Pre-embedding, fixing and filling integrated module for profiled steel floor junction box

The junction box made of flexible materials is pre-embedded and fixed filling module, and the mortar leakage problem caused by misalignment between the junction box and the wire box mouth is solved, ensuring the stability of construction and the convenience of subsequent operations.

CN221957196UActive Publication Date: 2024-11-05ZHONG JIAN WU JU SHUI LI NENG YUAN JIAN SHE YOU XIAN GONG SI
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420559784.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-21
Publication Date
2024-11-05
Estimated Expiration
2034-03-21

AI Technical Summary

Technical Problem

In the construction of press-shaped steel floor slabs, the junction box and the wire box opening are easily misaligned, resulting in the problem of mortar leakage during subsequent pouring.

Method used

The junction box is built with a flexible material, which includes a filling part and a clamping part. The ring groove is provided on the circumference of the junction part, and the filling part and the clamping part form a screw hole to ensure the junction box and the wire box opening. Correct alignment and fixation of

Benefits of technology

The mortar leakage problem is effectively avoided, and the module can be destroyed by tools after pouring and curing to expose the interior of the junction box.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221957196U_ABST
    Figure CN221957196U_ABST
Patent Text Reader

Abstract

The utility model discloses a profiled steel floor junction box pre-embedding, fixing and filling integrated module, which belongs to the field of constructional engineering, and is characterized by comprising a body made of flexible materials, and the body comprises a filling part used for sleeving a junction box and a clamping part used for being matched and connected with a profiled steel floor. According to the utility model, the problem that mortar leaks from the wire box opening during pouring can be avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the field of construction engineering, and more specifically relates to a pre-buried, fixed and filled integrated module for a junction box of a corrugated steel floor. Background Art

[0002] When constructing corrugated steel floor slabs, it is usually necessary to reserve a junction box on the steel floor slab, and for this purpose, workers need to cut the outlet of the junction box on the steel floor slab. The current construction practice is usually that workers prefabricate the junction box branches first, and then drill holes on the steel floor slab according to the positions on the drawings and lay pipelines. Since the hole diameter quality when drilling is often closely related to the workers' proficiency and sense of responsibility, the junction box and the outlet of the junction box are easily misaligned when laying the wire pipe, resulting in the problem that the mortar poured later will leak from the outlet of the junction box. Utility Model Content

[0003] In view of the deficiencies in the prior art, the utility model aims to provide a pre-embedded fixed filling integrated module for a junction box of a corrugated steel floor slab, which can avoid the problem of mortar leakage from the junction box opening during pouring.

[0004] In order to achieve the above purpose, the utility model provides the following technical solutions:

[0005] A pre-buried fixed filling integrated module for a corrugated steel floor junction box comprises a body made of a flexible material, wherein the body comprises a filling portion for sleeve installation of the junction box and a clamping portion for cooperating and connecting with the corrugated steel floor.

[0006] The advantages of this solution are at least that: after the opening of the wire box is opened, the flexible clamping part provided by this solution is clamped on the wire box opening to achieve the closure of the wire box opening, and at the same time, the filling part of the body can be inserted into the pre-buried junction box, thereby avoiding the misalignment of the junction box and the wire box opening, and further avoiding the problem of mortar leakage from the wire box opening during subsequent pouring. After pouring and curing, the module can be directly destroyed and removed by tools to expose the inside of the junction box.

[0007] The utility model is further configured as follows: the peripheral side of the clamping portion protrudes from the peripheral side wall of the filling portion, and the peripheral side wall of the clamping portion is provided with an annular groove.

[0008] The advantage of this solution is at least that: because the clamping portion is flexible and has a certain degree of deformation ability, it can be clamped on the edge of the wire box opening through the annular groove to fix the solution.

[0009] The utility model is further configured as follows: a screw hole is provided on the stepped surface formed by the filling portion and the clamping portion.

[0010] The advantage of this solution is at least that after the junction box is sleeved, the screw holes can be used to lock the junction box and the clamping portion by screws, thereby preventing the junction box from falling off the filling portion.

[0011] The utility model is further configured as follows: the peripheral side wall of the filling portion is inwardly recessed to form a clearance groove, and the screw hole is located at the end of the clearance groove.

[0012] The utility model is further configured as follows: the flexible material is at least one of high-density polyethylene and high-density polyvinyl chloride.

[0013] In summary, the utility model has at least the following advantages:

[0014] 1. By setting this module, after the opening of the wire box is opened, the flexible clamping part provided by this solution can be clamped on the wire box opening to achieve the closure of the wire box opening. At the same time, the filling part of the body can be inserted into the pre-buried junction box, thereby avoiding the misalignment of the junction box and the wire box opening, and further avoiding the problem of mortar leakage from the wire box opening during subsequent pouring. After pouring and curing, this module can be directly destroyed and removed by tools to expose the inside of the junction box;

[0015] 2. By setting the screw holes, the screw holes can be used to lock the junction box and the clamping part by screws after the junction box is installed, so as to avoid the problem of the junction box falling off from the filling part. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is an exploded schematic diagram of the main body, the corrugated steel floor and the junction box in a preferred embodiment;

[0017] Figure 2 An exploded cross-sectional view of the main body, the corrugated steel floor and the junction box in a preferred embodiment;

[0018] Figure 3 It is a cross-sectional schematic diagram of the body and the corrugated steel floor slab after being matched in a preferred embodiment.

[0019] Figure numerals: 1, main body; 11, filling part; 111, ring groove; 12, clamping part; 2, screw hole; 3, clearance groove; 4, corrugated steel floor; 5, junction box mouth; 6, junction box. DETAILED DESCRIPTION

[0020] The utility model is further described in detail below in conjunction with the accompanying drawings.

[0021] A pre-buried fixed filling integrated module for a corrugated steel floor junction box, such as Figure 1 and Figure 2 As shown, it includes a main body 1 made of a flexible material. In some embodiments, the flexible material is at least one of high-density polyethylene and high-density polyvinyl chloride, which has a certain deformation ability and can undergo a small deformation under the action of an external force.

[0022] The body 1 includes a filling portion 11 for the wire box to be set and a clamping portion 12 for cooperating with the corrugated steel floor 4, wherein the clamping portion 12 is located at one end of the filling portion 11. Preferably, the peripheral side of the clamping portion 12 protrudes from the peripheral side wall of the filling portion 11, and the peripheral side wall of the clamping portion 12 is provided with an annular groove 111. Figure 2 and Figure 3 As shown, after the wire box opening 5 on the corrugated steel floor 4 is opened, the flexible clamping portion 12 provided by the present solution is clamped on the wire box opening 5 to achieve the closure of the wire box opening 5, and at the same time, the filling portion 11 of the body 1 can be inserted into the pre-buried junction box 6, thereby avoiding the misalignment of the junction box 6 and the wire box opening 5, and further avoiding the problem of mortar leakage from the wire box opening 5 during subsequent pouring. After pouring and curing, the present module can be directly destroyed and removed by a tool such as a screwdriver to expose the inside of the junction box 6.

[0023] In order to further improve the stability between the junction box 6 and the body 1, a screw hole 2 is provided on the stepped surface formed by the filling portion 11 and the clamping portion 12. The screw hole 2 can be used to lock the junction box 6 and the clamping portion 12 by screws after the junction box 6 is sleeved. In some embodiments, in order to match the shape of the junction box 6, the side wall of the filling portion 11 is recessed inward to form a clearance groove 3, and the screw hole 2 is located at the end of the clearance groove 3.

[0024] The working process and beneficial effects of the utility model are as follows: after the wire box opening 5 on the corrugated steel floor 4 is opened, the flexible clamping part 12 provided by the present solution is clamped on the wire box opening 5 to achieve the closure of the wire box opening 5, and at the same time, the filling part 11 of the body 1 can be inserted into the pre-buried junction box 6, thereby avoiding the misalignment of the junction box 6 and the wire box opening 5, and further avoiding the problem of mortar leakage from the wire box opening 5 during subsequent pouring. After pouring and curing, the present module can be directly destroyed and dug out by tools to expose the inside of the junction box 6.

[0025] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the design concept of the present invention should be included in the protection scope of the present invention.

Claims

1. A pre-buried fixed filling integrated module for a corrugated steel floor junction box, characterized in that: It comprises a main body (1) made of a flexible material, wherein the main body (1) comprises a filling portion (11) for housing a wire box and a clamping portion (12) for cooperating with a corrugated steel floor slab (4).

2. The pre-buried fixed filling integrated module for the junction box of the corrugated steel floor according to claim 1 is characterized in that: The peripheral side of the clamping portion (12) protrudes from the peripheral side wall of the filling portion (11), and the peripheral side wall of the clamping portion (12) is provided with an annular groove (111).

3. The pre-buried fixed filling integrated module for the junction box of the corrugated steel floor according to claim 2 is characterized in that: A screw hole (2) is provided on the stepped surface formed by the filling portion (11) and the clamping portion (12).

4. The pre-buried fixed filling integrated module for the junction box of the corrugated steel floor according to claim 3 is characterized in that: The side wall of the filling portion (11) is inwardly recessed to form a clearance groove (3), and the screw hole (2) is located at the end of the clearance groove (3).

5. The pre-buried fixed filling integrated module for the junction box of the corrugated steel floor according to claim 1 is characterized in that: The flexible material is at least one of high-density polyethylene and high-density polyvinyl chloride.