Pre-closed waterproof post-cast strip structure
By setting up a cover body and pouring pipe in the rear casting belt structure, the design of first covering soil and pouring concrete during the settlement process is realized, which solves the problem of long construction cycle of the existing rear casting belt, and improves construction efficiency and waterproofing performance. .
Patent Information
- Application Number
- CN202323524645.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-21
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2033-12-21
AI Technical Summary
The construction of existing post-pouring belts requires roof soil covering and landscape construction to be carried out after settlement is stabilized, resulting in a long construction period and low efficiency.
Design a pre-enclosed waterproof post-pouring strip structure. By setting up a cover body and a pouring pipe between the first pouring strips, the soil is first covered during the waiting process, and after the settlement is stable, the post-pouring strip is formed by pouring concrete in the pouring pipe to improve the sealing and simplify the construction process.
The construction cycle is reduced, the construction efficiency is improved, and the waterproof performance and construction convenience are improved through designs such as waterproof sheets and mud fenders.
Smart Images

Figure CN222025111U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of post-cast strips, and in particular to a pre-enclosed waterproof post-cast strip structure. Background Art
[0002] Post-cast strips are concrete strips set at corresponding positions of foundation slabs, walls and beams in accordance with design or construction specifications to prevent harmful cracks that may occur in reinforced concrete structures due to uneven shrinkage or settlement. During the construction of the main building, the construction unit needs to cover the soil and carry out landscape construction at the post-cast strips around the main building due to landscape requirements.
[0003] The existing post-cast strip construction needs to wait until the settlement is stable before construction can be carried out, and then the top plate covering, greening, municipal construction and other processes can be carried out. Before the post-cast strip is closed, the landscape covering cannot be constructed in advance, resulting in a long construction time and a long construction period with low efficiency. Utility Model Content
[0004] In order to reduce the construction period, the present application provides a pre-sealed waterproof post-cast strip structure.
[0005] The present application provides a pre-enclosed waterproof post-cast strip structure adopts the following technical solution:
[0006] A pre-enclosed waterproof post-cast strip structure comprises two pre-cast strips, a gap is provided between the two pre-cast strips, a post-cast strip is arranged in the gap between the two pre-cast strips, a cover body is arranged between the two pre-cast strips, the cover body is located above the pre-cast strips and the two ends are respectively connected to the pre-cast strips on both sides, a casting pipe is connected above the cover body, and the casting pipe is detachably connected to the cover body.
[0007] By adopting the above technical solution, a cover body is arranged between the two pre-cast strips, and the gap between the two pre-cast strips is covered by the cover body. In the process of waiting for settlement, the pre-cast strip and the cover body can be covered with soil first. After the settlement is stabilized, concrete is poured into the two covers through a pouring pipe to form a post-cast strip, thereby reducing the construction period.
[0008] Optionally, the pre-cast strip is pre-embedded with a waterproof sheet, one end of the waterproof sheet is connected to the pre-cast strip, and the other end of the waterproof sheet is connected to the post-cast strip.
[0009] By adopting the above technical solution, a waterproof sheet 11 is provided between the precast strip 1 and the postcast strip 2, thereby improving the sealing of the gap between the precast strip 1 and the postcast strip 2, thereby improving the waterproof performance.
[0010] Optionally, a clamping hole is opened on the upper surface of the cover body, and the casting pipe is clamped in the clamping hole.
[0011] By adopting the above technical solution, a clamping hole is provided on the cover body, and the pouring pipe is clamped in the clamping hole. After pouring, the pouring pipe can be disassembled.
[0012] Optionally, a hook block is provided at the lower end of the casting pipe, and a hook groove is provided around the side wall of the clamping hole, and the diameter of the hook groove is larger than the diameter of the clamping hole.
[0013] By adopting the above technical solution, a hooking block is provided on the casting pipe. When the casting pipe is installed, the hooking block is hooked in the hooking groove, thereby fixing the casting pipe.
[0014] Optionally, an avoidance groove for avoiding the hooking block is opened on the upper surface of the cover body, and the avoidance groove is connected to the hooking groove.
[0015] By adopting the above technical scheme, an avoidance groove is opened. When the casting pipe is installed, the hooking block is moved to the position of the hooking groove through the avoidance groove, and then the casting pipe is rotated so that the hooking block is hooked in the hooking groove, thereby fixing the casting pipe. After the post-casting strip is cast, the casting pipe needs to be disassembled, and the casting pipe is rotated so that the hooking block is rotated to the avoidance groove, and then the casting pipe can be pulled out.
[0016] Optionally, a mud guard is provided at the lower end of the casting pipe, and the mud guard covers the avoidance groove.
[0017] By adopting the above technical solution, during the covering process, sand may enter the avoidance groove, thereby affecting the disassembly of the casting pipe. Therefore, a mud guard is provided on the casting pipe to block the mud and reduce the possibility of mud entering the avoidance groove.
[0018] Optionally, the mud guard portion is in the shape of a sheet, the upper portion of the mud guard portion is hinged to the casting pipe, and the lower portion of the mud guard portion covers the avoidance groove.
[0019] By adopting the above technical solution, during the process of pulling out the pouring pipe, since the mud guard is hinged to the pouring pipe, the mud guard will rotate in the direction close to the pouring pipe to facilitate pulling out the pouring pipe.
[0020] Optionally, a plurality of the casting pipes are provided, and the plurality of the casting pipes extend along the length direction of the post-cast strip.
[0021] By adopting the above technical solution, a plurality of pouring pipes are provided to facilitate pouring of different parts of the post-casting zone.
[0022] In summary, the utility model has the following beneficial effects:
[0023] 1. A cover is provided between the two pre-cast strips to cover the gap between the two pre-cast strips. In the process of waiting for settlement, soil can be covered on the pre-cast strips and the cover. After the settlement is stable, concrete is poured into the two covers through the pouring pipe to form a post-cast strip, which can reduce the construction period;
[0024] 2. In the process of pulling out the pouring pipe, since the mud guard is hinged to the pouring pipe, the mud guard will rotate in the direction close to the pouring pipe to facilitate pulling out the pouring pipe. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a structural schematic diagram of this embodiment;
[0026] Figure 2 yes Figure 1 A magnified schematic diagram of center A.
[0027] In the figure, 1, pre-cast strip; 11, waterproof sheet; 2, post-cast strip; 3, cover body; 31, clamping hole; 32, hook groove; 33, avoidance groove; 4, casting pipe; 41, hook block; 42, mud guard. DETAILED DESCRIPTION
[0028] The following is combined with Figure 1-2 This application is described in further detail.
[0029] The present application embodiment discloses a pre-enclosed waterproof post-casting strip structure, referring to Figure 1 and Figure 2 , including two precast strips 1, with a gap between the two precast strips 1, and a post-cast strip 2 is arranged in the gap between the two precast strips 1. A cover body 3 is arranged between the two precast strips 1, the cover body 3 is located above the precast strips 1 and the two ends of the cover body 3 are respectively fixedly installed on the precast strips 1 on both sides, and a pouring pipe 4 is detachably connected to the top of the cover body 3, and the pouring pipe 4 is connected to the inside of the cover body 3.
[0030] Reference Figure 1 and Figure 2 , a plurality of casting pipes 4 are provided, and a plurality of casting pipes 4 extend along the length direction of the post-cast strip 2. A plurality of casting pipes 4 are provided, so as to cast different parts of the post-cast strip 2, so that the post-cast strip 2 is cast more evenly.
[0031] Reference Figure 1 and Figure 2 The precast strip 1 is pre-buried with a waterproof sheet 11, one end of which is pre-buried and installed in the precast strip 1, and the other end of which is located in the cavity between the cover body 3 and the precast strip 1. The waterproof sheet 11 is arranged between the precast strip 1 and the postcast strip 2, thereby improving the sealing of the gap between the precast strip 1 and the postcast strip 2, and further improving the waterproof performance.
[0032] Reference Figure 1 and Figure 2 , a clamping hole 31 is formed through the upper surface of the cover body 3, and the casting pipe 4 is clamped in the clamping hole 31. A hooking block 41 is provided at the lower end of the casting pipe 4, and a hooking groove 32 is formed around the side wall of the clamping hole 31, and the diameter of the hooking groove 32 is larger than the diameter of the clamping hole 31. An avoidance groove 33 for avoiding the hooking block 41 is formed on the upper surface of the cover body 3, and the avoidance groove 33 is connected to the hooking groove 32. When installing the casting pipe 4, the hooking block 41 is passed through the avoidance groove 33 and moved to the position of the hooking groove 32, and then the casting pipe 4 is rotated so that the hooking block 41 and the avoidance groove 33 are staggered. At this time, the hooking block 41 is opened in the hooking groove 32, thereby realizing the installation of the casting pipe 4.
[0033] Reference Figure 1 and Figure 2 The lower end of the pouring pipe 4 is provided with a mud guard 42, and the mud guard 42 covers the avoidance groove 33. The mud guard 42 is in an arc-shaped sheet shape, the upper part of the mud guard 42 is hinged to the pouring pipe 4, and the lower part of the mud guard 42 covers the avoidance groove 33. In the process of pulling out the pouring pipe 4, since the mud guard 42 is hinged to the pouring pipe 4, the mud guard 42 will rotate in the direction close to the pouring pipe 4, so as to facilitate the pouring pipe 4 to be pulled out.
[0034] The implementation principle of the pre-enclosed waterproof post-cast strip 2 structure in the embodiment of the present application is as follows: a cover body 3 is arranged between two pre-cast strips 1, and the gap between the two pre-cast strips 1 is covered by the cover body 3. In the process of waiting for settlement, soil can be first covered on the pre-cast strip 1 and the cover body 3. After the settlement is stable, concrete is poured into the two cover bodies 3 through the pouring pipe 4, thereby forming a post-cast strip 2, which can reduce the construction period.
[0035] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A pre-enclosed waterproof post-cast strip structure, characterized in that: The invention comprises two precast strips (1), a gap is provided between the two precast strips (1), a postcast strip (2) is arranged in the gap between the two precast strips (1), a cover body (3) is arranged between the two precast strips (1), the cover body (3) is located above the precast strips (1) and the two ends are respectively connected to the precast strips (1) on both sides, a pouring pipe (4) is connected above the cover body (3), and the pouring pipe (4) is detachably connected to the cover body (3).
2. A pre-enclosed waterproof post-cast strip structure according to claim 1, characterized in that: The precast strip (1) is pre-buried with a waterproof sheet (11), one end of the waterproof sheet (11) is connected to the precast strip (1), and the other end of the waterproof sheet (11) is connected to the post-cast strip (2).
3. The pre-enclosed waterproof post-cast strip structure according to claim 1, characterized in that: The upper surface of the cover body (3) is provided with a clamping hole (31), and the pouring pipe (4) is clamped in the clamping hole (31).
4. A pre-enclosed waterproof post-cast strip structure according to claim 3, characterized in that: A hook block (41) is provided at the lower end of the pouring pipe (4), and a hook groove (32) is provided around the side wall of the clamping hole (31), wherein the diameter of the hook groove (32) is greater than the diameter of the clamping hole (31).
5. A pre-enclosed waterproof post-cast strip structure according to claim 4, characterized in that: An escape groove (33) for evading the hooking block (41) is provided on the upper surface of the cover body (3), and the escape groove (33) is connected to the hooking groove (32).
6. A pre-enclosed waterproof post-cast strip structure according to claim 5, characterized in that: A mud guard (42) is provided at the lower end of the pouring pipe (4), and the mud guard (42) covers the avoidance groove (33).
7. A pre-enclosed waterproof post-cast strip structure according to claim 6, characterized in that: The mud guard portion (42) is in the form of a sheet, the upper portion of the mud guard portion (42) is hinged to the pouring pipe (4), and the lower portion of the mud guard portion (42) covers the avoidance groove (33).
8. The pre-enclosed waterproof post-cast strip structure according to claim 1, characterized in that: A plurality of the pouring pipes (4) are provided, and the plurality of the pouring pipes (4) extend along the length direction of the post-casting strip (2).