Splicing seam structure for widening new bridge body and old bridge body
By designing widening gaps and expansion gaps between new and old bridges, combining high-tough concrete and tough steel frames, the repulsion problem between the new bridge and the old bridge is solved, ensuring the stability and safety of the bridge after widening , and enhance the crack and water resistance of the bridge body.
Patent Information
- Application Number
- CN202420671333.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-02
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2034-04-02
AI Technical Summary
During the widening of the elevated lane, the structural and material differences between the new bridge body and the old bridge body lead to repulsion, affecting the stability and safety of the widened bridge body.
Design a splicing seam structure that includes widening gaps and expansion gaps, and uses high-tough concrete and tough reinforced frames to ensure independence of deformation between the new bridge body and the old bridge body, and adapt to thermal expansion and cooling through expansion gaps and drip groove designs. Shrink deformation enhances the strength and stability of concrete.
Effectively avoid the repulsion between the new bridge body and the old bridge body, ensure the stability and safety of the widened bridge body, and enhance the strength and crack resistance of the bridge body through the design of high-tough concrete and tough steel frames. Ability to avoid water seepage diffusion problem.
Smart Images

Figure CN222065154U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of bridges, in particular to a joint seam structure used for widening new and old bridge bodies. Background Art
[0002] Many lanes have gradually been unable to meet the traffic needs of vehicles, and need to be widened or additional lanes. The widening of conventional road lanes often needs to affect other buildings on the road, involving a series of additional costs such as demolition. Therefore, the traffic problem is solved by adding elevated lanes above the road lanes. However, it becomes very difficult to solve the traffic problem in areas where elevated lanes already exist.
[0003] Due to the existence of the above problems, a better technical solution is to widen the elevated lane to solve the traffic demand problem. However, there are deviations in the structure and materials between the new bridge body and the old bridge body. If a continuous splicing structure is used during the splicing process, it is easy to cause repulsion between the new bridge body and the old bridge body, which is not conducive to widening the stability and safety of the new bridge body. Summary of the invention
[0004] The technical problem to be solved by the utility model is to provide a joint seam structure for widening new and old bridge bodies, which can avoid the repulsion phenomenon between the new bridge body and the old bridge body and ensure the stability and safety of the widened bridge body.
[0005] The technical solution adopted by the utility model to solve the above-mentioned problem is: a joint seam structure for widening a new bridge body and an old bridge body, comprising a new bridge body and an old bridge body, a widening gap is provided between the new bridge body and the old bridge body, high-toughness concrete is provided in the widening gap, the high-toughness concrete is fixedly connected to one end of the old bridge body close to the new bridge body, the widening gap also includes an expansion gap, the expansion gap is provided between the high-toughness concrete and the new bridge body, and the expansion gap is used to adapt to the expansion deformation of the high-toughness concrete.
[0006] Compared with the prior art, the advantages of the utility model are: a widening gap is provided between the new bridge body and the old bridge body, and through the design of the expansion gap, when the new bridge body and the old bridge body deform due to thermal expansion and contraction caused by weather deformation, sufficient deformation space can be provided for the new bridge body and the old bridge body, and the deformations of the new bridge body and the old bridge body are independent of each other and do not affect each other, so that dangerous phenomena such as cracking of the bridge body will not be caused due to the different deformations of the new bridge body and the old bridge body; the old bridge body has a long service life, its structural strength will decrease, and its deformation amplitude is difficult to calculate accurately, and the design of high-toughness concrete at the end of the old bridge body close to the new bridge body can make the deformation of the high-toughness concrete in the direction of the new bridge body be calculated as a new deformation standard, so as to better design the size of the expansion gap, avoid the new bridge body and the old bridge body from directly offsetting each other after expansion, thereby ensuring the stability and safety of the old bridge body after widening by the new bridge body.
[0007] As an improvement of the utility model, a tough steel bar frame is also provided in the widened gap, and the tough steel bar frame includes supporting steel bars, and the supporting steel bars include a connecting section and an expanded section. The connecting section is used to be fixedly connected to the main steel bar frame of the old bridge body, and the expanded section is provided in the widened gap to enhance the strength of high-toughness concrete. Through the improvement, the casting connection strength of the high-toughness concrete in the old bridge body is guaranteed.
[0008] As an improvement of the utility model, one end of the connecting section is used for welding and fixing with the upper end of the main steel bar frame, and the other end of the connecting section extends into the widened gap. The unfolded section is in the shape of a hook that first goes downward and then upward. Through the improvement, the stability of the high-toughness concrete after molding is ensured, and it is not easy to fall off or break.
[0009] As an improvement of the present invention, the tough steel bar frame also includes a plurality of frame steel bars, and the plurality of frame steel bars are arranged perpendicularly to the supporting steel bars. The plurality of frame steel bars include connecting frame steel bars uniformly welded on the connecting section along the setting direction of the connecting section and shaped frame steel bars on the inner side of the bending of the supporting steel bars. Through the improvement, the forming stability and firmness of the tough steel bar frame are guaranteed, thereby better ensuring the forming strength of high-toughness concrete.
[0010] As an improvement of the utility model, the width of the high-toughness concrete in the widened gap is greater than or equal to 100 mm and less than or equal to 150 mm, and the end of the unfolded section is in the shape of a hook inclined upward.
[0011] As an improvement of the present invention, the distance between two adjacent ductile steel bars is 180-220 mm.
[0012] As an improvement of the utility model, the width of the high-toughness concrete in the widened gap is greater than 150 mm, and the end of the unfolded section is in a hook shape that is first horizontal and then vertically upward.
[0013] As an improvement of the present invention, the distance between two adjacent ductile steel bars is 80-120 mm.
[0014] As an improvement of the utility model, the bottom end of the high-toughness concrete is arranged at a drip groove. Through the improvement, the old bridge body may not be designed with a drip groove, which results in strong diffusion of water discharge after water seepage in the old bridge body, which is not conducive to the use strength of the bridge body. After the improvement of the high-toughness concrete on the old bridge body, the design of the drip groove is added, and the water that seeps into the old bridge body is separated from the old bridge body along the drip groove, avoiding the formation of water seepage and diffusion on the old bridge body. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a schematic cross-sectional view of the overall structure of the utility model.
[0016] Figure 2 It is a schematic diagram of the connection structure of the toughness steel bar frame viewed from above of the utility model.
[0017] Figure 3 It is a structural schematic diagram of another embodiment of the supporting steel bar of the utility model.
[0018] As shown in the figure: 1. New bridge body, 2. Old bridge body, 2.1. Main steel bar frame, 3. Widening gap, 3.1. Expansion gap, 4. High-toughness concrete, 4.1. Drip groove, 5. Tough steel bar frame, 5.1. Support steel bars, 5.1.1. Connecting section, 5.1.2. Expanding section, 5.2. Frame steel bars, 5.2.1. Connecting frame steel bars, 5.2.2. Shaped frame steel bars. DETAILED DESCRIPTION
[0019] The embodiments of the present utility model are further described below in conjunction with the accompanying drawings.
[0020] like Figure 1-2 As shown, a joint structure for widening a new and old bridge body comprises a new bridge body 1 and an old bridge body 2, wherein a widening gap 3 is provided between the new bridge body 1 and the old bridge body 2, wherein high-toughness concrete 4 is provided in the widening gap 3, wherein the high-toughness concrete 4 is fixedly connected to one end of the old bridge body 2 close to the new bridge body 1, wherein the widening gap 3 further comprises an expansion gap 3.1, wherein the expansion gap 3.1 is provided between the high-toughness concrete 4 and the new bridge body 1, wherein the expansion gap 3.1 is used to adapt to the expansion deformation of the high-toughness concrete 4, and wherein the bottom end of the high-toughness concrete 4 is provided at a drip groove 4.1.
[0021] A tough steel bar frame 5 is also provided in the widened gap 3, and the tough steel bar frame 5 includes supporting steel bars 5.1, and the supporting steel bars 5.1 include a connecting section 5.1.1 and an expanding section 5.1.2. The connecting section 5.1.1 is used to be fixedly connected to the main steel bar frame 2.1 of the old bridge body 2, and the expanding section 5.1.2 is provided in the widened gap 3 to enhance the strength of the high-toughness concrete 4. One end of the connecting section 5.1.1 is used to be welded and fixed to the upper end of the main steel bar frame 2.1. The other end of 5.1.1 extends into the widened gap 3, and the unfolded section 5.1.2 is in the shape of a hook that first extends downward and then upward. The ductile steel bar frame 5 also includes a plurality of frame steel bars 5.2, and the plurality of frame steel bars 5.2 are vertically arranged with the supporting steel bars 5.1. The plurality of frame steel bars 5.2 include connecting frame steel bars 5.2.1 uniformly welded on the connecting section 5.1.1 along the setting direction of the connecting section 5.1.1 and shaped frame steel bars 5.2.2 on the inner side of the bend of the supporting steel bars 5.1.
[0022] like Figure 1 As shown, the width of the high-toughness concrete 4 in the widened gap 3 is greater than or equal to 100 mm and less than or equal to 150 mm, the end of the unfolded section 5.1.2 is in an upwardly inclined hook shape, and the spacing between two adjacent supporting steel bars 5.1 is 180 to 220 mm.
[0023] like Figure 3 As shown, the width of the high-toughness concrete 4 in the widened gap 3 is greater than 150 mm, the end of the unfolded section 5.1.2 is in a hook shape that is first horizontal and then vertically upward, and the spacing between two adjacent supporting steel bars 5.1 is 80 to 120 mm.
[0024] During the construction of the ductile steel bar frame 5, the supporting steel bars 5.1 are made of steel bars with a diameter of 12 mm, and the connecting frame steel bars 5.2.1 and the shaping frame steel bars 5.2.2 are made of steel bars with a diameter of 10 mm.
[0025] The minimum width of the high-toughness concrete 4 in the widened gap 3 is 100 mm, which is also the most ideal width. However, due to the deviation in the widening process, the width needs to be appropriately increased. However, if the width exceeds 200 mm, the structure of the toughness steel frame 5 needs to be redesigned and cannot be directly adopted. Figure 1 and Figure 3 structure.
[0026] like Figure 1As shown, during the construction of the tough steel frame 5, it is necessary to chisel out the concrete on the main steel frame 2.1 of the old bridge body 2 and the concrete on the top of the new bridge body 1 close to the old bridge, and then weld the tough steel frame 5 to the main steel frame 2.1, and then use high-toughness concrete 4 to pour on the old bridge body 2 and the new bridge body 1, covering the tough steel frame 5 to form and keep the old bridge body 2 and the new bridge body 1 at the same height and retain the expansion gap 3.1; finally, place aluminum foil waterproof membrane and stainless steel plate at the upper end of the expansion gap 3.1, and pour the asphalt layer on the top layer of the bridge deck.
[0027] The above description is only for the best embodiment of the utility model, but it cannot be understood as a limitation of the claims. The utility model is not limited to the above embodiments, and its specific structure is allowed to be changed. All changes made within the protection scope of the independent claims of the utility model are within the protection scope of the utility model.
Claims
1. A joint structure for widening a new and old bridge, characterized in that: The invention comprises a new bridge body (1) and an old bridge body (2), wherein a widening gap (3) is provided between the new bridge body (1) and the old bridge body (2), wherein high-toughness concrete (4) is provided in the widening gap (3), wherein the high-toughness concrete (4) is fixedly connected to one end of the old bridge body (2) close to the new bridge body (1), wherein the widening gap (3) further comprises an expansion gap (3.1), wherein the expansion gap (3.1) is provided between the high-toughness concrete (4) and the new bridge body (1), and wherein the expansion gap (3.1) is used to adapt to the expansion deformation of the high-toughness concrete (4).
2. A joint seam structure for widening a new and old bridge according to claim 1, characterized in that: A tough steel bar frame (5) is also provided in the widened gap (3), the tough steel bar frame (5) comprising supporting steel bars (5.1), the supporting steel bars (5.1) comprising a connecting section (5.1.1) and an expanded section (5.1.2), the connecting section (5.1.1) being used for fixed connection with the main steel bar frame (2.1) of the old bridge body (2), the expanded section (5.1.2) being provided in the widened gap (3) for enhancing the strength of the high-toughness concrete (4).
3. A joint seam structure for widening a new and old bridge according to claim 2, characterized in that: One end of the connecting section (5.1.1) is used for welding and fixing with the upper end of the main steel reinforcement frame (2.1), and the other end of the connecting section (5.1.1) extends into the widened gap (3). The unfolding section (5.1.2) is in the shape of a hook that first moves downward and then upward.
4. According to claim 3, a joint seam structure for widening a new and old bridge body is characterized in that: The ductile steel bar frame (5) further comprises a plurality of frame steel bars (5.2), wherein the plurality of frame steel bars (5.2) are arranged perpendicularly to the supporting steel bars (5.1), and the plurality of frame steel bars (5.2) comprise connecting frame steel bars (5.2.1) uniformly welded to the connecting section (5.1.1) along the setting direction of the connecting section (5.1.1) and shaped frame steel bars (5.2.2) on the inner side of the bend of the supporting steel bars (5.1).
5. According to claim 4, a joint seam structure for widening a new and old bridge body is characterized in that: The width of the high-toughness concrete (4) in the widened gap (3) is greater than or equal to 100 mm and less than or equal to 150 mm, and the end of the unfolded section (5.1.2) is in the shape of a hook inclined upward.
6. The joint structure for widening the new and old bridge bodies according to claim 5, characterized in that: The distance between two adjacent ductile steel bars is 180-220 mm.
7. The joint structure for widening the new and old bridge bodies according to claim 4, characterized in that: The width of the high-toughness concrete (4) in the widened gap (3) is greater than 150 mm, and the end of the unfolded section (5.1.2) is in the shape of a hook that is first horizontal and then vertically upward.
8. The joint structure for widening the new and old bridge bodies according to claim 7, characterized in that: The distance between two adjacent ductile steel bars is 80 to 120 mm.
9. The joint structure for widening a new and old bridge according to claim 1, characterized in that: The bottom end of the high-toughness concrete (4) is arranged on the drip groove (4.1).