Hydropower station underground powerhouse construction channel arrangement structure suitable for TBM continuous tunneling

By adopting a tunnel layout structure with continuous TBM excavation in the construction of the underground powerhouse of the hydropower station, the safety risks and surrounding rock disturbance problems of drill-and-blast construction were solved, enabling continuous excavation of five tunnels, shortening the construction period, and improving construction safety and environmental quality.

CN221973519UActive Publication Date: 2024-11-08POWERCHINA BEIJING ENG CORP
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202420019186.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-04
Publication Date
2024-11-08
Estimated Expiration
2034-01-04

AI Technical Summary

Technical Problem

In existing technologies, the drilling and blasting method used in the construction of underground cavern groups for pumped storage power stations has problems such as high safety risks, poor construction environment, large disturbance of surrounding rock, and adverse effects on the health of construction workers.

Method used

The underground powerhouse construction passage layout of the hydropower station adopts TBM continuous tunneling, including the layout of ventilation tunnels, upper drainage corridors of the powerhouse, central guide tunnels of the powerhouse, tailrace construction adits and No. 1 tailrace tunnel, which meets the requirements of continuous TBM tunneling in one go, and achieves continuous tunneling of five tunnels through TBM construction.

Benefits of technology

It improved construction safety and quality, shortened the construction period, reduced disturbance to the surrounding rock, improved the construction environment and personnel health, enabled the power station to generate electricity ahead of schedule, and improved project benefits.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221973519U_ABST
    Figure CN221973519U_ABST
Patent Text Reader

Abstract

The utility model discloses a hydropower station underground powerhouse construction channel arrangement structure suitable for TBM continuous tunneling. The hydropower station underground powerhouse construction channel arrangement structure comprises a ventilation hole, a powerhouse upper layer drainage gallery, a powerhouse middle pilot tunnel, a tail water construction adit and a 1 # tail water tunnel which are sequentially arranged to meet TBM one-time continuous tunneling. The starting point of the ventilation hole and the ground switching station share the same site platform, and the tail end of the ventilation hole and the plant top arch share the same elevation; the starting point of the workshop pilot tunnel is connected with the ending point of the ventilation hole; the starting point of the workshop upper-layer drainage gallery is connected with the tail end horizontal section of the ventilation hole, the terminal point of the workshop upper-layer drainage gallery is connected with the starting point of the tail water construction adit, the terminal point of the tail water construction adit is connected with the 1 # tail water tunnel, and the two ends of the 1 # tail water tunnel are connected with the workshop and the water inlet and outlet of the lower reservoir respectively. The method has the advantages that the TBM is applied to the position of a key line to the maximum extent, the total construction period is shortened to the maximum extent, power is generated in advance, and engineering benefits are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of TBM continuous excavation construction of a water transmission and power generation system of a hydropower station, in particular to an underground powerhouse construction channel arrangement structure of a hydropower station suitable for TBM continuous excavation. Background Art

[0002] At present, the construction of underground cavern groups in pumped-storage power stations usually adopts the "drilling and blasting method". The drilling and blasting method has mature construction technology, strong applicability, simple construction organization, flexibility and convenience. The average monthly excavation progress of tunnel construction using the drilling and blasting method is generally 90 to 150 m / month. However, the drilling and blasting method of tunnel construction has significant disadvantages such as high safety risks, poor construction environment, and large disturbance to the surrounding rock, which is not good for the occupational health of on-site construction and management personnel. Utility Model Content

[0003] The utility model aims to provide a construction passage arrangement structure of an underground powerhouse of a hydropower station suitable for continuous excavation by a TBM, thereby solving the above-mentioned problems existing in the prior art.

[0004] In order to achieve the above purpose, the technical solution adopted by the utility model is as follows:

[0005] A construction channel layout structure for an underground powerhouse of a hydropower station suitable for continuous TBM excavation comprises a ventilation tunnel, a drainage gallery on the upper floor of the powerhouse, a pilot tunnel in the powerhouse, a tailwater construction branch tunnel and a No. 1 tailwater tunnel which are arranged in sequence to meet the requirements of one continuous TBM excavation; the starting point of the ventilation tunnel is on the same site platform as the ground switch station, which is used as the TBM installation site and starting point in the early stage, and the end of the ventilation tunnel is at the same elevation as the top arch of the powerhouse; the starting point of the pilot tunnel in the powerhouse is connected to the end point of the ventilation tunnel and is coaxial with it, and the end point of the pilot tunnel in the powerhouse is located at the right end wall of the powerhouse; the drainage gallery on the upper floor of the powerhouse is located on the upstream side of the powerhouse and arranged parallel to the axis of the powerhouse, the starting point of the drainage gallery on the upper floor of the powerhouse is connected to the end horizontal section of the ventilation tunnel, the end point of the drainage gallery on the upper floor of the powerhouse is connected to the starting point of the tailwater construction branch tunnel, the end point of the tailwater construction branch tunnel is connected to the No. 1 tailwater tunnel, and the two ends of the No. 1 tailwater tunnel are respectively connected to the powerhouse and the water inlet and outlet of the lower reservoir, and the water inlet and outlet of the lower reservoir are used as the TBM recovery and disassembly site in the early stage.

[0006] Preferably, the layout of the ventilation tunnel entrance meets the requirements of the TBM installation platform, the minimum turning radius of the ventilation tunnel is greater than or equal to 60.0m, the average longitudinal slope is less than or equal to 8%, and the final cross-section is a circular cross-section of the TBM single-stage excavation construction.

[0007] Preferably, the excavated section of the guide tunnel in the factory building is circular, and the comprehensive longitudinal slope of the guide tunnel in the factory building is 0.

[0008] Preferably, the end point of the traffic tunnel is connected to the right end wall of the factory building, and the end of the upper drainage corridor of the factory building intersects the traffic tunnel vertically, and after passing through the traffic tunnel, intersects parallel to the starting point of the tailwater construction branch tunnel.

[0009] Preferably, the starting point of the upper drainage corridor of the factory building is at the same elevation as the horizontal section at the end of the ventilation tunnel, and the excavation section is circular; the axis of the upper drainage corridor of the factory building intersects with the axis at the end of the ventilation tunnel at a large angle, meeting the requirements of TBM oblique excavation; the end point of the upper drainage corridor of the factory building intersects with the straight section at the end of the traffic tunnel vertically, and the intersection point is at the same elevation as the bottom plate of the ventilation tunnel; the turning radius of the upper drainage corridor of the factory building is greater than or equal to 60.0m, and the comprehensive longitudinal slope is less than or equal to 8%.

[0010] Preferably, the starting point of the tailwater construction branch tunnel intersects vertically with the terminal straight segment of the traffic tunnel, the starting elevation of the tailwater construction branch tunnel is the same as the terminal elevation from the upper drainage corridor of the plant building to the traffic tunnel, the excavation section is circular, the axis of the tailwater construction branch tunnel intersects with the axis of the 1# tailwater tunnel at a large angle, meeting the TBM oblique excavation requirements, the intersection elevation is the same as the bottom plate design elevation of the 1# tailwater tunnel, the turning radius of the tailwater construction branch tunnel is greater than or equal to 60.0m, and the comprehensive longitudinal slope does not exceed 8%.

[0011] Preferably, the excavation section of the 1# tailwater tunnel is circular, the comprehensive longitudinal slope does not exceed 8%, and the turning radius is greater than or equal to 60.0m; the outlet of the 1# tailwater tunnel is located in the lower reservoir, and the outlet platform layout meets the requirements of the TBM recovery and disassembly site.

[0012] Preferably, it also includes a 2# tailwater tunnel, which is arranged parallel to the 1# tailwater tunnel, and its two ends are respectively connected to the powerhouse and the inlet and outlet of the lower reservoir; the end of the tailwater construction branch tunnel passes through the 2# tailwater tunnel and is connected to the 1# tailwater tunnel.

[0013] Preferably, after each tunnel is constructed by TBM, a horizontal road surface is formed by paving with waste slag or cast-in-place concrete to meet the requirements for the passage of construction machinery.

[0014] Preferably, a conveyor belt is set up on the side wall of the ventilation tunnel after the TBM construction is completed to meet the slag discharge requirements of the plant arch expansion and the upper drainage gallery of the plant, the tailwater construction branch tunnel and the No. 1 tailwater tunnel.

[0015] The beneficial effects of the utility model are as follows: 1. TBM construction is applied to replace traditional drilling and blasting construction on the key lines of the single project of the underground system of the hydropower station, which is difficult to construct and has a controlled construction period, to ensure safety and quality while speeding up construction and achieving the purpose of putting the power station into operation and generating electricity in advance. 2. The layout structure is suitable for TBM installation at one time to achieve continuous excavation construction of five tunnels; TBM is applied to the parts on the key lines to the maximum extent, shortening the total construction period to the maximum extent, generating electricity in advance, and improving project benefits; reducing the surrounding rock disturbance of the underground cavern group and improving the overall stability of the underground cavern group structure; it is beneficial to the occupational health of on-site construction and management personnel, and is beneficial to environmental protection and labor protection; it fully improves the tunnel construction environment and the health of construction workers. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a schematic plan view of the layout structure of the construction passage of the underground powerhouse of the hydropower station in the embodiment of the utility model;

[0017] Figure 2 It is a typical cross-sectional view of a tunnel constructed by TBM continuous excavation in an embodiment of the utility model.

[0018] In the figure: 1. Ground switch station; 2. Ventilation tunnel; 3. Drainage corridor on the upper side of the plant; 4. Pilot tunnel in the plant; 5. Tailwater construction branch tunnel; 6. 1# tailwater tunnel; 7. 2# tailwater tunnel; 8. Traffic tunnel; 9. Lower reservoir inlet and outlet; 10. TBM access road; 11. Horizontal road surface; 12. Conveyor belt; 13. Air duct. DETAILED DESCRIPTION

[0019] In order to make the purpose, technical solution and advantages of the utility model more clear, the utility model is further described in detail below in conjunction with the accompanying drawings. It should be understood that the specific implementation methods described here are only used to explain the utility model and are not used to limit the utility model.

[0020] like Figure 1 As shown, in this embodiment, a construction channel layout structure of an underground powerhouse of a hydropower station suitable for continuous TBM excavation is provided, including a ventilation tunnel 2, an upper drainage gallery 3 of the powerhouse, a pilot tunnel 4 in the powerhouse, a tailwater construction branch tunnel 5 and a 1# tailwater tunnel 6 which are arranged in sequence to meet the requirements of one continuous TBM excavation; the TBM is applied to the parts on the key line to the maximum extent, so that the TBM can be installed once and the excavation of five tunnels can be completed through continuous excavation construction, thereby shortening the total construction period to the maximum extent, generating electricity in advance, improving the project efficiency, and at the same time improving the intelligent construction rate of the project and the occupational health of on-site construction and management personnel.

[0021] The specific layout structure of the construction channel is as follows:

[0022] See attached Figure 1The starting point of the ventilation tunnel 2 is on the same site platform as the ground switch station 1, which is used as the TBM installation site and starting point in the early stage. The end of the ventilation tunnel 2 is at the same elevation as the top arch of the powerhouse; the starting point of the pilot tunnel 4 in the powerhouse is connected to the end point of the ventilation tunnel 2 and is coaxial with it, and the end point of the pilot tunnel 4 in the powerhouse is located at the right end wall of the powerhouse; the upper drainage gallery 3 of the powerhouse is located on the upstream side of the powerhouse and is arranged parallel to the axis of the powerhouse. The starting point of the upper drainage gallery 3 of the powerhouse is connected to the terminal horizontal section of the ventilation tunnel 2, and the end point of the upper drainage gallery 3 of the powerhouse is connected to the starting point of the tailwater construction branch tunnel 5, and the end point of the tailwater construction branch tunnel 5 is connected to the 1# tailwater tunnel 6. The two ends of the 1# tailwater tunnel 6 are respectively connected to the powerhouse and the inlet and outlet 9 of the lower reservoir, and the inlet and outlet 9 of the lower reservoir is used as the TBM recovery and disassembly site in the early stage.

[0023] In this embodiment, the opening layout of the ventilation tunnel 2 meets the requirements of the TBM installation platform, the minimum turning radius of the ventilation tunnel 2 is greater than or equal to 60.0m, the average longitudinal slope is less than or equal to 8%, and the final section is a circular section for TBM single excavation construction. Figure 1 In the figure, ventilation tunnel 2 is located on the left side of the plant, and the end of ventilation tunnel 2 intersects vertically with the left end wall of the plant. Similarly, ventilation tunnel 2 can be set on the right side of the plant, and the layout of other tunnels is the same as that of ventilation tunnel 2 on the left side of the plant.

[0024] In this embodiment, the pilot tunnel 4 in the factory building is coaxial with the ventilation tunnel 2, and the comprehensive longitudinal slope is 0.

[0025] In this embodiment, the end point of the traffic tunnel 8 is connected to the right end wall of the factory building, and the end of the upper drainage corridor 3 of the factory building intersects the traffic tunnel 8 vertically, and after passing through the traffic tunnel 8, it intersects parallel to the starting point of the tailwater construction branch tunnel 5.

[0026] In this embodiment, the starting point of the upper drainage corridor 3 of the factory building is at the same elevation as the horizontal section at the end of the ventilation tunnel 2, and the excavation section is circular; the axis of the upper drainage corridor 3 of the factory building intersects with the axis at the end of the ventilation tunnel 2 at a large angle, meeting the requirements of TBM oblique excavation; the end point of the upper drainage corridor 3 of the factory building intersects with the terminal straight section of the traffic tunnel 8 vertically, and the intersection point is at the same elevation as the bottom plate of the ventilation tunnel 2; the turning radius of the upper drainage corridor 3 of the factory building is greater than or equal to 60.0m, and the comprehensive longitudinal slope is less than or equal to 8%.

[0027] In this embodiment, the starting point of the tailwater construction branch tunnel 5 intersects vertically with the terminal straight segment of the traffic tunnel 8, the starting elevation of the tailwater construction branch tunnel 5 is the same as the terminal elevation of the upper drainage corridor 3 of the powerhouse to the traffic tunnel 8, the excavation section is circular, the axis of the tailwater construction branch tunnel 5 intersects with the axis of the 1# tailwater tunnel 6 at a large angle, meeting the TBM oblique excavation requirements, the intersection elevation is the same as the bottom plate design elevation of the 1# tailwater tunnel 6, the turning radius of the tailwater construction branch tunnel 5 is greater than or equal to 60.0m, and the comprehensive longitudinal slope does not exceed 8%.

[0028] In this embodiment, the excavation section of the 1# tailwater tunnel 6 is circular, the comprehensive longitudinal slope does not exceed 8%, and the turning radius is greater than or equal to 60.0m; the outlet of the 1# tailwater tunnel 6 is located in the lower reservoir, and the outlet platform layout meets the requirements of the TBM recovery and disassembly site.

[0029] In this embodiment, the 2# tailwater tunnel 7 is the same as the 1# tailwater tunnel 6 and is arranged parallel to the 1# tailwater tunnel 6, and its two ends are respectively connected to the powerhouse and the inlet and outlet 9 of the lower reservoir; the end of the tailwater construction branch tunnel 5 passes through the 2# tailwater tunnel 7 and is connected to the 1# tailwater tunnel 6.

[0030] like Figure 2 As shown, in this embodiment, after each tunnel is constructed by TBM, a horizontal road surface 11 is formed by paving with waste slag or pouring concrete in situ to meet the requirements for the passage of construction machinery. A conveyor belt 12 is set up on the side wall of the ventilation tunnel 2 after the TBM construction is completed to meet the requirements for slag discharge of the factory arch expansion and the upper drainage gallery 3 of the factory, the tailwater construction branch tunnel 5 and the 1# tailwater tunnel 6. An air duct 13 is set at the top of the tunnel to meet the ventilation requirements in the tunnel.

[0031] In this embodiment, the TBM needs to meet the following construction procedures to achieve continuous excavation: the TBM is assembled on the platform at the entrance of the ventilation tunnel, and the ventilation tunnel 2 needs to be constructed by drilling and blasting for 20m (i.e. Figure 1 The 20m in the figure is used as the starting section of TBM excavation. The excavation starts from ventilation tunnel 2. TBM is used to excavate 30m in advance between ventilation tunnel 2 and upper drainage gallery 3 of the powerhouse (the starting section of the upper drainage gallery of the powerhouse, i.e. Figure 1 30m in the middle) creates conditions for entering the upper drainage corridor 3 of the power building after completing the construction of the pilot tunnel 4 in the power building. After completing the construction of the pilot tunnel 4 in the power building, the TBM needs to retreat to the intersection of the upper drainage corridor 3 of the power building and the ventilation tunnel 2, and then the TBM enters the upper drainage corridor 3 of the power building for construction, and uses this section of the upper drainage corridor 3 of the power building to descend downhill to the traffic tunnel 8. The TBM enters the tailwater construction branch tunnel 5 through the traffic tunnel 8 for excavation construction. After the TBM excavates the tailwater construction branch tunnel 5, it passes through the 2# tailwater tunnel 7 and enters the 1# tailwater tunnel 6, and finally exits the tunnel from the lower reservoir inlet and outlet 9 through the 1# tailwater tunnel 6 to complete the construction. That is: TBM installation site (ground switch station 1) → ventilation tunnel 2 → upstream side of the upper drainage gallery 3 of the powerhouse (30m) → first retreat → remaining section of ventilation tunnel 2 → pilot tunnel 4 in the powerhouse → second retreat → upper drainage gallery 3 of the powerhouse → tailwater construction branch tunnel 5 → 1# tailwater tunnel 6 → TBM disassembly site (lower reservoir inlet and outlet 9).

[0032] In this embodiment, see the attached Figure 1The ventilation tunnel 2 includes a ventilation tunnel opening, a ventilation tunnel body starting section, a ventilation tunnel body descending section, a ventilation tunnel body turning section, a ventilation tunnel body horizontal section, a ventilation tunnel body arc section, and a ventilation tunnel end that are connected in sequence; the plant guide tunnel 4 includes a plant guide tunnel opening, a plant guide tunnel body horizontal section, and a plant guide tunnel end that are connected in sequence; the plant upper drainage corridor 3 includes a plant drainage corridor opening, a plant drainage corridor starting section, a plant drainage corridor horizontal section, The end of the plant drainage corridor; the tailwater construction branch tunnel 5 includes the tailwater construction branch tunnel entrance, the tailwater construction branch tunnel body section, the tailwater construction branch tunnel body turning section, the tailwater construction branch tunnel body arc section, and the end of the tailwater construction branch tunnel connected in sequence; the 1# tailwater tunnel 6 includes the 1# tailwater tunnel and the tailwater construction branch tunnel intersection section, the 1# tailwater tunnel body climbing section, the 1# tailwater tunnel body turning section, the 1# tailwater tunnel body arc section, and the 1# tailwater tunnel exit section connected in sequence. Therefore, the TBM excavation route is as follows: ventilation tunnel entrance, ventilation tunnel body starting section, ventilation tunnel body descending section, ventilation tunnel body turning section, ventilation tunnel body horizontal section, ventilation tunnel body arc section, powerhouse drainage corridor starting section, ventilation tunnel end, powerhouse middle guide tunnel entrance, powerhouse middle guide tunnel body horizontal section, powerhouse middle guide tunnel end, powerhouse drainage corridor entrance, powerhouse drainage corridor horizontal section, powerhouse drainage corridor end, tailwater construction branch tunnel entrance, tailwater construction branch tunnel body section, tailwater construction branch tunnel body turning section, tailwater construction branch tunnel body arc section, tailwater construction branch tunnel end, 1# tailwater tunnel and tailwater construction branch tunnel intersection section, 1# tailwater tunnel body climbing section, 1# tailwater tunnel body turning section, 1# tailwater tunnel body arc section, 1# tailwater tunnel exit section.

[0033] By adopting the above technical solution disclosed in the utility model, the following beneficial effects are obtained:

[0034] The utility model provides a construction channel layout structure for underground powerhouses of hydropower stations suitable for continuous TBM excavation. TBM construction is applied to replace traditional drilling and blasting construction on key lines of single projects with difficult construction and controlled construction period of underground systems of hydropower stations, ensuring safety and quality while accelerating construction, so as to achieve the purpose of early commissioning and power generation of power stations. The layout structure is suitable for TBM installation to achieve continuous excavation construction of five tunnels; TBM is applied to the parts on the key lines to the maximum extent, shortening the total construction period to the maximum extent, generating electricity in advance, and improving project benefits; reducing the surrounding rock disturbance of underground cavern groups, and improving the overall stability of the underground cavern group structure; it is beneficial to the occupational health of on-site construction and management personnel, and is beneficial to environmental protection and labor protection; it fully improves the tunnel construction environment and the health of construction workers.

[0035] The above is only a preferred embodiment of the present invention. It should be pointed out that ordinary technicians in this technical field can make several improvements and modifications without departing from the principle of the present invention. These improvements and modifications should also be considered as the protection scope of the present invention.

Claims

1. A construction channel layout structure for underground powerhouses of a hydropower station suitable for continuous TBM excavation, characterized in that: It includes ventilation tunnels, upper drainage corridors of powerhouses, pilot tunnels in powerhouses, tailwater construction branch tunnels and 1# tailwater tunnels, which are arranged in sequence to meet the requirements of one continuous excavation of TBM; the starting point of the ventilation tunnel is on the same site platform as the ground switch station, which is used as the TBM installation site and starting point in the early stage, and the end of the ventilation tunnel is at the same elevation as the top arch of the powerhouse; the starting point of the pilot tunnel in the powerhouse is connected to the end point of the ventilation tunnel and is coaxial with it, and the end point of the pilot tunnel in the powerhouse is located at the right end wall of the powerhouse; the upper drainage corridor of the powerhouse is located on the upstream side of the powerhouse and arranged parallel to the axis of the powerhouse, the starting point of the upper drainage corridor of the powerhouse is connected to the terminal horizontal section of the ventilation tunnel, the end point of the upper drainage corridor of the powerhouse is connected to the starting point of the tailwater construction branch tunnel, the end point of the tailwater construction branch tunnel is connected to the 1# tailwater tunnel, and the two ends of the 1# tailwater tunnel are respectively connected to the powerhouse and the inlet and outlet of the lower reservoir, and the inlet and outlet of the lower reservoir are used as the TBM recovery and disassembly site in the early stage.

2. The construction passage arrangement structure of the underground powerhouse of a hydropower station suitable for TBM continuous excavation according to claim 1 is characterized in that: The layout of the ventilation tunnel entrance meets the requirements of the TBM installation platform, the minimum turning radius of the ventilation tunnel is greater than or equal to 60.0m, the average longitudinal slope is less than or equal to 8%, and the final section is a circular section for TBM single-stage excavation construction.

3. The construction passage arrangement structure of the underground powerhouse of a hydropower station suitable for TBM continuous excavation according to claim 1 is characterized in that: The excavation section of the pilot tunnel in the factory building is circular, and the comprehensive longitudinal slope of the pilot tunnel in the factory building is 0.

4. The construction passage arrangement structure of the underground powerhouse of a hydropower station suitable for TBM continuous excavation according to claim 1 is characterized in that: The end of the traffic tunnel is connected to the right end wall of the powerhouse, and the end of the upper drainage corridor of the powerhouse intersects the traffic tunnel vertically, and after passing through the traffic tunnel, intersects parallel to the starting point of the tailwater construction branch tunnel.

5. The construction passage arrangement structure of the underground powerhouse of a hydropower station suitable for TBM continuous excavation according to claim 4 is characterized in that: The starting point of the upper drainage corridor of the powerhouse is at the same elevation as the horizontal section at the end of the ventilation tunnel, and the excavation section is circular; the axis of the upper drainage corridor of the powerhouse intersects with the axis at the end of the ventilation tunnel at a large angle, meeting the requirements of TBM oblique excavation; the end point of the upper drainage corridor of the powerhouse intersects with the straight section at the end of the traffic tunnel vertically, and the intersection point is at the same elevation as the bottom plate of the ventilation tunnel; the turning radius of the upper drainage corridor of the powerhouse is greater than or equal to 60.0m, and the comprehensive longitudinal slope is less than or equal to 8%.

6. The construction passage arrangement structure of the underground powerhouse of a hydropower station suitable for TBM continuous excavation according to claim 4 is characterized in that: The starting point of the tailwater construction branch tunnel intersects vertically with the terminal straight segment of the traffic tunnel. The starting elevation of the tailwater construction branch tunnel is the same as the terminal elevation from the upper drainage corridor of the powerhouse to the traffic tunnel. The excavation section is circular. The axis of the tailwater construction branch tunnel intersects with the axis of the No. 1 tailwater tunnel at a large angle, meeting the requirements of TBM oblique excavation. The elevation of the intersection point is the same as the design elevation of the bottom plate of the No. 1 tailwater tunnel. The turning radius of the tailwater construction branch tunnel is greater than or equal to 60.0m, and the comprehensive longitudinal slope does not exceed 8%.

7. The construction passage arrangement structure of the underground powerhouse of a hydropower station suitable for TBM continuous excavation according to claim 1 is characterized in that: The excavation section of the 1# tailwater tunnel is circular, with a comprehensive longitudinal slope of no more than 8% and a turning radius greater than or equal to 60.0m; the exit of the 1# tailwater tunnel is located in the lower reservoir, and the layout of the exit platform meets the requirements of the TBM recovery and disassembly site.

8. The construction passage arrangement structure of the underground powerhouse of a hydropower station suitable for TBM continuous excavation according to claim 1 is characterized by: It also includes a 2# tailwater tunnel, which is arranged parallel to the 1# tailwater tunnel, and its two ends are respectively connected to the powerhouse and the inlet and outlet of the lower reservoir; the end of the tailwater construction branch tunnel passes through the 2# tailwater tunnel and is connected to the 1# tailwater tunnel.

9. The construction passage arrangement structure of the underground powerhouse of a hydropower station suitable for TBM continuous excavation according to claim 1 is characterized in that: After each tunnel is constructed by TBM, a horizontal road surface is formed by paving with waste slag or cast-in-place concrete to meet the requirements for the passage of construction machinery.

10. The construction passage arrangement structure of the underground powerhouse of a hydropower station suitable for TBM continuous excavation according to claim 9, characterized in that: A conveyor belt is set up on the side wall of the ventilation tunnel after the TBM construction is completed to meet the slag discharge requirements of the plant arch expansion and the upper drainage gallery of the plant, the tailwater construction branch tunnel and the No. 1 tailwater tunnel.

Citation Information

Cited By

  • Hydropower station underground powerhouse construction channel supervision method based on TBM continuous tunneling

    CN120494449A

  • Supervision method for construction passage of underground powerhouse of hydropower station based on continuous TBM excavation

    CN120494449B