LNG (Liquefied Natural Gas) gasification and refrigerant conduction device
By designing LNG gasification and refrigerant conduction devices, cold energy is transferred to refrigerant by using atomization nozzles and heat exchangers, and a circulation is formed through the refrigerant pump station and refrigerant preheater, the problem of cold energy waste during LNG gasification is solved. , improve resource utilization and refrigerant cooling effect.
Patent Information
- Application Number
- CN202420726444.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-10
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2034-04-10
AI Technical Summary
The large amount of cold energy released during the gasification of existing LNG has not been effectively utilized, resulting in waste of resources.
A LNG gasification and refrigerant conduction device was designed, and liquid natural gas was sprayed on the surface of the heat exchanger using atomization nozzle and heat exchanger. Cold energy was transferred to the refrigerant through the heat exchanger, and preheated through the refrigerant pump station and refrigerant. The appliance and the refrigeration mechanism form a cycle to improve the utilization rate of cold energy.
The cooling energy released during LNG gasification is effectively reused, which improves the utilization rate of resources, avoids resource waste, and improves the cooling effect of refrigerant by accelerating the gasification process.
Smart Images

Figure CN221958659U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of LNG gasification, in particular to an LNG gasification and refrigerant conduction device. Background Art
[0002] LNG is one of the most low-carbon and environmentally friendly new energy sources. The main component of LNG is methane, which is colorless, odorless, non-toxic and non-corrosive. After combustion, liquefied natural gas causes very little air pollution. After combustion, it mainly produces water and releases a lot of heat, so liquefied natural gas is a relatively advanced energy source.
[0003] When LNG is used, it usually needs to be vaporized into gas before being burned. The LNG vaporization process will release a large amount of cold energy, but there is currently no good way to utilize this large amount of cold energy released. In most cases, a large amount of cold energy released is wasted, which is not conducive to the recycling of resources. Utility Model Content
[0004] The utility model aims to solve the shortcomings of the prior art and proposes an LNG gasification and refrigerant conduction device.
[0005] In order to achieve the above-mentioned purpose, the utility model adopts the following technical scheme: an LNG gasification and refrigerant conduction device, comprising an LNG cylinder, a first pipeline is fixedly connected to the front side of the LNG cylinder, the other end of the first pipeline is fixedly connected to the gasification bin, the inner bottom of the gasification bin is fixedly connected to the heat exchanger, the right side of the heat exchanger is fixedly connected to the ninth pipeline, the other end of the ninth pipeline is fixedly connected to the refrigerant preheater, the right side of the refrigerant preheater is fixedly connected to the eighth pipeline, the other end of the eighth pipeline is fixedly connected to the refrigerant pump station, the back of the refrigerant pump station is fixedly connected to the seventh pipeline, the other end of the seventh pipeline is fixedly connected to the central air conditioner, the left side of the heat exchanger is fixedly connected to the fourth pipeline, the other end of the fourth pipeline is fixedly connected to the refrigerant storage, the right side of the refrigerant storage is fixedly connected to the fifth pipeline, the other end of the fifth pipeline is fixedly connected to the refrigeration mechanism, and the refrigeration mechanism is fixedly connected to the central air conditioner through the sixth pipeline.
[0006] As a further description of the above technical solution:
[0007] An atomizing nozzle is fixedly connected to the inner wall of the gasification bin, and the atomizing nozzle is fixedly connected to the first pipeline.
[0008] As a further description of the above technical solution:
[0009] A second pipeline is fixedly connected to the left outer wall of the gasification bin, and the other end of the second pipeline is fixedly connected to a gas power machine.
[0010] As a further description of the above technical solution:
[0011] A third pipeline is fixedly connected to the back of the gas power machine, and the other end of the third pipeline is fixedly connected to a generator.
[0012] As a further description of the above technical solution:
[0013] A first wiring harness is fixedly connected to the right side surface of the generator, and the other end of the first wiring harness is fixedly connected to the back outer wall of the central air conditioner.
[0014] As a further description of the above technical solution:
[0015] A second wire harness is fixedly connected to the right side of the generator, and the other end of the second wire harness is fixedly connected to the right side of the refrigeration mechanism.
[0016] The utility model has the following beneficial effects:
[0017] 1. Compared with the prior art, the LNG gasification and refrigerant conduction device, through the LNG cylinder, the first pipeline, the atomizing nozzle, the heat exchanger, the second pipeline, the gas power machine, the generator, the first wiring harness, the central air conditioner, the second wiring harness, the refrigeration mechanism, the fourth pipeline, the refrigerant storage, the fifth pipeline, the sixth pipeline, the seventh pipeline, the refrigerant pump station, the eighth pipeline and the refrigerant preheater, when in use, the LNG cylinder transports the liquid natural gas to the atomizing nozzle position through the first pipeline, the atomizing nozzle sprays the liquid natural gas onto the surface of the heat exchanger, the liquid natural gas absorbs the heat of the refrigerant in the heat exchanger and gasifies into natural gas gas, and at the same time transfers the cold energy to the refrigerant in the heat exchanger, the gasified natural gas enters the gas power machine through the second pipeline and burns, the combustion generates power, and then the power is transferred to the generator through the third pipeline to drive the generator to generate electricity, the generator supplies power to the central air conditioner through the first wiring harness, the generator supplies power to the refrigeration mechanism through the second wiring harness, and the heat exchanger reduces the The heated refrigerant is transferred to the refrigerant storage through the fourth pipeline, the refrigerant in the refrigerant storage is then transported to the refrigeration mechanism through the fifth pipeline, the refrigerant in the refrigeration mechanism is then transported to the central air-conditioning through the sixth pipeline for cooling, the heated refrigerant after the central air-conditioning works is then transported to the refrigerant pump station through the seventh pipeline, the refrigerant is pressurized in the refrigerant pump station, and then flows into the refrigerant preheater through the eighth pipeline, the refrigerant preheater preheats the refrigerant, and the preheated refrigerant is then passed into the heat exchanger, and the circulation work starts from then on. Compared with the existing LNG gasification device, the LNG gasification process will release a large amount of cold energy, but there is currently no good method for utilizing this large amount of cold energy released. In most cases, a large amount of cold energy released is wasted, which is not conducive to the recycling of resources. The LNG gasification and refrigerant conduction device can reuse the large amount of cold energy released in the LNG gasification process, greatly improves the utilization rate of resources, and avoids the waste of resources.
[0018] 2. Compared with the prior art, this LNG gasification and refrigerant conduction device uses an atomizing nozzle and a heat exchanger. When in use, the atomizing nozzle can evenly spray LNG on the surface of the heat exchanger, thereby accelerating the LNG gasification process and achieving a better cooling effect of the refrigerant in the heat exchanger. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 This is a schematic diagram of the overall structure of an LNG gasification and refrigerant conduction device proposed by the utility model;
[0020] Figure 2 This is a cross-sectional view of the overall structure of an LNG gasification and refrigerant conduction device proposed by the utility model;
[0021] Figure 3 This is a schematic diagram of the overall structure of an LNG gasification and refrigerant conduction device proposed by the utility model;
[0022] Figure 4 This is a schematic diagram from another perspective of an LNG gasification and refrigerant conduction device proposed by the utility model.
[0023] Legend:
[0024] 1. LNG cylinder; 2. First pipeline; 3. Gasification chamber; 4. Atomizing nozzle; 5. Heat exchanger; 6. Second pipeline; 7. Gas power machine; 8. Third pipeline; 9. Generator; 10. First wiring harness; 11. Central air conditioner; 12. Fourth pipeline; 13. Refrigerant storage; 14. Fifth pipeline; 15. Refrigeration mechanism; 16. Sixth pipeline; 17. Seventh pipeline; 18. Refrigerant pump station; 19. Eighth pipeline; 20. Refrigerant preheater; 21. Ninth pipeline; 22. Second wiring harness. DETAILED DESCRIPTION
[0025] Reference Figure 1-4 The utility model provides an LNG gasification and refrigerant conduction device, including an LNG cylinder 1, a first pipeline 2 is fixedly connected to the front side of the LNG cylinder 1, a gasification bin 3 is fixedly connected to the other end of the first pipeline 2, a heat exchanger 5 is fixedly connected to the inner bottom of the gasification bin 3, a ninth pipeline 21 is fixedly connected to the right side of the heat exchanger 5, the ninth pipeline 21 is the inlet of the refrigerant in the heat exchanger 5, a refrigerant preheater 20 is fixedly connected to the other end of the ninth pipeline 21, an eighth pipeline 19 is fixedly connected to the right side of the refrigerant preheater 20, a refrigerant pump station 18 is fixedly connected to the other end of the eighth pipeline 19, and the refrigerant pump station 18 is fixedly connected to the back side thereof. The seventh pipe 17 is the outlet of the refrigerant in the central air conditioner 11. The other end of the seventh pipe 17 is fixedly connected to the central air conditioner 11. The left side of the heat exchanger 5 is fixedly connected to the fourth pipe 12. The fourth pipe 12 is the outlet of the refrigerant in the heat exchanger 5. The other end of the fourth pipe 12 is fixedly connected to the refrigerant storage 13. The right side of the refrigerant storage 13 is fixedly connected to the fifth pipe 14. The other end of the fifth pipe 14 is fixedly connected to the refrigeration mechanism 15. The refrigeration mechanism 15 is a condenser. The refrigeration mechanism 15 is fixedly connected to the central air conditioner 11 through the sixth pipe 16. The sixth pipe 16 is the inlet of the refrigerant in the central air conditioner 11.
[0026] The inner wall of the gasification bin 3 is fixedly connected with an atomizing nozzle 4, which is responsible for spraying liquid natural gas evenly on the surface of the heat exchanger 5. The atomizing nozzle 4 is fixedly connected to the first pipeline 2, and the left outer wall of the gasification bin 3 is fixedly connected with a second pipeline 6, and the other end of the second pipeline 6 is fixedly connected with a gas power machine 7, and the back of the gas power machine 7 is fixedly connected with a third pipeline 8, and the other end of the third pipeline 8 is fixedly connected with a generator 9. The gas power machine 7 can ignite gaseous natural gas to do work, and the energy generated by the work is provided to the generator 9 for power supply. The right side of the generator 9 is fixedly connected with a first wiring harness 10, and the other end of the first wiring harness 10 is fixedly connected to the back outer wall of the central air conditioner 11. The right side of the generator 9 is fixedly connected with a second wiring harness 22, and the other end of the second wiring harness 22 is fixedly connected to the right side of the refrigeration mechanism 15. Part of the electricity of the generator 9 is supplied to the central air conditioner 11, and the other part of the generator 9 and the heat are supplied to the refrigeration mechanism 15.
[0027] Working principle: When in use, the LNG cylinder 1 transports the liquefied natural gas to the atomizing nozzle 4 through the first pipeline 2, and the atomizing nozzle 4 sprays the liquefied natural gas onto the surface of the heat exchanger 5. The liquefied natural gas absorbs the heat of the refrigerant in the heat exchanger 5 and vaporizes into natural gas gas, and at the same time transfers the cold energy to the refrigerant in the heat exchanger 5. The vaporized natural gas enters the gas power machine through the second pipeline 6 and burns. The combustion generates power, and then the power is transferred to the generator 9 through the third pipeline 8 to drive the generator 9 to generate electricity. The generator 9 supplies power to the central air conditioner 11 through the first wiring harness 10, and the generator 9 supplies power to the refrigeration mechanism 15 through the second wiring harness 22. Power is supplied, and the heat exchanger 5 transfers the cooled refrigerant to the refrigerant storage 13 through the fourth pipe 12. The refrigerant in the refrigerant storage 13 is then transported to the refrigeration mechanism 15 through the fifth pipe 14. The refrigerant in the refrigeration mechanism 15 is then transported to the central air conditioner 11 through the sixth pipe 16 for cooling. The heated refrigerant after the central air conditioner 11 works is then transported to the refrigerant pump station 18 through the seventh pipe 17. The refrigerant is pressurized in the refrigerant pump station 18 and then flows into the refrigerant preheater 20 through the eighth pipe 19. The refrigerant preheater 20 preheats the refrigerant, and the preheated refrigerant is then passed into the heat exchanger 5, and the circulation work starts from then on.
[0028] Finally, it should be noted that the above is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. An LNG gasification and refrigerant conduction device, comprising an LNG cylinder (1), characterized in that: The front side of the LNG cylinder (1) is fixedly connected to a first pipeline (2), the other end of the first pipeline (2) is fixedly connected to a gasification bin (3), the inner bottom of the gasification bin (3) is fixedly connected to a heat exchanger (5), the right side of the heat exchanger (5) is fixedly connected to a ninth pipeline (21), the other end of the ninth pipeline (21) is fixedly connected to a refrigerant preheater (20), the right side of the refrigerant preheater (20) is fixedly connected to an eighth pipeline (19), the other end of the eighth pipeline (19) is fixedly connected to a refrigerant pump station (18), and the refrigerant pump station A seventh pipe (17) is fixedly connected to the back of the heat exchanger (18), and the other end of the seventh pipe (17) is fixedly connected to the central air conditioner (11). A fourth pipe (12) is fixedly connected to the left side of the heat exchanger (5), and the other end of the fourth pipe (12) is fixedly connected to the refrigerant storage (13). A fifth pipe (14) is fixedly connected to the right side of the refrigerant storage (13), and the other end of the fifth pipe (14) is fixedly connected to a refrigeration mechanism (15). The refrigeration mechanism (15) is fixedly connected to the central air conditioner (11) via a sixth pipe (16).
2. The LNG gasification and refrigerant conduction device according to claim 1, characterized in that: An atomizing nozzle (4) is fixedly connected to the inner wall of the gasification bin (3), and the atomizing nozzle (4) is fixedly connected to the first pipeline (2).
3. The LNG gasification and refrigerant conduction device according to claim 1, characterized in that: A second pipeline (6) is fixedly connected to the left outer wall of the gasification bin (3), and a gas power machine (7) is fixedly connected to the other end of the second pipeline (6).
4. The LNG gasification and refrigerant conduction device according to claim 3, characterized in that: A third pipeline (8) is fixedly connected to the back of the gas power machine (7), and a generator (9) is fixedly connected to the other end of the third pipeline (8).
5. The LNG gasification and refrigerant conduction device according to claim 4, characterized in that: A first wiring harness (10) is fixedly connected to the right side of the generator (9), and the other end of the first wiring harness (10) is fixedly connected to the back outer wall of the central air conditioner (11).
6. The LNG gasification and refrigerant conduction device according to claim 4, characterized in that: A second wiring harness (22) is fixedly connected to the right side of the generator (9), and the other end of the second wiring harness (22) is fixedly connected to the right side of the refrigeration mechanism (15).