Existing high and steep slope roadbed widening structure
By using foamed lightweight soil, protective walls, steel pipes, and anchor bolts to construct an overall load-bearing structure for widening steep roadbed slopes, the problems of large engineering volume and poor stability in widening steep roadbed slopes were solved, achieving space saving and improved stability.
Patent Information
- Application Number
- CN202420158936.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-22
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2034-01-22
AI Technical Summary
Existing technologies involve large engineering work, are prone to settlement, and occupy land resources in widening steep roadbed slopes, resulting in poor stability and making it difficult to solve the problem effectively.
Foamed lightweight soil is used as the subgrade filler, and a protective wall is formed by combining it with side plates and bottom plates. Steel pipes and anchor rods are added, guardrail bases are set up, and an overall load-bearing structure is constructed. Grouting of steel pipes provides anti-slip and bearing capacity, and stability is improved by combining drainage layer and geogrid.
It reduces the space required for widening, enhances the stability and anti-slip capability of steep slopes, reduces the risk of settlement, and improves the overall stability and protection performance of the roadbed.
Smart Images

Figure CN222043737U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of roadbed widening structures, in particular to an existing high and steep slope roadbed widening structure. Background Art
[0002] Some highways are facing the problem of traffic saturation and need to be expanded. When expanding highways, the roadbed needs to be widened. Mountain roads are affected by topography and often have high and steep roadbed slopes. The widening plan is directly related to the stability of the entire roadbed and the normal traffic of the road. If the widening position of the high and steep roadbed slope is not handled properly, it is easy to cause uneven settlement of the new and old roadbeds, and in severe cases, it will cause roadbed collapse, which will have a great impact on the normal operation of the road.
[0003] In existing projects, the roadbed slope is often widened by filling, and the differential settlement of the new and old roadbeds is reduced by measures such as excavating steps and laying geogrids. However, for high and steep roadbed slopes, the filling and widening project is large, and the compaction control requirements are high. In weather such as heavy rain, it is very easy to cause settlement of the high-filled roadbed. Due to the high fill of the slope, once the roadbed settlement or landslide disaster occurs, it is difficult to deal with it, and the project investment increases significantly. At the same time, widening the high-filled roadbed will add more land, occupy land resources, and cause damage to the natural resources in the occupied location. Utility Model Content
[0004] The purpose of the utility model is to provide a widening structure for an existing high and steep slope roadbed in response to the defects of the prior art. The roadbed widening part adopts foam lightweight soil as the roadbed filler, and the side plates and the bottom plate are used to form a protective wall on the outside of the foam lightweight soil as a constraint structure of the foam lightweight soil. No additional soil is required, and the utility model is suitable for widening high and steep slopes. Compared with general slopes, the required lateral space for widening is smaller, and the required slope flange safety distance is smaller. Steel flower pipes are added to fix the position of the protective wall to resist slippage and improve the vertical bearing capacity. A guardrail base is arranged on the top to bear the road surface and connect the guardrail at the same time, so as to improve the protection performance.
[0005] In order to achieve the above purpose, the following technical solutions are adopted:
[0006] An existing high and steep slope roadbed widening structure, comprising:
[0007] The protection wall comprises a bottom plate and side plates, wherein the bottom plate is placed on a horizontal plane formed by excavating a high and steep slope, and the side plates face toward a step formed by excavating the high and steep slope, and a filling area with an opening facing upward is formed between the protection wall and the step;
[0008] The steel flower pipe has one end extending through the bottom plate into the high and steep slope, and the other end is located in the fill area;
[0009] Foam lightweight soil is distributed in the filling area, and the top of the foam lightweight soil is covered with a leveling layer that is flush with the top of the side plate;
[0010] The guardrail base is placed on the leveling layer and the protective wall. A guardrail is arranged on the edge of the top surface of the guardrail base, and a widened road surface is paved between the guardrail and the existing road surface.
[0011] Furthermore, it also includes an anchor rod, one end of which extends into the step, and the other end is located in the filling area, and the anchor rod located in the filling area is provided with a bending portion.
[0012] Furthermore, a gravel drainage layer is laid at the bottom of the filling area, foam lightweight soil covers the gravel drainage layer, and the steel flower pipe passes through the gravel drainage layer and extends into the foam lightweight soil.
[0013] Furthermore, the gravel drainage layer is connected to the drainage layer drainage pipe, one end of the drainage layer drainage pipe passes through the protective wall and extends to the outside of the filling area, and the other end is located in the filling area and connected to the gravel drainage layer.
[0014] Furthermore, a geotextile is laid between the foam lightweight soil and the leveling layer, and a geogrid is laid on the top surface and inside of the foam lightweight soil below the geotextile, and the geogrid extends into the existing roadbed.
[0015] Furthermore, the vertical cross-section of the guardrail base is L-shaped, and the top surface of the guardrail base with a higher vertical height is connected to the guardrail; the side of the guardrail base with a lower vertical height is arranged close to the existing road surface and is lined under the widened road surface.
[0016] Furthermore, a graded gravel blind ditch is provided between the side of the guardrail base with a lower vertical height and the widened road surface, and the graded gravel blind ditch is connected to the outside through a blind ditch drainage pipe that penetrates the guardrail base.
[0017] Furthermore, slurry is annularly injected inside and outside the steel flower tube.
[0018] Furthermore, the steel flower pipes are provided in a plurality of groups distributed in the longitudinal direction of the highway, and each group includes a plurality of steel flower pipes arranged at intervals in the transverse direction of the highway.
[0019] Furthermore, the bottom of the side plate is connected to the bottom plate to form a structure with an L-shaped vertical section, and one end of the bottom plate away from the existing roadbed extends to the outside of the side plate.
[0020] Compared with the prior art, the utility model has the following advantages and positive effects:
[0021] (1) In view of the current problems of large workload and easy settlement in filling and widening high and steep slopes, foam lightweight soil is used as the roadbed filler for the widening part. The side plates and bottom plates on the outside of the foam lightweight soil form a protective wall as the constraint structure of the foam lightweight soil. No additional soil is required. It is suitable for widening high and steep slopes. Compared with general slopes, the required lateral space for widening is smaller and the required slope flange safety distance is smaller. Steel flower pipes are added to fix the position of the protective wall. The grouting steel flower pipes are used to provide lateral anti-slip force and bearing capacity to resist sliding and improve vertical bearing capacity, thereby reducing settlement problems.
[0022] (2) The steel tube is filled with slurry inside and around it, which has a strong anti-overturning ability. In addition, its bottom end can be buried in the rock layer or effective bearing layer of the steep slope to enhance the overall stability of the steep slope. In addition, the steel tube should extend into the filling area and be integrated with the "L"-shaped protective wall foundation and foam lightweight soil casting to form an integral force-bearing structure.
[0023] (3) A graded gravel drainage layer is adopted at the bottom of the foam lightweight soil. The subgrade seepage water can flow downward into the drainage layer through the existing subgrade soil-foam lightweight soil interface. After being collected by the drainage layer, it flows out of the widened subgrade through the drainage pipe pre-buried on the protective wall, thus ensuring the stability of the existing subgrade.
[0024] (4) A layer of geogrid should be set on the top and below the foam lightweight soil to improve the crack resistance of the lightweight soil. At the same time, the use of geogrids to penetrate into the existing interior can reduce the differential settlement of the new and old roadbeds and improve the overall stability of the existing roadbed and the widened roadbed. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] The drawings in the specification, which constitute a part of the present invention, are used to provide a further understanding of the present invention. The illustrative embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation on the present invention.
[0026] Figure 1 It is a schematic diagram of the existing high and steep slope roadbed widening structure in the embodiment of the utility model.
[0027] Figure 2 Schematic diagram of the position of the guardrail in the embodiment of the present utility model.
[0028] In the figure, 1. existing roadbed, 2. widened roadbed, 3. foam lightweight soil, 4. gravel drainage layer, 5. steel flower pipe, 6. protective wall, 7. guardrail base, 8. guardrail, 9. steps, 10. anchor rod, 11. geotextile, 12. geogrid, 13. widened road surface, 14. existing road surface, 15. leveling layer, 16. drainage layer drainage pipe, 17. high and steep slope, 18. graded gravel blind ditch, 19. blind ditch drainage pipe. DETAILED DESCRIPTION
[0029] In a typical implementation of the present invention, Figure 1-Figure 2 As shown in the figure, a widening structure of an existing high and steep slope roadbed is proposed.
[0030] Below, an existing high and steep slope roadbed widening structure is described in detail with reference to the accompanying drawings.
[0031] The existing high and steep slope roadbed widening structure in this embodiment is located on the side of the existing roadbed 1 and the existing road surface 14, including a widened roadbed 2 and a widened road surface 13, wherein the widened roadbed 2 uses foam lightweight soil 3 as a roadbed filler, and the outer side of the foam lightweight soil 3 uses an "L"-shaped protective wall 6 as an outer protective support structure; the widened road surface 13 is arranged on the widened roadbed 2 and connected to the existing road surface 14.
[0032] The existing steep slope 17 widening space is narrow and the foundation pit excavation is large, which not only causes the risk of instability of the existing slope, but also makes construction difficult. The existing steep slope roadbed widening structure provided in this embodiment can excavate the foundation pit within the roadbed widening width to achieve widening and avoid excessive slope excavation.
[0033] Specifically, the protection wall 6 includes a bottom plate and a side plate, which are the main structures for bearing and constraining the width of the splicing. The bottom plate is placed on the horizontal plane formed by the excavated high and steep slope 17, corresponding to the bottom surface of the excavated foundation pit; the side plate faces the step 9 formed by the excavated high and steep slope 17, corresponding to the side of the excavated foundation pit, and a filling area with an opening facing upward is formed between the protection wall 6 and the step 9 for filling with the foam lightweight soil 3. The foam lightweight soil 3 is distributed in the filling area, and the top of the foam lightweight soil 3 is covered with a leveling layer 15 flush with the top of the side plate.
[0034] For the steps 9 formed when excavating the foundation pit, the slope ratio and the steps 9 should be reasonably determined according to the widening width and the slope of the high and steep slope 17. For the roadbed widening project with a wider widening width, multi-step steps 9 should be adopted. For the narrow roadbed project that does not have the conditions for multi-step steps 9, a single-step step 9 should be adopted.
[0035] One end of the steel tube 5 passes through the bottom plate and extends into the high and steep slope 17, and the other end is located in the filling area; the steel tube 5 is used as an anti-slip measure for the widened part of the foam lightweight soil 3 and a measure to improve the vertical bearing capacity.
[0036] The steel flower tubes 5 are provided with a plurality of groups distributed along the longitudinal direction of the highway, and each group includes a plurality of steel flower tubes 5 arranged at intervals in the transverse direction of the highway; the steel flower tubes 5 are circumferentially injected with slurry inside and outside.
[0037] The steel pipe 5 is constructed by drilling, embedding the steel pipe 5, and grouting, which can effectively ensure the construction quality. The steel pipe 5 needs to have a strong anti-overturning ability, so it needs to be buried in the rock layer or effective bearing layer of the steep slope 17. In order to enhance the overall stability of the steep slope 17, the steel pipe 5 should be exposed for a certain length, and be cast together with the "L"-shaped protective wall 6 foundation and the foam lightweight soil 3 to form an integral force-bearing structure.
[0038] In this embodiment, the bottom width of the foam lightweight soil 3 should be greater than 2 m, and driven anchor rods 10 are used as a connection reinforcement measure between the new and old roadbeds.
[0039] One end of the anchor rod 10 extends into the step 9, and the other end is located in the filling area. The anchor rod 10 located in the filling area is provided with a bending portion; specifically, the bending portion of the exposed portion of the driven anchor rod 10 adopts a right-angle hook form to strengthen the connection with the foam lightweight soil 3 filling body. The driven anchor rod 10 should be driven into a sufficient depth. When it is difficult to drive in, drilling and grouting can be used for construction.
[0040] like Figure 1 and Figure 2 As shown, since the widening of the foam lightweight soil 3 roadbed blocks the drainage path of the original roadbed slope, a graded gravel drainage cushion layer is adopted at the bottom of the foam lightweight soil 3 to form a gravel drainage layer 4 located at the bottom of the filling area, the foam lightweight soil 3 covers the gravel drainage layer 4, and the steel flower pipe 5 passes through the gravel drainage layer 4 and extends into the foam lightweight soil 3.
[0041] The gravel drainage layer 4 is connected to the drainage layer drainage pipe 16. One end of the drainage layer drainage pipe 16 passes through the protective wall 6 and extends outside the filling area. The other end is located in the filling area and connected to the gravel drainage layer 4. In this embodiment, the drainage layer drainage pipe 16 is a PVC drainage pipe.
[0042] The roadbed seepage water can flow downward into the gravel drainage layer 4 through the soil-foam lightweight soil 3 interface, and after being collected by the gravel drainage layer 4, it flows out of the widened roadbed 2 through the PVC drainage pipe pre-buried on the protective wall 6, thereby ensuring the stability of the existing roadbed 1.
[0043] A geotextile 11 is laid between the foam lightweight soil and the leveling layer 15 , and a geogrid 12 is laid on the top surface and inside of the foam lightweight soil 3 below the geotextile 11 , and the geogrid 12 extends into the existing roadbed 1 .
[0044] A geogrid 12 is arranged on and below the top of the foamed lightweight soil 3 to improve the crack resistance of the foamed lightweight soil 3. At the same time, the top geogrid 12 is used to penetrate into the existing roadbed 1 to reduce the differential settlement of the new and old roadbeds and improve the overall stability of the existing roadbed 1 and the widened roadbed 2.
[0045] In order to improve the waterproof performance of the widened part, a layer of anti-seepage geotextile 11 is arranged on the top of the foam lightweight soil 3 to isolate the influence of a small amount of seepage water of the pavement structure layer on the foam lightweight soil 3 and improve the durability of the foam lightweight soil 3.
[0046] like Figure 2 As shown, the guardrail base 7 is placed on the leveling layer 15 and the protection wall 6, a guardrail 8 is provided on the edge of the top surface of the guardrail base 7, and a widened road surface 13 is laid between the guardrail 8 and the existing road surface 14. The vertical section of the guardrail base 7 is L-shaped, and the top surface of the guardrail base 7 with a higher vertical height is connected to the guardrail 8; the side of the guardrail base 7 with a lower vertical height is arranged close to the existing road surface 14 and is lined below the widened road surface 13.
[0047] The anti-collision guardrail 8 on the top of the foam lightweight soil 3 needs to be provided with a guardrail base 7, and the guardrail base 7 adopts an "inverted L" reinforced concrete structure. One end of the guardrail base 7 extends into the bottom of the pavement structure layer, which can improve the anti-collision performance and wind load resistance of the guardrail 8. The length of the guardrail base 7 should be determined according to the anti-collision level of the corresponding highway guardrail 8. The guardrail 8 adopts an "SS" grade anti-collision guardrail 8, which should not be less than 1.4m. The bottom of the guardrail 8 can be leveled through the bottom base of the pavement structure layer.
[0048] In order to achieve drainage of the pavement structure layer, a blind ditch and a pre-buried drainage pipe should be set above the guardrail base 7. Specifically, a graded gravel blind ditch 18 is set between the side of the guardrail base 7 with a lower vertical height and the widened road surface 13, and the graded gravel blind ditch 18 is connected to the outside through a blind ditch drainage pipe 19 that runs through the guardrail base 7.
[0049] The splicing of the existing road surface 14 and the widened road surface 13 can be implemented according to a specific road surface splicing method.
[0050] The bottom of the side plate is connected to the bottom plate to form a structure with an L-shaped vertical section, and one end of the bottom plate away from the existing roadbed 1 extends outside the side plate. Both the side plate and the bottom plate are concrete structures.
[0051] The above description is only the preferred embodiment of the utility model, and is not intended to limit the utility model. For those skilled in the art, the utility model can have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.
Claims
1. An existing high and steep slope roadbed widening structure, characterized in that: include: The protection wall comprises a bottom plate and side plates, wherein the bottom plate is placed on a horizontal plane formed by excavating a high and steep slope, and the side plates face toward a step formed by excavating the high and steep slope, and a filling area with an opening facing upward is formed between the protection wall and the step; The steel flower pipe has one end extending through the bottom plate into the high and steep slope, and the other end is located in the fill area; Foam lightweight soil is distributed in the filling area, and the top of the foam lightweight soil is covered with a leveling layer that is flush with the top of the side plate; the guardrail base is placed on the leveling layer and the protective wall, a guardrail is provided on the edge of the top surface of the guardrail base, and a widened road surface is paved between the guardrail and the existing road surface.
2. The existing high and steep slope roadbed widening structure as claimed in claim 1, characterized in that: It also includes an anchor rod, one end of which extends into the step, and the other end is located in the filling area. The anchor rod located in the filling area is provided with a bending portion.
3. The existing high and steep slope roadbed widening structure as claimed in claim 1 or 2, characterized in that: A crushed stone drainage layer is laid at the bottom of the filling area, foam lightweight soil covers the crushed stone drainage layer, and the steel flower pipe passes through the crushed stone drainage layer and extends into the foam lightweight soil.
4. The existing high and steep slope roadbed widening structure as claimed in claim 3, characterized in that: The gravel drainage layer is connected to the drainage layer drainage pipe, one end of the drainage layer drainage pipe passes through the protection wall and extends to the outside of the filling area, and the other end is located in the filling area and connected to the gravel drainage layer.
5. The existing high and steep slope roadbed widening structure as claimed in claim 1, characterized in that: A geotextile is laid between the foam lightweight soil and the leveling layer, and a geogrid is laid on the top surface and inside of the foam lightweight soil below the geotextile, and the geogrid extends into the existing roadbed.
6. The existing high and steep slope roadbed widening structure as claimed in claim 1 or 5, characterized in that: The vertical cross-section of the guardrail base is L-shaped, and the top surface of the guardrail base with a higher vertical height is connected to the guardrail; the side of the guardrail base with a lower vertical height is arranged close to the existing road surface and is lined under the widened road surface.
7. The existing high and steep slope roadbed widening structure as claimed in claim 6, characterized in that: A graded crushed stone blind ditch is arranged between the side of the guardrail base with a lower vertical height and the widened road surface, and the graded crushed stone blind ditch is connected to the outside through a blind ditch drainage pipe that penetrates the guardrail base.
8. The existing high and steep slope roadbed widening structure as claimed in claim 1, characterized in that: The steel flower tube is circumferentially injected with slurry inside and outside.
9. The existing high and steep slope roadbed widening structure according to claim 1 or 8, characterized in that: The steel flower tubes are provided in a plurality of groups distributed along the longitudinal direction of the highway, and each group includes a plurality of steel flower tubes arranged at intervals in the transverse direction of the highway.
10. The existing high and steep slope roadbed widening structure as claimed in claim 1, characterized in that: The bottom of the side plate is connected to the bottom plate to form a structure with an L-shaped vertical section, and one end of the bottom plate away from the existing roadbed extends to the outside of the side plate.