Cooling and flushing equipment for steel pipe production and manufacturing

By designing a cooling and flushing equipment for steel pipe production and manufacturing including spray rack, water spray pipe, recycling tank and fan unit, the problem of insufficient water resource waste and cleaning strength is solved, and the water reuse and attachment of dust and waste slag is realized. Thoroughly clean to ensure the quality of the steel pipe and facilitate subsequent use.

CN221951929UActive Publication Date: 2024-11-05FOSHAN TONGHONG METAL CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420192556.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-26
Publication Date
2024-11-05
Estimated Expiration
2034-01-26

AI Technical Summary

Technical Problem

The existing cooling and flushing equipment for steel pipe production and manufacturing does not consider the water recycling and reuse during the flushing process, resulting in waste of water resources and increased production costs. The cleaning force of clean water flushing is insufficient, and it is impossible to effectively clean up tightly attached dust and waste slag.

Method used

A device including a spray rack, water spray pipe, water tank, recycling tank, filter mesh, conveying pipe and water pump is designed. The steel pipe is flushed and cooled by spraying clean water, and the water poured into the recycling trough and filtered through the filter mesh. It is then recycled and reused; at the same time, the fan unit, cleaning drum and electric heating plate are used to match the conveyor belt and blower to achieve the cleaning of dust and waste slag and the drying of steel pipes.

Benefits of technology

It effectively solves the problem of insufficient water resources and insufficient cleaning efforts, realizes the reuse of water and the thorough cleaning of attached dust and waste slag, ensuring the quality of the steel pipe and the convenience of subsequent use.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221951929U_ABST
    Figure CN221951929U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of steel pipe production and manufacturing, and discloses a cooling and flushing device for steel pipe production and manufacturing, which comprises two bearing frames, a conveying belt is arranged in the middle of the two bearing frames, the bottoms of the two bearing frames are fixedly connected with supporting plates, a spraying frame is arranged above the supporting plates, and the spraying frame is arranged above the conveying belt. The bottom of the spraying frame is fixedly connected to the upper sides of the two bearing frames, and a water spraying pipe is fixedly connected to the inner top of the spraying frame. According to the cleaning device, through the cooperation of the spraying frame, the water spraying pipe, the water tank, the water inlet pipe, the connecting pipe, the water pump, the recycling groove, the cooling fins, the conveying pipe and the water outlet, the problems that water resources are wasted and the production cost is increased due to the fact that flushing water is not recycled and reused are solved, and through the cooperation of the fan unit, the cleaning roller, the conveying belt and the air blowing opening, the cleaning efficiency is improved. The problem that dust and waste residues which are tightly attached cannot be cleaned off from the steel pipe only through clean water flushing is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of steel pipe production and manufacturing, in particular to cooling and flushing equipment for steel pipe production and manufacturing. Background Art

[0002] With the progress of the times, industry and construction have also developed rapidly. Steel pipes are often needed in construction and industrial production. Newly produced steel pipes are often accompanied by high temperatures, and there may be some dust and metal waste slag generated when the steel pipes are produced on the surface. If the steel pipes are not cooled and cleaned in time, the dust and waste slag attached to the surface of the steel pipes may adhere to the steel pipes after the steel pipes are cooled, thereby affecting the collection and use of the steel pipes, and also causing the quality of the steel pipes to decrease. Therefore, when the steel pipes are just produced, cooling and flushing equipment for steel pipe production and manufacturing is needed to cool and flush them.

[0003] At present, most of the cooling and flushing equipment for steel pipe production and manufacturing available on the market only considers flushing and cooling the steel pipe with clean water, but does not consider recycling and reusing the water in the flushing process, which will cause waste of water resources and increase production costs. Utility Model Content

[0004] In order to make up for the above deficiencies, the utility model provides a cooling and flushing equipment for steel pipe production and manufacturing, aiming to improve the problem that the water recycling and reuse in the flushing process are not taken into consideration, which will cause waste of water resources and increase production costs, and the cleaning power of the steel pipe is not enough only by flushing with clean water, and some tightly attached dust and waste residue cannot be cleaned from the steel pipe by flushing with clean water alone.

[0005] In order to achieve the above-mentioned purpose, the utility model adopts the following technical scheme: a cooling and flushing equipment for steel pipe production and manufacturing, comprising two load-bearing frames, a conveyor belt is arranged in the middle of the two load-bearing frames, the bottoms of the two load-bearing frames are fixedly connected to support plates, a spray frame is arranged above the support plate, the bottom of the spray frame is fixedly connected to the upper side of the two load-bearing frames, the inner top of the spray frame is fixedly connected to a water spray pipe, the top of the spray frame is fixedly connected to a water tank, the water spray pipe is connected to the water tank, a recovery trough is fixedly connected between the inner walls of the two support plates, a drain outlet is arranged at the bottom of the recovery trough, a delivery pipe is fixedly connected to the bottom of the drain outlet, a water pump is arranged at the bottom of the recovery trough, and the end of the delivery pipe away from the recovery trough is fixedly connected to the input end of the water pump.

[0006] As a further description of the above technical solution:

[0007] One end of the top of the water tank is fixedly connected with a water inlet pipe, the other end of the top of the water tank is fixedly connected with a connecting pipe, and the other end of the connecting pipe is fixedly connected to the output end of the water pump.

[0008] As a further description of the above technical solution:

[0009] A filter screen is arranged on the top of the drain outlet, and a heat dissipation fin is fixedly connected to the top of the water tank.

[0010] As a further description of the above technical solution:

[0011] The recovery tank is arranged below the water spray pipe, and the water pump is arranged between two supporting plates.

[0012] As a further description of the above technical solution:

[0013] A main box is fixedly connected to the upper sides of the two load-bearing frames, and fan units are fixedly connected to the front and rear sides of the main box. Two electric push rods are fixedly connected to the left side of the interior of the main box, one end of one of the electric push rods is fixedly connected to a motor box, and a motor is fixedly connected to the interior of the motor box, one end of the other electric push rod is rotatably connected to one end of a cleaning roller, and the other end of the cleaning roller is fixedly connected to the output end of the motor, and an air blowing port is fixedly connected to the inner wall of the main box, and the air blowing port is connected to the fan unit.

[0014] As a further description of the above technical solution:

[0015] Two partitions are fixedly connected inside the main box, and silicone cloth strips are fixedly connected to the bottoms of the two partitions. The air outlet is arranged between the two partitions.

[0016] As a further description of the above technical solution:

[0017] A track groove is arranged on the left side inside the main box, the motor box is slidably connected to the middle of the track groove, and belt holes are arranged on the outer periphery of the conveyor belt.

[0018] As a further description of the above technical solution:

[0019] An electric heating plate is fixedly connected to the right side of the inner wall of the main box, and the electric heating plate is arranged between one of the partitions and the main box.

[0020] The utility model has the following beneficial effects:

[0021] 1. In the utility model, through the cooperation of the spray rack, the water spray pipe, the water tank, the water inlet pipe, the connecting pipe, the water pump, the recovery tank, the heat dissipation fins, the delivery pipe and the drain port, clean water is injected into the water tank through the water inlet pipe, and then sprayed through the water spray pipe, so as to flush and cool the steel pipe, and the sprinkled water flows into the recovery tank below, and after filtering impurities through the filter net, it flows into the water pump through the delivery pipe, and then is transported back to the water tank through the connecting pipe for secondary utilization, and the heat dissipation fins on the water tank can cool the water in the water tank. This structure solves the problem that the flushed water is not recycled and reused during the flushing process, which will cause a waste of water resources and increase production costs.

[0022] 2. In the utility model, through the cooperation of the fan unit, the cleaning roller, the conveyor belt and the air outlet, the motor in the motor box is started to make the cleaning roller rotate, so as to achieve the purpose of cleaning and scrubbing the steel pipe, and the fan unit is started to make the wind blow out from the air outlet, and the dust and waste residue that are brushed off but still stained on the steel pipe to be cleaned are cleaned for the second time by wind blowing, and the temperature is lowered again, thereby solving the problem that the cleaning force of the steel pipe is not enough only by flushing with clean water, and some tightly attached dust and waste residue cannot be cleaned from the steel pipe by flushing with clean water alone, and the cleaned steel pipe is dried by the electric heating plate, which is convenient for subsequent collection and use, and also prevents erosion caused by water accumulation on the surface of the steel pipe. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 This is a three-dimensional schematic diagram of a cooling and flushing device for steel pipe production and manufacturing proposed by the utility model;

[0024] Figure 2 This is a structural schematic diagram of a main box of a cooling and flushing device for steel pipe production and manufacturing proposed by the utility model;

[0025] Figure 3 This is a schematic diagram of the structure of a recovery tank of a cooling and flushing equipment for steel pipe production and manufacturing proposed by the utility model;

[0026] Figure 4 This is a schematic diagram of the structure of a partition of a cooling and flushing equipment for steel pipe production and manufacturing proposed by the utility model;

[0027] Figure 5 The utility model discloses a structural schematic diagram of a connecting pipe of a cooling and flushing device for steel pipe production.

[0028] Legend:

[0029] 1. Main box; 2. Fan unit; 3. Cleaning roller; 4. Electric push rod; 5. Track groove; 6. Spray rack; 7. Water spray pipe; 8. Water tank; 9. Water inlet pipe; 10. Connecting pipe; 11. Water pump; 12. Recovery tank; 13. Conveyor belt; 14. Support plate; 15. Conveying pipe; 16. Belt hole; 17. Load-bearing frame; 18. Motor box; 19. Cooling fins; 20. Drain outlet; 21. Partition; 22. Blowing outlet; 23. Electric heating plate; 24. Silicone cloth strip. DETAILED DESCRIPTION

[0030] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0031] Reference Figure 1-5 The utility model provides an embodiment: a cooling and flushing equipment for steel pipe production and manufacturing, including two load-bearing frames 17, the load-bearing frames 17 are convenient for bearing the structure thereon, a conveyor belt 13 is arranged in the middle of the two load-bearing frames 17, the conveyor belt 13 is convenient for transmitting the steel pipes just produced thereon, the bottoms of the two load-bearing frames 17 are fixedly connected with support plates 14, the support plates 14 are convenient for supporting the equipment and facilitating the use of the equipment, a spray frame 6 is arranged above the support plate 14, the bottom of the spray frame 6 is fixedly connected to the upper side of the two load-bearing frames 17, a water spray pipe 7 is fixedly connected to the inner top of the spray frame 6, a water tank 8 is fixedly connected to the top of the spray frame 6, the water spray pipe 7 is connected to the water tank 8, a recovery tank 12 is fixedly connected between the inner walls of the two support plates 14, and the recovery tank A drain port 20 is provided at the bottom of 12, and a delivery pipe 15 is fixedly connected to the bottom of the drain port 20. A water pump 11 is provided at the bottom of the recovery tank 12, and one end of the delivery pipe 15 away from the recovery tank 12 is fixedly connected to the input end of the water pump 11. The conveyor belt 13 is started, so that the steel pipe passes under the spray rack 6 and under the main box 1 in sequence under the drive of the conveyor belt 13. When passing through the spray rack 6, clean water can be injected into the water tank 8 through the water inlet pipe 9, and the clean water in the water tank 8 is sprayed through the water spray pipe 7, so as to rinse and cool the steel pipe. The sprayed water flows into the recovery tank 12 below through the belt holes 16 on the conveyor belt 13, and flows into the water pump 11 through the delivery pipe 15 after filtering impurities through the filter net, and then is transported back to the water tank 8 through the connecting pipe 10 for secondary utilization.

[0032] One end of the top of the water tank 8 is fixedly connected with a water inlet pipe 9, which is convenient for pouring clean water into the water tank 8. The other end of the top of the water tank 8 is fixedly connected with a connecting pipe 10, and the other end of the connecting pipe 10 is fixedly connected to the output end of the water pump 11. A filter is arranged on the top of the drain outlet 20. This structure can prevent dust and waste residues from flowing into the water pump 11 under flushing and causing failure of the water pump 11. The top of the water tank 8 is fixedly connected with a heat dissipation fin 19, and the heat dissipation fin 19 can cool the water in the water tank 8. Because the newly produced steel pipe is hotter, the temperature of the water can be prevented from rising after multiple flushing of the newly produced steel pipe, and the cooling efficiency of subsequent flushing is reduced. The recovery tank 12 is arranged below the water spray pipe 7 to facilitate the collection of the water flowing down after flushing. The water pump 11 is arranged between the two supporting plates 14, the main box 1 is fixedly connected to the upper sides of the two load-bearing frames 17, the fan units 2 are fixedly connected to the front and rear sides of the main box 1, and two electric push rods 4 are fixedly connected to the left side of the inside of the main box 1, one end of one of the electric push rods 4 is fixedly connected to the motor box 18, the inside of the motor box 18 is fixedly connected to the motor, and one end of the other electric push rod 4 is rotatably connected to one end of the cleaning roller 3, and the electric push rod 4 is adjusted to make the cleaning roller 3 reach the required height, which is consistent with the thickness of the steel pipe just produced, so as to clean the surfaces of steel pipes of different thicknesses, and the other end of the cleaning roller 3 is fixedly connected to the output end of the motor, and the motor in the motor box 18 is started to make the cleaning roller 3 rotate. The main box 1 is moved to achieve the purpose of cleaning and scrubbing the steel pipe. The inner wall of the main box 1 is fixedly connected with an air blowing port 22, and the air blowing port 22 is connected to the fan unit 2. The fan unit 2 is started to blow wind out from the air blowing port 22, and the dust and waste residue that are brushed off but still stained on the steel pipe to be cleaned are cleaned for the second time, and the temperature is reduced again. Two partitions 21 are fixedly connected to the inside of the main box 1. The bottoms of the two partitions 21 are fixedly connected with silicone cloth strips 24. The air blowing port 22 is arranged between the two partitions 21. The two partitions 21 and the silicone cloth strips 24 at their lower parts can ensure that the dust and waste residue blown off are blocked from spreading, and the steel pipe to be cleaned can be unobstructed under the transmission of the conveyor belt 13. A track groove 5 is arranged on the left side of the main box 1. The machine box 18 is slidably connected to the middle of the track groove 5 to prevent the motor box 18 from shifting during the sliding process. The outer periphery of the conveyor belt 13 is provided with belt holes 16, which is convenient for the water flow for flushing the steel pipe to flow into the recovery tank 12 through the belt holes 16, and is also convenient for flushing and blowing off dust and waste residue to fall, which is convenient for cleaning. An electric heating plate 23 is fixedly connected to the right side of the inner wall of the main box 1. When the steel pipe passes between the two electric heating plates 23 under the drive of the conveyor belt 13, the electric heating plate 23 is started to dry the cleaned steel pipe, which is convenient for subsequent collection and use, and also prevents erosion caused by water accumulation on the surface of the steel pipe. The electric heating plate 23 is arranged between one of the partitions 21 and the main box 1, thereby preventing the work between the fan unit 2 and the electric heating plate 23 from affecting each other.

[0033] Working principle: before using this equipment, place this equipment in the required position, and the finished steel pipe falls on the conveyor belt 13, and the conveyor belt 13 is started, so that the steel pipe passes under the spray rack 6 and under the main box 1 in turn under the drive of the conveyor belt 13. When passing through the spray rack 6, clean water can be injected into the water tank 8 through the water inlet pipe 9, and the clean water in the water tank 8 is sprayed through the water spray pipe 7, so as to rinse and cool the steel pipe. The sprinkled water flows into the recovery tank 12 below through the belt holes 16 on the conveyor belt 13, and flows into the water pump 11 through the conveying pipe 15 after filtering impurities through the filter screen, and then flows back to the water tank 8 through the connecting pipe 10 for secondary utilization. The heat dissipation fins 19 on the water tank 8 can cool the water in the water tank 8. Because the newly produced steel pipe is hotter, this can prevent the temperature of the water from rising after multiple flushing of the newly produced steel pipe, and the subsequent flushing and cooling efficiency is reduced. This structure solves the problem that the flushed water is not recycled and reused during the flushing process, which will cause waste of water resources and increase production costs. The electric The push rod 4 is moved to make the cleaning roller 3 reach the required height, which is consistent with the thickness of the steel pipe just produced, so as to clean the surface of steel pipes of different thicknesses and remove the contaminated dust and waste residue. At the same time, the motor in the motor box 18 is started to make the cleaning roller 3 rotate, so as to achieve the purpose of cleaning and scrubbing the steel pipe. The fan unit 2 is started to make the wind blow out from the blowing port 22, and the dust and waste residue that are brushed off but still contaminated on the steel pipe to be cleaned are cleaned by secondary wind blowing, and the temperature is reduced again, thereby solving the problem of only relying on clean water to rinse the steel pipe. The cleaning force is not enough, and some tightly attached dust and waste residue cannot be cleaned from the steel pipe by just flushing with clean water. The two partitions 21 and the silicone cloth strips 24 at their lower parts can prevent the dust and waste residue from spreading while allowing the steel pipe to be cleaned to pass smoothly under the conveyor belt 13. After that, when the steel pipe passes between the two electric heating plates 23 under the drive of the conveyor belt 13, the electric heating plate 23 is started to dry the cleaned steel pipe, which is convenient for subsequent collection and use, and also prevents erosion caused by water accumulation on the surface of the steel pipe.

[0034] Finally, it should be noted that the above is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A cooling and flushing device for steel pipe production, comprising two load-bearing frames (17), characterized in that: A conveyor belt (13) is arranged in the middle of the two load-bearing frames (17); the bottoms of the two load-bearing frames (17) are fixedly connected to support plates (14); a spray frame (6) is arranged above the support plate (14); the bottom of the spray frame (6) is fixedly connected to the upper sides of the two load-bearing frames (17); a water spray pipe (7) is fixedly connected to the inner top of the spray frame (6); the top of the spray frame (6) is fixedly connected to a water tank (8); the water spray pipe (7) is communicated with the water tank (8); a recovery trough (12) is fixedly connected between the inner walls of the two support plates (14); a drain outlet (20) is arranged at the bottom of the recovery trough (12); a delivery pipe (15) is fixedly connected to the bottom of the drain outlet (20); a water pump (11) is arranged at the bottom of the recovery trough (12); one end of the delivery pipe (15) away from the recovery trough (12) is fixedly connected to the input end of the water pump (11).

2. The cooling and flushing equipment for steel pipe production according to claim 1 is characterized in that: One end of the top of the water tank (8) is fixedly connected to a water inlet pipe (9), the other end of the top of the water tank (8) is fixedly connected to a connecting pipe (10), and the other end of the connecting pipe (10) is fixedly connected to the output end of the water pump (11).

3. The cooling and flushing equipment for steel pipe production according to claim 2 is characterized in that: A filter screen is provided at the top of the drain outlet (20), and a heat dissipation fin (19) is fixedly connected to the top of the water tank (8).

4. The cooling and flushing equipment for steel pipe production according to claim 1 is characterized in that: The recovery tank (12) is arranged below the water spray pipe (7), and the water pump (11) is arranged between two support plates (14).

5. The cooling and flushing equipment for steel pipe production according to claim 1, characterized in that: The upper sides of the two load-bearing frames (17) are fixedly connected to a main box (1), and the front and rear sides of the main box (1) are fixedly connected to a fan unit (2). Two electric push rods (4) are fixedly connected to the left side of the interior of the main box (1), one end of one of the electric push rods (4) is fixedly connected to a motor box (18), and the interior of the motor box (18) is fixedly connected to a motor, and one end of the other electric push rod (4) is rotatably connected to one end of a cleaning roller (3), and the other end of the cleaning roller (3) is fixedly connected to the output end of the motor. The inner wall of the main box (1) is fixedly connected to an air outlet (22), and the air outlet (22) is connected to the fan unit (2).

6. The cooling and flushing equipment for steel pipe production according to claim 5, characterized in that: Two partitions (21) are fixedly connected inside the main box (1), and silicone cloth strips (24) are fixedly connected to the bottoms of the two partitions (21), and the air outlet (22) is arranged between the two partitions (21).

7. The cooling and flushing equipment for steel pipe production according to claim 5, characterized in that: A track groove (5) is arranged on the left side inside the main box (1), the motor box (18) is slidably connected to the middle of the track groove (5), and belt holes (16) are arranged on the outer periphery of the conveyor belt (13).

8. The cooling and flushing equipment for steel pipe production according to claim 6, characterized in that: An electric heating plate (23) is fixedly connected to the right side of the inner wall of the main box (1), and the electric heating plate (23) is arranged between one of the partitions (21) and the main box (1).