Quick connection sand prevention and water stop device

By using a combination of rubber seal and shield tail brush in the sand and waterproof device, combined with grease pipes to supplement grease, the leakage problem caused by the simple structure of the existing sand and waterproof device is solved, and a more efficient sand and waterproof effect is achieved, ensuring that Construction safety.

CN222045806UActive Publication Date: 2024-11-22THE THIRD CONSTRUCTION CO OF CCCC SECOND HARBOR ENGINEERING CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420875238.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-25
Publication Date
2024-11-22
Estimated Expiration
2034-04-25

AI Technical Summary

Technical Problem

The existing sand and waterproofing device has a simple structure. When the water volume is large, the sealing ring lacks a limit structure and is easily damaged by water pressure, resulting in leakage, especially at the arc-shaped working well tunnel doors.

Method used

Using a rubber seal and two shield tail brush sealing method, combined with the water stop device for inlet and outlet hole construction of the pipe and the shield tail brush water stop concept, the water stop effect is enhanced by replenishing grease by grease pipes, and the pipe is used to drive installation The good rubber sheet forms a reverse water stop device.

Benefits of technology

It effectively improves the sand prevention and water resistance effect, ensures that the mud does not leak during the ejection process, and enhances construction safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222045806U_ABST
    Figure CN222045806U_ABST
Patent Text Reader

Abstract

The utility model discloses a quick-connection sand prevention and water stop device, relates to the technical field of underground pipe jacking, and solves the problems that an existing sand prevention and water stop device is simple in structure and easy to leak. The device comprises a pre-buried tunnel portal steel ring, a steel pressing ring, a water stop plate, a flange plate, a steel plate cushion block, a grease pipe and two shield tail brushes. The pre-buried tunnel portal steel ring, the water stop plate, the flange plate and the steel plate cushion block are sequentially fixed to the edge of a tunnel portal opening from outside to inside through bolts. Two shield tail brushes are arranged in the tunnel portal in the axis direction. One end of the grease pipe is arranged at the position of a tunnel portal, and the other end is arranged between the two shield tail brushes; a steel pressing ring is arranged on the pre-buried tunnel portal steel ring. According to the sand prevention and water stop device, the concept of pipe jacking construction in-out hole water stop device and the concept of shield tail brush water stop of a shield tunneling machine are combined, sand prevention and water stop are conducted in the mode that one rubber seal and two shield tail brush seals are adopted, and the sand prevention and water stop effect is effectively improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of underground pipe jacking, in particular to a quick-connect sand-proof and water-stopping device. Background Art

[0002] During the underground pipe jacking construction in areas with great burial depth and abundant groundwater, leakage is very likely to occur in the starting and receiving stages, which poses a great safety hazard to the construction. Pipe jacking construction also requires waterproofing. Therefore, it is necessary to install a sand-proof and water-stopping device at the starting hole of the pipe jacking construction. However, the existing sand-proof and water-stopping device has a relatively simple structure. When the water volume is large, the sealing ring lacks a limiting structure. When the water pressure is large, the soft rubber is easily turned outward, causing leakage. When the working shaft door is arc-shaped, directly installing the water-stopping device is also prone to water leakage. Utility Model Content

[0003] In order to solve the problem that the existing sand-proof and water-stopping devices mentioned above are simple in structure and prone to leakage, the utility model proposes a quick-connect sand-proof and water-stopping device. The utility model combines the concepts of the water-stopping device for entering and exiting the tunnel during pipe jacking construction and the water-stopping device for the tail brush of the shield machine, and adopts a rubber seal plus two shield tail brush seals to prevent sand and stop water, which effectively improves the effect of sand-proof and water-stopping.

[0004] The utility model proposes a quick-connect sand and water-stopping device, which specifically comprises a pre-buried tunnel gate steel ring, a steel pressure ring, a water stop plate, a flange, a steel plate pad, a grease pipe and two shield tail brushes. The pre-buried tunnel gate steel ring, the water stop plate, the flange and the steel plate pad are sequentially fixed at the edge of the tunnel gate opening from outside to inside by bolts; two shield tail brushes are arranged in the tunnel gate along the axial direction; one end of the grease pipe is arranged at the tunnel gate opening position, and the other end is arranged between the two shield tail brushes; a steel pressure ring is arranged on the pre-buried tunnel gate steel ring.

[0005] Furthermore, the thickness of the flange is 20 mm.

[0006] Furthermore, the water stop plate is made of rubber and has a thickness of 20 mm.

[0007] Furthermore, the grease tube has a diameter of 25 mm.

[0008] Furthermore, the spacing between the shield tail brushes is 250 mm, and the distance between the shield tail brush close to the tunnel entrance and the tunnel entrance is 200 mm.

[0009] The beneficial effects of the quick-connect sand and water-stopping device described in the utility model are:

[0010] (1) The quick-connect anti-sand and water-stopping device described in the utility model combines the concepts of the water-stopping device for entering and exiting the tunnel during pipe jacking construction and the water-stopping device for the shield tail brush of the shield machine. It adopts a rubber seal plus two shield tail brush seals to prevent sand and water. The installed rubber plate is driven by the pipe jacking to form a reverse water-stopping device, which ultimately ensures that the mud breaks through the sealing structure during the jacking process.

[0011] (2) The quick-connect anti-sand and water-stopping device described in the utility model replenishes grease between two shield tail brushes through a grease pipe to enhance the water-stopping effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] The drawings constituting a part of the present application are used to provide a further understanding of the present invention. The illustrative embodiments of the present invention and the description thereof are used to explain the present invention and do not constitute an improper limitation on the present invention.

[0013] In the attached picture:

[0014] Figure 1 It is a structural schematic diagram of a quick-connect sand-proof and water-stopping device described in the utility model;

[0015] Among them: 1-embedded tunnel gate steel ring, 2-bolts, 3-steel pressure ring, 4-water stop plate, 5-flange, 6-steel plate gasket, 7-grease pipe, 8-shield tail brush, 9-tunnel gate. DETAILED DESCRIPTION

[0016] The specific implementation of the utility model is further described in detail below with reference to the accompanying drawings:

[0017] Specific implementation method 1: See Figure 1The embodiment described in this embodiment is a quick connection sand and water stopping device, which specifically includes a pre-buried tunnel gate steel ring 1, a steel pressure ring 3, a water stop plate 4, a flange 5, a plurality of steel plate pads 6, a plurality of grease pipes 7 and two shield tail brushes 8, wherein the water stop plate 4 and the shield tail brush 8 are annular structures; a plurality of steel plate pads 6 are arranged on the tunnel gate 9, a flange 5 is arranged on the plurality of steel plate pads 6, a water stop plate 4 is arranged on the flange 5, a pre-buried tunnel gate steel ring 1 is arranged on the water stop plate 4, and a bolt 2 is passed through the pre-buried tunnel gate steel ring 1, the water stop plate 4, the flange 5 and the steel plate pads 6 in sequence and the above four are fixed on the tunnel gate 9 At the edge of the tunnel entrance, a steel pressure ring 3 is arranged on the embedded tunnel portal steel ring 1; two shield tail brushes 8 are coaxially arranged along the inner axis direction of the tunnel portal 9; one end of the grease pipe 7 is arranged at the tunnel entrance of the tunnel portal 9, and the other end is arranged between the two shield tail brushes 8, and grease is replenished between the two shield tail brushes 8 through the grease pipe 7; when the jacking pipe enters the tunnel portal 9, the jacking pipe passes through the center of the water stop plate 4 and the shield tail brush 8, and the water stop plate 4 and the shield tail brush 8 are in contact with the jacking pipe to achieve sand prevention and water stopping, and the installed water stop plate 4 is driven by the pipeline jacking to form a reverse water stopping device, which finally ensures that the mud breaks through the sealing structure during the jacking process.

[0018] The thickness of the flange 5 is 20 mm.

[0019] The water stop plate 4 is made of rubber with a thickness of 20 mm. The rubber water stop plate 4 has a high elongation (greater than 300) and wear resistance, a hardness of 45-55, and a permanent deformation of no more than 10%.

[0020] The diameter of the grease tube 7 is 25 mm.

[0021] The distance between the heads of the two shield tail brushes 8 is 250 mm, and the distance between the shield tail brush 8 close to the opening of the tunnel door 9 and the opening of the tunnel door 9 is 200 mm.

[0022] After the shield tail brush 8 is installed, it is necessary to apply grease to the shield tail brush 8 by hand, including the following steps:

[0023] 1) A special tool, a small spatula, is required for hand grease application. The production method is as follows: a 5mm thick steel plate with a size of 50x200mm is used. The front end of the steel plate is made into a spade shape, and a handle about 200mm long is welded to the tail end.

[0024] 2) Before applying shield tail grease by hand, carefully check the shield tail brush 8, pull out all the binding wires on the shield tail brush 8, clean up the debris on the shield tail brush 8, and clean up the debris and dust in the groove between the shield tail brush 8. No water marks should be left.

[0025] 3) Clean the tool used to apply the shield tail brush 8. No dust, sand, debris, etc. should be left on the tool.

[0026] 4) Dip the spatula and rubber gloves in a proper amount of water or lubricating oil to prevent grease from sticking to the spatula and hands;

[0027] 5) It is strictly forbidden to step on the wire brush during the application process, otherwise it will easily cause the wire brush to deform, resulting in the wire brush and the pipe segment not fitting closely during the construction process, affecting the sealing effect;

[0028] 6) Rub the shield tail grease into a long strip with a diameter of about 6 cm, or a ball with a diameter of 4-6 cm. During the rubbing process, ensure that the gloves and grease are clean to prevent sand and dust from contaminating the gloves and grease.

[0029] 7) Start from the first wire brush at the bottom. Two people work together. One person uses a homemade shovel to pry open the wire, and the other person stuffs the rubbed grease into the wire brush. Use the shovel to stuff the grease to the bottom as much as possible, and tamp it with a wooden stick. Repeat 2 to 3 times until it covers the wire.

[0030] 8) The greasing positions are the gaps between the two spring plates and the wire brushes, the gaps between the four wire brushes, and the corners where the shield tail brush 8 is welded to the shield tail, which are not easily reached by machine grease.

[0031] 9) From bottom to top, apply grease to each wire brush to ensure that there is enough grease on the wire of each wire brush.

[0032] 10) After applying the first full circle, apply the second coat with a wire brush in the same manner, starting from the inside of the shield tail to the outside.

[0033] 11) Apply the grease to the triangular area where the wire brush meets the shield tail. Rub the grease into strips with a diameter of 4-6 cm. Use a spatula to press it into the triangular area and squeeze it tightly. The application range of the triangular area should be at least 3-5 cm.

[0034] 12) Fill each seam fully, fill it to the bottom, continuously and fully, and apply it until the surface of the wire brush is covered with grease. It is required that the entire circle of the shield tail brush 8 should not be missed. Apply about 1 to 1.5 barrels of hand-applied grease to the two shield tail brushes 8.

[0035] 13) After the workers finish painting, the technicians should check the coating effect of the shield tail brush 8. Each shield tail brush 8 should be checked layer by layer. The inspection standard is: filling to the bottom, continuous, full, and coating until the surface of the wire brush is covered with grease. If the inspection does not meet the standard, the workers are required to refill until it is qualified.

[0036] 14) After the shield tail brush 8 is greased, it should be covered with asbestos cloth in time to prevent various factors from destroying the integrity of the grease and preventing welding slag from falling and catching fire.

[0037] To summarize the above implementation cases, the quick-connect sand-proof and water-stopping device described in the utility model combines the concepts of the water-stopping device for entering and exiting the tunnel during pipe jacking construction and the water-stopping device of the shield tail brush of the shield machine, and adopts a rubber seal plus two shield tail brush seals to perform sand-proof and water-stopping. The installed rubber plate is driven by the pipe jacking to form a reverse water-stopping device, which ultimately ensures that the mud breaks through the sealing structure during the jacking process. The quick-connect sand-proof and water-stopping device described in the utility model replenishes grease between the two shield tail brushes 8 through the grease pipe 7 to enhance the water-stopping effect.

[0038] The specific embodiments described above further describe the purpose, technical solutions and beneficial effects of the utility model in detail. It should be understood that the above description is only a specific embodiment of the utility model and is not intended to limit the utility model. It can also be a reasonable combination of the features recorded in the above implementation methods. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.

Claims

1. A quick-connect sand and water-stopping device, characterized in that: The invention comprises a pre-buried tunnel gate steel ring (1), a steel pressure ring (3), a water stop plate (4), a flange (5), a plurality of steel plate gaskets (6), a plurality of grease pipes (7) and two shield tail brushes (8); the water stop plate (4) and the shield tail brush (8) are annular structures; the pre-buried tunnel gate steel ring (1), the water stop plate (4), the flange (5) and the steel plate gasket (6) are fixed in sequence from outside to inside at the edge of the tunnel gate (9) opening; two shield tail brushes (8) are coaxially arranged in the tunnel gate (9) along the axial direction; one end of the grease pipe (7) is arranged at the opening of the tunnel gate (9), and the other end is arranged between the two shield tail brushes (8); and a steel pressure ring (3) is arranged on the pre-buried tunnel gate steel ring (1).

2. The quick connection sand and water stopping device according to claim 1 is characterized in that: The thickness of the flange (5) is 20 mm.

3. The quick connection sand and water stopping device according to claim 1 is characterized in that: The water stop plate (4) is made of rubber and has a thickness of 20 mm.

4. The quick connection sand and water stopping device according to claim 1 is characterized in that: The diameter of the grease pipe (7) is 25 mm.

5. The quick connection sand and water stopping device according to claim 1 is characterized in that: The spacing between the shield tail brushes (8) is 250 mm, and the distance between the shield tail brush (8) close to the opening of the tunnel door (9) and the opening of the tunnel door (9) is 200 mm.