Building structure for drainage butt joint of heating and ventilation equipment

By designing the building structure for drainage docking of HVAC equipment, using the sliding connection of slide chutes and sliders and the adjustment of support columns, the problem of inconvenient fixing methods in the existing technology is solved, efficient pipeline installation and disassembly, and protection is achieved The components buffer external forces, improving the fixing effect and safety of the pipe.

CN222044784UInactive Publication Date: 2024-11-22HEBEI RUNYUN CONSTRUCTION ENGINEERING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420658719.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-01
Publication Date
2024-11-22
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

When laying pipes, existing HVAC equipment relies on a large number of bolts to fix it, resulting in inconvenient installation and disassembly.

Method used

A building structure for drainage docking of HVAC equipment was designed, using main body panels, second mounting plates, mounting grooves, slide chutes, slide blocks, support columns and protective components, and the sliding connection between slide chutes and slide blocks is used to support columns. Adjustment enables the fixation of the pipe, reduces the use of bolts, and buffers external forces through protective plates, springs and dampers.

Benefits of technology

It greatly reduces the number of bolts used, improves the installation and disassembly efficiency of pipelines, and provides effective protection for pipelines to prevent the direct effect of external forces on the pipelines.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222044784U_ABST
    Figure CN222044784U_ABST
Patent Text Reader

Abstract

The building structure comprises a main body plate, second mounting plates are fixedly mounted on the upper side and the lower side of the main body plate, mounting grooves are formed in the second mounting plates, sliding blocks are slidably connected into sliding grooves, limiting plates are fixedly mounted on the front faces of the sliding blocks, and the limiting plates are fixedly mounted on the front faces of the sliding blocks. Supporting columns are fixedly installed on the front faces of the limiting plates, and the pipelines are located between the adjacent supporting columns. According to the building structure for drainage butt joint of the heating and ventilation equipment, when the main body plate is installed, the main body plate can be installed on a wall through cooperation of the second installation plates and the installation grooves on the upper side and the lower side of the main body plate and self-tapping screws, and after installation, a pipeline is placed between the vertically-adjacent supporting columns, so that fixing of the pipeline can be completed; according to the fixing mode, all the pipelines are fixed at the same time through the main body plate and the supporting columns, the using number of self-tapping screws is greatly reduced, and therefore the pipeline mounting and dismounting efficiency is greatly improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of HVAC equipment, in particular to a building structure for drainage docking of HVAC equipment. Background Art

[0002] As an important part of the construction field, HVAC equipment plays an increasingly important role in modern buildings. HVAC equipment mainly includes heating equipment, ventilation equipment and air conditioning equipment. Heating equipment is used to provide a warm indoor environment. Common heating equipment includes electric heaters, gas radiators, floor heating, etc.

[0003] When HVAC equipment is in use, HVAC pipes need to be laid. When laying the HVAC pipes, the pipes need to be fixed to the wall. The existing fixing method is generally through a pipe fixing frame, which uses a pipe fixing frame with self-tapping screws to fix the pipes to the wall. This fixing method requires the use of a large number of bolts, which makes installation and disassembly very inconvenient.

[0004] To this end, the utility model provides a building structure for HVAC equipment drainage docking to solve the above problems. Utility Model Content

[0005] In view of the deficiencies in the prior art, the utility model provides a building structure for HVAC equipment drainage docking, which solves the above problems.

[0006] To achieve the above objectives, the utility model is implemented through the following technical solutions: a building structure for HVAC equipment drainage docking, including a main body plate, second mounting plates are fixedly installed on the upper and lower sides of the main body plate, a mounting groove is opened inside the second mounting plate, a mounting assembly is arranged on the front of the main body plate, a pipe is arranged on the front of the mounting assembly, a fixing assembly is arranged on the front of the pipe, a protective assembly is arranged on the front of the fixing assembly, the mounting assembly includes a slide groove, a slider is slidably connected inside the slide groove, a limit plate is fixedly installed on the front of the slider, a support column is fixedly installed on the front of the limit plate, and the pipe is located between adjacent support columns.

[0007] Preferably: a second bolt is screwed on the back of the slider, the nut diameter of the second bolt is larger than the width of the slide groove, the nut of the second bolt is attached to the back of the main plate, and the limit plate is attached to the front of the main plate.

[0008] By adopting the above technical solution, the sliding block can be fixed at any position in the sliding groove by tightening the second bolt.

[0009] Preferably, the pipeline is located between two parallel supporting columns on the left and right, and a pipeline is provided between every two adjacent supporting columns on the upper and lower sides.

[0010] By adopting the above technical solution, multiple pipelines are supported up and down by supporting columns.

[0011] Preferably, the fixing assembly comprises a fixing plate, a first mounting plate is fixedly mounted on both upper and lower sides of the fixing plate, the first mounting plate is fixedly connected to the main plate by a first bolt, and the fixing plate is located in front of the support column and the pipeline.

[0012] By adopting the above technical solution, the front side of the pipeline is fixed by the fixing plate.

[0013] Preferably, the protective assembly comprises a protective plate, a damper is fixedly mounted on the back of the protective plate, the damper is fixedly mounted on the front side of the main body plate of the fixed plate, a spring is fixedly mounted between the protective plate and the fixed plate, and the spring is sleeved on the outside of the damper.

[0014] By adopting the above technical solution, the force acting on the protective plate can be buffered by the spring and the damper.

[0015] Preferably, a transparent plate is embedded inside the protective plate, the front and rear sides of the transparent plate are respectively flush with the front and rear sides of the protective plate, and the transparent plate is a transparent acrylic plate.

[0016] By adopting the above technical solution, the internal pipeline conditions can be easily observed through the protective plate through the transparent acrylic plate.

[0017] Beneficial Effects

[0018] The utility model provides a building structure for HVAC equipment drainage connection. Compared with the prior art, it has the following beneficial effects:

[0019] 1. The building structure for the drainage docking of the HVAC equipment can be installed on the wall through the second mounting plates and mounting grooves on the upper and lower sides of the main plate and self-tapping screws. After installation, the pipes can be fixed by placing them between the upper and lower adjacent support columns. This fixing method fixes all the pipes at the same time through the main plate and the support column, which greatly reduces the number of self-tapping screws used, thereby greatly improving the efficiency of pipe installation and disassembly.

[0020] 2. The building structure for drainage connection of HVAC equipment, when the pipeline is subjected to external force, the force will first act on the protective plate. The spring and damper behind the protective plate can absorb and buffer the force acting on the protective plate, thereby greatly reducing the force acting on the pipeline, thereby achieving the protection effect of the pipeline. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] In order to more clearly illustrate the implementation scheme of the utility model or the technical scheme in the prior art, the drawings required for use in the implementation scheme or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some implementation schemes of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.

[0022] Figure 1 It is a three-dimensional diagram of the external structure of the utility model;

[0023] Figure 2 This is a three-dimensional diagram of the disassembled structure of the protection component of the utility model;

[0024] Figure 3 It is a three-dimensional diagram of the internal structure of the utility model;

[0025] Figure 4 This is an enlarged front structural view of the installation assembly of the utility model;

[0026] Figure 5 It is an enlarged view of the back structure of the installation component of the utility model.

[0027] In the figure: 1. main plate; 2. protection assembly; 21. protection plate; 22. transparent plate; 23. damper; 24. spring; 3. fixing assembly; 31. fixing plate; 32. first mounting plate; 33. first bolt; 4. mounting assembly; 41. support column; 42. limit plate; 43. slider; 44. slide groove; 45. second bolt; 5. second mounting plate; 6. mounting groove; 7. pipeline. DETAILED DESCRIPTION

[0028] It should be noted that in the description of the embodiments of the present application, the terms "front, rear", "left, right", "up, down", etc. indicating directions or positional relationships are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present application. The terms "install", "connect", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be a connection between the two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present application can be understood according to specific circumstances.

[0029] The present application is further described in detail below through drawings and examples.

[0030] Reference Figures 1 to 5The embodiment of the present application provides a building structure for drainage docking of HVAC equipment, including a main body plate 1, second mounting plates 5 are fixedly installed on the upper and lower sides of the main body plate 1, and a mounting groove 6 is opened inside the second mounting plate 5. A mounting component 4 is arranged on the front of the main body plate 1, a pipe 7 is arranged on the front of the mounting component 4, a fixing component 3 is arranged on the front of the pipe 7, and a protective component 2 is arranged on the front of the fixing component 3. The mounting component 4 includes a slide groove 44, and a slider 43 is slidably connected inside the slide groove 44. A limit plate 42 is fixedly installed on the front of the slider 43, and a support column 41 is fixedly installed on the front of the limit plate 42. The pipe 7 is located between adjacent support columns 41.

[0031] The back of the slider 43 is screwed with a second bolt 45 , the nut diameter of the second bolt 45 is larger than the width of the slide slot 44 , the nut of the second bolt 45 fits on the back of the main plate 1 , and the limiting plate 42 fits on the front of the main plate 1 .

[0032] The pipeline 7 is located between two parallel support columns 41 on the left and right, and a pipeline 7 is provided between every two adjacent support columns 41 on the upper and lower sides.

[0033] In this embodiment, when fixing the pipes 7, the main plate 1 is installed at the position where multiple pipes 7 need to be fixed. When the main plate 1 is installed, it can be installed on the wall through the second mounting plates 5 and the mounting grooves 6 on the upper and lower sides thereof in combination with self-tapping screws. After installation, the pipes 7 can be fixed by placing them between the upper and lower adjacent support columns 41. This fixing method fixes all the pipes 7 at the same time through the main plate 1 and the support columns 41. This method greatly reduces the number of self-tapping screws used, thereby greatly improving the efficiency of installing and removing the pipes 7; and when the pipes 7 are fixed through the support columns 41, when it is necessary to fix pipes 7 of different diameters, the fixation of the slider 43 can be released by loosening the second bolt 45, and the slider 43 can be slid inside the slide groove 44 to achieve adjustment of the position of the support column 41. By adjusting the position of the support column 41, it can be achieved that when facing pipes 7 of different diameters, they can be clamped and fixed by the support column 41.

[0034] Reference Figures 1 to 5 In one aspect of the present embodiment, the fixing assembly 3 includes a fixing plate 31, and a first mounting plate 32 is fixedly mounted on both upper and lower sides of the fixing plate 31. The first mounting plate 32 is fixedly connected to the main plate 1 by a first bolt 33, and the fixing plate 31 is located in front of the support column 41 and the pipe 7.

[0035] The protection component 2 includes a protection plate 21 , a damper 23 is fixedly installed on the back of the protection plate 21 , and the damper 23 is fixedly installed on the main body plate 1 of the fixing plate 31 . A spring 24 is fixedly installed between the front protection plate 21 and the fixing plate 31 , and the spring 24 is sleeved on the outside of the damper 23 .

[0036] A transparent plate 22 is embedded in the protective plate 21 . The front and rear sides of the transparent plate 22 are flush with the front and rear sides of the protective plate 21 , respectively. The transparent plate 22 is a transparent acrylic plate.

[0037] In this embodiment, after the pipe 7 is fixed, the fixing plate 31 can be installed on the front of the main plate 1 by the first bolt 33 and the first mounting plate 32, and after installation, the fixing plate 31 is located in the front of the support column 41 and the pipe 7, and the front of the pipe 7 is fixed and limited by the fixing plate 31, so that the fixing effect of the pipe 7 is better, and a protective plate 21 is installed in front of the fixing plate 31. When the pipe 7 is subjected to external force, the force will first act on the protective plate 21. The spring 24 and the damper 23 behind the protective plate 21 can absorb and buffer the force acting on the protective plate 21, so that the force acting on the pipe 7 can be greatly reduced, thereby achieving a protective effect on the pipe 7.

[0038] Working principle: when fixing the pipes 7, the main plate 1 is installed at the position where multiple pipes 7 need to be fixed. When the main plate 1 is installed, it can be installed on the wall through the second mounting plates 5 and the mounting grooves 6 on the upper and lower sides thereof with self-tapping screws. After installation, the pipes 7 are placed between the upper and lower adjacent support columns 41 to complete the fixing of the pipes 7. This fixing method fixes all the pipes 7 at the same time through the main plate 1 and the support columns 41. This method greatly reduces the number of self-tapping screws used, thereby greatly improving the efficiency of installing and removing the pipes 7; and when fixing the pipes 7 through the support columns 41, when it is necessary to fix pipes 7 of different diameters, the fixation of the slider 43 can be released by loosening the second bolt 45, and the slider 43 can be slid in the slide groove 44 to adjust the position of the support column 41. By adjusting the position of the support column 41, it can be achieved that when facing pipes 7 of different diameters, they can be clamped and fixed by the support column 41. After the pipe 7 is fixed, the fixing plate 31 can be installed on the front of the main plate 1 by the first bolt 33 and the first mounting plate 32. After the installation, the fixing plate 31 is located on the front of the support column 41 and the pipe 7. The front of the pipe 7 is fixed and limited by the fixing plate 31, so that the fixing effect of the pipe 7 is better, and a protective plate 21 is installed in front of the fixing plate 31. When the pipe 7 is subjected to external force, the force will first act on the protective plate 21. The spring 24 and the damper 23 behind the protective plate 21 can absorb and buffer the force acting on the protective plate 21, so that the force acting on the pipe 7 can be greatly reduced, thereby achieving a protective effect on the pipe 7.

[0039] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.

[0040] Although the embodiments of the present application have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present application, and that the scope of the present application is defined by the appended claims and their equivalents.

Claims

1. A building structure for connecting drainage of HVAC equipment, comprising a main plate (1), Features: A second mounting plate (5) is fixedly mounted on both upper and lower sides of the main body plate (1), a mounting groove (6) is provided inside the second mounting plate (5), a mounting assembly (4) is arranged on the front of the main body plate (1), a pipe (7) is arranged on the front of the mounting assembly (4), a fixing assembly (3) is arranged on the front of the pipe (7), a protective assembly (2) is arranged on the front of the fixing assembly (3), the mounting assembly (4) comprises a slide groove (44), a slider (43) is slidably connected inside the slide groove (44), a limit plate (42) is fixedly mounted on the front of the slider (43), a support column (41) is fixedly mounted on the front of the limit plate (42), and the pipe (7) is located between adjacent support columns (41).

2. A building structure for HVAC equipment drainage docking according to claim 1, Features: A second bolt (45) is screwed onto the back of the slider (43), the nut diameter of the second bolt (45) is larger than the width of the slide groove (44), the nut of the second bolt (45) is fitted onto the back of the main plate (1), and the limit plate (42) is fitted onto the front of the main plate (1).

3. A building structure for HVAC equipment drainage docking according to claim 1, Features: The pipeline (7) is located between two parallel support columns (41) on the left and right, and a pipeline (7) is provided between every two adjacent support columns (41) on the upper and lower sides.

4. A building structure for HVAC equipment drainage docking according to claim 1, Features: The fixing assembly (3) comprises a fixing plate (31), and first mounting plates (32) are fixedly mounted on both upper and lower sides of the fixing plate (31). The first mounting plate (32) is fixedly connected to the main plate (1) via first bolts (33). The fixing plate (31) is located in front of the support column (41) and the pipeline (7).

5. A building structure for HVAC equipment drainage docking according to claim 1, Features: The protection component (2) comprises a protection plate (21), a damper (23) is fixedly mounted on the back of the protection plate (21), the damper (23) is fixedly mounted on the front of the main body plate (1) of the fixing plate (31), a spring (24) is fixedly mounted between the protection plate (21) and the fixing plate (31), and the spring (24) is sleeved on the outside of the damper (23).

6. A building structure for HVAC equipment drainage docking according to claim 5, Features: A transparent plate (22) is embedded inside the protective plate (21), and the front and rear sides of the transparent plate (22) are respectively flush with the front and rear sides of the protective plate (21), and the transparent plate (22) is a transparent acrylic plate.