the same arc-shaped top mold 46; the two ends of the first telescopic assembly 52 are also respectively hinged to the sub-gantry group and the first arc-shaped side mold 51, and the hinged connection at both ends means that when the adjusting assembly 45 and the first telescopic assembly 52 are extended or shortened, the angle will also be adjusted automatically to achieve the curvature adjustment of the first arc-shaped side mold 51 and the arc-shaped top mold 46.

[0033] Furthermore, the template structure also includes a second side mold system arranged on the side of the main portal 10 away from the auxiliary portal, and the second side mold system includes a plurality of second arc-shaped side molds 61 hinged to each other, and a third telescopic component 62 connecting the second arc-shaped side mold 61 and the main portal 10.

[0034] The working principle of the second arc-shaped side mold 61 is the same as that of the first arc-shaped side mold 51 , which will not be elaborated here. It should be noted that the connection between the first arc-shaped side mold 51 and the arc-shaped top mold 46 is hinged, and the connection between the second arc-shaped side mold 61 and the arc-shaped top mold 46 is also hinged.

[0035] Preferably, in this embodiment, both the first telescopic assembly 52 and the third telescopic assembly 62 use oil cylinders.

[0036] Furthermore, the sub-gantry group is composed of a plurality of sub-gantry frames, and adjacent sub-gantry frames are detachably connected.

[0037] It can be understood that tunnels often have multiple variable cross-section sections, so it is necessary to design multiple sub-gantry frames of different sizes. In this embodiment, the tunnel has three cross-section sections, so the sub-gantry group includes a first sub-gantry 20 and a second sub-gantry 30. The size of the first sub-gantry 20 is larger than that of the second sub-gantry 30. When the main gantry 10, the first sub-gantry 20 and the second sub-gantry 30 are combined, the size of the entire second lining trolley meets the tunnel with the largest cross-section section. As the tunnel cross-section gradually decreases, the second sub-gantry 30 and the second sub-gantry 30 can be removed in turn. When the second sub-gantry 30 and the first sub-gantry 20 are removed, the following steps are performed simultaneously: removing the jacking assembly 41 thereon, controlling the second telescopic assembly 44 to pull the second support frame body 43, and removing the adjustment assembly 45 and the arc-shaped top mold 46 on the first support frame body 42.

[0038] Further, the first support frame 42 includes a plurality of first main beams spaced apart along the extension direction of the tunnel, and a plurality of first beams spaced apart between the first main beams, and the second support frame 43 includes a plurality of second main beams spaced apart along the extension direction of the tunnel, and a plurality of second beams spaced apart between the second main beams, and the second main beams are slidably connected to the first main beams;

[0039] The second telescopic assembly 44 is fixedly connected to one end of the first support frame 42 away from the auxiliary door frame assembly, and the extended end of the second telescopic assembly 44 is connected to the second support frame 43 .

[0040] It can be understood that a slide groove 48 for the second main beam to slide is provided on the first main beam. When the auxiliary gantry assembly is removed, the second telescopic assembly 44 is synchronously started to pull the second main beam to slide along the slide groove 48 on the first main beam.

[0041] Preferably, the second telescopic assembly 44 also adopts an oil cylinder, and the second telescopic assembly 44 is fixedly connected to the top of the first main beam through a mounting plate 47.

[0042] Preferably, the lifting assembly 41 includes a plurality of jacks arranged in an array below the supporting assembly, and the top mold system 40 can be lifted by the jacks.

[0043] Preferably, the adjustment assembly 45 includes a plurality of oil cylinders arranged in an array above the support assembly, and each row of the plurality of oil cylinders arranged along the extension direction of the tunnel are connected to the same arc-shaped top mold 46 .

[0044] It can be understood that the adjustment component 45 not only plays a role in adjusting the angle of the arc-shaped top mold 46, but also plays a supporting role. Multiple cylinders in the same row are started synchronously, and the supporting capacity is stronger.

[0045] Specifically, in the present embodiment, adjacent arc-shaped top molds 46 are rotatably connected via a detachable hinge, which is similar to the hinge for connecting arc-shaped mold plates in the prior art and is therefore not shown in the figure.

[0046] It should be noted that when dismantling the auxiliary portal frame, since some of the arc-shaped templates are removed, there may be a loose joint when adjusting the angle of the arc-shaped top template 46. Therefore, it can be cut manually according to the actual situation to meet the requirement of tight joints.

[0047] Furthermore, it also includes a rail system (not shown in the figure) located below the secondary lining trolley, and a walking system (not shown in the figure) matching the rail system is provided below the main portal 10 and the auxiliary portal assembly.

[0048] The workflow of the tunnel construction system in the utility model is as follows:

[0049] First, construction starts from the larger section of the tunnel. The first sub-gantry 20 and the second sub-gantry 30 are all installed, and the walking system is started to drive the second lining trolley forward. When it reaches the designated position, the first telescopic assembly 52, the third telescopic assembly 62 and the jacking assembly 41 are started to prop up the first arc-shaped side form 51, the second arc-shaped side form 61 and the arc-shaped top form 46, and then grouting is performed. After the concrete solidifies, the formwork is retracted, and the walking system continues to move forward until the section is poured;

[0050] When the tunnel cross section becomes smaller, the second sub-gantry 30 is now removed. At the same time, the jacking assembly 41 on the second sub-gantry 30 is removed, the second telescopic assembly 44 is controlled to pull the second support frame 43 to the top of the first sub-gantry 20, and a row of adjustment assemblies 45 and arc-shaped top molds 46 near one end of the first support frame 42 near the second support frame 43 are removed, and then the remaining arc-shaped top molds 46 are reintegrated. The angle can be adjusted by telescoping the adjustment assembly 45 until the re-adjusted template curvature matches the curvature of the inner wall of the tunnel;

[0051] Then continue pouring according to the same steps. When the tunnel cross section becomes smaller again, the first auxiliary portal frame 20 is removed, and the above steps are repeated to continue pouring until the second lining concrete of the entire tunnel is poured.

[0052] In summary, the tunnel construction system in the above-mentioned embodiment of the utility model does not need to dismantle the secondary lining trolley again, and only needs to dismantle the auxiliary portal assembly and adjust the top formwork system thereon to achieve the requirement of convenient disassembly and assembly.

[0053] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the utility model. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.

[0054] The above-mentioned embodiments only express several implementation methods of the utility model, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the patent of the utility model. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the concept of the utility model, and these all belong to the protection scope of the utility model. Therefore, the protection scope of the utility model patent shall be based on the attached claims.

Claims

1. A tunnel construction system, characterized in that: The invention comprises a secondary lining trolley for grouting formwork, wherein the secondary lining trolley comprises a main portal, a secondary portal group detachably arranged on a side of the main portal close to a change in tunnel cross section, and a template structure arranged around the main portal and the secondary portal group, wherein the template structure comprises a first side template system arranged on a side of the secondary portal group away from the main portal, and a top template system located above the main portal and the secondary portal group, wherein the first side template system comprises a plurality of first arc-shaped side templates hinged to each other, and a first telescopic assembly connecting the first arc-shaped side template and the secondary portal group, and the top template The system includes a support assembly, a plurality of arc-shaped top molds hinged to each other and located above the support assembly, and an adjustment assembly connecting the support assembly and the arc-shaped top mold. The main portal and the auxiliary portal group are connected to the support assembly through a lifting assembly. The support assembly includes a first support frame body located above the main portal, and a second support frame body located above the auxiliary portal group. The second support frame body is slidably connected to the first support frame body through a second telescopic assembly, and both ends of the adjustment assembly are rotatably connected to the support assembly and the arc-shaped top mold respectively.

2. The tunnel construction system according to claim 1, characterized in that: The sub-gantry group is composed of a plurality of sub-gantry frames, and adjacent sub-gantry frames are detachably connected.

3. The tunnel construction system according to claim 1, characterized in that: The first support frame includes a plurality of first main beams arranged at intervals along the extension direction of the tunnel, and a plurality of first beams arranged at intervals between the first main beams. The second support frame includes a plurality of second main beams arranged at intervals along the extension direction of the tunnel, and a plurality of second beams arranged at intervals between the second main beams. The second main beams are slidably connected to the first main beams.

4. The tunnel construction system according to claim 1, characterized in that: The second telescopic assembly is fixedly connected to one end of the first supporting frame body away from the auxiliary door frame group, and the extended end of the second telescopic assembly is connected to the second supporting frame body.

5. The tunnel construction system according to claim 1, characterized in that: The lifting assembly includes a plurality of jacks arranged in an array below the supporting assembly.

6. The tunnel construction system according to claim 1, characterized in that: The adjusting assembly comprises a plurality of oil cylinders arranged in an array above the supporting assembly, and each row of the plurality of oil cylinders arranged along the extension direction of the tunnel are connected to the same arc-shaped top mold.

7. The tunnel construction system according to claim 1, characterized in that: The template structure also includes a second side mold system arranged on the side of the main portal away from the auxiliary portal, and the second side mold system includes a plurality of second arc-shaped side molds hinged to each other, and a third telescopic component connecting the second arc-shaped side mold and the main portal.

8. The tunnel construction system according to claim 1, characterized in that: Adjacent arc-shaped top molds are rotatably connected via detachable hinges.

9. The tunnel construction system according to claim 1, characterized in that: It also includes a rail system located below the secondary lining trolley, and a walking system matching the rail system is provided below the main portal and the auxiliary portal assembly.