Environment-friendly joint structure of cement concrete pavement and asphalt pavement
By installing joint sheaths, embedded pipes and fillers at the joints between cement concrete pavement and asphalt pavement, combined with components such as connecting pipes, connecting rods, springs and sliders, the extrusion caused by top breakage and thermal expansion at the joint is solved. The pressure problem has achieved effective protection of the joints and improved driving safety and road management convenience.
Patent Information
- Application Number
- CN202420298241.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-19
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2034-02-19
AI Technical Summary
The joints of existing cement concrete pavement and asphalt pavement are prone to the problem of top breaking and spreading downward, which affects driving safety and increases the repair burden of road management.
An environmentally friendly joint structure is designed, including the installation of joint sheath, embedded pipe and filler on the top of the roadbed, and the use of components such as connecting pipes, connecting rods, springs and sliders to prevent extrusion, warping and damage caused by thermal expansion. And improve nesting stability and buried stability through U-shaped and rectangular structures.
Effectively prevent the tops of the joints between cement concrete pavement and asphalt pavement, improve driving safety, reduce repair needs, and simplify road management.
Smart Images

Figure CN221956459U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of highway construction, in particular to an environmentally friendly joint structure of a cement concrete pavement and an asphalt pavement. Background Art
[0002] With the continuous development of the economy, infrastructure is constantly improving, and highways are a very important one. The current highway pavement mainly includes cement concrete pavement and asphalt concrete pavement. During the highway construction process, the problem of connecting the rigid cement concrete pavement with the flexible asphalt concrete pavement is often encountered. It is necessary to fill the joints to ensure the combination of the rigid pavement and the flexible pavement. The prior art discloses an environmentally friendly joint structure of a cement concrete pavement and an asphalt pavement with an authorization announcement number of CN214530030U, which involves the technical field of highway engineering construction. It includes a dowel rod for transmitting stress arranged between the cement concrete pavement and the asphalt pavement, one end of the dowel rod is slidingly arranged in the cement concrete pavement, and the other end of the dowel rod is fixedly connected to the asphalt pavement. A support plate for stably setting the dowel rod is arranged in the cement concrete pavement, and an adjustment component for adjusting the horizontality of the dowel rod is arranged on the support plate. The present application can effectively buffer the stress between the cement concrete pavement and the asphalt concrete pavement through the dowel rod.
[0003] However, it was found during use that the above design is not convenient for protecting the joint between the cement concrete pavement and the asphalt pavement. During long-term use, the joint between the cement concrete pavement and the asphalt pavement is prone to breakage at the top and spread downward, which is not conducive to driving safety and requires frequent repairs, causing a lot of trouble for road management. Utility Model Content
[0004] In view of the above problems, the purpose of the utility model is to provide an environmentally friendly joint structure between a cement concrete pavement and an asphalt pavement, which can effectively protect the joints of the cement concrete pavement and the asphalt pavement, prevent the top of the joint from breaking and spreading downward to form potholes, which is beneficial to driving safety, effectively reduces repair problems, brings great convenience to road management, and solves the problems raised in the above-mentioned background technology.
[0005] To achieve the above objectives, the utility model adopts the following technical solution: an environmentally friendly joint structure of a cement concrete pavement and an asphalt pavement, comprising a cement concrete pavement and an asphalt pavement arranged on the top of a roadbed, wherein a joint sleeve is provided on the side of the cement concrete pavement and the asphalt pavement close to each other, a filler is provided between the two joint sleeves, a plurality of embedded pipes with an open end are embedded in the cement concrete pavement and the asphalt pavement, the open ends of the embedded pipes are fixed to the inner walls of the corresponding joint sleeves, a limiting clamp is provided on the fixed sleeve of the embedded pipe, a connecting block is fixedly installed on the top and bottom of the embedded pipe, and one end of the connecting block is fixed to the inner wall of the joint sleeve.
[0006] In order to effectively prevent the problem of extrusion, warping and damage at the joints of cement concrete pavement and asphalt pavement:
[0007] As a further improvement of the above technical solution: the two joint sheaths also include a plurality of connecting tubes, the connecting tubes penetrate the filler, the two ends of the connecting tubes respectively slide and extend into the corresponding embedded tubes, two connecting rods are slidably installed in the connecting tubes, one end of the connecting rods extends to the outside of the connecting tubes and is fixed on the inner wall of the corresponding embedded tubes, a spring is provided in the connecting tube, the two ends of the spring are respectively in contact with the corresponding connecting rods, a rectangular through groove is penetrated on the connecting rod, two sliders are fixedly installed in the connecting tube, and the sliders slide and penetrate the corresponding rectangular through grooves.
[0008] The beneficial effect of this improvement is that by such an arrangement, the problem of cement concrete pavement and asphalt pavement being squeezed against each other due to thermal expansion can be effectively prevented, and the problem of squeezing, warping and damage at the connection between the cement concrete pavement and the asphalt pavement can be effectively prevented.
[0009] In order to facilitate the joint sheath to be firmly nested on the end surface of cement concrete pavement and asphalt pavement:
[0010] As a further improvement of the above technical solution: the joint sheath is a U-shaped structure.
[0011] The beneficial effect of this improvement is that, through such an arrangement, the joint sheath can be firmly nested on the end faces of the cement concrete pavement and the asphalt pavement.
[0012] In order to improve the stability of the buried pipe:
[0013] As a further improvement of the above technical solution: the embedded pipe is a rectangular structure.
[0014] The beneficial effect of this improvement is that by such an arrangement, the stability of the buried pipe can be improved.
[0015] In order to make the filler have a certain flexibility:
[0016] As a further improvement of the above technical solution: the material of the filler is a mixture of asphalt, water-based epoxy resin and gravel.
[0017] The beneficial effect of this improvement is that, through such an arrangement, the filler has a certain flexibility and can reduce pollution.
[0018] To facilitate the sliding of the connecting pipe in and out of the embedded pipe:
[0019] As a further improvement of the above technical solution: a plurality of rectangular through holes are passed through the joint sheath, and the connecting pipe slides through two corresponding rectangular through holes.
[0020] The beneficial effect of this improvement is that by providing the rectangular through hole, it is convenient for the connecting pipe to slide in and out of the embedded pipe.
[0021] To make the slider more stable:
[0022] As a further improvement of the above technical solution: a limit rod is fixedly installed in the rectangular through groove, and the limit rod slides through the corresponding sliding block.
[0023] The beneficial effect of this improvement is that by setting the limit rod, the slider can be limited, so that the sliding of the slider is more stable.
[0024] The beneficial effects of the utility model are: through a simple joint protection structure, the connecting end faces of the cement concrete pavement and the asphalt pavement can be effectively protected, and the top of the joint can be prevented from breaking and spreading downward to form potholes, which is beneficial to driving safety, effectively reduces repair problems, and brings great convenience to road management work. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 This is a schematic diagram of the main cross-sectional structure of the utility model;
[0026] Figure 2 It is a schematic diagram of the side cross-sectional structure of the joint sheath in the utility model;
[0027] Figure 3 For this utility model Figure 1 A schematic diagram of the enlarged structure of part A;
[0028] Figure 4 For this utility model Figure 2 A schematic diagram of the enlarged structure of part B;
[0029] Figure 5 It is a schematic diagram of the three-dimensional sectional assembly structure of the embedded pipe and the connecting rod in the utility model.
[0030] In the figure: 1. roadbed; 2. cement concrete pavement; 3. asphalt pavement; 4. joint sheath; 5. filling material; 6. embedded pipe; 7. limit clamp; 8. connecting block; 9. connecting pipe; 10. connecting rod; 11. spring; 12. rectangular through groove; 13. slider. DETAILED DESCRIPTION
[0031] In order to enable those skilled in the art to better understand the technical solution of the utility model, the utility model is described in detail below in conjunction with the accompanying drawings. The description in this part is only exemplary and explanatory and should not have any limiting effect on the protection scope of the utility model.
[0032] like Figure 1-5As shown, an environmentally friendly joint structure of a cement concrete pavement and an asphalt pavement comprises a cement concrete pavement 2 and an asphalt pavement 3 arranged on the top of a roadbed 1, a joint sleeve 4 is arranged on the side where the cement concrete pavement 2 and the asphalt pavement 3 are close to each other, a filler 5 is arranged between the two joint sleeves 4, a plurality of embedded pipes 6 with one end being open are embedded in the cement concrete pavement 2 and the asphalt pavement 3, the open ends of the embedded pipes 6 are fixed to the inner walls of the corresponding joint sleeves 4, a limiting clamp 7 is fixedly sleeved on the embedded pipes 6, a connecting block 8 is fixedly installed on the top and bottom of the embedded pipe 6, and one end of the connecting block 8 is fixed to the inner wall of the joint sleeve 4 Through a simple joint protection structure, the connection end faces of cement concrete pavement and asphalt pavement can be effectively protected, and the top of the joint can be prevented from breaking and spreading downward to form potholes, which is beneficial to driving safety and effectively reduces the repair problem, bringing great convenience to road management work. The two joint sheaths 4 also include a plurality of connecting pipes 9, and the connecting pipes 9 penetrate the filling material 5. The two ends of the connecting pipes 9 are respectively slidably extended into the corresponding embedded pipes 6. Two connecting rods 10 are slidably installed in the connecting pipes 9. One end of the connecting rod 10 extends outside the connecting pipe 9 and is fixed on the inner wall of the corresponding embedded pipe 6. The connecting pipes 9 are A spring 11 is provided, and the two ends of the spring 11 are respectively in contact with the corresponding connecting rod 10. The connecting rod 10 is penetrated with a rectangular through groove 12. Two sliders 13 are fixedly installed in the connecting pipe 9, and the sliders 13 slide through the corresponding rectangular through grooves 12. Through such an arrangement, the problem of mutual extrusion between the cement concrete pavement and the asphalt pavement due to thermal expansion can be effectively prevented, and the problem of extrusion, warping and damage at the connection between the cement concrete pavement and the asphalt pavement can be effectively prevented. The joint sheath 4 is a U-shaped structure. Through such an arrangement, it is convenient for the joint sheath 4 to be firmly nested on the end faces of the cement concrete pavement and the asphalt pavement. The embedded pipe 6 is a rectangular structure. The structure is configured in this way, so as to facilitate improving the stability of the buried pipe 6. The material of the filler 5 is asphalt, water-based epoxy resin and gravel mixture. Through this configuration, the filler has a certain flexibility and can reduce pollution. A plurality of rectangular through holes are penetrated on the joint sheath 4, and the connecting pipe 9 slides through the corresponding two rectangular through holes. By setting the rectangular through holes, it is convenient for the connecting pipe 9 to slide in and out of the buried pipe 6. A limiting rod is fixedly installed in the rectangular through groove 12, and the limiting rod slides through the corresponding slider 13. By setting the limiting rod, the slider 13 can be limited, so that the sliding of the slider 13 is more stable.
[0033] The working principle of the utility model is as follows: when in use, firstly place two joint sleeves 4 on the roadbed 1, adjust the distance between the two joint sleeves 4 to a suitable value, then cast the cement concrete pavement and the asphalt pavement, so that a plurality of pre-buried pipes 6 are respectively buried in the cement concrete pavement and the asphalt pavement, after the cement concrete pavement and the asphalt pavement are hardened, the two joint sleeves 4 are respectively fixedly nested in one end of the cement concrete pavement and the asphalt pavement, and then filler 5 is filled between the two joint sleeves 4, when the car drives to the joint of the cement concrete pavement and the asphalt pavement, the wheels collide and apply force to the top of the two joint sleeves 4, so as to effectively avoid the top of the joint of the cement concrete pavement and the asphalt pavement from being damaged, and by such an arrangement, it is possible to prevent water The connecting end faces of the mud concrete pavement and the asphalt pavement are effectively protected, which can prevent the top of the joint from breaking and spreading downward to form potholes, which is beneficial to driving safety and effectively reduces the repair problem, bringing great convenience to road management. When the temperature rises, the cement concrete pavement and the asphalt pavement will have thermal expansion problems, the two joint sheaths 4 are driven closer to each other, the filler 5 is squeezed and narrowed, and the embedded pipe 6 drives the connecting rod 10 to slide into the corresponding connecting pipe 9, so that the spring 11 is compressed and provides buffering. Through such an arrangement, the cement concrete pavement and the asphalt pavement can be effectively prevented from squeezing each other due to thermal expansion, and the connection between the cement concrete pavement and the asphalt pavement can be effectively prevented from being squeezed against each other, and the problem of extrusion, warping and damage can be effectively prevented.
[0034] It should be noted that, in this article, the terms "comprises", "includes" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, article or apparatus that includes a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or apparatus.
[0035] This article uses specific examples to illustrate the principles and implementation methods of the utility model. The above examples are only used to help understand the method and core ideas of the utility model. The above is only the preferred implementation method of the utility model. It should be pointed out that due to the limitations of textual expression, there are objectively infinite specific structures. For ordinary technicians in this technical field, without departing from the principle of the utility model, they can make several improvements, embellishments or changes, and can also combine the above technical features in an appropriate manner; these improvements, embellishments, changes or combinations, or the direct application of the concept and technical solution of the utility model to other occasions without improvement, should be regarded as the protection scope of the utility model.
Claims
1. An environmentally friendly joint structure of a cement concrete pavement and an asphalt pavement, comprising a cement concrete pavement (2) and an asphalt pavement (3) arranged on top of a roadbed (1), characterized in that: The cement concrete pavement (2) and the asphalt pavement (3) are both provided with a joint sleeve (4) on the side where they are close to each other, and a filler (5) is provided between the two joint sleeves (4). A plurality of embedded pipes (6) with one end being open are embedded in the cement concrete pavement (2) and the asphalt pavement (3), and the open ends of the embedded pipes (6) are fixed to the inner walls of the corresponding joint sleeves (4). A limiting clamp (7) is fixedly provided on the embedded pipes (6), and connection blocks (8) are fixedly installed on the top and bottom of the embedded pipes (6), and one end of the connection block (8) is fixed to the inner wall of the joint sleeve (4).
2. The environmentally friendly joint structure of cement concrete pavement and asphalt pavement according to claim 1 is characterized by: The two joint sheaths (4) further include a plurality of connecting tubes (9), wherein the connecting tubes (9) penetrate the filling material (5), and the two ends of the connecting tubes (9) respectively extend into the corresponding embedded tubes (6) by sliding, and two connecting rods (10) are slidably installed in the connecting tubes (9), and one end of the connecting rod (10) extends outside the connecting tubes (9) and is fixed on the inner wall of the corresponding embedded tube (6), and a spring (11) is provided in the connecting tubes (9), and the two ends of the spring (11) are respectively in contact with the corresponding connecting rods (10), and a rectangular through groove (12) penetrates the connecting rods (10), and two sliding blocks (13) are fixedly installed in the connecting tubes (9), and the sliding blocks (13) slide through the corresponding rectangular through grooves (12).
3. The environmentally friendly joint structure of cement concrete pavement and asphalt pavement according to claim 1 is characterized by: The joint sheath (4) is a U-shaped structure.
4. The environmentally friendly joint structure of cement concrete pavement and asphalt pavement according to claim 1 is characterized by: The embedded pipe (6) is a rectangular structure.
5. The environmentally friendly joint structure of cement concrete pavement and asphalt pavement according to claim 1 is characterized by: The material of the filler (5) is a mixture of asphalt, water-based epoxy resin and gravel.
6. The environmentally friendly joint structure of cement concrete pavement and asphalt pavement according to claim 2 is characterized by: The joint sleeve (4) is penetrated by a plurality of rectangular through holes, and the connecting pipe (9) slides through two corresponding rectangular through holes.
7. The environmentally friendly joint structure of cement concrete pavement and asphalt pavement according to claim 2 is characterized by: A limiting rod is fixedly installed in the rectangular through slot (12), and the limiting rod slides through the corresponding sliding block (13).