Pit-based membrane material and composite device for preparing pit-based membrane material
By designing a multi-layer structure pit base film material, combining polyethylene and polyvinyl chloride materials and glass fiber chip filling, the problem of slippage and wear of geomembrane in pit base construction is solved, and higher wear resistance and Waterproof performance improves construction efficiency and reliability.
Patent Information
- Application Number
- CN202420531442.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-19
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2034-03-19
AI Technical Summary
The existing geomembrane is prone to slip, landslide, and wear during pit foundation construction, resulting in inconvenience in construction and requires multiple repairs, affecting construction efficiency and waterproofing effect.
A multi-layer structure pit base film material is designed, including a first adhesive mesh layer, a first protective layer, a waterproof layer, a second protective layer and a second adhesive mesh layer, through a combination of polyethylene and polyvinyl chloride materials, Combined with glass fiber chips or nonwoven fiber chip filler materials, a raised structure is formed to improve wear resistance and waterproof performance.
It improves the wear resistance strength and waterproof and anti-permeability of the membrane material, reduces slip and wear problems during construction, enhances the puncture resistance of the membrane material, and ensures the reliability and efficiency of the construction.
Smart Images

Figure CN222007673U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of civil engineering construction materials, and relates to a pit foundation membrane material and a composite device for preparing the pit foundation membrane material. Background Art
[0002] Pit foundation membrane material is a kind of geomembrane, which plays the role of waterproofing, anti-seepage, soil isolation, and strengthening the strength of pit foundation during pit foundation construction. At present, geomembranes are generally polyvinyl chloride (PVC) geomembranes, polyvinyl chloride composite (composite cloth layer) geomembranes, polyethylene (PE) geomembranes, polyethylene composite geomembranes, etc., which are laid and used in the form of rolls during the construction process.
[0003] During pit foundation construction, after the pit is excavated, the pit bottom and slope walls need to be reinforced (compacted or covered with soil). After laying the geomembrane, pump out the water and cover the soil again. Then, on this basis, place the steel cage up and down, install the mold and pour, and fill the soil after removing the mold. When laying the geomembrane, the slope of the pit wall should not be too small, otherwise it will cause the geomembrane to slide. During the pumping and covering operations, it is also easy to cause the geomembrane to slip, dislocate, and wrinkle. The laying of the geomembrane and the subsequent sliding of the geomembrane relative to the ground not only affect the construction, but also easily cause geomembrane wear (stones squeeze the geomembrane, puncture and scratch the geomembrane). Therefore, the laying of the geomembrane often requires multiple repairs before covering the soil to ensure that there is no leakage before backfilling and covering the soil.
[0004] Based on the defects of existing geomembranes, this application proposes a geomembrane that is easy to construct and wear-resistant, which is particularly suitable for construction environments such as pit foundations that are deeper and have steeper slopes. Utility Model Content
[0005] The purpose of the utility model is to provide a pit foundation membrane material and a composite device for preparing the pit foundation membrane material in view of the above-mentioned problems existing in the prior art. The technical problem to be solved by the utility model is how to improve the wear resistance of the membrane material.
[0006] The purpose of the utility model can be achieved through the following technical solutions: a pit foundation membrane material, characterized in that, from one side of the membrane material to the other side, the membrane material includes a first glue mesh layer, a first protective layer, a waterproof layer, a second protective layer and a second glue mesh layer, the first protective layer is provided with protrusions one corresponding one to one with the mesh holes of the first glue mesh layer, and the second protective layer is provided with protrusions two corresponding one to one with the mesh holes of the second glue mesh layer.
[0007] Furthermore, the height of the first protrusion is smaller than the thickness of the first adhesive mesh layer, and the height of the second protrusion is smaller than the thickness of the second adhesive mesh layer.
[0008] Furthermore, a filling material is filled between the first protective layer and the waterproof layer, and between the second protective layer and the waterproof layer. The filling material between the first protective layer and the waterproof layer is located between the first inner wall of the protrusion and the waterproof layer, and the filling material between the second protective layer and the waterproof layer is located between the second inner wall of the protrusion and the waterproof layer.
[0009] Furthermore, the first protective layer and the second protective layer are made of polyethylene material, and the waterproof layer is made of polyvinyl chloride material.
[0010] Polyethylene has good toughness and softness, which makes it have good processability, wear resistance and barrier properties. It is not easy to be scratched or torn when in contact with soil. It is also easy to form protrusions one and two during processing.
[0011] Polyvinyl chloride has poor toughness, but good strength, heat resistance and corrosion resistance. It is sandwiched between the first protective layer and the second protective layer to extend the effective duration of the geomembrane's waterproof and anti-permeability properties in the soil.
[0012] Furthermore, the first adhesive mesh layer and the second adhesive mesh layer are both adhesive-coated fiber woven meshes, that is, hot melt adhesive is coated on the silk threads of the fiber woven fabric, and a coating layer is formed on the silk threads after curing.
[0013] Furthermore, the filling material is glass fiber scraps or non-woven fiber scraps. The filling material is used to maintain the shapes of the first and second protrusions so that they are not easily pressed, and to improve the protection strength, especially the strength of being punctured.
[0014] The second purpose of the utility model is to provide a composite device for pit foundation membrane materials.
[0015] The composite device comprises a first composite unit and a second composite unit, wherein the first composite unit comprises a first glue web feed roller, a first protective feed roller, two first upper clamping rollers, two first lower clamping rollers, a first heating assembly and a first scrap material adding assembly, wherein the first heating assembly is located between the two first upper clamping rollers, the first glue web layer and the first protective layer are composited and passed over the two first upper clamping rollers, turned back and passed between the first upper clamping roller and the first lower clamping roller and then pulled out, the first scrap material adding assembly is located behind the first heating assembly, the waterproof layer passes through the first upper clamping roller and the first lower clamping roller synchronously, and the waterproof layer, the first glue web layer and the first protective layer form a semi-finished membrane material with a three-layer structure;
[0016] The second composite unit includes a second glue web feed roller, a second protective feed roller, two second upper clamping rollers, two second lower clamping rollers, a second heating assembly and a second scrap material adding assembly. The second heating assembly is located between the two second upper clamping rollers. After the second glue web layer and the second protective layer are composited, they pass over the two second upper clamping rollers, turn back and pass between the second upper clamping roller and the second lower clamping roller and are then pulled out. The second scrap material adding assembly is located behind the first heating assembly. The semi-finished film material, the second glue web layer and the second protective layer form a finished film material with a five-layer structure.
[0017] Furthermore, the first heating assembly and the second heating assembly are both a plurality of heat blast guns arranged laterally. The existence of the heating temperature and the existence of the airflow can deform the first protective layer and the second protective layer to form the first protrusion and the second protrusion, and the temperature and the airflow intensity are controlled to ensure that the protrusion height of the first protrusion and the second protrusion does not exceed the outer side surface of the first adhesive mesh layer and the second adhesive mesh layer.
[0018] Furthermore, the first scrap material adding assembly and the second scrap material adding assembly both include a hopper and a driven roller located at the bottom of the hopper, and the driven roller is in close contact with the surface of the film material to which the scrap material needs to be added.
[0019] Furthermore, the glue used to bond the waterproof layer to the first protective layer is mixed with the scraps in the first scrap material adding component; the glue used to bond the waterproof layer to the second protective layer is mixed with the scraps in the second scrap material adding component. Compared with coating glue on the waterproof layer, mixing glue into the filling material can form a solid filling after the glue is cured in the first and second protrusions, which has better cushioning and puncture resistance effects than simple scraps.
[0020] It is not difficult to see that the surface of the pit foundation membrane material with a multi-layer structure that contacts the soil is composed of a rubber net and protrusions protruding from the mesh holes of the rubber net. There are gaps between the soil blocks and the mesh wires of the rubber net, which together form an anti-slip structure with the soil surface. At the same time, the waterproof layer is protected by the rubber net and the protrusions, which is a guarantee for the effective waterproofing and anti-penetration of the membrane material. The protrusions themselves also have a high anti-puncture ability. Therefore, it has better one-time construction performance during the geomembrane construction process. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is a structural schematic diagram of a pit foundation membrane material composite device.
[0022] Figure 2 It is an exploded view of the multi-layer structure of the pit foundation membrane material.
[0023] Figure 3 It is a cross-sectional view of the pit foundation membrane material.
[0024] Figure 4 It is a schematic diagram of the structure of the first chip adding component and the second chip adding component.
[0025] Figure 5 yes Figure 3 A zoomed-in view of middle game A.
[0026] In the figure, 11, the first rubber mesh layer; 12, the first protective layer; 13, the waterproof layer; 14, the second protective layer; 15, the second rubber mesh layer; 21, the protrusion one; 22, the protrusion two; 31, the first rubber mesh feeding roller; 32, the first protective feeding roller; 33, the first upper clamping roller; 34, the first lower clamping roller; 35, the first heating component; 36, the first scrap material adding component; 41, the second rubber mesh feeding roller; 42, the second protective feeding roller; 43, the second upper clamping roller; 44, the second lower clamping roller; 45, the second heating component; 46, the second scrap material adding component; 51, the hopper; 52, the driven roller. DETAILED DESCRIPTION
[0027] The following are specific embodiments of the present invention and the accompanying drawings to further describe the technical solution of the present invention, but the present invention is not limited to these embodiments.
[0028] like Figure 2 , Figure 3 and Figure 5 As shown, from one side to the other side of the membrane material, the membrane material includes a first adhesive mesh layer 11, a first protective layer 12, a waterproof layer 13, a second protective layer 14 and a second adhesive mesh layer 15. The first protective layer 12 is provided with protrusions 21 corresponding one-to-one to the mesh holes of the first adhesive mesh layer 11, and the second protective layer 14 is provided with protrusions 22 corresponding one-to-one to the mesh holes of the second adhesive mesh layer 15.
[0029] The height of the first protrusion 21 is smaller than the thickness of the first adhesive mesh layer 11 , and the height of the second protrusion 22 is smaller than the thickness of the second adhesive mesh layer 15 .
[0030] Filling material is filled between the first protective layer 12 and the waterproof layer 13 and between the second protective layer 14 and the waterproof layer 13. The filling material between the first protective layer 12 and the waterproof layer 13 is located between the inner wall of the protrusion 1 21 and the waterproof layer 13, and the filling material between the second protective layer 14 and the waterproof layer 13 is located between the inner wall of the protrusion 22 and the waterproof layer 13.
[0031] The first protective layer 12 and the second protective layer 14 are made of polyethylene material, and the waterproof layer 13 is made of polyvinyl chloride material.
[0032] Polyethylene has good toughness and softness, which makes it have good processability, wear resistance and barrier properties. It is not easy to be scratched or torn when in contact with soil. It is also easy to form the protrusion 1 21 and the protrusion 2 22 during the processing.
[0033] Polyvinyl chloride has poor toughness, but good strength and heat resistance, and excellent corrosion resistance. It is sandwiched between the first protective layer 12 and the second protective layer 14 to extend the effective duration of the geomembrane's waterproof and anti-permeability properties in the soil.
[0034] The first adhesive mesh layer 11 and the second adhesive mesh layer 15 are both adhesive-coated fiber woven meshes, that is, hot melt adhesive is coated on the silk threads of the fiber woven fabric, and a coating layer is formed on the silk threads after curing.
[0035] The filling material is glass fiber scraps or non-woven fiber scraps. The filling material is used to maintain the shape of the first protrusion 21 and the second protrusion 22 so that they are not easily pressed, and to improve the protection strength, especially the strength of being pierced.
[0036] like Figure 1 and Figure 4 The pit foundation membrane material composite device shown includes a first composite unit and a second composite unit. The first composite unit includes a first glue web feed roller 31, a first protective feed roller 32, two first upper clamping rollers 33, two first lower clamping rollers 34, a first heating assembly 35 and a first scrap material adding assembly 36. The first heating assembly 35 is located between the two first upper clamping rollers 33. After the first glue web layer 11 and the first protective layer 12 are composited, they pass over the two first upper clamping rollers 33, turn back and pass between the first upper clamping roller 33 and the first lower clamping roller 34, and then are pulled out. The first scrap material adding assembly 36 is located after the first heating assembly 35. The waterproof layer 13 passes through the first upper clamping roller 33 and the first lower clamping roller 34 synchronously. The waterproof layer 13, the first glue web layer 11 and the first protective layer 12 form a semi-finished membrane material with a three-layer structure.
[0037] The second compounding unit includes a second glue web feed roller 41, a second protective feed roller 42, two second upper clamping rollers 43, two second lower clamping rollers 44, a second heating assembly 45 and a second scrap material adding assembly 46. The second heating assembly 45 is located between the two second upper clamping rollers 43. After compounding, the second glue web layer 15 and the second protective layer 14 pass over the two second upper clamping rollers 43, turn back and pass between the second upper clamping rollers 43 and the second lower clamping rollers 44 and then are pulled out. The second scrap material adding assembly 46 is located behind the first heating assembly 35. The semi-finished film material, the second glue web layer 15 and the second protective layer 14 form a finished film material with a five-layer structure.
[0038] The first heating assembly 35 and the second heating assembly 45 are both a plurality of heat blast guns arranged transversely. The existence of the heating temperature and the existence of the airflow can deform the first protective layer 12 and the second protective layer 14 to form the first protrusion 21 and the second protrusion 22, and the temperature and the airflow intensity are controlled to ensure that the protrusion height of the first protrusion 21 and the second protrusion 22 does not exceed the outer side of the first adhesive mesh layer 11 and the second adhesive mesh layer 15.
[0039] The first scrap material adding assembly 36 and the second scrap material adding assembly 46 both include a hopper 51 and a driven roller 52 located at the bottom of the hopper 51 . The driven roller 52 is in close contact with the surface of the film material to which scrap materials need to be added.
[0040] The compounding process includes the following steps: A. The first rubber mesh layer 11 and the first protective layer 12 are compounded under the clamping of the first rubber mesh feeding roller 31 and the first protective feeding roller 32. Before compounding, the compound surface of the first rubber mesh layer 11 is coated with glue; B. At the position between the two first upper clamping rollers 33, the first heating component 35 sprays hot air to the surface of the first protective layer 12. Due to the support of the first rubber mesh layer 11, a protrusion 21 is formed on the surface of the first protective layer 12, which is concave into the mesh of the first rubber mesh layer 11; C. After the protrusion 21 is formed, the first scrap material adding component 36 is Before the waterproof layer 13 and the first protective layer 12 are composited, filling material is added into the protrusion 21, and the waterproof layer 13 and the first protective layer 12 are glued; D. The second protective layer 14 and the second adhesive mesh layer 15 are composited in the same manner as steps A and B, and a protrusion 22 is formed on the surface of the second protective layer 14; E. After the protrusion 22 is formed, the second scrap material adding component 46 adds filling material into the protrusion 22 before the waterproof layer 13 and the second protective layer 14 are composited, and the waterproof layer 13 and the second protective layer 14 are glued, completing the composite of the five-layer structure of the pit foundation membrane material.
[0041] The glue used to bond the waterproof layer 13 and the first protective layer 12 is mixed in the scraps in the first scrap adding component 36; the glue used to bond the waterproof layer 13 and the second protective layer 14 is mixed in the scraps in the second scrap adding component 46. Compared with coating glue on the waterproof layer 13, mixing glue into the filling material can form a solid filling after the glue is cured in the protrusion 1 21 and the protrusion 2 22, which has better cushioning and puncture resistance effects than simple scraps.
[0042] It is not difficult to see that the surface of the pit foundation membrane material of the multi-layer structure that contacts the soil is composed of a rubber net and protrusions protruding from the mesh holes of the rubber net. There are gaps between the soil blocks and the mesh wires of the rubber net, which together form an anti-slip structure with the soil surface. At the same time, the waterproof layer 13 is protected by the rubber net and the protrusions, which is a guarantee for the effective waterproofing and anti-penetration of the membrane material, and the protrusions themselves also have a high anti-puncture ability. Therefore, it has better one-time construction performance during the geomembrane construction process.
[0043] The filling material containing glue will also be attached to both sides of the waterproof layer in small amounts, which strengthens the interlayer strength and makes it more wear-resistant and puncture-resistant. Since there are glue nets on both sides of the membrane material, the bonding at the splicing positions is more reliable during laying construction.
[0044] The specific embodiments described herein are merely examples of the spirit of the present invention. Those skilled in the art may make various modifications or additions to the specific embodiments described or replace them in similar ways, but they will not deviate from the spirit of the present invention or exceed the scope defined by the appended claims.
Claims
1. A pit foundation membrane material, characterized in that: From one side of the membrane material to the other side, the membrane material comprises a first adhesive mesh layer (11), a first protective layer (12), a waterproof layer (13), a second protective layer (14) and a second adhesive mesh layer (15); the first protective layer (12) is provided with protrusions (21) corresponding one-to-one to the mesh holes of the first adhesive mesh layer (11); the second protective layer (14) is provided with protrusions (22) corresponding one-to-one to the mesh holes of the second adhesive mesh layer (15).
2. A pit foundation membrane material according to claim 1, characterized in that: The height of the first protrusion (21) is less than the thickness of the first adhesive mesh layer (11), and the height of the second protrusion (22) is less than the thickness of the second adhesive mesh layer (15).
3. A pit foundation membrane material according to claim 2, characterized in that: Filling material is filled between the first protective layer (12) and the waterproof layer (13), and between the second protective layer (14) and the waterproof layer (13); the filling material between the first protective layer (12) and the waterproof layer (13) is located between the inner wall of the first protrusion (21) and the waterproof layer (13), and the filling material between the second protective layer (14) and the waterproof layer (13) is located between the inner wall of the second protrusion (22) and the waterproof layer (13).
4. The pit foundation membrane material according to claim 2, characterized in that: The first protective layer (12) and the second protective layer (14) are made of polyethylene material, and the waterproof layer (13) is made of polyvinyl chloride material.
5. The pit foundation membrane material according to claim 2, characterized in that: The first rubber mesh layer (11) and the second rubber mesh layer (15) are both rubber-coated fiber woven meshes.
6. The pit foundation membrane material according to claim 3, characterized in that: The filling material is glass fiber scraps or non-woven fiber scraps.
7. A composite device for preparing a pit foundation membrane material, used for preparing the pit foundation membrane material according to any one of claims 1 to 6, characterized in that: The invention comprises a first compounding unit and a second compounding unit, wherein the first compounding unit comprises a first glue web feeding roller (31), a first protective feeding roller (32), two first upper clamping rollers (33), two first lower clamping rollers (34), a first heating component (35) and a first scrap material adding component (36), wherein the first heating component (35) is located between the two first upper clamping rollers (33), the first glue web layer (11) and the first protective layer (12) are compounded, passed over the two first upper clamping rollers (33), turned back, passed between the first upper clamping roller (33) and the first lower clamping roller (34), and then pulled out, the first scrap material adding component (36) is located behind the first heating component (35), the waterproof layer (13) passes through the first upper clamping roller (33) and the first lower clamping roller (34) synchronously, and the waterproof layer (13) forms a semi-finished membrane material with a three-layer structure with the first glue web layer (11) and the first protective layer (12); The second compounding unit comprises a second glue web feeding roller (41), a second protective feeding roller (42), two second upper clamping rollers (43), two second lower clamping rollers (44), a second heating assembly (45) and a second scrap material adding assembly (46); the second heating assembly (45) is located between the two second upper clamping rollers (43); after compounding, the second glue web layer (15) and the second protective layer (14) pass over the two second upper clamping rollers (43), turn back and pass between the second upper clamping rollers (43) and the second lower clamping rollers (44) and are then pulled out; the second scrap material adding assembly (46) is located after the first heating assembly (35); the semi-finished film material, the second glue web layer (15) and the second protective layer (14) form a finished film material with a five-layer structure.
8. A composite device for preparing a pit foundation membrane material according to claim 7, characterized in that: The first heating component (35) and the second heating component (45) are both a plurality of heat blast guns arranged laterally.
9. A composite device for preparing a pit foundation membrane material according to claim 7, characterized in that: The first scrap material adding assembly (36) and the second scrap material adding assembly (46) both comprise a hopper (51) and a driven roller (52) located at the bottom of the hopper (51), wherein the driven roller (52) is in close contact with the surface of the film material to which scrap material needs to be added.
10. A composite device for preparing a pit foundation membrane material according to claim 7, characterized in that: The glue used to bond the waterproof layer (13) and the first protective layer (12) together is mixed with the scraps in the first scrap adding component (36); and the glue used to bond the waterproof layer (13) and the second protective layer (14) together is mixed with the scraps in the second scrap adding component (46).