Iron chain type integral hoist shaped like Chinese character'wang '
Through the Wangzi iron chain-type overall lifting, mechanical positioning is used instead of manual adjustment, the problems of long time, unstable quality and high safety risks during the lifting process of rectangular steel cages are solved, and a more efficient and safer steel cage installation process is achieved. .
Patent Information
- Application Number
- CN202420173326.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-24
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2034-01-24
AI Technical Summary
The existing rectangular steel cage lifting process has problems such as long overall adjustment time, high quality affected by the lifting point position, high safety risks and low construction efficiency.
The integrated lifting of the king-shaped iron chain is adopted, including a specially made "king"-shaped spreader, hanging chain and hook. The mechanical positioning reduces the need for manual position adjustment and improves the stability and safety of the lifting.
The installation and positioning time of steel cages is greatly reduced, construction efficiency is improved, safety is enhanced, personnel and time investment is reduced, and the stability of the quality of steel cages is ensured.
Smart Images

Figure CN221987944U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of hoisting equipment, in particular to a W-shaped iron chain type integral hoisting. Background Art
[0002] The surface layer of the breakwater is composed of the breakwater top cushion stone and the concrete slab (hereinafter referred to as: slab) structure. After the construction of the top cushion stone and the site leveling work are completed, the slab is cast in place, including the installation of the slab formwork, the binding and installation of the steel cage, and the pouring of concrete. The main functions of the breakwater are: first, to reduce the intensity of the waves in the water body to achieve the effect of wave elimination, thereby protecting the coastline and port facilities from erosion and scouring by waves; second, to control the water flow and protect the embankment, maintain the depth of the seabed, prevent the accumulation of silt on the seabed from causing ships to run aground, and ensure the safety of large commercial ships.
[0003] According to previous project construction experience, the tying of the steel cage of the breakwater slab (steel cage size 12m*4.5m) is mainly done on-site. The width of the breakwater top is small, and the on-site tying of the steel cage has defects such as narrow operating space, many cross operations, high construction safety risks, and low construction efficiency. After demonstration, it was decided to adopt the "rear site steel cage tying overall lifting and installation" construction process. The implementation of this process doubles the efficiency of the original on-site tying, effectively avoiding the impact of the narrow on-site space and reducing the time of cross-operation on-site.
[0004] The current hoisting process is to use 4 evenly spaced lifting points on the rectangular steel cage as lifting points, and use matching wire ropes and clamps for overall hoisting operations. Installation begins after the steel cage is transported to the site. Before installation, the steel cage is hoisted above the cushion layer, and the steel cage is hoisted and stabilized. It is manually pulled and hoisted to the center of the main reinforcement marked on the upper and lower sections, and then slowly lowered. After the position is measured and verified to meet the requirements, the steel cage is lowered and installed, and the supporting force-bearing steel pipe is taken out to carry out the next link of the operation, and the operation is cyclic. The above hoisting process has the following problems:
[0005] (1) The overall hoisting and adjustment time is relatively long, at least 2 hours, which has a certain impact on the construction progress;
[0006] (2) When using the original slings for lifting operations, the overall quality of the steel cage will be affected by factors such as the lifting points during the lifting process and the weight of the steel cage itself (3.2T). There will be varying degrees of deformation of the steel cage at the positions where the lifting points bear the force. After deformation, it will affect the placement of the steel cage, have an impact on the formwork installation, and subsequent significant adjustments to the steel cage will be required. This will further affect the positions of some steel bars, resulting in non-compliance with the steel bar spacing standards and ineffective control of the protective layer thickness, thereby affecting the quality and durability of the construction of the entire breakwater slab. Moreover, a large amount of manpower and time are consumed for adjusting the steel bar spacing and formwork, greatly reducing the construction efficiency;
[0007] (3) A relatively large number of operators are required for the lifting of the steel cage. In addition to the commander, 4 more staff members are needed to cooperate in using the towing ropes to install it onto the transportation tool, and this process is repeated during the unloading process. Moreover, there are significant safety risks during the lifting process due to the influence of the lifting tools and lifting points. There are potential risks such as object strikes and the dropping of the steel cage during the operation of personnel, and the safety risk coefficient is relatively large. More safety management measures and related costs need to be invested in the overall construction. Summary of the Invention
[0008] The technical problem to be solved by the present invention is to provide a king-shaped chain type integral lifting in view of the above deficiencies. The present invention can solve the problem of large deflection of the rectangular steel cage, enhance the stability and safety of the integral lifting, convert the manual position adjustment operation into a mechanical positioning operation, reduce the construction lifting risk, and reduce the input of personnel and time.
[0009] To solve the above technical problems, the present invention adopts the following technical solutions:
[0010] A king-shaped chain type integral lifting, including a lifting tool, lifting chains and a hook. The shape of the lifting tool is "king" shaped. There are several lifting chains arranged on the lifting tool. The top end of the lifting chain is connected to the lifting tool, and the hook is arranged at the bottom end of the lifting chain.
[0011] Further, the lifting tool includes a main beam and three secondary beams. The three secondary beams are respectively arranged at the front, middle and rear parts of the main beam. The middle part of the secondary beam is arranged on the main beam, and the secondary beam is perpendicular to the main beam.
[0012] Further, reinforcing ribs are arranged between the main beam and the secondary beam.
[0013] Further, several lifting lugs are arranged on the main beam.
[0014] Further, the top end of the lifting chain is connected to the secondary beam. Three lifting chains are arranged on each secondary beam, and the three lifting chains are respectively arranged at the left, middle and right parts of the secondary beam.
[0015] Furthermore, the length of the main beam is 9000 mm, and the length of the secondary beam is 3780 mm.
[0016] Furthermore, the number of the lifting ears is two, and the two lifting ears are symmetrically arranged on the front and rear sides of the main beam, and the distance between the two lifting ears is 5060mm.
[0017] Compared with the prior art, the utility model has the following advantages after adopting the above technical solution:
[0018] (1) Converting manual position adjustment operations into mechanical positioning operations reduces construction and hoisting risks and reduces the investment in manpower and time;
[0019] (2) It can improve the integrity and stability of the steel cage during placement, greatly reduce the placement and positioning time of the steel cage, and reduce the hoisting operation time. At the same time, the deformation of the steel cage is small, and the template can be installed in place at one time, which reduces the adjustment time and improves the construction efficiency of the hoisting operation;
[0020] (3) Compared with the old process of hoisting two steel bars, the hoisting operation is stable and will not shake, which improves the safety factor of construction workers and ensures the quality of the steel cage after hoisting;
[0021] (4) The materials used for the formwork hanger are easy to obtain, and the structure is simple and reasonable, which is convenient for processing and installation, reducing the investment cost.
[0022] The utility model is described in detail below with reference to the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 It is a front view of an embodiment of the utility model;
[0024] Figure 2 It is a right side view of an embodiment of the utility model;
[0025] Figure 3 It is a top view of an embodiment of the utility model.
[0026] In the accompanying drawings, the components represented by the reference numerals are listed as follows:
[0027] 1. Lifting equipment; 11. Main beam; 12. Secondary beam; 2. Lifting chain; 3. Lifting hook; 4. Strengthening rib; 5. Lifting lug; 6. Steel cage; 7. Lifting rope; 8. Gantry crane hook. DETAILED DESCRIPTION
[0028] The principles and features of the present invention are described below in conjunction with the accompanying drawings. The examples given are only used to explain the present invention and are not used to limit the scope of the present invention.
[0029] In the description of the present utility model, it should be noted that the orientation or positional relationship indicated by the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", "clockwise" and "counterclockwise", etc. is based on the orientation or positional relationship shown in the drawings. It is only for the convenience of describing the present utility model and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be construed as a limitation to the present utility model.
[0030] As Figure 1 , Figure 2 and Figure 3 shown, a king-shaped chain-type integral hoisting device includes a spreader 1, sling chains 2 and hooks 3. The spreader 1 is in the shape of a "king", and a plurality of sling chains 2 are arranged on the spreader 1. The top ends of the sling chains 2 are connected to the spreader 1, and the hooks 3 are arranged at the bottom ends of the sling chains 2.
[0031] The spreader 1 includes a main beam 11 and three secondary beams 12. The three secondary beams 12 are respectively arranged at the front, middle and rear parts of the main beam 11. The middle parts of the secondary beams 12 are arranged on the main beam 11, and the secondary beams 12 are perpendicular to the main beam 11.
[0032] Adopting the above technical solution, the problem of large deflection of the rectangular steel reinforcement cage is solved, the stability and safety of hoisting are enhanced, and the on-site work efficiency can be improved. The position adjustment by manual is converted into mechanical positioning operation, greatly reducing the safety risk of construction hoisting, reducing the input of personnel and time, avoiding the influence of too long hoisting time on the overall quality of the steel reinforcement cage, and creating favorable conditions for the large slab concrete pouring construction and the improvement of the overall progress.
[0033] Embodiment 1:
[0034] In this embodiment, the length of the main beam 11 is 9000 mm, the number of secondary beams 12 is three, and the three secondary beams 12 are respectively arranged at the front, middle and rear parts of the main beam 11. Three sling chains 2 are arranged on each secondary beam 12, and hooks 3 are arranged at the bottom ends of the three sling chains 2. The three secondary beams 12 are evenly distributed on the secondary beam 12;
[0035] Reinforcing ribs 4 are arranged between the main beam 11 and the secondary beams 12. The angles between the reinforcing ribs 4 and the main beam 11 and the secondary beams 12 are both 45°. The two ends of the reinforcing ribs 4 are respectively connected to the main beam 11 and the secondary beams 12. A short reinforcing rib with a length of 370 mm and a long reinforcing rib with a length of 1580 mm are arranged at the angle between the main beam 11 and the secondary beams 12;
[0036] Two lifting lugs 5 are arranged at the top of the main beam 11, and the distance between the lifting lugs 5 and the nearest end of the main beam 11 is 1970 mm.
[0037] In this example, the main beam 11 and the secondary beam 12 are made of I-beams, the reinforcing ribs 4 are made of channel steels, and the whole is fixedly connected by welding.
[0038] The use process of this utility model:
[0039] Connect the lifting rope 7 to the lifting lug 5 on the lifting device 1, and connect the lifting rope 7 to the gantry crane hook 8;
[0040] Before the steel cage is hoisted, a gantry crane is used to hoist the hoisting device 1 above the completed steel cage 6;
[0041] After aligning the lifting device 1 with the edge of the steel cage 6, the nine lifting chains 2 are passed to the bottom of the steel cage 6, and the hooks 3 are fixedly connected to the steel cage 6 at the bottom. After the nine hooks 3 are fixed, the steel cage 6 is hoisted as a whole onto a flatbed truck by a gantry crane, and then transported to the breakwater construction area after being fixed;
[0042] After the steel cage 6 is transported to the breakwater construction area, an 80T crawler crane is used to unload the steel cage 6 and the steel cage 6 is placed at the designated location.
[0043] The "W-shaped" iron chain-type integral lifting tool has strong stability and integrity, and has the characteristics of high safety factor and high installation precision. With the cooperation of the crawler crane, the time for manual angle and precision adjustment is greatly reduced during the transfer and installation of the steel cage. It also eliminates the safety risks caused by uneven force on the steel cage and deformation of the steel bars. Finally, the large steel cage of the breakwater slab was installed with high quality in an overall control time of 15 minutes.
[0044] The above is an example of the best implementation of the utility model, and the parts not described in detail are common knowledge of ordinary technicians in this field. The protection scope of the utility model is based on the content of the claims, and any equivalent transformation based on the technical inspiration of the utility model is also within the protection scope of the utility model.
Claims
1. A Wang-shaped iron chain type integral lifting, characterized in that: It includes a spreader (1), a sling chain (2) and a hook (3). The shape of the spreader (1) is in the shape of a "king" character. A number of sling chains (2) are provided on the spreader (1). The top end of the sling chain (2) is connected to the spreader (1), and the hook (3) is provided at the bottom end of the sling chain (2).
2. The Wang-shaped iron chain integral hoisting device according to claim 1 is characterized in that: The spreader (1) includes a main beam (11) and three secondary beams (12). The three secondary beams (12) are respectively arranged at the front, middle and rear parts of the main beam (11). The middle part of the secondary beam (12) is arranged on the main beam (11), and the secondary beam (12) is perpendicular to the main beam (11).
3. The Wang-shaped iron chain integral lifting device according to claim 2 is characterized in that: Reinforcing ribs (4) are provided between the main beam (11) and the secondary beam (12).
4. The Wang-shaped iron chain integral hoisting device according to claim 2 is characterized in that: A number of lifting lugs (5) are provided on the main beam (11).
5. The Wang-shaped iron chain integral hoisting device according to claim 2 is characterized in that: The top end of the sling chain (2) is connected to the secondary beam (12). Three sling chains (2) are provided on each secondary beam (12), and the three sling chains (2) are respectively arranged at the left, middle and right parts of the secondary beam (12).
6. The Wang-shaped iron chain integral hoisting device according to claim 2 is characterized in that: The length of the main beam (11) is 9000 mm, and the length of the secondary beam (12) is 3780 mm.
7. The Wang-shaped iron chain integral hoisting device according to claim 4 is characterized in that: The number of the lifting lugs (5) is two. The two lifting lugs (5) are symmetrically arranged on the front and rear sides of the main beam (11), and the distance between the two lifting lugs (5) is 5060 mm.