Building material elevator
By introducing a lifting mechanism and locking mechanism driven by hydraulic telescopic rod into the building material elevator, the maintenance inconvenience caused by fixing the lifting frame at a high place after the steel cable is broken, safe fixing and convenient maintenance are achieved, and construction safety is improved and efficiency.
Patent Information
- Application Number
- CN202420408561.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-04
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2034-03-04
AI Technical Summary
When the existing building material lifting device breaks, the lifting frame is fixed at a high place, resulting in inconvenience in maintenance and affecting safety and efficiency.
A building material elevator was designed, including a base, an articulated lifting frame, a lifting mechanism driven by hydraulic telescopic rod, a lifting component and a locking mechanism. The lifting frame is controlled to be flipped through hydraulic telescopic rod, so that the lifting frame is lowered to the ground parallel, making it easier to inspect and repair. , and the lifting frame position is fixed when the cable is loose or broken through the locking mechanism to prevent falling.
It realizes safe fixing and convenient maintenance of the lifting frame when the steel cable breaks, avoids staff climbing high places, improves the safety and convenience of maintenance, and ensures the safety of construction workers.
Smart Images

Figure CN221971003U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of construction equipment, in particular to a building material hoist. Background Art
[0002] A material hoist is a machine that uses a gear rack meshing method or a steel cable rope lifting method to make the cage move vertically or tilted to transport personnel and materials. It is used in material lifting in various industries, especially in the construction industry, where hoists are used more widely. However, in the process of lifting construction materials, in order to ensure the safety of construction workers, most of them need to add an anti-fall mechanism to the hoist to prevent materials from falling.
[0003] For example, the Chinese utility model patent with patent number CN202121978187.4 provides a fall-proof construction material transport lift. When the device is in use, the gear in the device can only rotate unidirectionally on the connecting shaft. By using the set rack and the meshing between the rack and the gear, the gear can only move unidirectionally on the rack, which can prevent the gear from moving downward. When the connecting rope breaks, the gear can stay on the rack to prevent the movable plate from falling downward, thereby ensuring the safety of the construction workers.
[0004] However, the existing material hoists still have certain drawbacks when in use. For example, when the steel cable of the existing building material lifting device breaks, most of them can only lock the position of the lifting frame, so that the lifting frame is fixed at a high place, and the staff need to climb to the relative position to inspect the hoist, which makes the inspection of the lifting frame inconvenient. Utility Model Content
[0005] In view of the shortcomings of the prior art, the utility model proposes a construction material hoist to solve the technical problem raised in the above background technology that when the steel cable of the existing construction material lifting device breaks, most of them can only lock the position of the lifting frame, so that the lifting frame is fixed at a high place, which makes the maintenance of the lifting frame inconvenient.
[0006] To achieve the above purpose, the utility model provides the following technical solution, a building material hoist, comprising:
[0007] Base;
[0008] A lifting frame is hinged to the base, and a lifting frame lifted by a steel cable is arranged inside the lifting frame;
[0009] A lifting mechanism, disposed on the base and connected to the lifting frame, to drive the lifting frame to flip along a hinge point between the lifting frame and the base;
[0010] a lifting assembly, disposed on the lifting frame, for winding the steel cable; and
[0011] A locking mechanism is arranged on the lifting frame and connected to the lifting frame to lock the position of the lifting frame when the steel cable is loose.
[0012] In a preferred embodiment, a plurality of groups of first buffer seats are disposed on the base, a plurality of groups of second buffer seats are disposed at the bottom of the lifting frame, and the plurality of groups of the first buffer seats abut against the plurality of groups of the second buffer seats.
[0013] In a preferred embodiment, the lifting mechanism includes a hydraulic telescopic rod, one end of which is hinged to the lifting frame, and the other end of which is hinged to the base.
[0014] In a preferred embodiment, the lifting frame is provided with a plurality of groups of support rods, the lifting frame is provided with a plurality of groups of positioning rings, and the plurality of groups of positioning rings are respectively slidably sleeved on the plurality of groups of support rods.
[0015] In a preferred embodiment, the lifting assembly includes:
[0016] A winding wheel is rotatably arranged on the lifting frame along its axis, and one end of the steel cable is wound around the winding wheel; and
[0017] The lifting motor is arranged on the lifting frame, and the output shaft of the lifting motor is connected with the winding wheel.
[0018] In a preferred embodiment, the locking mechanism includes:
[0019] A positioning frame is arranged at the bottom of the lifting frame, a locking rod is slidably arranged in the positioning frame, and the end of the locking rod is ratchet-shaped;
[0020] A locking block is arranged on the locking rod, and an inclined groove is provided on the locking block, and an end of the steel cable passes through the inclined groove and is fixedly connected to the lifting frame;
[0021] A baffle plate is arranged at the bottom of the lifting frame, an elastic member is arranged between the locking block and the baffle plate, and the elastic member is in a compressed state when the steel cable is tensioned; and
[0022] A ratchet bar is arranged on the support rod, and the end of the locking rod can be clamped on the ratchet bar.
[0023] Compared with the prior art, the utility model has the following beneficial effects:
[0024] When the device is in use, the steel cable can be retracted and released through the lifting assembly, thereby controlling the lifting frame to rise and fall, so as to lift and transport the building materials. When the steel cable is loose or broken, the position of the lifting frame is fixed by the locking mechanism to prevent the lifting frame from falling and causing harm to the staff. After the position of the lifting frame is fixed, if the position of the lifting frame is too high, it will be inconvenient to inspect and repair the lifting frame. The lifting frame can be controlled by the lifting mechanism to rotate and flip along the hinge point between it and the base, so that the lifting frame moves parallel to the ground, thereby lowering the lifting frame for easy inspection and maintenance. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] In order to more clearly illustrate the specific implementation of the utility model, the following will briefly introduce the drawings required for use in the specific implementation. In all the drawings, each element or part is not necessarily drawn according to the actual scale.
[0026] Figure 1 A three-dimensional structural schematic diagram of a building material hoist provided by the utility model;
[0027] Figure 2 This is a schematic diagram of the upward shaft side structure of a building material hoist according to the utility model;
[0028] Figure 3 for Figure 2 A magnified schematic diagram of area a in the middle;
[0029] Reference numerals:
[0030] 101. base; 102. first buffer seat; 103. hydraulic telescopic rod;
[0031] 201, lifting frame; 202, support rod; 203, ratchet bar; 204, lifting motor; 205, winding wheel; 206, steel cable; 207, second buffer seat;
[0032] 301, lifting frame; 302, positioning frame; 303, baffle; 304, locking rod; 305, locking block; 306, inclined groove; 307, elastic member; 308, positioning ring. DETAILED DESCRIPTION
[0033] The following embodiments of the technical solution of the utility model are described in detail in conjunction with the accompanying drawings. The following embodiments are only used to more clearly illustrate the technical solution of the utility model, and are therefore only used as examples, and cannot be used to limit the protection scope of the utility model.
[0034] Example:
[0035] like Figure 1 , 2As shown, the utility model provides a building material hoist, including a base 101, a hinged lifting frame 201 is arranged on the base 101, a lifting frame 301 lifted by a steel cable 206 is arranged inside the lifting frame 201, a lifting component for winding the steel cable 206 is arranged on the lifting frame 201, the lifting component includes a winding wheel 205 rotatable along its axis and arranged on the lifting frame 201, one end of the steel cable 206 is wound on the winding wheel 205, a lifting motor 204 is arranged on the lifting frame 201, and the output shaft of the lifting motor 204 is connected to the winding wheel 205.
[0036] The winding wheel 205 can be driven to rotate by controlling the rotation of the lifting motor 204. The winding wheel 205 retracts and releases the steel cable 206 during the rotation, so that the lifting frame 201 is raised and lowered to lift the material. In addition, multiple groups of support rods 202 are arranged on the lifting frame 201, and multiple groups of positioning rings 308 are arranged on the lifting frame 301. The multiple groups of positioning rings 308 are slidably sleeved on the multiple groups of support rods 202 respectively. The movement of the lifting frame 301 is positioned by the cooperation of the positioning rings 308 and the support rods 202, so as to prevent the lifting frame 301 from tilting or deflecting during the movement, thereby improving the stability of material transportation.
[0037] like Figure 2 , 3 As shown, in this embodiment, a locking mechanism connected to the lifting frame 201 is provided on the lifting frame 301, and the position of the lifting frame 301 is locked by the locking mechanism when the steel cable 206 is relaxed. The locking mechanism includes a positioning frame 302 arranged at the bottom of the lifting frame 301, a locking rod 304 is slidably arranged in the positioning frame 302, the end of the locking rod 304 is ratchet-shaped, a locking block 305 is arranged on the locking rod 304, and an inclined groove 306 is opened on the locking block 305. The end of the steel cable 206 passes through the inclined groove 306 and is fixedly connected to the lifting frame 301. A baffle 303 is arranged at the bottom of the lifting frame 301, and an elastic member 307 is arranged between the locking block 305 and the baffle 303. When the steel cable 206 is tensioned, the elastic member 307 is compressed. A ratchet bar 203 is arranged on the support rod 202, and the end of the locking rod 304 can be clamped on the ratchet bar 203.
[0038] When the steel cable 206 is not broken, the steel cable 206 is in a tensioned state, and the tensioning force causes the steel cable 206 to be located at the highest point of the inclined slot 306, so that the locking rod 304 is retracted and the elastic member 307 is compressed. When the steel cable 206 is broken or loosened, the locking rod 304 loses the tension of the steel cable 206, and the locking rod 304 slides in the positioning frame 302 under the reset ability of the elastic member 307 until the locking rod 304 is stuck on the ratchet bar 203, completing the position locking of the lifting frame 301, and preventing the lifting frame 301 from falling and causing injuries to the staff.
[0039] like Figure 1 , 2 As shown, in this embodiment, a lifting mechanism connected to the lifting frame 201 is provided on the base 101, and the lifting frame 201 is driven to flip along the hinge point between the lifting frame 201 and the base 101 by the lifting mechanism. The lifting mechanism includes a hydraulic telescopic rod 103, one end of the hydraulic telescopic rod 103 is hinged to the lifting frame 201, and the other end is hinged to the base 101. Multiple groups of first buffer seats 102 are provided on the base 101, and multiple groups of second buffer seats 207 are provided at the bottom of the lifting frame 201, and the multiple groups of first buffer seats 102 abut against the multiple groups of second buffer seats 207.
[0040] When the position of the lifting frame 301 is locked, if the hoist needs to be repaired, the lifting frame 201 can be turned along the hinge point between the lifting frame 201 and the base 101 by controlling the hydraulic telescopic rod 103 to contract until the lifting frame 201 moves parallel to the ground, and the lifting frame 301 can be repaired without the need for workers to climb high places, thereby improving the safety and convenience of maintenance. The lifting frame 201 can be restored to the use state by controlling the extension of the hydraulic telescopic rod 103, and the movement of the lifting frame 201 is buffered and supported by multiple groups of first buffer seats 102 and multiple groups of second buffer seats 207, thereby improving the safety of the device when in use.
[0041] Specific usage and beneficial effects of the utility model:
[0042] When the device is in use, the lifting motor 204 can control the winding wheel 205 to rotate and release the steel cable 206, thereby controlling the lifting frame 301 to lift and transport the building materials. When the steel cable 206 is loose or broken, the locking block 305 loses the force of the steel cable 206, so that the locking rod 304 is clamped on the ratchet bar 203 under the action of the elastic member 307 to fix the position of the lifting frame 301 and prevent the lifting frame 301 from falling and causing harm to the staff. After the position of the lifting frame 301 is fixed, if the position of the lifting frame 301 is high, it will cause inconvenience to the maintenance of the lifting frame 301. The hydraulic telescopic rod 103 can be controlled to shrink to drive the lifting frame 201 to rotate and flip along the hinge point between it and the base 101, so that the lifting frame 201 moves to be parallel to the ground, thereby causing the lifting frame 301 to descend, which is convenient for maintenance.
[0043] The basic principle and main features of the present invention and the advantages of the present invention are shown and described above. For those skilled in the art, it is obvious that the present invention is not limited to the details of the above exemplary embodiments.
Claims
1. A building material hoist, characterized in that: Included are: Base (101); A lifting frame (201) is hinged to the base (101), and a lifting frame (301) is provided inside the lifting frame (201) for lifting by a steel cable (206); A lifting mechanism, arranged on the base (101) and connected to the lifting frame (201), so as to drive the lifting frame (201) to flip along a hinge point between the lifting frame (201) and the base (101); A lifting assembly, arranged on the lifting frame (201) to wind the steel cable (206); and A locking mechanism is arranged on the lifting frame (301) and connected to the lifting frame (201) so as to lock the position of the lifting frame (301) when the steel cable (206) is relaxed.
2. A building material hoist according to claim 1, characterized in that: The base (101) is provided with a plurality of groups of first buffer seats (102), and the bottom of the lifting frame (201) is provided with a plurality of groups of second buffer seats (207), and the plurality of groups of the first buffer seats (102) are in abutment with the plurality of groups of the second buffer seats (207).
3. A building material hoist according to claim 1, characterized in that: The lifting mechanism comprises a hydraulic telescopic rod (103), one end of the hydraulic telescopic rod (103) is hinged to the lifting frame (201), and the other end is hinged to the base (101).
4. A building material hoist according to claim 1, characterized in that: The lifting frame (201) is provided with a plurality of groups of support rods (202), and the lifting frame (301) is provided with a plurality of groups of positioning rings (308). The plurality of groups of positioning rings (308) are respectively slidably sleeved on the plurality of groups of support rods (202).
5. A building material hoist according to claim 4, characterized in that: The lifting assembly comprises: A winding wheel (205) is rotatably arranged on the lifting frame (201) along its axis, and one end of the steel cable (206) is wound around the winding wheel (205); and A lifting motor (204) is arranged on the lifting frame (201), and an output shaft thereof is connected to the winding wheel (205).
6. A building material hoist according to claim 5, characterized in that: The locking mechanism comprises: A positioning frame (302) is arranged at the bottom of the lifting frame (301), a locking rod (304) is slidably arranged in the positioning frame (302), and the end of the locking rod (304) is ratchet-shaped; A locking block (305) is arranged on the locking rod (304), an inclined groove (306) is provided on the locking block (305), an end of the steel cable (206) passes through the inclined groove (306) and is fixedly connected to the lifting frame (301); A baffle (303) is arranged at the bottom of the lifting frame (301), an elastic member (307) is arranged between the locking block (305) and the baffle (303), and the elastic member (307) is in a compressed state when the steel cable (206) is tensioned; and A ratchet bar (203) is arranged on the support rod (202), and an end of the locking rod (304) can be clamped on the ratchet bar (203).