Grouting sleeve steel bar connecting piece sample preparation system

By designing the sample preparation system for grouting sleeve steel bar connections, using structures such as support frames and fixture fixtures, the quality and stability problems in the production of grouting sleeve joint specimens in prefabricated buildings are solved, and high-quality specimens are achieved Accuracy of production and test results.

CN221945682UActive Publication Date: 2024-11-01THE THIRD CONSTR ENG CO LTD OF CHINA CONSTR SECOND ENG BUREAU
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420011870.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-03
Publication Date
2024-11-01
Estimated Expiration
2034-01-03

AI Technical Summary

Technical Problem

In prefabricated building construction, there is a lack of special auxiliary tools during the production of grouting sleeve joint specimens, which makes it difficult to ensure the quality of the joint specimens. The specimens are easily affected by artificial vibration during the condensation and hardening process, resulting in unqualified phenomena, and grouting When the air groove inside the sleeve affects the integrity of the connection, it leads to errors in the test results.

Method used

A sample preparation system for grouting sleeve steel bar connection parts is designed, including at least two sets of support frames, fixing frames and sleeve brackets. The grouting sleeves and steel bars are fixed through holes to ensure that the grouting sleeve is vertically stable and avoid air grooves. , and reduce space occupancy through a foldable structure.

Benefits of technology

The quality of the specimen production is improved, the interference of human factors is reduced, the grout is full, the air groove is avoided, the accuracy of the test results is improved, and the stability is maintained during use through the foldable structure is maintained to reduce the impact of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221945682U_ABST
    Figure CN221945682U_ABST
Patent Text Reader

Abstract

The utility model discloses a grouting sleeve steel bar connecting piece sample preparation system which comprises at least two sets of supporting frames, a clamp fixing frame and a sleeve bracket are sequentially arranged between every two adjacent sets of supporting frames from top to bottom, and a plurality of holes used for containing grouting sleeves are formed in each sleeve bracket at intervals. The hole diameter of the hole is matched with the outer diameter of the grouting sleeve body part, the bottom sleeve body of the grouting sleeve is arranged in the hole in a penetrating mode, a grouting pipe at the bottom of the grouting sleeve abuts against the sleeve bracket on the periphery of the hole, and a steel bar inserted into the top of the grouting sleeve vertically extends upwards to the clamp fixing frame. The grouting sleeve is clamped and fixed through steel bar clamping pieces correspondingly arranged on the clamp fixing frame, and steel bars inserted into the bottom of the grouting sleeve vertically extend downwards and abut against the ground. The device is simple in structure and convenient to manufacture, the grouting sleeve can be kept vertical and stable all the time in the manufacturing process, and the manufacturing quality of a test piece is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of grouting sleeve testing, in particular to a grouting sleeve steel bar connector sample preparation system. Background Art

[0002] According to relevant national standards, during the construction of prefabricated buildings, in order to determine the connection effect between the grouting sleeve, grouting material and steel bars, the grouting sleeve should be subjected to process inspection and joint pull-out inspection before the components enter the site, so samples need to be produced for testing.

[0003] In order to better complete the production of joint specimens, auxiliary tools are needed to fix the grouting sleeve, prefabricated end steel bars and anchor end steel bars before grouting. For prefabricated and assembled construction sites, there are no special auxiliary tools for the production of grouting joint specimens. The quality of grouting joint specimens is difficult to guarantee, and there are inevitably disturbances from other types of work during the production and construction of the specimens, which can easily cause harmful vibrations during the coagulation and hardening of the joint specimens, and then human errors lead to unqualified phenomena that affect the accuracy of the test results. At the same time, when grouting the full grouting sleeve, in order to facilitate placement, the sleeve is mostly laid flat, but an air groove will appear inside the sleeve, which will affect the integrity of the connection between the sleeve, steel bars and grouting materials, and will also cause errors in the test results. Utility Model Content

[0004] The utility model aims to provide a sample preparation system for a grouting sleeve steel bar connector to solve the technical problems described in the background technology.

[0005] In order to achieve the above technical purpose, the utility model adopts the following technical solutions:

[0006] A grouting sleeve steel bar connector sample preparation system comprises at least two groups of support frames, wherein a clamp fixing frame and a sleeve bracket are sequentially arranged between two adjacent groups of support frames from top to bottom, wherein the sleeve bracket is provided with a plurality of holes for placing grouting sleeves at intervals, wherein the aperture of the holes matches the outer diameter of the cylindrical portion of the grouting sleeve, the bottom cylindrical portion of the grouting sleeve is passed through the holes, and the grouting pipe at the bottom of the grouting sleeve abuts against the sleeve bracket at the periphery of the holes, the steel bars inserted at the top of the grouting sleeve extend vertically upward to the clamp fixing frame, and are clamped and fixed by the steel bar clamping pieces correspondingly arranged on the clamp fixing frame, and the steel bars inserted at the bottom of the grouting sleeve extend vertically downward and abut against the ground.

[0007] Preferably, the support frame includes a vertically extending support upright, a support cross bar hingedly fixed to the bottom end of the support upright, the support cross bars are arranged in pairs, the two support cross bars arranged in pairs are respectively arranged on both sides of the support upright, and the support cross bars and the support upright are connected by a support diagonal bar, the top and bottom ends of the support diagonal bar are respectively hingedly connected to the support upright and the support cross bar by hinge shafts, an oblong slide groove is provided on the support cross bar, and the hinge shaft at the bottom end of the support diagonal bar is arranged in the slide groove and can slide along the slide groove.

[0008] Preferably, a counterweight block is provided at the end of the supporting cross bar.

[0009] Preferably, a steel bar bracket is further provided on the support frame below the sleeve bracket, and the steel bars inserted at the bottom of the grouting sleeve extend vertically downward and abut against the steel bar bracket.

[0010] Preferably, a plurality of groups of bolt holes are vertically spaced apart on the support pole, and the clamp fixing frame, sleeve bracket and steel bar bracket are respectively fixed to one of the groups of bolt holes opened on the support pole by bolting.

[0011] Compared with the prior art, the beneficial effects of the utility model are as follows: the utility model has a simple structure and is easy to manufacture, and can keep the grouting sleeve vertical and stable at all times during the manufacturing process, thereby ensuring full grouting, avoiding the appearance of air grooves, reducing the interference of human factors on the test results, and improving the quality of specimen manufacturing. At the same time, the foldable support frame can, on the one hand, ensure the stability of the frame support when in use, and avoid adverse effects on the specimen caused by accidental interference; on the other hand, it can reduce the on-site space occupancy when in the storage state, and avoid affecting the normal construction of other processes. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] The above and / or other aspects and advantages of the present invention will become clearer and easier to understand through the detailed description made in conjunction with the following drawings, which are only schematic and do not limit the present invention, wherein:

[0013] Figure 1 The utility model is a structural schematic diagram of a grouting sleeve steel bar connector sample preparation system.

[0014] Figure numerals: 1. Support frame; 101. Support vertical pole; 102. Support horizontal rod; 103. Support diagonal rod; 104. Hinge shaft; 105. Slide groove; 106. Counterweight; 2. Clamp fixing frame; 3. Steel bar clamping piece; 4. Sleeve bracket; 5. Hole; 6. Grouting sleeve; 7. Steel bar; 8. Steel bar bracket. DETAILED DESCRIPTION

[0015] Hereinafter, an embodiment of a sample preparation system of a grouting sleeve steel bar connector of the utility model will be described with reference to the accompanying drawings. The embodiments described herein are specific embodiments of the utility model, which are used to illustrate the concept of the utility model, are explanatory and exemplary, and should not be interpreted as limiting the implementation mode of the utility model and the scope of the utility model. In addition to the embodiments described herein, those skilled in the art can also adopt other obvious technical solutions based on the contents disclosed in the claims and the specification of this application, including technical solutions that adopt any obvious replacements and modifications to the embodiments described herein.

[0016] In the description of the present invention, it should be noted that the terms "front", "rear", "left", "right", "top", "bottom", "up", "down", "inside", "outside", "horizontal", "longitudinal", "vertical", "oblique" and the like indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second" and the like are only used for descriptive purposes and cannot be understood as indicating or implying relative importance.

[0017] The drawings of this specification are schematic diagrams, which assist in explaining the concept of the utility model and schematically show the shapes of various parts and their mutual relationships. Please note that in order to clearly show the structure of various components of the embodiments of the utility model, the drawings are not drawn according to the same scale. The same reference numerals are used to represent the same parts.

[0018] The principles and features of the present invention are described below in conjunction with the accompanying drawings. The embodiments are only used to explain the present invention and are not intended to limit the scope of the present invention. Figure 1 , the preferred embodiments of the utility model are further described in detail:

[0019] like Figure 1As shown, the utility model preferably adopts a grouting sleeve steel bar connector sample preparation system, comprising at least two groups of support frames 1, and a clamp fixing frame 2 and a sleeve bracket 4 are sequentially arranged from top to bottom between the two adjacent groups of support frames 1, and a plurality of holes 5 for placing the grouting sleeve 6 are arranged at intervals on the sleeve bracket 4, and the aperture of the hole 5 matches the outer diameter of the cylinder part of the grouting sleeve 6, and the bottom cylinder of the grouting sleeve 6 is penetrated in the hole 5, and the grouting pipe at the bottom of the grouting sleeve 6 abuts against the sleeve bracket 4 outside the hole 5 to prevent the grouting sleeve 6 from sliding downward, and the steel bar 7 inserted at the top of the grouting sleeve 6 extends vertically upward to the clamp fixing frame 2, and is clamped and fixed by the steel bar clamping piece 3 correspondingly arranged on the clamp fixing frame 2, so as to limit the position of the prefabricated end steel bar 7 and prevent the specimen from shaking left and right, and the steel bar 7 inserted at the bottom of the grouting sleeve 6 extends vertically downward and abuts against the ground to prevent the anchor end steel bar 7 from sliding downward;

[0020] Since the types and specifications of the specimens to be prepared on site may be different, in order to make the present invention applicable to the preparation of grouting sleeve 6 specimens of different specifications at the same time, the present invention solves this problem by setting up multiple groups of support frames 1. Generally, considering the on-site construction space and the stability of the frame, three groups of support frames 1 are preferably set, that is, the same preparation system can prepare grouting sleeve 6 specimens of two different specifications at most;

[0021] Prefabricated building construction sites require a large number of components to be stacked, and the on-site space is limited. In order to minimize the occupation of construction space, the utility model optimizes the support frame 1 into a foldable structure, so that it is portable and easy to store, while ensuring the stability of the frame. Specifically, the support frame 1 includes a vertically extending support upright 101, and a support cross bar 102 is hingedly fixed to the bottom end of the support upright 101. The support cross bars 102 are arranged in pairs, and the two support cross bars 102 arranged in pairs are respectively arranged on both sides of the support upright 101, and the support cross bars 102 and the support upright 101 are connected by a support diagonal bar 103. The top and The bottom ends are respectively hingedly connected to the support vertical rod 101 and the support cross bar 102 through hinge shafts 104. The support cross bar 102 is provided with an oblong slide groove 105. The hinge shaft 104 at the bottom end of the support diagonal rod 103 is arranged in the slide groove 105 and can slide along the slide groove 105. On this basis, in order to further improve the stability of the support frame 1, the end of the support cross bar 102 is preferably detachably provided with a counterweight block 106 in the form of a clamp. The counterweight block 106 can avoid the stability of the support cross bar 102 and avoid the problem of its folding back due to accidental disturbance. On the other hand, it can also improve the stability of the entire frame, improve its ability to resist overturning interference, and prevent the frame from becoming unstable.

[0022] In order to reduce the impact of on-site construction disturbance on the grouting sleeve 6 test piece, and at the same time, avoid the problem of unstable test piece installation position caused by uneven ground, it is advisable to add a steel bar bracket 8 on the support frame 1 below the sleeve bracket 4, and support the steel bars 7 at the bottom of the grouting sleeve 6 by replacing the ground with the flat steel bar bracket 8, so that the steel bars 7 inserted at the bottom of the grouting sleeve 6 corresponding to the same model of test pieces can all extend vertically downward and abut against the steel bar bracket 8 at the same horizontal plane position;

[0023] Since the types and specifications of the test pieces to be prepared on site may be different, in order to improve the applicability of the utility model, the heights of the fixture fixing frame 2, the sleeve bracket 4 and the steel bar bracket 8 on the support frame 1 are all set to be vertically adjustable. Specifically, a plurality of groups of bolt holes are vertically spaced apart on the support upright 101, and the fixture fixing frame 2, the sleeve bracket 4 and the steel bar bracket 8 are respectively fixed to one of the groups of bolt holes opened on the support upright 101 in a bolted manner;

[0024] Considering the material acquisition problem at the construction site, the sleeve bracket 4 and the steel bar bracket 8 are both made of steel plates, and are bolted and fixed on the supporting pole 101 with angle brackets;

[0025] In order to cooperate with the clamping and fixing of specimens of different types, the steel bar clamp 3 needs to adapt to different diameters of steel bars 7. For this purpose, the steel bar clamp 3 is set to a structural form of an arc-shaped iron sheet + bolt, and bolt holes are arranged at intervals on the arc-shaped iron sheet and the clamp fixing frame 2. The arc-shaped iron sheet presses the prefabricated end steel bar 7 tightly on the clamp fixing frame 2, and the arc-shaped iron sheet is fixed to the clamp fixing frame 2 by bolts arranged on both sides of the prefabricated end steel bar 7. When fixing the prefabricated end steel bar 7, it is only necessary to unscrew one bolt on one side of the arc-shaped iron sheet, and then put the steel bar 7 into the arc-shaped iron sheet, and then select a suitable bolt hole position and re-fix the unscrewed bolt. The steel bar clamp 3 adopts a design similar to an adjustable belt buckle, which can fix various types of steel bars 7.

[0026] When in use, first move the utility model to the selected position, then open the folded support cross bar 102, and stably place the support frame 1 at the selected position, and then place the counterweight 106 at the end of the support cross bar 102 for reinforcement. Next, adjust the relative positions of the clamp fixing frame 2, the sleeve bracket 4 and the steel bar bracket 8 on the support frame 1 according to the model of the test piece to be made. Then, assemble the steel bar 7 and the grouting sleeve 6, and insert the test piece into the sleeve bracket 4 from top to bottom, so that the bottom end of the anchor end steel bar 7 rests on the steel bar bracket 8 plate surface, and the grouting pipe at the bottom of the grouting sleeve 6 rests on the sleeve bracket 4 plate surface outside the hole 5. After that, use the steel bar clamp 3 to clamp the prefabricated end steel bar 7 to fix the test piece. Finally, perform the test piece grouting and subsequent operations according to the requirements of the specification. After the cement solidifies and reaches the strength, release the fixation of the steel bar clamp 3, and pull the test piece upward to complete the test piece production.

[0027] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention shall be included in the protection scope of the present invention.

Claims

1. A grouting sleeve steel bar connector sample preparation system, characterized in that: The invention comprises at least two groups of support frames (1), wherein a clamp fixing frame (2) and a sleeve bracket (4) are sequentially arranged between two adjacent groups of support frames (1) from top to bottom, wherein the sleeve bracket (4) is provided with a plurality of holes (5) for placing grouting sleeves (6) at intervals, wherein the hole (5) has a hole diameter that matches the outer diameter of the cylinder portion of the grouting sleeve (6), wherein the bottom cylinder of the grouting sleeve (6) is inserted into the hole (5), and the grouting pipe at the bottom of the grouting sleeve (6) abuts against the sleeve bracket (4) outside the hole (5), wherein the steel bar (7) inserted at the top of the grouting sleeve (6) extends vertically upward to the clamp fixing frame (2) and is clamped and fixed by a corresponding steel bar clamping piece (3) arranged on the clamp fixing frame (2), and wherein the steel bar (7) inserted at the bottom of the grouting sleeve (6) extends vertically downward and abuts against the ground.

2. A grouting sleeve steel bar connector sample preparation system according to claim 1, characterized in that: The support frame (1) comprises a vertically extending support upright (101), the bottom end of the support upright (101) being hingedly fixed with a support cross bar (102), the support cross bars (102) being arranged in pairs, the two support cross bars (102) being arranged in pairs being arranged on both sides of the support upright (101) respectively, and the support cross bars (102) and the support upright (101) being connected via a support diagonal bar (103), the top and bottom ends of the support diagonal bar (103) being hingedly connected to the support upright (101) and the support cross bar (102) respectively via a hinge shaft (104), the support cross bar (102) being provided with an oblong sliding groove (105), the hinge shaft (104) at the bottom end of the support diagonal bar (103) being arranged in the sliding groove (105) and being able to slide along the sliding groove (105).

3. A grouting sleeve steel bar connector sample preparation system according to claim 2, characterized in that: A counterweight block (106) is provided at the end of the supporting crossbar (102).

4. A grouting sleeve steel bar connector sample preparation system according to claim 2, characterized in that: A steel bar bracket (8) is also provided on the support frame (1) below the sleeve bracket (4), and the steel bars (7) inserted at the bottom of the grouting sleeve (6) extend vertically downward and abut against the steel bar bracket (8).

5. A grouting sleeve steel bar connector sample preparation system according to claim 4, characterized in that: A plurality of groups of bolt holes are vertically spaced apart on the support pole (101), and the clamp fixing frame (2), the sleeve bracket (4) and the steel bar bracket (8) are respectively fixed to one of the groups of bolt holes on the support pole (101) by bolting.