Foundation structure of newly-built elevator above tunnel
Through foundation grouting reinforced and compensated reinforced concrete box raft foundation structure, the problem of pile rafts in the construction of new elevators above the tunnel and pile hole obstacles is solved, and construction without pile formation is achieved, which shortens the construction cycle and improves the Safety and applicability.
Patent Information
- Application Number
- CN202420603246.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-27
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2034-03-27
AI Technical Summary
In the construction of new elevator infrastructure structures above the tunnel, there are problems such as pile rafts that cannot be realized, soil obstacles under the pile holes lead to difficulties in pile formation, narrow space and damage to old foundations, resulting in complex construction, lengthening of cycles and increasing costs.
The foundation treatment method is used in combination with the compensation type reinforced concrete box raft foundation, and the foundation is reinforced by static grouting to avoid the pile formation process. The compensation foundation raft plate and box-shaped structure are used to support the elevator columns to reduce the impact on underground tunnels.
A new elevator infrastructure without piles has been realized, which shortens the construction cycle, reduces the cost of enclosure, improves construction safety and applicability, reduces the impact of underground obstacles, and improves the construction environment and safety.
Smart Images

Figure CN222065544U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of structural foundation construction, in particular to a foundation structure for a newly-built elevator above a tunnel. Background Art
[0002] The process of renovating urban facilities for the benefit of the elderly is constantly advancing, and the construction of new elevators in multi-story residential buildings is an important part of it.
[0003] In the existing practice of adding ladders, the common foundation structure is pile raft (such as Figure Collection 22J943-1 / 22G621-1, Shanghai Standard DG / TJ 08-2381-2021), in which the piles are mainly anchor static pressure piles. However, there are the following deficiencies in engineering practice:
[0004] 1. For special underground conditions, such as tunnels and culverts under the site, pile raft foundation cannot be implemented;
[0005] 2. There are isolated rocks or unknown obstacles in the soil under the pile hole, which makes it difficult to form (sink) piles, delaying the progress, causing repeated construction or even redesign, extending the construction period and increasing the construction cost;
[0006] 3. Limited by the layout of new and old structures, the space for pile formation (sinking) is narrow, the required anchor pile position is not ideal, the pile sealing is difficult, and it is easy to cause quality problems of the pile head;
[0007] 4. When the pile is arranged on the old foundation, the pile hole needs to destroy the old foundation, which requires high operation and complicated construction process. Summary of the invention
[0008] The purpose of the utility model is to provide a foundation structure for a newly built elevator above a tunnel in accordance with the above-mentioned deficiencies of the prior art, which adopts a foundation treatment method combined with a new compensation foundation method, so that no pile formation (sinking) is required and the depth of influence of the soil under the base is shallow, thereby ensuring the safety, reliability and applicability of the newly built elevator under the premise of minimal impact on the tunnel below the site, and the tunnel includes a subway tunnel, a road tunnel, a municipal culvert, etc.
[0009] The purpose of this utility model is achieved by the following technical solutions:
[0010] A foundation structure for a newly built elevator above a tunnel is arranged above an existing tunnel buried in the soil, and is characterized in that: the foundation structure includes a compensating reinforced concrete box raft foundation, and the compensating reinforced concrete box raft foundation is composed of a compensating foundation raft plate and a compensating foundation box structure, wherein the compensating foundation box structure is arranged above the compensating foundation raft plate and the two form an integral structure, the compensating foundation box structure is used to connect and support the upper structure columns of the newly built elevator above, and a foundation grouting reinforcement body is arranged below the compensating foundation raft plate.
[0011] The foundation grouting reinforcement body is realized by arranging a grouting pipe in the soil body for grouting, and the grouting pipe is buried in the soil body and buried in the compensation foundation raft slab.
[0012] The compensation type reinforced concrete box raft foundation is buried in backfill soil, and a foundation cushion layer is arranged below the compensation type reinforced concrete box raft foundation.
[0013] A construction method for a new elevator foundation structure above the tunnel, characterized in that the construction method comprises the following steps:
[0014] S1. According to the foundation pit support plan, the support structure is driven into the foundation pit in advance;
[0015] S2. Install several grouting steel pipes in place within the grouting reinforcement range at the bottom of the foundation pit;
[0016] S3, grouting the plurality of grouting steel pipes in the order of skip hole interval, first the outer periphery and then the inner periphery;
[0017] S4. After grouting is completed, the grouting pipe is sealed and the foundation reinforcement test is carried out;
[0018] S5. After the foundation reinforcement test is qualified, the foundation pit is excavated and the enclosure structure is constructed between the enclosure bodies;
[0019] S6, constructing the foundation cushion layer, the compensation foundation raft slab, and the pre-embedded column foot, wherein the pre-embedded column foot corresponds to the column foot of the compensation foundation box structure to be constructed above;
[0020] S7, constructing the side walls, top plate and column foot of the compensation foundation box structure;
[0021] S8. Backfill the foundation pit and construct the new elevator superstructure.
[0022] The grouting slurry of the grouting pipe adopts single-liquid cement slurry or double-liquid mixed slurry, and the water-cement ratio, slump, grouting pressure and setting time of the slurry are determined according to actual working conditions.
[0023] The grouting pipe is made of galvanized steel pipe or stainless steel pipe, and grouting holes are opened in the corresponding grouting sections of the grouting pipe. The grouting holes are arranged at intervals and staggered, and barbs are welded outside the grouting holes; the grouting pipes are connected by sleeve welding.
[0024] The foundation reinforcement test includes using static penetration to detect the uniformity of the reinforced stratum and using a plate load test to detect the foundation bearing capacity and the compression modulus of the reinforced soil layer.
[0025] The advantages of the utility model are:
[0026] 1) Applicable to the construction of new elevators above tunnels, filling the technical gap;
[0027] 2) No need to build (sink) piles, avoiding the difficulties in sinking piles, hidden dangers of pile sealing, and damage to old foundations in the original process of building (sinking) piles;
[0028] 3) There is no need to wait for the foundation concrete to solidify before forming (sinking) piles, which shortens the exposure time of the foundation pit, reduces the cost of enclosure, reduces soil disturbance, and improves safety;
[0029] 4) Compared with existing new elevator technology, it effectively reduces underground obstacles;
[0030] 5) Effectively reduce the content and time of operations near the foundation pit, greatly improve the working environment on the construction site, and enhance construction safety;
[0031] 6) It has strong feasibility, economy and applicability. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] Figure 1 This is a schematic cross-sectional view of the original state of the site of an embodiment of the utility model;
[0033] Figure 2 A schematic cross-sectional view of a grouting construction state of an embodiment of the utility model;
[0034] Figure 3 It is a cross-sectional schematic diagram of the foundation pit excavation and enclosure state of an embodiment of the utility model;
[0035] Figure 4 It is a cross-sectional schematic diagram of the foundation construction state of an embodiment of the utility model;
[0036] Figure 5 It is a cross-sectional schematic diagram of the foundation pit backfilling state according to an embodiment of the utility model. DETAILED DESCRIPTION
[0037] The following is a further detailed description of the features of the present invention and other related features through embodiments in conjunction with the accompanying drawings to facilitate understanding by technicians in the same industry:
[0038] like Figure 1-5 As shown, the marks 1-11 in the figure respectively represent: soil tunnel (including subway tunnel, road tunnel, municipal culvert, etc.) 1, natural ground 2, tunnel top height 3, retaining steel piles 4, grouting pipe 5, grouting pipe joint 6, foundation pit purlin and support 7, compensation foundation raft 8, compensation foundation box structure 9, backfill soil 10, upper structure column 11.
[0039] Example: Figures 1 to 5As shown, the foundation structure of the newly built elevator above the tunnel in this embodiment includes two technologies: foundation treatment and new foundation. The foundation treatment technology is static pressure grouting, and the new foundation technology is a compensating reinforced concrete box raft foundation. Through the combined application of the two technologies, the safety, reliability and applicability of the newly built elevator are guaranteed under the premise of minimal impact on the tunnel below the site.
[0040] Specifically, the construction method in this embodiment is applied in Figure 1 In the construction scene shown, an existing soil tunnel 1 is buried in the soil, and there is a certain distance between the tunnel top height 3 and the natural ground 2. The foundation of the new elevator needs to be constructed within this range.
[0041] The construction method in this embodiment includes the following steps:
[0042] 1) According to the foundation pit support plan, retaining steel piles 4 are driven around the foundation pit in advance.
[0043] In this embodiment, the retaining steel piles 4 are made of Larsen water-stop steel sheet piles and channel steels, and the retaining position includes the side walls of the foundation pit and the soil under the original building foundation at the bottom of the foundation pit.
[0044] 2) Process the grouting pipe 5 and use the drilling method or the driving method to put the grouting steel pipe in place. When the drilling method is used, reliable grouting prevention measures should be set to prevent the cement slurry in the drill hole from returning.
[0045] In this embodiment, the grouting pipe 5 is made of galvanized steel pipe or stainless steel pipe, which has certain corrosion resistance and stability. Holes are arranged at intervals in the grouting section, barbs are arranged outside the holes, and the extension is welded by sleeve. Among them, by arranging barbs on the outside of the grouting pipe 5, the pull-out resistance of the grouting pipe 5 in the soil is improved, and the connection performance between the grouting pipe 5 and the soil is further improved.
[0046] 3) Use qualified grouting pipe joints 6 and hoses to connect the grouting pipe 5 for grouting, and perform grouting in the order of skip hole interval, first the outer periphery and then the inner periphery. When there is flowing groundwater, grouting should be started from the high head end. When grouting soil layers with similar permeability coefficients, grouting should be performed first to seal the top, and then grouting should be performed from bottom to top.
[0047] In this embodiment, the grouting pipe joint 6 adopts a galvanized one-way valve, which is externally connected to a grouting hose, and the diameter of the hose is determined according to the grouting requirements.
[0048] 4) Determine the time to stop grouting according to the grouting stop standard. After stopping, use fast-setting slurry to grout the grouting pipe 5 to ensure that there is no leakage of slurry.
[0049] 5) Check the grouting quality and seal the grouting pipe 5.
[0050] In this embodiment, static pressure grouting is used to carry out targeted foundation reinforcement, improve the uniformity of soil distribution under the foundation, improve its anti-deformation ability, and ensure that the foundation soil does not produce excessive differential deformation under the action of uneven base stress. The grouting slurry uses single-liquid cement slurry or double-liquid mixed slurry, and the slurry water-cement ratio, slump, grouting pressure, setting time and other requirements are determined according to actual working conditions.
[0051] 6) Conduct foundation reinforcement testing, use static penetration testing to test the uniformity of the reinforced stratum, and use plate load testing to test the foundation bearing capacity and compression modulus of the reinforced soil layer.
[0052] 7) After the foundation reinforcement test is qualified, the internal foundation pit area surrounded by the retaining steel piles 4 is excavated, and the foundation pit purlins and supports 7 and other retaining measures are taken in the construction pit.
[0053] In this embodiment, the foundation pit purlin and support 7 are made of double-jointed channel steel or hot-rolled I-beam, and angle braces are added when necessary.
[0054] 8) Construction of foundation cushion, compensation foundation raft slab 8 and pre-embedded column foot.
[0055] In this embodiment, the compensation foundation raft 8 adopts a reinforced concrete structure, and its size is determined by calculation based on the additional stress requirements of the base, the overall stability requirements, the overall anti-floating requirements, etc.
[0056] 9) Construction of side walls, top plate and column base of compensation foundation box structure 9.
[0057] In this embodiment, the compensation foundation box structure 9 adopts a reinforced concrete structure, and the design size is calculated and determined according to the elevator foundation pit size requirements, overall anti-floating requirements, site reservation conditions, etc.
[0058] The compensation foundation raft 8 and the compensation foundation box structure 9 are combined to form a compensation type reinforced concrete box raft foundation. The reinforced concrete compensation foundation box structure 9 is arranged around the stepped column foot to achieve the purpose of compensating the original soil weight with the structural weight. The compensation foundation raft 8 of the reinforced concrete structure is arranged around the compensation foundation box structure 9 to achieve the purpose of leveling the uneven base stress in various working conditions with the covering soil weight. The actual material requirements of the reinforced concrete box raft structure can be adjusted according to the regulations or soil conditions of different regions.
[0059] 10) The foundation pit is backfilled with backfill soil 10, and the elevator superstructure is constructed. The superstructure columns 11 are supported by the compensation foundation box structure 9.
[0060] Although the above embodiments have described the concepts and embodiments of the purpose of the utility model in detail with reference to the accompanying drawings, ordinary technicians in this field can recognize that various improvements and modifications can still be made to the utility model without departing from the scope of the claims, so they are not described one by one here.
Claims
1. A foundation structure for a newly built elevator above a tunnel, arranged above an existing tunnel buried in soil, characterized in that: The foundation structure includes a compensation type reinforced concrete box raft foundation, which is composed of a compensation foundation raft plate and a compensation foundation box structure, wherein the compensation foundation box structure is arranged above the compensation foundation raft plate and the two form an integral structure, and the compensation foundation box structure is used to connect and support the upper structure columns of the newly built elevator above, and a foundation grouting reinforcement body is arranged below the compensation foundation raft plate.
2. The basic structure of a new elevator above a tunnel according to claim 1, characterized in that: The foundation grouting reinforcement body is realized by arranging a grouting pipe in the soil body for grouting, and the grouting pipe is buried in the soil body and in the compensation foundation raft slab.
3. The basic structure of a new elevator above a tunnel according to claim 1, characterized in that: The compensation type reinforced concrete box raft foundation is buried in backfill soil, and a foundation cushion layer is arranged below the compensation type reinforced concrete box raft foundation.