Filling system
By designing a refueling tank and calibration structure in the refueling system, online flow measurement was achieved, solving the problems of long calibration cycle and large accuracy error of external calibration flowmeters, and improving the metering and calibration accuracy of rocket propellant refueling.
Patent Information
- Application Number
- CN202420827219.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-19
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2034-04-19
AI Technical Summary
In the existing technology, the calibration cycle of externally calibrated flow meters is long, which affects the usage requirements during periods of intensive tasks. In addition, there is the problem of inconsistent calibration media. Differences in pipeline diameter, level gauge installation method and operating parameters between the external calibration system and the actual filling system lead to large accuracy errors.
Design a filling system including a filling tank, a filling passage structure, and a calibration structure. By directly installing the calibration structure in the filling system, online metering is performed using the flow meter of the filling passage structure. The calibration medium is consistent with the actual medium, reducing system errors. Furthermore, the calibration accuracy is improved by combining volumetric and gravimetric methods.
It shortens the flow meter calibration cycle, meets the usage requirements during intensive missions, improves the metering accuracy of rocket propellant loading, reduces system errors, and solves the problem of low calibration accuracy in existing technologies.
Smart Images

Figure CN222047431U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of flow meter calibration, in particular to a filling system. Background Art
[0002] The flowmeter is a key device for measuring the filling volume of the rocket filling system. The rocket medium filling volume is measured by the rocket tank liquid level and the flowmeter of the ground filling system at the launch site. The medium filling volume consists of the basic filling volume and the supplementary filling volume. The basic filling volume is determined by the liquid level measurement of the rocket tank, and the supplementary filling volume is obtained by the ground flowmeter. The accuracy of the supplementary filling volume is limited by the measurement accuracy of the ground flowmeter.
[0003] Accurate measurement of the filling volume is a key factor in ensuring the successful launch of a rocket. At present, in order to ensure the accuracy of each flow meter in the conventional filling system of each launch site, the flow meter is calibrated once a year. Generally, the flow meter is disassembled and sent to a unit with calibration qualifications for calibration, or the flow meter is calibrated by using the online filling tank level measurement and reflux.
[0004] The use of externally calibrated flow meters has not only a long calibration cycle, which seriously affects the use needs during intensive missions, but also the problem of inconsistent calibration media. The medium in the external standard system is water, while the medium in the actual filling system is various conventional media. In addition, the system pipeline diameter of the external standard flow meter, the installation method of the liquid level meter, and the operating parameters are all different from the current filling system at the launch site. These all lead to large systematic errors in the accuracy of the external standard flow meter. Utility Model Content
[0005] Therefore, the technical problem to be solved by the utility model is that the use of an externally calibrated flow meter has a long calibration cycle, which seriously affects the use requirements during intensive tasks. There is also a problem of inconsistent calibration media. The medium in the external standard system is water, and the medium in the actual filling system is various conventional media. In addition, the system pipeline diameter of the external standard flow meter, the installation method of the liquid level meter, and the operating parameters are all different from the current filling system of the launch site. These all make the accuracy of the external standard flow meter have a large systematic error.
[0006] To this end, the utility model provides a filling system, comprising:
[0007] A filling tank, suitable for storing a medium to be filled, and a first liquid outlet is provided on the filling tank;
[0008] a filling passage structure, wherein a liquid input end of the filling passage structure is connected to the first liquid outlet, and a liquid output end of the filling passage structure is suitable for being connected to a propulsion device;
[0009] A verification structure, wherein a liquid input end of the verification structure is also connected to a liquid output end of the filling passage structure;
[0010] Wherein, the filling passage structure also includes a plurality of flow meters; the filling passage structure has a working state that allows the medium to flow through the flow meter to the verification structure, so that the verification structure receives the medium in the filling tank to verify the metering accuracy of the flow meter.
[0011] Optionally, the above verification structure includes:
[0012] A calibration tank, wherein the calibration tank is provided with a liquid inlet and outlet;
[0013] A liquid level meter, which is arranged on the calibration tank and is suitable for detecting the liquid level in the calibration tank;
[0014] A recording device is used to record the number of flow pulses of the flow meter.
[0015] Optionally, the above verification structure further includes:
[0016] A weighing piece is arranged at the bottom of the calibration tank.
[0017] Optionally, the filling tank is further provided with a first liquid inlet; the filling passage structure comprises a first pipeline and a second pipeline;
[0018] The verification structure also includes:
[0019] A switching member, wherein the switching member is provided with at least three communication ports;
[0020] a third pipeline, wherein one end of the third pipeline close to the calibration tank is connected to the first liquid inlet;
[0021] Among them, three of the at least three connecting ports on the reversing member are respectively connected to the liquid inlet and outlet, an end of the third pipeline away from the filling tank and the first pipeline.
[0022] Optionally, the first pipeline mentioned above includes:
[0023] A first pipeline, one end of which is connected to the first liquid outlet of the filling tank, and the other end of which is connected to both the verification structure and the propulsion device;
[0024] And connected in series on the first pipeline in sequence along the flow direction of the medium: a filling power component, a first large flow meter and a second large flow meter; the filling power component can extract the medium in the filling tank and transport it through the first large flow meter and the second large flow meter to the propulsion device or the verification structure.
[0025] Optionally, the first pipeline includes:
[0026] a first valve body, the first valve body being arranged at one end of the first pipeline close to the filling tank;
[0027] A second valve body, wherein two second valve bodies are provided, and the two second valve bodies are respectively arranged on the first pipelines on both sides of the filling power component;
[0028] A third valve body is arranged on a first pipeline at one end of the second large flow meter away from the filling power component.
[0029] Optionally, the second pipeline includes:
[0030] A second pipeline, one end of which is arranged on the first pipeline on the side of the second large flow meter close to the filling power part; the other end of which is arranged on the side of the third valve body away from the filling power part;
[0031] And a first small flow meter and a second small flow meter are sequentially connected in series on the second pipeline along the flow direction of the medium; the filling power component can extract the medium in the filling tank and flow it through the first small flow meter and the second small flow meter to the propulsion device or the verification structure.
[0032] Optionally, the second pipeline includes:
[0033] A fourth valve body is arranged on a side of the second small flow meter away from the filling power component to control the opening and closing of the second pipeline.
[0034] Optionally, the first pipeline includes:
[0035] A fifth valve body is arranged at one end of the first pipeline close to the verification structure.
[0036] Optionally, the third pipeline includes:
[0037] a third pipe, one end of which is connected to one of the communication ports of the reversing member, and the other end of which is connected to the first liquid inlet of the filling tank;
[0038] and a pipeline signal device, a sixth valve body and a seventh valve body which are sequentially connected in series on the third pipeline along the conveying direction of the medium, wherein the pipeline signal device is used to detect a flow signal of the medium in the pipeline;
[0039] The sixth valve body and the seventh valve body are suitable for opening and closing the third pipeline.
[0040] The technical solution provided by the utility model has the following advantages:
[0041] 1. The utility model provides a filling system, including a filling tank, a filling passage structure and a verification structure, wherein the inner shell of the filling tank stores a medium to be filled, and the medium to be filled is a propellant, which is used to be filled into the inside of a propulsion device, and the propulsion device can be a rocket, etc.; the medium can be filled through an additional liquid inlet on the filling tank; a first liquid outlet is provided on the filling tank, and the liquid input end of the filling passage structure is connected to the first liquid outlet, specifically, the liquid input end of the filling passage structure is inserted into the filling tank from the first liquid outlet until the liquid input end of the filling passage structure extends into the inner tank bottom of the filling tank, so as to ensure that during the filling process, suction can be performed from the inner bottom of the filling tank to avoid wasting propellant. There are two liquid output ends of the filling passage structure, one connected to the propulsion device, and the other connected to the verification structure. When the propulsion device is normally filled with medium, the liquid output end of the filling passage structure connected to the verification structure needs to be isolated, and only the liquid output end connected to the propulsion device is retained.
[0042] Several flow meters are arranged on the filling passage structure to control the precise measurement of the flow rate filled into the propulsion device. In order to calibrate the flow meter, the liquid output end connected to the propulsion device can be isolated, and the liquid output end of the filling passage structure connected to the calibration structure can be opened, so that the calibration structure receives the medium drained from the filling passage structure. This calibration structure is directly installed in the entire filling system to realize the online measurement of the flow meter, which not only shortens the flow meter calibration cycle and meets the use requirements during intensive tasks, but also further improves the accuracy of rocket propellant filling measurement. In addition, the system pipeline caliber, flow meter installation method and operating parameters are consistent with the current filling system of the launch site, and there will be no differences, reducing the system error of calibration. At the same time, the medium for calibration is the filling medium, which avoids the calibration accuracy problem caused by different media, and solves the shortcomings of low calibration accuracy or instability in the existing ground filling system flow meter calibration method. BRIEF DESCRIPTION OF THE DRAWINGS
[0043] In order to more clearly illustrate the specific implementation methods of the utility model or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0044] Figure 1 The overall structural diagram of the filling system provided by the utility model;
[0045] Description of reference numerals:
[0046] 1- filling tank; 11- first liquid outlet; 12- first liquid inlet;
[0047] 2-filling passage structure; 21-first pipeline; 211-first pipeline; 212-filling power piece; 213-first large flowmeter; 214-second large flowmeter; 215-first valve body; 216-second valve body; 217-third valve body; 218-fifth valve body; 22-second pipeline; 221-second pipeline; 222-first small flowmeter; 223-second small flowmeter; 224-fourth valve body;
[0048] 3-calibration structure; 31-calibration tank; 32-liquid level gauge; 33-reversing element; 34-third pipeline; 341-third pipeline; 342-pipeline signaler; 343-sixth valve body; 344-seventh valve body. DETAILED DESCRIPTION
[0049] The technical solution of the utility model will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0050] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention. In addition, the terms "first" and "second" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.
[0051] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0052] In addition, the technical features involved in the different embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.
[0053] Example 1
[0054] like Figure 1 As shown, this embodiment provides a filling system, including a filling tank 1, a filling passage structure 2 and a verification structure 3, wherein the inner shell of the filling tank 1 stores a medium to be filled, and the filled medium is a propellant, which is used to be filled into the interior of a propulsion device, and the propulsion device can be a rocket, etc.; the medium can be filled through an additional liquid inlet opened on the filling tank 1; a first liquid outlet 11 is opened on the filling tank 1, and the liquid input end of the filling passage structure 2 is connected to the first liquid outlet 11, specifically, the liquid input end of the filling passage structure 2 is inserted into the interior of the filling tank 1 from the first liquid outlet 11 until the liquid input end of the filling passage structure 2 extends into the inner tank bottom of the filling tank 1, to ensure that during the filling process, suction can be performed from the inner bottom of the filling tank 1 to avoid wasting propellant. There are two liquid output ends of the filling passage structure 2, one connected to the propulsion device (not shown in the figure), and the other connected to the verification structure 3; the liquid output end connected to the propulsion device is located on the first pipeline 21 between the connection point of the second pipeline 22 and the first pipeline 21 away from the filling power part 212 and the fifth valve body 218. When the medium is normally filled in the propulsion device, the liquid output end of the filling passage structure 2 connected to the verification structure 3 needs to be isolated, and only the liquid output end connected to the propulsion device is retained.
[0055] Several flow meters are arranged on the filling passage structure 2 to control the accurate measurement of the flow rate filled into the propulsion device. In order to calibrate the flow meter, the liquid output end connected to the propulsion device can be isolated, and the liquid output end of the filling passage structure 2 connected to the verification structure 3 can be opened, so that the verification structure 3 receives the medium drained from the filling passage structure 2. This verification structure 3 is directly installed in the entire filling system to realize the online measurement of the flow meter, which not only shortens the flow meter calibration cycle, meets the use requirements during intensive tasks, but also further improves the accuracy of rocket propellant filling measurement. In addition, the system pipeline caliber, flow meter installation method and operating parameters are consistent with the current filling system of the launch site, and there will be no difference, which reduces the system error of calibration. At the same time, the medium for verification is the filling medium, which avoids the calibration accuracy problem caused by different media, and solves the shortcomings of low calibration accuracy or instability in the existing ground filling system flow meter calibration method.
[0056] like Figure 1As shown, specifically, the calibration structure 3 includes: a calibration tank 31, a liquid level meter 32, a recording device, a weighing piece, a reversing piece 33 and a third pipeline 34. A liquid inlet and outlet are provided at the bottom of the calibration tank 31, a first liquid inlet 12 is provided on the filling tank 1, and a reversing piece 33 is installed at the liquid inlet and outlet ends. The reversing piece 33 can be a T-type three-way reversing ball valve, and the other two through holes of the reversing piece 33 are respectively connected to the liquid output end of the filling passage structure 2 and the liquid output end of the third pipeline 34, and the other end of the third pipeline 34 is connected to the first liquid inlet 12; and the liquid level meter 32 is vertically arranged on the outside of the calibration tank 31, and the liquid level meter 32 is used to sense whether the liquid level in the calibration tank 31 reaches the preset liquid level; the recording device is used to detect the pulse index at the start time and the final time of the calibration flowmeter accuracy. The weighing piece is arranged at the bottom of the calibration tank 31 to measure the mass of the calibration tank 31.
[0057] When the flow meter needs to be calibrated, firstly, the medium flow rate in the filling passage structure 2 is adjusted to the flow rate to be checked through the filling system, the reversing member 33 connects the liquid output end of the first pipe 211 with the liquid inlet and outlet, and the filling passage structure 2 passes the medium in the filling tank 1 into the calibration tank 31, and at the same time, the initial pulse number of several flow meters is recorded by a recording device; when the medium is filled to the preset liquid level above the calibration tank 31, the reversing valve at the bottom of the calibration tank 31 is closed, and at the same time, the ending pulse number of several flow meters when the reversing member 33 at the bottom of the calibration tank 31 is closed is recorded by a recording device; the flow coefficient before the flow meter calibration is obtained by using the ending pulse number and the initial pulse number.
[0058] After the delay, when the liquid level of the calibration tank 31 and the reading of the weighing piece are stable, the liquid level meter 32 and the weighing piece are used to read the reading of the liquid level meter 32 and the weight of the medium flowing into the calibration tank 31. The volumetric flow coefficient is calculated by reading the liquid level meter 32 and the set flow rate to be verified; the gravimetric flow coefficient is calculated by reading the weight of the medium flowing into the calibration tank 31 and the set flow rate to be verified. After calculating the average value of the two, the coefficient value set by the flow meter itself is changed to the calculated flow coefficient value, so as to make corrections. After the correction is completed, the reversing member 33 can be opened to connect the liquid inlet and outlet and the liquid input end of the third pipeline 34 to return the medium in the calibration tank 31 to the filling tank 1. By using the weighing method and the volumetric method for calculation and taking the average value, the accuracy of the calibration is improved. At the same time, the medium in the calibration tank 31 can also be returned to the filling tank 1, saving the calibration cost. The volumetric method and the gravimetric method can be implemented separately, but in order to ensure accuracy, they can be implemented simultaneously.
[0059] In traditional online calibration, the flow meter is usually calibrated by using the liquid level gauge 32 of the online filling tank 1. However, due to the large volume of the filling tank 1, which is generally 50m3 -100m 3The flow rate of the launch site filling system is generally 50-2000L / min. The volume difference between the filling tank 1 and the flow meter is large, which makes the liquid level meter 32 not accurate enough, thus affecting the calibration effect of the flow meter. 3 The volume difference between the two is small, which solves the problem of accurate measurement.
[0060] like Figure 1 As shown, in this embodiment, the filling passage structure 2 includes a first pipeline 21 and a second pipeline 22; the first pipeline 21 is a large flow pipeline, and the second pipeline 22 is a small flow pipeline connected in parallel to the first pipeline 21. Specifically, the first pipeline 21 includes a first pipeline 211, a filling power part 212, a first large flow meter 213, a second large flow meter 214, a first valve body 215, a second valve body 216, a third valve body 217 and a fifth valve body 218; the liquid input end of the first pipeline 211 is connected to the first liquid outlet 11, and the liquid output end of the second pipeline 221 is respectively connected to the reversing member 33 and the propulsion member 34. The device is connected, the filling power piece 212, the first large flow meter 213 and the second large flow meter 214 are sequentially connected in series on the first pipeline 211 along the flow direction of the medium, the first valve body 215, the second valve body 216 and the third valve body 217 are all connected in series on the first pipeline 211, and the first valve body 215 is arranged at one end of the first pipeline 211 close to the filling tank 1, the second valve body 216 is provided with two, and the two second valve bodies 216 are arranged on both sides of the filling power piece 212, and the third valve body 217 is arranged at one end of the second large flow meter 214 away from the filling power piece 212. The fifth valve body 218 is arranged at one end of the first pipeline 211 close to the verification structure 3.
[0061] The second pipeline 22 includes: a second pipeline 221, a first small flowmeter 222, a second small flowmeter 223 and a fourth valve body 224. The liquid input end of the second pipeline 221 is arranged on the first pipeline 211 on the side of the second large flowmeter 214 close to the filling power pump, and the other end of the second pipeline 221 is arranged on the side of the third valve body 217 away from the filling power part 212; the first small flowmeter 222, the second small flowmeter 223 and the fourth valve body 224 are connected in series in sequence on the second pipeline 221 along the flow direction of the medium.
[0062] When it is necessary to fill the propulsion device with a large flow rate, the first valve body 215, the second valve body 216, the third valve body 217 and the fifth valve body are all opened; the fourth valve body 224 is closed, and the filling power part 212 is started to extract the medium in the filling tank 1. The medium flows in the first pipeline 211 and flows through the first valve body 215, the two second valve bodies 216, the first large flow meter 213, the second large flow meter 214 and the third valve body 217 to the propulsion structure. When a certain amount is filled, it is necessary to use the second pipeline 22 for small flow filling. The first valve body 215, the second valve body 216 and the fourth valve body 224 are opened, the third valve body 217 and the fifth valve body 218 are closed, and the filling power part 212 is started to extract the medium in the filling tank 1. The medium first flows in the first pipeline 211, passes through the first valve body 215, the two second valve bodies 216 and the first large flowmeter 213, and then flows to the second pipeline 221, flows through the first small flowmeter 222, the second small flowmeter 223 and the fourth valve body 224, and then flows to the rear end of the first pipeline 211 to fill the propulsion device with a small flow rate. The filling of the medium can be accurately controlled.
[0063] When the flowmeter needs to be calibrated, the two large flowmeters are calibrated first, the first valve body 215, the second valve body 216, the third valve body 217 and the fifth valve body 218 are opened, the liquid output end of the first pipeline 211 connected to the propulsion structure is closed, and the fourth valve body 224 is closed. The filling power part 212 is started, and the reversing part 33 is rotated to connect the first pipeline 211 and the liquid inlet and outlet. At the same time, the initial flow pulse values of the first large flowmeter 213 and the second large flowmeter 214 are recorded, and the medium flows through the first valve body 215, the two second valve bodies 216, the first large flowmeter 213, the second large flowmeter 214, the third valve body 217 and the fifth valve body 218 on the first pipeline 21, and is finally transported to the calibration structure 3. Through the calculation method mentioned above, the flow coefficients of the first large flowmeter 213 and the second large flowmeter 214 before calibration are calculated respectively, as well as the average values of the volumetric flow coefficient and the gravimetric flow coefficient in the measurement process. The coefficient values set in the first large flow meter 213 and the second large flow meter 214 are changed to the calculated flow coefficient values by using the average value, thereby making corrections.
[0064] Moreover, the specifications of the first large flowmeter 213 and the second large flowmeter 214 are the same, and the flow pulse coefficients of the first large flowmeter 213 and the second large flowmeter 214 are not much different. During the verification process, the flow coefficient of the first large flowmeter 213, the flow coefficient of the second large flowmeter 214 and the flow coefficient obtained by the verification structure 3 can be verified with each other. For example, if the flow coefficient obtained by the verification structure 3 is too different from the flow coefficient of the first large flowmeter 213 and the flow coefficient of the second large flowmeter 214, the staff can be prompted to re-verify to ensure the accuracy of the verification.
[0065] The large flowmeter is precision-checked using the above steps. The pulse values of the first large flowmeter 213 and the second large flowmeter 214 are compared. Through the above steps, the flow coefficients of the first large flowmeter 213 and the second large flowmeter 214 are calibrated, and then the medium in the calibration tank 31 is discharged through the third pipe 341.
[0066] Secondly, the small flow meter is calibrated. The first valve body 215, the second valve body 216, the fourth valve body 224 and the fifth valve body 218 are opened, the liquid output end connected to the first pipeline 211 and the propulsion structure is closed, and the third valve body 217 is closed. Driven by the filling power part 212, the medium flows through the first valve body 215, the two second valve bodies 216, the first large flow meter 213, the first small flow meter 222, the second small flow meter 223, the fourth valve body 224 and the fifth valve body 218; the accuracy of the first large flow meter 213 has been calibrated, and the flow coefficient obtained by calibrating the small flow meter of the calibration structure 3 can be obtained by using the steps in the previous text, and the final calibration flow coefficients of the first small flow meter 222 and the second small flow meter 223 are calculated in combination with the flow coefficient of the first large flow meter 213, and the calibration coefficients of the first small flow meter 222 and the second small flow meter 223 are calibrated.
[0067] Moreover, by the same token, the first small flow meter 222 and the second small flow meter 223 have the same specifications, which can also ensure the accuracy of the calibration of the first small flow meter 222 and the second small flow meter 223.
[0068] like Figure 1As shown, in this embodiment, the third pipeline 34 includes: a third pipeline 341, a pipeline signaler 342, a sixth valve body 343 and a seventh valve body 344, one end of the third pipeline 341 is connected to one of the connecting ports of the reversing member 33, and the other end of the third pipeline 341 is connected to the first liquid inlet 12 of the filling tank 1; the pipeline signaler 342, the sixth valve body 343 and the seventh valve body 344 are sequentially connected in series on the third pipeline 341 along the conveying direction of the medium, and the pipeline signaler 342 is used to detect the flow signal of the medium in the pipeline. The third pipeline 34 controls the medium in the calibration tank 31 to flow back to the filling tank 1. When the calibration of the flowmeter is completed, the liquid inlet and outlet are connected to the liquid input end of the third pipeline 34, the sixth valve body 343 and the seventh valve body 344 are opened, and the medium in the calibration tank 31 flows through the sixth valve body 343 and the seventh valve body 344 to the filling tank 1.
[0069] like Figure 1 As shown, in this embodiment, by providing two second valve bodies 216, it is convenient to disassemble and repair the filling power part 212, by providing the fifth valve and the sixth valve, it is convenient to disassemble and repair the calibration tank 31, and by providing the first valve body 215 and the seventh valve body 344, it is convenient to disassemble and repair the filling tank 1, thereby improving maintenance efficiency and saving maintenance costs.
[0070] Obviously, the above embodiments are merely examples for the purpose of clear explanation, and are not intended to limit the implementation methods. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the implementation methods here. The obvious changes or modifications derived therefrom are still within the scope of protection of the invention of the utility model.
Claims
1. A filling system, characterized in that: include: A filling tank (1) is suitable for storing a medium that needs to be filled, and a first liquid outlet (11) is provided on the filling tank (1); A filling passage structure (2), wherein a liquid input end of the filling passage structure (2) is connected to the first liquid outlet (11), and a liquid output end of the filling passage structure (2) is suitable for being connected to a propulsion device; A verification structure (3), wherein the liquid input end of the verification structure (3) is also connected to the liquid output end of the filling passage structure (2); The filling passage structure (2) further comprises a plurality of flow meters; the filling passage structure (2) has a working state in which the medium flows through the flow meter to the verification structure (3), so that the verification structure (3) receives the medium in the filling tank (1) to verify the metering accuracy of the flow meter.
2. The filling system according to claim 1, characterized in that: The verification structure (3) comprises: A calibration tank (31), wherein a liquid inlet and outlet are provided on the calibration tank (31); a liquid level meter (32), the liquid level meter (32) being arranged on the calibration tank (31) and being suitable for detecting the liquid level in the calibration tank (31); A recording device is used to record the number of flow pulses of the flow meter.
3. The filling system according to claim 2, characterized in that: The verification structure (3) further includes: A weighing piece is arranged at the bottom of the calibration tank (31).
4. The filling system according to claim 2, characterized in that: The filling tank (1) is also provided with a first liquid inlet (12); the filling passage structure (2) comprises a first pipeline (21) and a second pipeline (22); The verification structure (3) further includes: A reversing member (33), wherein the reversing member (33) is provided with at least three communication ports; a third pipeline (34), wherein one end of the third pipeline (34) close to the calibration tank (31) is connected to the first liquid inlet (12); Among them, three of the at least three communication ports on the reversing member (33) are respectively connected to the liquid inlet and outlet, an end of the third pipeline (34) away from the filling tank (1) and the first pipeline (21).
5. The filling system according to claim 4, characterized in that: The first pipeline (21) comprises: a first pipeline (211), one end of the first pipeline (211) being connected to the first liquid outlet (11) of the filling tank (1), and the other end of the first pipeline (211) being connected to both the verification structure (3) and the propulsion device; and a filling power component (212), a first large flow meter (213) and a second large flow meter (214) which are sequentially connected in series on the first pipeline (211) along the flow direction of the medium; the filling power component (212) can extract the medium in the filling tank (1) and convey it through the first large flow meter (213) and the second large flow meter (214) to the propulsion device or the verification structure (3).
6. The filling system according to claim 5, characterized in that: The first pipeline (21) comprises: a first valve body (215), the first valve body (215) being arranged at one end of the first pipeline (211) close to the filling tank (1); A second valve body (216), wherein two second valve bodies (216) are provided, and the two second valve bodies (216) are respectively arranged on the first pipeline (211) on both sides of the filling power component (212); A third valve body (217), wherein the third valve body (217) is arranged on the first pipeline (211) at one end of the second large flow meter (214) away from the filling power component (212).
7. The filling system according to claim 6, characterized in that: The second pipeline (22) comprises: a second pipeline (221), one end of the second pipeline (221) being arranged on the first pipeline (211) on the side of the second large flow meter (214) close to the filling power component (212); and the other end of the second pipeline (221) being arranged on the side of the third valve body (217) away from the filling power component (212); and a first small flow meter (222) and a second small flow meter (223) which are sequentially connected in series on the second pipeline (221) along the flow direction of the medium; the filling power component (212) can extract the medium in the filling tank (1) and convey it through the first small flow meter (222) and the second small flow meter (223) to the propulsion device or the verification structure (3).
8. The filling system according to claim 7, characterized in that: The second pipeline (22) comprises: A fourth valve body (224), the fourth valve body (224) is arranged on a side of the second small flow meter (223) away from the filling power component (212) to control the opening and closing of the second pipeline (221).
9. The filling system according to claim 6, characterized in that: The first pipeline (21) comprises: A fifth valve body (218), wherein the fifth valve body (218) is arranged at one end of the first pipeline (211) close to the verification structure (3).
10. The filling system according to any one of claims 4 to 9, characterized in that: The third pipeline (34) comprises: A third pipe (341), one end of the third pipe (341) being connected to one of the communication ports of the reversing member (33), and the other end of the third pipe (341) being connected to the first liquid inlet (12) of the filling tank (1); and a pipeline signal device (342), a sixth valve body (343) and a seventh valve body (344) which are sequentially connected in series on the third pipeline (341) along the conveying direction of the medium, wherein the pipeline signal device (342) is used to detect a flow signal of the medium in the pipeline; The sixth valve body (343) and the seventh valve body (344) are suitable for opening and closing the third pipeline (341).
Citation Information
Cited By
Rocket conventional propellant filling training system and method
CN120968960A