Reinforcement cage centering device for pile foundation construction
By using orifice brackets, floats and steel cage brackets in pile foundation construction, using pin hammers and cross-shaped engraving lines to determine the position of steel cages, the problems of low accuracy and difficult operation in traditional methods are solved, and more efficient Pile foundation construction.
Patent Information
- Application Number
- CN202323336160.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-07
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2033-12-07
AI Technical Summary
The traditional steel cage centering method has problems such as low accuracy, long operating time, and large position deviation in pile foundation construction, especially difficult positioning in mud, resulting in poor quality control of pile foundation pile formation.
A device including an orifice bracket, a float and a steel cage bracket is designed to determine whether the steel cage position is centered by hanging plumbing and cross-shaped engraving lines, and a convenient centering operation is achieved in combination with a rubber cushion layer and a reel assembly.
The centering accuracy and construction efficiency of the steel cage are improved, on-site operation is simplified, and the quality and progress of pile foundation construction are ensured.
Smart Images

Figure CN221972382U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of pile foundation construction equipment, and in particular relates to a steel cage centering device used for pile foundation construction. Background Art
[0002] The process of bored pile construction is usually used in pile foundation construction. Bored pile construction refers to forming pile holes in the foundation soil by mechanical drilling, steel pipe squeezing or manual excavation at the construction site, placing steel cages in them, and pouring concrete to make piles. According to different hole-forming methods, bored piles can be divided into several categories, such as sinking pipe bored piles, bored piles and excavated bored piles. In order to ensure the construction quality of bored pile foundation, the more important control indicator during the construction process is to make the steel cage as central as possible in the pile hole, so the steel cage needs to be centered.
[0003] The traditional method of aligning the steel cage is to use the "cross" alignment method up and down. Specifically, the steel cage is lowered to the position of the casing hole, and a "cross" line is hung on the main reinforcement at the top of the steel cage, and then the "cross" line of the pile guards around the hole is hung. The "cross" line of the pile guard positioning is located above the "cross" line of the main reinforcement at the top of the steel cage. A plumb bob is hung on the top of the "cross" line of the pile guard positioning, and the plumb bob is aligned with the "cross" line of the support stirrups at the top of the bottom steel cage for alignment, and then slowly lowered to the steel cage position. Since the top position of most pile foundation steel cages is located below the mud in the hole, it is inevitable that the steel cage will be offset during the process of lowering the steel cage into place, resulting in low precision in the positioning of the steel cage. In addition, the traditional steel cage alignment method takes a long time to operate, the steel cage position deviation is large, and the pile foundation quality control precision is low. At the same time, it has also become a common quality problem of the steel cage alignment deviation of bored cast-in-place piles, especially for pile foundations with long suspension bars. Since the steel cage is completely immersed in the mud and cannot be accurately positioned, it often causes the steel cage to be out of center after the pile head is broken, and may even exceed the specification requirements.
[0004] In summary, in order to ensure the quality of bored pile foundation construction (such as bridge engineering construction), speed up the construction progress and improve the construction efficiency, a device for centering the pile foundation steel cage should be developed and designed for the steel cage in place construction process of bridge pile foundation construction. Utility Model Content
[0005] The utility model provides a steel cage centering device for pile foundation construction which has a simple structure, is easy to operate and has a good centering effect in order to solve the technical problems existing in the known technology, thereby ensuring the quality of pile foundation construction, improving the efficiency of pile foundation construction and accelerating the construction progress.
[0006] The utility model adopts the following technical scheme to solve the technical problems existing in the known technology: a steel cage centering device for pile foundation construction comprises an orifice bracket installed at the orifice position of the pile hole, a buoy floating on the mud and a steel cage bracket installed on the top of the steel cage, a plumb bob is suspended at the center of the orifice bracket by a plumb bob suspension rope, a cross-shaped engraved line is provided on the top of the buoy to cooperate with the bottom tip of the plumb bob to show whether it is centered, and the middle position of the bottom of the buoy is connected to the middle position of the steel cage bracket by a connecting suspension rope.
[0007] Preferably: the orifice bracket includes a central base with a longitudinally through-going slot, a connecting column is provided on the top of the central base and on the side of the slot, a plurality of supporting arms are provided at equal angle intervals in the circumferential direction of the outer side of the central base, an arc-shaped supporting plate is installed at the outer end of each supporting arm, a rubber pad is installed on the outer side of each supporting plate, and the upper end of the plumb bob rope is fixedly connected to the connecting column.
[0008] Preferably, the buoy comprises a cylindrical buoy body, the lower end of the buoy body is pointed and a counterweight is arranged inside, a circular top plate is arranged on the top of the buoy body, and the cross-shaped engraved line is arranged in the middle of the top plate.
[0009] Preferably: the steel cage support includes a first steel wire and a second steel wire, each end of which is connected to the steel bars in the corresponding position at the top of the steel cage, the lower end of the connecting rope is connected to the intersection of the first steel wire and the second steel wire, and the connection strength between the connecting rope and the two steel wires is greater than the connection strength between the two steel wires and the steel cage.
[0010] Preferably: a reel assembly is also installed at the bottom of the buoy and the upper end of the connecting rope is connected to the reel assembly; the reel assembly includes two opposite side plates, the upper ends of the two side plates are fixedly connected to the bottom of the buoy body, a reel is installed between the two side plates, the upper end of the connecting rope is wound around the middle position of the reel, an operating handle is installed at one end of the reel, and a ratchet pawl structure is also provided between the reel and the side plates.
[0011] The advantages and positive effects of the utility model are:
[0012] The utility model provides a steel cage centering device for pile foundation construction with a reasonable structural design, by installing an orifice bracket at the orifice position and suspending a plumb bob in the middle of the orifice bracket, installing the steel cage bracket on the top of the steel cage and arranging a buoy with a cross-shaped engraved line on the top, so as to achieve the technical effect of judging whether the steel cage is centered by relying on the relative position relationship between the bottom tip of the plumb bob and the cross-shaped engraved line, the operation is convenient and labor-saving, and the centering effect is good.
[0013] Compared with the existing steel cage centering device and steel cage centering operation method, the centering device in the utility model is easy to operate and use on site, ensures the quality of pile foundation construction, improves the efficiency of pile foundation construction, and speeds up the construction progress. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a schematic diagram of the structure of the utility model, which is a state of use when installed in a pile hole;
[0015] Figure 2 yes Figure 1 A schematic diagram of the structure of the wellhead support;
[0016] Figure 3 yes Figure 1 Schematic diagram of the structure of the middle buoy;
[0017] Figure 4 yes Figure 1 Schematic diagram of the structure of the steel cage support.
[0018] In the figure:
[0019] 1. Orifice bracket; 1-1. Center base; 1-2. Connecting column; 1-3. Support arm; 1-4. Notch; 1-5. Support plate; 1-6. Rubber cushion; 2. Plumb rope; 3. Plumb; 4. Float; 4-1. Float body; 4-2. Top plate; 4-3. Counterweight; 5. Pile hole; 6. Mud; 7. Reel assembly; 7-1. Side plate; 7-2. Reel; 7-3. Ratchet and pawl structure; 7-4. Operating handle; 8. Steel cage bracket; 8-1. First steel wire; 8-2. Second steel wire; 9. Steel cage; 10. Connecting rope; 11. Orifice casing. DETAILED DESCRIPTION
[0020] In order to further understand the content, features and effects of the present invention, the following embodiments are given to explain in detail.
[0021] See also Figure 1 The steel cage centering device for pile foundation construction of the utility model comprises an orifice bracket 1 installed at the orifice position of the pile hole 5, a buoy 4 floating on the mud 6 and a steel cage bracket 8 installed on the top of the steel cage 9. A plumb bob 3 is suspended by a plumb bob rope 2 at the center of the orifice bracket 1. A cross-shaped engraved line is provided on the top of the buoy 4 to cooperate with the bottom tip of the plumb bob 3 to show whether it is centered. The middle position of the bottom of the buoy 4 is connected to the middle position of the steel cage bracket 8 by a connecting rope 10.
[0022] The centering principle is: a plumb bob 3 connected below the center position of the orifice bracket 1 is used to reflect the center position of the pile hole 5, and a buoy 4 with a cross-shaped mark on the top, which is connected to the center position of the steel cage bracket 8 on the top of the steel cage 9, is used to reflect the position of the steel cage 9 in the pile hole 5 (immersed in the mud 6). The construction personnel judge whether the position of the steel cage 9 in the pile hole 5 meets the centering requirement by observing the relative position relationship between the plumb bob 3 and the cross-shaped mark. If the bottom tip of the plumb bob 3 deviates from the intersection position of the cross-shaped mark, it is judged that it is not centered. At this time, the crane of the steel cage 9 is adjusted, and the steel cage 9 is appropriately shifted until the bottom tip of the plumb bob 3 is aligned with the intersection position of the cross-shaped mark to achieve the centering effect.
[0023] See also Figure 2 , we can see that:
[0024] The orifice bracket 1 includes a central base 1-1 with a longitudinally through-going notch 1-4, a connecting column 1-2 is provided at the top of the central base 1-1 and the side of the notch 1-4, the upper end of the plumb rope 2 is fixedly connected to the connecting column 1-2 and the plumb rope 2 passes through the notch 1-4. In order to make the plumb rope 2 strictly located at the center position, the inner end of the notch 1-4 should be located at the center position of the central base 1-1, and the connecting column 1-2 is set off-center on the central base 1-1. When in use, the upper end of the plumb rope 2 is buckled and hung on the connecting column 1-2, and the height of the mobile plumb 3 is adjusted by adjusting the position of the buckle on the plumb rope 2.
[0025] A plurality of arms 1-3 are arranged at equal angles in the circumferential direction on the outer side of the central base 1-1, an arc-shaped support plate 1-5 is installed at the outer end of each arm 1-3, and a rubber cushion layer 1-6 is installed on the outer side of each support plate 1-5. As shown in the figure, three groups of arms 1-3, support plates 1-5 and rubber cushion layers 1-6 are arranged at 120° intervals in the circumferential direction.
[0026] Generally, a hole mouth casing 11 is also provided at the hole mouth position of the pile hole 5, so the effective outer diameter of the hole mouth bracket 1 should be adapted to the inner diameter of the hole mouth casing 11. During installation, the hole mouth bracket 1 is placed in the hole mouth casing 11 as a whole and kept horizontal. At this time, each rubber cushion layer 1-6 is in contact with the inner wall of the hole mouth casing 11 and is subjected to a certain extrusion effect, so the hole mouth bracket 1 can be stably installed at the hole mouth position of the pile hole 5. Since there is an open space between the two adjacent groups of support arms 1-3, the support plate 1-5 and the rubber cushion layer 1-6 of the hole mouth bracket 1, the hoisting cable of the crane equipment for lifting and lowering the steel cage 9 can pass through the aforementioned open space.
[0027] See also Figure 3 , we can see that:
[0028] The buoy 4 includes a cylindrical buoy body 4-1, the lower end of the buoy body 4-1 is a pointed tip and a counterweight 4-3 is arranged inside, a circular top plate 4-2 is arranged on the top of the buoy body 4-1, and the cross-shaped engraved line is arranged in the middle position of the top plate 4-2. The buoy 4 is injection molded or blow molded as a whole, and the counterweight 4-3 is integrally molded inside the buoy body 4-1. The buoy body 4-1 is a sealed structure as a whole, and the purpose of setting the counterweight 4-3 is to enhance the stability of the buoy 4 on the surface of the mud 6 to avoid random shaking and displacement. As shown in the figure, in a stable state, the bottom tip of the plumb bob 3 is located above the center position of the top plate 4-2 and has a suitable distance, which is convenient for on-site construction personnel to judge the relative position relationship by observation.
[0029] See also Figure 3 A reel assembly 7 is also installed at the bottom of the buoy 4 and the upper end of the connecting rope 10 is connected to the reel assembly 7. The purpose of setting the reel assembly 7 is to adjust the effective length of the connecting rope 10 by reeling or unreeling the upper end of the connecting rope 10. The effective length should be suitable for the distance between the upper end of the steel cage 9 and the surface of the mud 6, so that the connecting rope 10 can be in a suitable tension state.
[0030] In this embodiment, the reel assembly 7 includes two opposite side panels 7-1, the upper ends of the two side panels 7-1 are fixedly connected to the bottom of the float body 5-1 (they can be fixedly connected by bonding, welding, etc.), and a reel 7-2 is installed between the lower ends of the two side panels 7-1. The upper end of the connecting rope 10 is wound around the middle position of the reel 7-2. An operating handle 7-4 is installed at one end of the reel 7-2, and the reel 7-2 is rotated by operating the operating handle 7-4.
[0031] A ratchet pawl structure 7-3 is also provided between the reel 7-2 and the side plate 7-1. The ratchet pawl structure 7-3 can lock the reel 7-2 in the current position without rotating by itself. Specifically, the ratchet pawl structure 7-3 includes a ratchet mounted on the reel 7-2 and a pawl mounted on the side plate 7-1. The pawl is embedded in the teeth on the side of the ratchet wheel. The ratchet pawl structure 7-3 allows the reel 7-2 to rotate forward. When the reel 7-2 needs to rotate in the reverse direction, the pawl needs to be manually moved to separate from the ratchet wheel.
[0032] See also Figure 4 , we can see that:
[0033] The steel cage support 8 includes a first steel wire 8-1 and a second steel wire 8-2, each end of which is connected to the steel bars in the corresponding position at the top of the steel cage 9, and the lower end of the connecting rope 10 is connected to the intersection of the first steel wire 8-1 and the second steel wire 8-2, and the connection strength between the connecting rope 10 and the two steel wires is greater than the connection strength between the two steel wires and the steel cage 9.
[0034] Since the ends of the first steel wire 8-1 and the second steel wire 8-2 are connected to the steel bars at the corresponding positions, both steel wires pass through the top center of the steel cage 9, and the intersection of the first steel wire 8-1 and the second steel wire 8-2 is the top center of the steel cage 9. Because the buoy 4 floats on the surface of the mud 6 under the action of buoyancy and plays a role in pulling and tensioning the connecting suspension rope 10, the cross-shaped engraved line at the top center of the buoy 4 reflects the center position of the steel cage 9 below in a stable state.
[0035] The purpose of making the connection strength between the connecting rope 10 and the two steel wires greater than the connection strength between the two steel wires and the steel cage 9 is: after completing the centering operation of the steel cage 9 in the pile hole 5, it is necessary to remove the centering device and pour concrete. At this time, by applying an upward pulling force to the connecting rope 10, the ends of the first steel wire 8-1 and the second steel wire 8-2 are forced to separate from the top steel bars of the steel cage 9, so that the steel cage bracket 8 can be disassembled from the top of the steel cage 9.
[0036] Directions:
[0037] The steel cage 9 is lowered into the pile hole 5 by a crane. When the upper end of the steel cage 9 enters the hole position, the lowering is stopped. The steel cage bracket 8 is installed and set on the top of the steel cage 9 by tying the first steel wire 8-1 and the second steel wire 8-2. The lower end of the connecting rope 10 is firmly connected to the intersection of the first steel wire 8-1 and the second steel wire 8-2. According to the depth of the pile hole 5, the depth of the mud 6 and the height of the steel cage 9, the effective length value of the connecting rope 10 is calculated, and the length of the connecting rope 10 is adjusted and set by operating the reel assembly 7. Then, the steel cage 9 is continued to be lowered into the mud 6 and reaches a suitable depth. At this time, the buoy 4 floats on the surface of the mud 6 and the connecting rope 10 is tensioned.
[0038] The orifice bracket 1 is installed inside the orifice casing 11. Specifically, the orifice bracket 1 is placed in the port of the orifice casing 11 in a horizontal posture, and each rubber cushion layer 1-6 of the orifice bracket 1 is in contact with the inner wall of the orifice casing 11, so that the orifice bracket 1 is fixedly installed; then, a buckle is fastened at a suitable position on the plumb bob rope 2 according to the height distance between the orifice bracket 1 and the top of the buoy 4, and the buckle position is mounted and connected with the connecting column 1-2, and at this time, the plumb bob 3 is suspended at a certain height above the buoy 4;
[0039] The construction personnel on site judge whether the steel cage 9 is centered in the pile hole 5 by observing the relative position relationship between the plumb bob 3 and the cross-shaped engraved line below it. If the plumb bob 3 is offset from the middle position of the cross-shaped engraved line, it is judged that it is not centered. At this time, the operator of the crane equipment should be instructed to properly shift the steel cage 9 until the plumb bob 3 is aligned with the middle position of the cross-shaped engraved line to achieve the centering effect of the steel cage 9;
[0040] After completing the centering operation, remove the hole mouth bracket 1, the plumb bob rope 2 and the plumb bob 3 from the top, then pull the buoy 4 upward, and the connecting rope 10 applies an upward pulling effect to the first steel wire 8-1 and the second steel wire 8-2 of the steel cage bracket 8. The ends of the two steel wires are separated from the top steel bars of the steel cage 9. At this time, the buoy 4, the steel cage bracket 8 and the connecting rope 10 are removed; then the concrete pouring process is implemented in the pile hole 5.
Claims
1. A steel cage centering device for pile foundation construction, characterized by: The invention comprises an orifice bracket (1) installed at the orifice position of a pile hole (5), a buoy (4) floating on mud (6), and a steel cage bracket (8) installed on the top of a steel cage (9). A plumb bob (3) is suspended at the center of the orifice bracket (1) by a plumb bob suspension rope (2). A cross-shaped engraved line is provided on the top of the buoy (4) to cooperate with the bottom tip of the plumb bob (3) to indicate whether it is centered. The middle position of the bottom of the buoy (4) is connected to the middle position of the steel cage bracket (8) by a connecting suspension rope (10).
2. The reinforcement cage centering device for pile foundation construction according to claim 1, characterized in that: The orifice bracket (1) comprises a central base (1-1) with a longitudinally penetrating notch (1-4); a connecting column (1-2) is arranged at the top of the central base (1-1) and at the side of the notch (1-4); a plurality of supporting arms (1-3) are arranged at equal angles in the circumferential direction of the outer side of the central base (1-1); an arc-shaped supporting plate (1-5) is installed at the outer end of each supporting arm (1-3); a rubber cushion layer (1-6) is installed at the outer side of each supporting plate (1-5); and the upper end of a plumb bob rope (2) is fixedly connected to the connecting column (1-2).
3. The reinforcement cage centering device for pile foundation construction according to claim 2, characterized in that: The buoy (4) comprises a cylindrical buoy body (4-1), the lower end of the buoy body (4-1) is pointed and a counterweight (4-3) is arranged inside, a circular top plate (4-2) is arranged on the top of the buoy body (4-1), and the cross-shaped engraved line is arranged in the middle position of the top plate (4-2).
4. The reinforcement cage centering device for pile foundation construction as claimed in claim 3, characterized in that: The steel cage support (8) comprises a first steel wire (8-1) and a second steel wire (8-2), the ends of which are connected to steel bars at the top of the steel cage (9) in a corresponding position, the lower end of the connecting rope (10) is connected to the intersection of the first steel wire (8-1) and the second steel wire (8-2), and the connection strength between the connecting rope (10) and the two steel wires is greater than the connection strength between the two steel wires and the steel cage (9).
5. The steel cage centering device for pile foundation construction as claimed in claim 4 is characterized in that: A reel assembly (7) is also installed at the bottom of the buoy (4), and the upper end of the connecting sling (10) is connected to the reel assembly (7); the reel assembly (7) comprises two opposite side plates (7-1), the upper ends of the two side plates (7-1) are fixedly connected to the bottom of the buoy body (4-1), a reel (7-2) is installed between the two side plates (7-1), the upper end of the connecting sling (10) is wound around the middle of the reel (7-2), an operating handle (7-4) is installed at one end of the reel (7-2), and a ratchet pawl structure (7-3) is also provided between the reel (7-2) and the side plate (7-1).