Tunnel passing structure passing through fault fracture zone
By setting up filling concrete and reinforced steel bar groups in the cavity of the fault crushing belt, the problem of damage to the tunnel structure by the fault crushing belt is solved, ensuring the safety and stable operation of the tunnel construction, and preventing blockage and landslides.
Patent Information
- Application Number
- CN202420705922.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-08
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2034-04-08
AI Technical Summary
The fault breaking zone has a great impact on the stability of the tunnel, resulting in easy damage to the tunnel structure, which may cause geological disasters such as blockage, landslides and sudden water surges, posing a threat to the safety of construction workers.
The cavity of the fault breaking belt is equipped with filled concrete, sprayed concrete layers and reinforced anchors, and reinforced steel bar groups are arranged along the length of the tunnel, including arc-shaped steel arch frames and connecting bars. They are fixed by locking anchors to form a reinforced structure Enhance the load bearing capacity of the tunnel surrounding rock.
Effectively reinforce the tunnel structure, ensure construction safety and stable operation, prevent the influx of filling in the fault breaking belt, avoid tunnel blockage and landslides, and improve the load-bearing capacity of surrounding rocks.
Smart Images

Figure CN222045764U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of tunnel engineering, in particular to a tunnel passage structure passing through a fault fracture zone. Background Art
[0002] Fault fracture zone is a strongly fractured area of rock containing fault breccia, broken rock, fault mud, etc. generated by faults. It has a certain width and extension length, which makes the surrounding rock mass lose its continuity and integrity. Fault fracture zone has a great influence on the stability of tunnels, can change the physical and mechanical properties of rock mass, and reduce the bearing capacity of surrounding rock. In tunnel engineering, especially hydraulic tunnel engineering, when the tunnel passes through the fault fracture zone, the filling material in the fault fracture zone will flow to the tunnel clearance surface, causing tunnel blockage and support structure damage, and even causing tunnel collapse, large deformation, sudden water inrush and other major construction geological disasters, which will bring difficulties to on-site support work and pose a serious threat to the life safety of construction personnel. Utility Model Content
[0003] The purpose of the utility model is to overcome the deficiencies of the above-mentioned prior art and provide a tunnel passage structure for passing through a fault fracture zone, which can solve the problem that the tunnel structure is easily damaged when the tunnel passes through the fault fracture zone.
[0004] To this end, the utility model adopts the following technical solutions:
[0005] A tunnel passage structure for passing through a fault fracture zone. When the tunnel passes through the fault fracture zone, a fault fracture zone cavity is formed on one side of the tunnel, including a baffle fixed at the junction of the tunnel and the fault fracture zone cavity. One side of the baffle is provided with filling concrete for filling the fault fracture zone cavity, and the other side of the baffle is provided with a concrete layer sprayed on the inner wall of the tunnel. A plurality of reinforcing anchor rods extending out of the tunnel are provided in the circumference of the concrete layer. A reinforcing steel bar group is also fixed to the inner wall of the concrete layer. Locking anchor rods are respectively provided at the bottom ends of both sides of the reinforcing steel bar group. The reinforcing steel bar group is arranged along the length direction of the tunnel and passes through the fault fracture zone.
[0006] On the basis of adopting the above technical solutions, the present invention can also adopt the following further technical solutions, or use these further technical solutions in combination:
[0007] The reinforcing steel bar group includes an arc-shaped steel arch frame fixed to the inner wall of the concrete layer, and a plurality of arc-shaped steel arch frames are arranged along the length direction of the tunnel. The arch feet at both ends of the arc-shaped steel arch frame are respectively provided with locking foot anchor rods, and the locking foot anchor rods are located below the baffle.
[0008] The reinforcement steel bar group also includes connecting bars fixedly connected between a plurality of arc-shaped steel arch frames, and a plurality of connecting bars are arranged along the circumference of the arc-shaped steel arch frames.
[0009] The filling concrete is composed of several layers of backfill concrete, each layer of backfill concrete is 20-30 cm thick, and correspondingly, the baffle is composed of several baffle segments spliced from bottom to top, and the height of the baffle segment depends on the thickness of the backfill concrete.
[0010] The spacing between the reinforcing anchor rods located in the cavity of the fault fracture zone is closer than the spacing between the other reinforcing anchor rods, and the length of the reinforcing anchor rod inserted into the filling concrete is greater than the thickness of the filling concrete at the insertion position.
[0011] The distance between two adjacent arc-shaped steel arch frames in the length direction of the tunnel depends on the distance between them and the cavity of the fault fracture zone. The closer to the cavity of the fault fracture zone, the smaller the distance between the two adjacent arc-shaped steel arch frames in the length direction of the tunnel.
[0012] Compared with the prior art, the utility model has the following advantages and beneficial effects: a tunnel passage structure that passes through a fault fracture zone is proposed, by setting filling concrete in the cavity of the fault fracture zone, the filling concrete and the concrete layer sprayed on the inner wall of the tunnel are combined with reinforcement anchor rods, and reinforcing steel bar groups and locking anchor rods are set at the same time, so as to effectively reinforce the tunnel surrounding rock and the fault fracture zone, thereby ensuring safe passage during the tunnel construction period and structural stability during the operation period. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 This is a schematic cross-sectional view of the tunnel when the fault fracture zone of the utility model is not processed.
[0014] Figure 2 It is a schematic diagram of the cross-sectional structure of the utility model.
[0015] Figure 3 For this utility model Figure 2 Schematic diagram of the cross-sectional structure at AA in the middle. DETAILED DESCRIPTION
[0016] In order to enable those skilled in the art to better understand the technical solution of the present invention, the preferred implementation scheme of the present invention is described below in conjunction with specific embodiments. Examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent elements with the same or similar functions. However, it should be understood that the accompanying drawings are only used for illustrative purposes and cannot be understood as limitations on the present invention. In order to better illustrate the present embodiment, some parts of the accompanying drawings may be omitted, enlarged or reduced, and do not represent the size of the actual product. For those skilled in the art, it is understandable that some well-known structures and their descriptions in the accompanying drawings may be omitted, and the positional relationship described in the accompanying drawings is only used for illustrative purposes and cannot be understood as limitations on the present invention.
[0017] The present invention is further described below in conjunction with the accompanying drawings and embodiments, but they are not intended to limit the present invention.
[0018] The utility model provides a tunnel passage structure for passing through a fault fracture zone. When the tunnel passes through the fault fracture zone, a fault fracture zone cavity is formed on one side of the tunnel, including a baffle 2 fixed at the junction of the tunnel and the fault fracture zone cavity, one side of the baffle 2 is provided with a filling concrete 1 for filling the fault fracture zone cavity, the other side of the baffle 2 is provided with a concrete layer 3 sprayed on the inner wall of the tunnel, a plurality of reinforcing anchor rods 4 extending out of the tunnel are provided around the concrete layer 3, a reinforcing steel bar group 6 is also fixed to the inner wall of the concrete layer 3, locking anchor rods 5 are respectively provided at the bottom ends of both sides of the reinforcing steel bar group 6, and the reinforcing steel bar group 6 is arranged along the length direction of the tunnel and passes through the fault fracture zone.
[0019] The filling concrete 1 is composed of several layers of backfill concrete, each layer of which is 20-30 cm thick. Accordingly, the baffle 2 is composed of several baffle segments 21 spliced from bottom to top, and the height of the baffle segment 21 depends on the thickness of the backfill concrete.
[0020] In this embodiment, both the filling concrete 1 and the concrete layer 3 use C30 concrete.
[0021] During the tunnel excavation process, a flexible support system is formed by spraying C30 concrete on the inner wall of the tunnel and applying prestressed anchor support to ensure the overall stability of the tunnel; Figure 1 As shown, when the tunnel is excavated to the fault fracture zone, the fault fracture zone filling in the fault fracture zone will flow to the tunnel clearance surface to form a fault fracture zone cavity. At this time, it is necessary to manually clean the fault fracture zone filling in the fault fracture zone cavity.
[0022] In this embodiment, the baffle section 21 is a 3 mm thick steel plate.
[0023] After the filling material of the fault fracture zone in the cavity of the fault fracture zone is cleaned, the baffle segment 21 is fixed at the junction of the cavity of the fault fracture zone and the tunnel as the backfill boundary of the filling concrete 1, and concrete is sprayed to the bottom of the cavity of the fault fracture zone to perform layered backfilling. The thickness of the backfilling concrete for each layered backfilling is 20-30 cm, and the concrete setting time is 2 hours. After each layer of backfilling concrete is completed, a baffle segment 21 is superimposed on the baffle segment 21, and then the next layer of backfilling concrete is sprayed to prevent the backfilling concrete from flowing out of the cavity of the fault fracture zone before solidification, until the filling concrete 1 is completed and the entire cavity of the fault fracture zone is filled. At this time, a number of baffle segments 21 form a baffle 2; Figure 2As shown, the dotted line in the filling concrete 1 divides the filling concrete 1 into four layers of backfill concrete. Accordingly, the baffle 2 has four baffle segments 21. The dotted line is only used as an example. During actual construction, the number of layers of the filling concrete 1 and the number of superpositions of the baffle segments 21 are set according to the site conditions.
[0024] C30 concrete is sprayed on the inner wall of the tunnel passing through the cavity area of the fault fracture zone (including the baffle 2 filling the inside of the tunnel) to form a concrete layer 3, and then prestressed anchor rods (i.e., reinforcement anchor rods 4) are applied.
[0025] The spacing between the reinforcing anchor rods 4 located in the cavity of the fault fracture zone is closer than the spacing between the other reinforcing anchor rods 4, and the length of the reinforcing anchor rod 4 inserted into the filling concrete 1 is greater than the thickness of the filling concrete 1 at the insertion position.
[0026] By combining the reinforcement anchor rod 4 with the filling concrete 1, the concrete layer 3 and the baffle 2, the area where the filling concrete 1 is located and the surrounding rock of the tunnel are transformed into an integral bearing structure.
[0027] The reinforcing steel bar group 6 includes an arc-shaped steel arch frame 61 fixed to the inner wall of the concrete layer 3. A plurality of arc-shaped steel arch frames 61 are arranged along the length direction of the tunnel. Locking foot anchor rods 5 are respectively provided at the arch feet at both ends of the arc-shaped steel arch frame 61, and the locking foot anchor rods 5 are located below the baffle 2.
[0028] The reinforcement steel bar group 6 further includes connecting bars 62 fixedly connected between a plurality of arc-shaped steel arch frames 61 , and a plurality of connecting bars 62 are arranged along the circumference of the arc-shaped steel arch frames 61 .
[0029] The distance between two adjacent arc-shaped steel arch frames 61 in the length direction of the tunnel depends on the distance between them and the cavity of the fault fracture zone. The closer to the cavity of the fault fracture zone, the smaller the distance between two adjacent arc-shaped steel arch frames 61 in the length direction of the tunnel.
[0030] In this embodiment, the arc-shaped steel arch frame 61 is made of H125 steel arch frame, and the connecting rib 62 is made of No. 14 I-beam steel.
[0031] like Figure 3 As shown, the spacing between two adjacent arc-shaped steel arch frames 61 in the cavity area of the fault shattering zone is 0.6m. In the interactive tunnel section where the tunnel is far away from the cavity of the fault shattering zone, the spacing between two adjacent arc-shaped steel arch frames 61 increases to 1.3m. At a distance farther from the cavity of the fault shattering zone, the spacing between two adjacent arc-shaped steel arch frames 61 increases to 2.0m. After the tunnel is completely away from the fault shattering zone area and it is ensured that there are no other safety issues, it can be considered to stop supporting the arc-shaped steel arch frames 61.
[0032] According to the description and drawings of the utility model, those skilled in the art can easily manufacture or use the tunnel passage structure of the utility model for crossing a fault fracture zone, and can produce the positive effects recorded in the utility model.
[0033] It should be noted that the terms "including" and "having" and any variations thereof in the specification and claims of the present utility model and the above-mentioned drawings are intended to cover non-exclusive inclusions. The terms "installed", "set", "provided with", "connected", "connected", and "socketed" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral structure; it can be a mechanical connection, or an electrical connection; it can be directly connected, or indirectly connected through an intermediate medium, or it can be an internal connection between two mechanisms, elements or components. For those of ordinary skill in the art, the specific meanings of the above terms in the present utility model can be understood according to the specific circumstances.
[0034] In the description of the present invention, it should be understood that the terms "one end", "the other end", "outside", "inside", "horizontal", "end", "length", "outer end", "left", "right" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the mechanism or element referred to must have a specific position, be constructed and operated in a specific position, and therefore cannot be understood as a limitation on the present invention. The terms "first" and "second" are also used only for the simplicity of description, and do not indicate or imply relative importance.
[0035] Furthermore, in practicing the claims of the present invention, those skilled in the art may understand and affect variations to the disclosed embodiments by studying the drawings, disclosure, and appended claims. In addition, in the claims and the specification, words such as "comprises", "comprising", etc. do not exclude other elements or steps, and non-plural nouns do not exclude their plural forms.
[0036] The above is only a preferred embodiment of the present invention and is not intended to limit the scope of implementation of the present invention. That is, all equivalent changes and modifications made according to the present invention are covered by the scope of the claims of the present invention and will not be listed one by one here.
Claims
1. A tunnel passage structure passing through a fault fracture zone, wherein when the tunnel passes through the fault fracture zone, a fault fracture zone cavity is formed on one side of the tunnel, characterized in that: The invention comprises a baffle (2) fixed at the junction of a tunnel and a cavity of a fault fracture zone, wherein one side of the baffle (2) is provided with filling concrete (1) for filling the cavity of the fault fracture zone, and the other side of the baffle (2) is provided with a concrete layer (3) sprayed on the inner wall of the tunnel, and the circumference of the concrete layer (3) is provided with a plurality of reinforcing anchor rods (4) extending out of the tunnel, and the inner wall of the concrete layer (3) is also fixed with a reinforcing steel bar group (6), and the bottom ends of both sides of the reinforcing steel bar group (6) are respectively provided with locking anchor rods (5), and the reinforcing steel bar group (6) is arranged along the length direction of the tunnel and passes through the fault fracture zone.
2. A tunnel passage structure for passing through a fault zone as claimed in claim 1, characterized in that: The reinforcing steel bar group (6) comprises an arc-shaped steel arch frame (61) fixed to the inner wall of the concrete layer (3), and a plurality of arc-shaped steel arch frames (61) are arranged along the length direction of the tunnel. The locking foot anchor rods (5) are respectively provided at the arch feet at both ends of the arc-shaped steel arch frame (61), and the locking foot anchor rods (5) are located below the baffle (2).
3. A tunnel passage structure for passing through a fault zone as claimed in claim 1, characterized in that: The reinforcing steel bar group (6) further comprises connecting bars (62) fixedly connected between the plurality of arc-shaped steel arch frames (61), and the plurality of connecting bars (62) are arranged along the circumference of the arc-shaped steel arch frames (61).
4. A tunnel passage structure for passing through a fault zone as claimed in claim 1, characterized in that: The filling concrete (1) is composed of several layers of backfill concrete, each layer of backfill concrete is 20 to 30 cm thick, and correspondingly, the baffle (2) is composed of several baffle segments (21) spliced from bottom to top, and the height of the baffle segment (21) depends on the thickness of the backfill concrete.
5. A tunnel passage structure for passing through a fault zone as claimed in claim 1, characterized in that: The spacing between the reinforcing anchor rods (4) located in the cavity of the fault fracture zone is closer than the spacing between the other reinforcing anchor rods (4), and the length of the reinforcing anchor rod (4) inserted into the filling concrete (1) is greater than the thickness of the filling concrete (1) at the insertion point.
6. A tunnel passage structure for passing through a fault zone as claimed in claim 2, characterized in that: The distance between two adjacent arc-shaped steel arch frames (61) in the tunnel length direction depends on the distance between them and the cavity of the fault fracture zone. The closer the distance to the cavity of the fault fracture zone is, the smaller the distance between the two adjacent arc-shaped steel arch frames (61) in the tunnel length direction is.