Arc-structure wall stone dry hanging structure

By using wire rope clamps and dry-hanging connectors, combined with mechanical anchor bolts and tie bolts, the problems of inconvenience in installation and arc adjustment of stone on curved structure walls are solved, and the perfect fit and resistance between stone and wall are achieved.

CN222009454UInactive Publication Date: 2024-11-15CHINA CONSTR FIRST BUREAU GRP INTERIOR FITOUT ENG +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420611758.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-28
Publication Date
2024-11-15
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In the prior art, the stone on the arc-shaped wall is inconvenient to install, and it is impossible to ensure that each piece of stone fits perfectly with the wall. The rigid material of the vertical keel needs to be bent in advance, and the arc cannot be adjusted on site, and the flexibility is relatively small.

Method used

The wire rope is used as the support member. Through the wire rope clamp and dry-hanging connection, combined with mechanical anchor bolts and tie bolts, the flexible installation and arc adjustment of the stone are achieved, ensuring that the stone is perfectly fitted with the curved wall.

Benefits of technology

It realizes flexible installation and arc adjustment of stone, ensuring that the stone is perfectly fitted with the curved wall, and enhancing the installation's robustness, wind pressure and earthquake resistance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222009454U_ABST
    Figure CN222009454U_ABST
Patent Text Reader

Abstract

A stone dry hanging structure of an arc-shaped structure wall relates to the technical field of building construction, the dry hanging surface of the arc-shaped structure wall is an arc-shaped surface, the bottom end of the arc-shaped surface is a transverse vertical surface, the stone dry hanging structure comprises two upper pre-buried plates connected to the top end of the arc-shaped surface and two lower pre-buried plates connected to the vertical surface, and the upper pre-buried plates and the lower pre-buried plates are symmetrically arranged. The steel wire ropes are tied between the corresponding upper and lower pre-buried plates, the dry-hanging connecting pieces are supported by the steel wire ropes and are connected to the arc-shaped surfaces, and the stone is hung on the dry-hanging connecting pieces. The utility model solves the problems that the stones on the arc-shaped structure wall body are inconvenient to install, and each stone can not be perfectly attached to the wall surface of the arc-shaped structure wall body, and also solves the problems that in the prior art, rigid vertical keels are used as load-bearing members, bending prefabrication needs to be carried out in a factory in advance, the radian can not be adjusted on site, and the flexibility is small.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction, in particular to an arc-shaped wall stone dry hanging structure. Background Art

[0002] The existing solution is to install embedded plates on the structural walls, fix the vertical keels with connectors, and then dry-hang the stones on the vertical keels through adapter leveling components. However, the vertical keels are rigid materials and need to be bent and prefabricated in the factory in advance. The curvature cannot be adjusted on-site, and the flexibility is relatively low. Utility Model Content

[0003] The purpose of the utility model is to provide a dry hanging structure for stones on a curved structure wall, so as to solve the problem that it is inconvenient to install stones on the curved structure wall and it is impossible to ensure that each stone can perfectly fit the wall surface of the curved structure wall. At the same time, it solves the problem that the rigid vertical keel of the existing technology material as a load-bearing component needs to be bent and prefabricated in the factory in advance, the curvature cannot be adjusted on site, and the flexibility is relatively low.

[0004] In order to achieve the above purpose, the utility model adopts the following technical solutions:

[0005] The stone dry hanging structure of the curved structure wall has a curved surface, and the bottom of the curved surface is a horizontal vertical surface, including two upper embedded plates connected to the top of the curved surface, and two lower embedded plates connected to the vertical surface. The upper and lower embedded plates are symmetrically arranged, and the steel wire rope is tied between the corresponding upper and lower embedded plates. The steel wire rope is supported by the steel wire rope and connected to the dry hanging connector on the curved surface, and the stone is hung on the dry hanging connector.

[0006] The stones are arranged in groups on the curved surface. The stones in each group are arranged in sequence from top to bottom, and the four corners of each stone are connected to the curved surface.

[0007] The dry hanging connector includes a pair of rectangular wire rope clamps, a pair of U-shaped openings are opened in the middle of the top edges of the pair of wire rope clamps, a U-shaped clamp is clamped between the pair of U-shaped openings, and the pair of wire rope clamps are clamped by the U-shaped clamp; the four corners of the pair of wire rope clamps are connected by connecting bolts.

[0008] The wire rope is connected between a pair of wire rope clamps.

[0009] The center of the wire rope clamp is connected to the arc surface of the arc structure wall through a connecting rod.

[0010] A stone hanger is hung on a pair of wire rope clamps, and the stone hanger and the outer side of the wire rope clamp are clamped by an H-shaped plug; a threaded hole is opened in the center of the top surface of the stone hanger, and a height adjustment screw is passed through the threaded hole from top to bottom, and the bottom end of the height adjustment screw is against the bottom surface of the U-shaped clamp; a threaded hole is opened in the center of the front of the stone hanger, and a front and rear distance adjustment screw is passed through the threaded hole from outside to inside, and the front and rear distance adjustment screw serves as a stone hanging point.

[0011] A further preferred technical solution: the connecting rod includes a mechanical anchor bolt and a tie bolt.

[0012] In each group of stones, the centers of the wire rope clamps located on the two top corners of the top stone and the centers of the wire rope clamps located on the two bottom corners of the bottom stone are connected to the arc-shaped structural wall through mechanical anchor bolts, and the centers of the wire rope clamps located at the remaining positions are connected to the arc-shaped surface of the arc-shaped structural wall through tie bolts.

[0013] A further preferred technical solution is that the stone pendant is an integrated structure, including a U-shaped bayonet portion and an isosceles trapezoidal support portion, and both ends of the U-shaped bayonet portion and the bottom end of the isosceles trapezoidal support portion are provided with U-shaped sockets.

[0014] A further preferred technical solution is as follows: the U-shaped bayonet portion is engaged with the outer sides of the top edges of a pair of wire rope clamps, and the isosceles trapezoidal support portion is supported on the outer side surfaces of the wire rope clamps.

[0015] A further preferred technical solution is that the H-shaped plug-in block fits in the U-shaped socket.

[0016] A further preferred technical solution is that the top edges of the two upper embedded plates do not exceed the top edge of the stone located at the uppermost end.

[0017] A further preferred technical solution is as follows: two steel wire ropes are tied between each pair of corresponding upper and lower embedded plates, and the two steel wire ropes are located on both sides of the mechanical anchor bolt or on both sides of the tie bolt.

[0018] A further preferred technical solution is as follows: the upper and lower embedded plates have the same structure, the upper embedded plate is a rectangular plate, and the four corners are connected to the arc surface of the arc structure wall by anchor bolts; the two lower embedded plates are connected to the vertical surface of the arc structure wall by anchor bolts.

[0019] A further preferred technical solution: the stone is a flat stone or an arc-shaped stone.

[0020] Compared with the prior art, the utility model has the following characteristics and beneficial effects:

[0021] The utility model adopts a steel wire rope as a weighing member for the stone material. The curvature of the steel wire rope can be adjusted according to the needs on site, and the steel wire rope is used for support and flexible load bearing.

[0022] The primary technical problem solved by the utility model is how to adapt to the installation of stones on the surface of the curved structure wall to ensure that each piece of stone can perfectly fit with the surface of the curved structure wall.

[0023] The utility model tightly fixes the steel wire rope to the dry hanging connecting piece on the back of the stone, and then the stone is dry hung to the dry hanging connecting piece. This connection method ensures the firmness of the stone connection and can effectively resist external forces such as wind pressure and earthquake. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 It is a three-dimensional diagram of the stone dry hanging structure of the curved wall of the utility model;

[0025] Figure 2 This utility model Figure 1 Enlarged view of part A in the middle;

[0026] Figure 3 This is a perspective view of the utility model of the dry hanging structure of the curved wall stone material;

[0027] Figure 4 It is a three-dimensional diagram of the dry hanging connector of the utility model;

[0028] Figure 5 It is a schematic diagram of a mechanical anchor bolt in the uppermost dry hanging connector of the utility model;

[0029] Figure 6 It is a schematic diagram of the mechanical anchor bolt of the utility model;

[0030] Figure 7 It is a schematic diagram of the tie bolt in the dry hanging connector located in the middle of the utility model;

[0031] Figure 8 It is a schematic diagram of the tie bolt of the utility model;

[0032] Fig. 9 It is a three-dimensional diagram of the connection between a pair of steel wire rope clamps and a U-shaped clamp of the utility model;

[0033] Fig.10 It is a schematic diagram of a pair of wire rope clamps of the utility model;

[0034] Fig.11 It is a schematic diagram of the stone pendant of the utility model;

[0035] Fig.12 It is a schematic diagram of the U-shaped clamp of the utility model;

[0036] Fig.13 It is a schematic diagram of the H-shaped plug block of the utility model;

[0037] Fig.14 It is a schematic diagram of the upper embedded plate of the utility model;

[0038] Fig.15 It is a schematic diagram of the steel wire rope of the utility model;

[0039] Reference numerals:

[0040] 1—upper embedded plate, 2—lower embedded plate, 3—stone, 4—dry hanging connection piece, 5—wire rope,

[0041] 4.1—Wire rope clamp, 4.2—U-shaped clamp, 4.3—U-shaped mouth, 4.4—Connecting bolt, 4.5—Tie bolt, 4.6—Mechanical anchor, 4.7—Stone hanger, 4.8—H-shaped plug, 4.9—Height adjustment screw, 4.10—Front and rear distance adjustment screw,

[0042] 4.7.1—U-shaped socket. DETAILED DESCRIPTION

[0043] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0044] See also Figures 1 to 15 As shown, the utility model is a dry hanging structure for stone materials on an arc-shaped wall, wherein the dry hanging surface of the arc-shaped wall is an arc-shaped surface, and the bottom end of the arc-shaped surface is a horizontal vertical surface; it includes two upper embedded plates 1 connected to the top of the arc-shaped surface, and two lower embedded plates 2 connected to the vertical surface, the upper and lower embedded plates are symmetrically arranged, and a steel wire rope 5 is tied between the corresponding upper and lower embedded plates, and a dry hanging connector 4 supported and connected to the arc-shaped surface by the steel wire rope 5, and a stone 3 is hung on the dry hanging connector 4.

[0045] The stones 3 are arranged in groups on the curved surface of the curved structure wall, and the stones 3 in each group are arranged closely up and down and connected on the curved surface.

[0046] The stone 3 is a flat stone or an arc-shaped stone. In a specific embodiment, the length of the arc-shaped stone is 785 mm, the width is 800 mm, the thickness is 25 mm, the diameter of the circle where the arc of the arc-shaped stone is located is 9055 mm, and the arc length is 818.4 mm; the specific size and curvature of the stone 3 are determined according to the arc surface of the arc-shaped structural wall and are adapted to the curvature of the arc surface; compared with flat stones, the arc-shaped stone has a better overall effect after installation.

[0047] Two upper embedded plates 1 are connected to the top of the curved surface of the curved structure wall at intervals in the horizontal direction, and two lower embedded plates 2 are connected to the vertical surface at intervals in the horizontal direction; the top edges of the two upper embedded plates 1 do not exceed the top edges of the stone 3 located at the uppermost end, that is, the two upper embedded plates 1 are hidden behind the stone 3 located at the uppermost end; the upper and lower embedded plates have the same structure, the upper embedded plate 1 is a rectangular plate, and the four corners are connected to the curved surface of the curved structure wall by anchor bolts; the two lower embedded plates 2 are connected to the vertical surface of the curved structure wall by anchor bolts.

[0048] The four corners of the back side of the stone material 3 are connected to the arc surface of the arc structure wall through dry hanging connectors 4.

[0049] The center of the wire rope clamp 4.1 is connected to the arc surface of the arc structure wall through a connecting rod; the connecting rod includes a mechanical anchor bolt 4.6 and a tie bolt 4.5, and the dry hanging connector 4 includes a pair of rectangular wire rope clamps 4.1, a pair of U-shaped openings 4.3 are opened in the middle of the top edges of the pair of wire rope clamps 4.1, a U-shaped clamp 4.2 is clamped between the pair of U-shaped openings, and the pair of wire rope clamps 4.1 are clamped by the U-shaped clamp 4.2; the four corners of the pair of wire rope clamps 4.1 are connected by connecting bolts 4.4; the wire rope clamps 4.1 located at the two top corners of the uppermost stone 3. The center of the steel wire rope clamp 4.1 and the center of the steel wire rope clamp 4.1 located at the two bottom corners of the lowest stone 3 are connected to the arc-shaped structure wall through mechanical anchor bolts 4.6, and the steel wire rope clamp 4.1 is pushed outward by the mechanical anchor bolts 4.6, so as to realize that the steel wire rope 5 engaged between a pair of steel wire rope clamps 4.1 is pushed outward, and the installation distance is pushed out between the steel wire rope 5 and the arc surface of the arc-shaped structure wall; the center of the steel wire rope clamp 4.1 located at the remaining positions is connected to the arc surface of the arc-shaped structure wall through the tie bolts 4.5, and the curvature of the steel wire rope 5 is adjusted by the tie bolts 4.5.

[0050] Two steel wire ropes 5 are tied between each pair of corresponding upper and lower embedded plates, and the dry hanging connector 4 is installed on the two steel wire ropes 5. A pair of steel wire rope clamps 4.1 are arranged in front and behind the two steel wire ropes 5 and are closed by connecting bolts 4.4. The two steel wire ropes 5 are located on both sides of the mechanical anchor bolts 4.6 or on both sides of the tie bolts 4.5.

[0051] A stone hanger 4.7 is suspended on a pair of wire rope clamps 4.1. The stone hanger 4.7 is an integrated structure, including a U-shaped bayonet portion and an isosceles trapezoidal support portion. Both ends of the U-shaped bayonet portion and the bottom end of the isosceles trapezoidal support portion are provided with U-shaped sockets 4.7.1; the U-shaped bayonet portion is clamped on the outer side of the top edge of the pair of wire rope clamps 4.1, and the isosceles trapezoidal support portion is supported on the outer side of the wire rope clamp 4.1; the U-shaped socket 4.7.1 and the outer side of the wire rope clamp 4.1 are clamped by an H-shaped plug 4.8, and the H-shaped plug 4.8 fits and is inserted in the U-shaped socket 4.7.1; the top of the U-shaped bayonet portion A threaded hole is provided in the center of the plate, and a height adjustment screw 4.9 is passed through the threaded hole from top to bottom. The bottom end of the height adjustment screw 4.9 abuts against the bottom surface of the U-shaped clamp 4.2, and the height of the stone hanger 4.7 can be adjusted up and down by turning the height adjustment screw 4.9; a threaded hole is provided in the center of the top plate of the isosceles trapezoidal support portion, and a front-to-back distance adjustment screw 4.10 is passed through the threaded hole from outside to inside, and a fixing nut is passed through the front-to-back distance adjustment screw 4.10, and the front-to-back distance adjustment screw 4.10 serves as a stone hanging point, and the front-to-back distance adjustment of the hanging point can be achieved by adjusting the front-to-back distance adjustment screw 4.10.

[0052] The construction method of the utility model of the curved structure wall stone dry hanging structure comprises the following steps:

[0053] Step 1: Lay out and position according to the design drawings.

[0054] Lay out the lines to determine the positions of the upper embedded plate 1, the lower embedded plate 2 and the positions and elevations of the stone hanging points on all dry hanging connectors 4.

[0055] Step 1: engage the U-shaped clamp 4.2 between a pair of wire rope clamps 4.1 to fix the distance between the pair of wire rope clamps 4.1.

[0056] Step 1: Use the upper embedded plate 1 to fix the top end of the steel wire rope 5 to the top of the arc-shaped structure wall, use the lower embedded plate 2 to fix the bottom end of the steel wire rope 5 to the bottom of the arc-shaped structure wall, and tighten the steel wire rope 5.

[0057] Two steel wire ropes 5 are fixed on each embedded plate.

[0058] Step 1: fix a pair of wire rope clamps 4.1 on the arc-shaped structural wall through mechanical anchor bolts 4.6, then clamp the wire rope on both sides of the pair of wire rope clamps 4.1, and then enclose the wire rope 5 in the pair of wire rope clamps 4.1 through connecting bolts 4.4, and at the same time push the wire rope 5 outward through the mechanical anchor bolts 4.6.

[0059] Step 1: Clamp the stone hanger 4.7 onto a pair of wire rope clamps 4.1, and then insert an H-shaped plug 4.8 into the gap between the pair of wire rope clamps 4.1 to clamp it.

[0060] Step 1: Turn the height adjustment screw 4.9 to adjust the upper and lower positions of the stone hanger 4.7 to the designed height; turn the front and rear distance adjustment screw 4.10 to adjust the front and rear positions of the stone hanger 4.7 to the designed hanging point position.

[0061] Step 1: Hang the stone 3 on the hanging point of the stone hanger 4.7 and apply stone glue to complete the installation.

[0062] It is obvious to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be regarded as exemplary and non-restrictive from any point of view, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present invention. Any reference numeral in a claim should not be regarded as limiting the claim to which it relates.

[0063] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. Curved wall stone dry hanging structure, the dry hanging surface of the curved wall is a curved surface, and the bottom of the curved surface is a horizontal vertical surface. Features: It comprises two upper embedded plates (1) connected to the top of the arc surface, two lower embedded plates (2) connected to the vertical surface, the upper and lower embedded plates are symmetrically arranged, a steel wire rope (5) tied between the corresponding upper and lower embedded plates, a dry hanging connector (4) supported and connected to the arc surface by the steel wire rope (5), and a stone (3) hung on the dry hanging connector (4); The stones (3) are arranged in groups on the arc surface, the stones (3) in each group are arranged in sequence from top to bottom, and the four corners of each stone (3) are connected to the arc surface; The dry hanging connector (4) comprises a pair of rectangular steel wire rope clamps (4.1), a pair of U-shaped openings (4.3) are opened in the middle of the top edges of the pair of steel wire rope clamps (4.1), a U-shaped clamp (4.2) is clamped between the pair of U-shaped openings, and the pair of steel wire rope clamps (4.1) are clamped by the U-shaped clamp (4.2); the four corners of the pair of steel wire rope clamps (4.1) are connected by connecting bolts (4.4); The steel wire rope (5) is threaded between a pair of steel wire rope clamps (4.1); The center of the wire rope clamp (4.1) is connected to the arc surface of the arc structure wall through a connecting rod; A stone hanger (4.7) is suspended on a pair of steel wire clamps (4.1), and the stone hanger (4.7) and the outer side surface of the steel wire clamp (4.1) are clamped by an H-shaped plug (4.8); a threaded hole is opened at the center of the top surface of the stone hanger (4.7), and a height adjustment screw (4.9) is inserted from top to bottom in the threaded hole, and the bottom end of the height adjustment screw (4.9) abuts against the bottom surface of the U-shaped clamp (4.2); a threaded hole is opened at the center of the front of the stone hanger (4.7), and a front and rear distance adjustment screw (4.10) is inserted from outside to inside in the threaded hole, and the front and rear distance adjustment screw (4.10) serves as a stone hanging point; The stone (3) is a flat stone or an arc-shaped stone; the length of the arc-shaped stone is 785 mm, the width is 800 mm, the thickness is 25 mm, the diameter of the circle where the arc of the arc-shaped stone is located is 9055 mm, and the arc length is 818.4 mm.

2. The curved wall stone dry hanging structure according to claim 1, Features: The connecting rod includes a mechanical anchor bolt (4.6) and a tie bolt (4.5); In each group of stones, the centers of the steel wire rope clamps (4.1) located at the two top corners of the topmost stone (3) and the centers of the steel wire rope clamps (4.1) located at the two bottom corners of the bottommost stone (3) are connected to the arc-shaped structural wall through mechanical anchor bolts (4.6), and the centers of the steel wire rope clamps (4.1) located at other positions are connected to the arc surface of the arc-shaped structural wall through tie bolts (4.5).

3. The curved wall stone dry hanging structure according to claim 1, Features: The stone hanger (4.7) is an integrated structure, comprising a U-shaped bayonet portion and an isosceles trapezoidal support portion, and both ends of the U-shaped bayonet portion and the bottom end of the isosceles trapezoidal support portion are provided with U-shaped sockets (4.7.1).

4. The curved wall stone dry hanging structure according to claim 3, Features: The U-shaped bayonet portion is engaged with the outer sides of the top edges of a pair of steel wire rope clamps (4.1), and the isosceles trapezoidal support portion is supported on the outer side surfaces of the steel wire rope clamps (4.1).

5. The curved wall stone dry hanging structure according to claim 3, Features: The H-shaped plug block (4.8) fits into the U-shaped socket (4.7.1).

6. The curved wall stone dry hanging structure according to claim 1, Features: The top edges of the two upper embedded plates (1) do not exceed the top edge of the stone material (3) located at the uppermost end.

7. The curved wall stone dry hanging structure according to claim 2, Features: Two steel wire ropes (5) are tied between each pair of corresponding upper and lower embedded plates, and the two steel wire ropes (5) are located on both sides of the mechanical anchor bolt (4.6) or on both sides of the tie bolt (4.5).

8. The curved wall stone dry hanging structure according to claim 1, Features: The upper and lower embedded plates have the same structure. The upper embedded plate (1) is a rectangular plate, and its four corners are connected to the arc surface of the arc structure wall through anchor bolts; the two lower embedded plates (2) are connected to the vertical surface of the arc structure wall through anchor bolts.