Colorful composite pavement structure of steel bridge deck

By designing epoxy anti-slip paving, drainage structure and loading and unloading structure on the steel bridge deck, the problems of water accumulation and bump maintenance in rainy days of bridge deck are solved, and the water discharge of bridge areas and rapid replacement of bumps are achieved, which improves driving safety and service life.

CN222008642UActive Publication Date: 2024-11-15SHANGHAI TONGLI NEW MATERIAL TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420533159.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-19
Publication Date
2024-11-15
Estimated Expiration
2034-03-19

AI Technical Summary

Technical Problem

The existing steel bridge deck color composite paving structure is prone to accumulation of water on rainy days, affecting driving safety, and inconvenient maintenance of bumps, resulting in wear and shortening of service life.

Method used

A color composite paving structure of steel bridge deck including epoxy anti-slip paving, drainage structure and reinforced structure was designed. The drainage structure realizes water discharge through support plates and cover plates, and the loading and unloading structure realizes convex blocks through rubber plugs and screws. Easy to replace.

Benefits of technology

Effectively prevent water from bridge area, extend service life, and simplify the process of replacing bumps, improving driving safety and maintenance efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222008642U_ABST
    Figure CN222008642U_ABST
Patent Text Reader

Abstract

The utility model provides a colored composite pavement structure of a steel bridge deck, which belongs to the technical field of bridge construction and comprises a steel plate, an epoxy anti-skid pavement, a drainage structure and a blind sidewalk, the epoxy anti-skid pavement is paved at the top end of the steel plate, a high polymer colored pavement is paved at the top end of the epoxy anti-skid pavement, and the drainage structure is inserted into one side of the interior of the epoxy anti-skid pavement. And paving the top end of the epoxy antiskid pavement. According to the device, the supporting plate is used for supporting the water outlet groove in the epoxy anti-skid pavement, accumulated water on the road surface is discharged, the cover plate is pulled upwards to leave the interior of the moving groove, and the interior of the water groove can be cleaned conveniently, so that the accumulated water dredging function of the device is achieved, the accumulated water on the road surface is discharged conveniently, and the road surface is prevented from being accumulated in rainy days; meanwhile, enough gaps are reserved to absorb deformation of the pavement layer caused by thermal expansion and cold contraction, and the service life of the pavement layer is prolonged.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of bridge construction, in particular to a steel bridge deck color composite paving structure. Background Art

[0002] The non-motorized vehicle lanes and pedestrian steel bridges on steel bridge decks require colored paving materials with excellent durability, anti-skid performance and comfort, and easy construction and maintenance. At present, the colored paving of pedestrian steel bridges often adopts epoxy-sprinkled gravel anti-skid paving, but it is brittle, easy to crack, and the gravel is easy to fall off. In summary, a colored composite paving structure for steel bridge decks is proposed.

[0003] After searching, the Chinese patent application number 202223503738.9 discloses a composite pavement structure for a steel bridge deck, including an ultra-high performance concrete layer, a high ductility concrete layer, a waterproof bonding layer, a surface layer, a T-shaped plate and a steel mesh; the ultra-high performance concrete layer, the high ductility concrete layer, the waterproof bonding layer and the surface layer are arranged on the steel bridge deck in sequence from bottom to top; the flange of the T-shaped plate is arranged in the ultra-high performance concrete layer, and the belly is arranged in the high ductility concrete layer; the belly of the T-shaped plate is connected to the steel bridge deck; the steel mesh is laid in the ultra-high performance concrete layer; the belly of the T-shaped plate is connected to the transverse steel bars of the steel mesh, and the vertical steel bars of the steel mesh are arranged between two adjacent T-shaped plates. The composite bridge deck pavement structure of the utility model has good high-temperature stability and crack controllability, so that the bridge deck is not easy to deform or crack under high temperature conditions and negative bending moment zones; it has low requirements on the construction environment and temperature, is simple to operate, and is convenient to construct, which can greatly improve the construction process and shorten the construction period;

[0004] The above patent still has the following deficiencies: (1) Water easily accumulates on the bridge deck on rainy days. In severe weather during thunderstorm seasons, water easily accumulates on the bridge deck on rainy days, which not only affects driving safety, because the accumulated water may cause vehicles to slip, increasing the risk of accidents, but may also damage the pavement layer. Moreover, long-term accumulated water may penetrate into the pavement layer, causing material aging and corrosion, thereby shortening the service life of the pavement structure;

[0005] (2) It is inconvenient to replace and maintain the bumps, which may be easily worn and damaged during driving or when pedestrians step on them, causing the bumps to be at the same level as the road surface, affecting the normal walking of the blind on the surface of the blind path. In addition, since the bumps are usually integrated with the blind path, the blind path needs to be removed and replaced, wasting a lot of manpower and material resources.

[0006] Therefore, there is an urgent need for a steel bridge deck colored composite paving structure to solve the above problems. Utility Model Content

[0007] The purpose of the utility model is to address the existing defect of prone to cracks. When the device is used in summer, since the thermal expansion coefficient of the material may be different from that of the steel bridge deck, problems such as pavement layer shedding and cracking may occur, which affect the service life of the bridge deck and driving safety.

[0008] In order to achieve the above-mentioned invention object, the utility model provides the following technical solutions:

[0009] A steel bridge deck colored composite paving structure, comprising a steel plate, and further comprising:

[0010] Epoxy anti-skid paving is paved on the top of the steel plate, and the top of the epoxy anti-skid paving is paved with a polymer colored pavement;

[0011] Drainage structure, inserted on one side of the epoxy anti-slip paving;

[0012] A reinforcement structure is inserted into the epoxy anti-slip paving, and the top of the reinforcement structure is connected to a loading and unloading structure, and the top of the loading and unloading structure is provided with a bump;

[0013] The blind path is laid on top of the epoxy anti-slip pavement.

[0014] As a preferred technical solution of the present application, the reinforcement structure includes a connecting frame transversely inserted into the epoxy anti-slip paving and reinforcing ribs longitudinally inserted into the epoxy anti-slip paving and passing through the connecting frame.

[0015] As a preferred technical solution of the present application, the drainage structure includes a support plate fixed inside the epoxy anti-slip pavement and connected to the connecting frame, an asphalt layer paved on the top of the steel plate, a waterproof paint layer arranged on the outer wall of the support plate, a cover plate sliding inside the movable groove, and a movable groove fixed at the top of one side of the support plate.

[0016] As a preferred technical solution of the present application, the loading and unloading structure includes a mounting shell fixed on the top of the reinforcing rib, a connecting seat installed on the bottom of the protrusion, a screw block fixed inside the mounting shell, a fixing bolt inserted inside the connecting seat, and a rubber plug installed on the top of the protrusion.

[0017] As a preferred technical solution of the present application, holes are evenly opened on the top of the cover plate, and the support plates are symmetrically distributed on the vertical center line of the cover plate.

[0018] As a preferred technical solution of the present application, an external thread is arranged on the outer side wall of the fixing bolt, and an internal thread cooperating with the external thread is arranged inside the screw block.

[0019] Compared with the prior art, the utility model has the following beneficial effects:

[0020] In the scheme of this application:

[0021] 1. The supporting plate supports the water trough inside the epoxy anti-skid pavement to discharge the accumulated water on the road surface. The cover plate is pulled upward to leave the inside of the movable trough, which is convenient for cleaning the inside of the water trough. This realizes the function of draining the accumulated water on the road surface, which is convenient for draining the accumulated water on the road surface, preventing water accumulation on the road surface during rainy days, and ensuring driving safety. At the same time, sufficient gaps are reserved to absorb the deformation of the pavement layer caused by thermal expansion and contraction, thereby extending the service life of the pavement layer;

[0022] 2. By pulling out the rubber plug and using a tool to rotate the rubber plug to separate it from the screw block, the damaged bump can be taken out from the inside of the mounting shell for replacement, thereby realizing the easy replacement function of the device, facilitating the disassembly and replacement of the damaged bump, reducing the time wasted by road maintenance personnel in maintaining the pavement layer, and reducing the cost of maintaining the pavement layer. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 This is one of the schematic diagrams of the structure of the utility model;

[0024] Figure 2 This is the second schematic diagram of the structure of the utility model;

[0025] Figure 3 A schematic diagram of the three-dimensional cross-sectional structure of the drainage structure provided for this application;

[0026] Figure 4 This is a schematic diagram of the three-dimensional cross-sectional structure of the loading and unloading structure provided in this application.

[0027] Markings in the figure: 1. Steel plate; 2. Reinforcement structure; 201. Connecting frame; 202. Reinforcement rib; 3. Bump; 4. Drainage structure; 401. Support plate; 402. Asphalt layer; 403. Waterproof paint layer; 404. Cover plate; 405. Moving groove; 5. Polymer colored pavement; 6. Blind path; 7. Loading and unloading structure; 701. Mounting shell; 702. Connecting seat; 703. Screw block; 704. Fixing bolt; 705. Rubber plug; 8. Epoxy anti-slip paving. DETAILED DESCRIPTION

[0028] To make the purpose, technical solution and advantages of the embodiment of the utility model clearer, the technical solution in the embodiment of the utility model will be described clearly and completely in conjunction with the accompanying drawings. Obviously, the described embodiment is a part of the embodiment of the utility model, not all of the embodiments.

[0029] like Figure 1-4 As shown, a steel bridge deck color composite pavement structure proposed in this embodiment includes a steel plate 1, and also includes:

[0030] The epoxy anti-skid pavement 8 is paved on the top of the steel plate 1, and the top of the epoxy anti-skid pavement 8 is paved with a polymer colored pavement 5;

[0031] The drainage structure 4 is inserted on one side of the epoxy anti-slip paving 8;

[0032] The reinforcement structure 2 is inserted into the epoxy anti-slip paving 8, and the top of the reinforcement structure 2 is connected to the loading and unloading structure 7, and the top of the loading and unloading structure 7 is provided with a protrusion 3;

[0033] The blind path 6 is laid on the top of the epoxy anti-slip pavement 8.

[0034] like Figure 1 , Figure 2 , Figure 3 and Figure 4 As shown, as a preferred embodiment, on the basis of the above method, further, the reinforcement structure 2 includes a connecting frame 201 inserted horizontally inside the epoxy anti-slip paving 8 and a reinforcing rib 202 inserted longitudinally inside the epoxy anti-slip paving 8 and passing through the connecting frame 201, the drainage structure 4 includes a support plate 401 fixed inside the epoxy anti-slip paving 8 and connected to the connecting frame 201, an asphalt layer 402 paved on the top of the steel plate 1, a waterproof paint layer 403 arranged on the outer wall of the support plate 401, a cover plate 404 sliding inside the movable groove 405 and a movable groove 405 fixed at the top of one side of the support plate 401, and the cover plate Holes are evenly arranged on the top of 404, and the support plates 401 are symmetrically distributed on the vertical center line of the cover plate 404. The support plates 401 support the water trough inside the epoxy anti-skid pavement 8 to guide the accumulated water on the road surface, so that the accumulated water on the road surface can be quickly discharged. Foreign objects are intercepted by the cover plate 404 to prevent sand, gravel, branches and leaves from clogging the water trough. At the same time, due to the presence of a larger water trough inside the epoxy anti-skid pavement 8, the deformation of the pavement layer caused by thermal expansion and contraction can be absorbed, thereby extending the service life of the pavement layer. By pulling the cover plate 404 upward to leave the inside of the movable groove 405, the inside of the water trough can be cleaned easily.

[0035] like Figure 1 , Figure 2 and Figure 4As shown, as a preferred embodiment, on the basis of the above-mentioned method, further, the loading and unloading structure 7 includes a mounting shell 701 fixed on the top of the reinforcing rib 202, a connecting seat 702 installed on the bottom end of the protrusion 3, a screw block 703 fixed inside the mounting shell 701, a fixing bolt 704 inserted inside the connecting seat 702 and a rubber plug 705 installed on the top of the protrusion 3, an outer wall of the fixing bolt 704 is provided with an external thread, and the interior of the screw block 703 is provided with an internal thread that cooperates with the external thread. By welding the mounting shell 701 to the top of the connecting frame 201, the mounting shell 701 is not easily fallen off by force. When the protrusion 3 is damaged, the damaged protrusion 3 can be taken out from the interior of the mounting shell 701 for replacement by pulling out the rubber plug 705 and then using a tool to rotate the rubber plug 705 to separate it from the screw block 703.

[0036] Specifically, when the Bengang bridge deck colored composite pavement structure is used: the steel plate 1 needs to be shot blasted and derusted, and the required rust removal level is Sa2.5, and the roughness is 50-100μm. The bonding strength between the epoxy resin used in the epoxy anti-skid pavement 8 and the steel plate 1 is 25℃>5.0MPa. The construction of the polymer colored pavement 5 can be done by manual scraping or small mechanical spraying, and the bonding strength with the anti-skid pavement layer is 25℃>2.0MPa. At the same time, the polymer colored pavement 5 is mixed with high-performance environmentally friendly emulsion, colored wear-resistant fine aggregate, color paste, nano stabilizer, reinforcing agent, etc. After mixing at room temperature, it is constructed on the road surface by a small spraying machine or manual scraping. Traffic can be opened after 4 hours, and the connecting frame 201 and the connecting frame 201 are staggered inside the epoxy anti-skid pavement 8 to increase the compression resistance and strength of the epoxy anti-skid pavement 8.

[0037] Specifically, when the Bengang bridge deck colored composite pavement structure is in use: when water accumulates on the road surface, the support plate 401 supports a water trough inside the epoxy anti-skid pavement 8 to guide the accumulated water on the road surface, which is convenient for quickly draining the accumulated water on the road surface. Foreign objects are intercepted by the cover plate 404 to prevent sand, gravel, branches and leaves from clogging the water trough. At the same time, due to the presence of a larger water trough inside the epoxy anti-skid pavement 8, the deformation of the pavement layer caused by thermal expansion and contraction can be absorbed, thereby extending the service life of the pavement layer. By pulling the cover plate 404 upward to leave the inside of the movable groove 405, the inside of the water trough can be cleaned easily.

[0038] Specifically, when the Bensteel bridge deck colored composite paving structure is in use: by welding the mounting shell 701 to the top of the connecting frame 201, the mounting shell 701 is not easily fallen off by force. When the protrusion 3 is damaged, the rubber plug 705 is pulled out, and then the rubber plug 705 is separated from the screw block 703 by using a tool, and the damaged protrusion 3 can be taken out from the inside of the mounting shell 701 for replacement.

[0039] The above embodiments are only used to illustrate the present invention and are not intended to limit the technical solutions described in the present invention. Although the present invention has been described in detail with reference to the above embodiments, the present invention is not limited to the above specific implementation methods. Therefore, any modification or equivalent replacement of the present invention; and all technical solutions and improvements thereof that do not depart from the spirit and scope of the invention are included in the scope of the claims of the present invention.

Claims

1. A steel bridge deck colored composite paving structure, comprising a steel plate (1), It is characterized in that Also includes, An epoxy anti-skid pavement (8) is paved on the top of the steel plate (1), and a polymer colored pavement (5) is paved on the top of the epoxy anti-skid pavement (8); A drainage structure (4) is inserted into one side of the epoxy anti-slip paving (8); A reinforcement structure (2) is inserted into the epoxy anti-slip paving (8), and the top of the reinforcement structure (2) is connected to a loading and unloading structure (7), and the top of the loading and unloading structure (7) is provided with a protrusion (3); The blind path (6) is laid on the top of the epoxy anti-slip paving (8).

2. A steel bridge deck color composite pavement structure according to claim 1, It is characterized in that The reinforcement structure (2) comprises a connection frame (201) inserted transversely into the epoxy anti-slip paving (8) and a reinforcement rib (202) inserted longitudinally into the epoxy anti-slip paving (8) and passing through the connection frame (201).

3. A steel bridge deck color composite pavement structure according to claim 2, It is characterized in that The drainage structure (4) comprises a support plate (401) fixed inside the epoxy anti-slip paving (8) and connected to the connecting frame (201), an asphalt layer (402) paved on the top of the steel plate (1), a waterproof paint layer (403) arranged on the outer wall of the support plate (401), a cover plate (404) sliding inside the moving groove (405), and the moving groove (405) fixed at the top of one side of the support plate (401).

4. The steel bridge deck color composite pavement structure according to claim 2, It is characterized in that The loading and unloading structure (7) comprises a mounting shell (701) fixed to the top of the reinforcing rib (202), a connecting seat (702) mounted at the bottom of the protrusion (3), a screw block (703) fixed inside the mounting shell (701), a fixing bolt (704) inserted inside the connecting seat (702), and a rubber plug (705) mounted on the top of the protrusion (3).

5. The steel bridge deck color composite pavement structure according to claim 3, It is characterized in that The top of the cover plate (404) is evenly provided with holes, and the support plates (401) are symmetrically distributed on the vertical center line of the cover plate (404).

6. A steel bridge deck color composite pavement structure according to claim 4, It is characterized in that The outer wall of the fixing bolt (704) is provided with an external thread, and the interior of the screw block (703) is provided with an internal thread that cooperates with the external thread.