Repairable deformation joint waterproof structure
By adopting an outsourcing waterproof layer, embedded with elastic rods and sealant in the deformed joint waterproof structure, and combining with flexible drainage pipes, the problem of difficult to repair after leakage of the deformation joint of the underground side wall is achieved, and the rapid and green Environmentally friendly restoration effect ensures the normal use of the building.
Patent Information
- Application Number
- CN202420432505.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-06
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2034-03-06
AI Technical Summary
The existing waterproof structure of the deformed joint of the underground wall is difficult to repair after leakage, the construction is complex and the cycle is long, and the leakage point cannot be monitored in real time, affecting the normal use of the building.
A waterproof structure for repairable deformation joints is designed, using an outsourcing waterproof layer, an outer waterproof belt, and a first elastic rod, a sealant and a flexible drain pipe embedded in the groove to form a drainage cavity, and using elastic rod and seal The glue resists water pressure, and the flexible drain pipe guides water leakage. The preferred materials are rubber, SBS, PE, etc., combined with high elastic and low-mode modified silicone sealant to achieve self-recovery function.
It effectively reduces the probability of diffuse leakage, quickly discovers and repairs leakage points, reduces maintenance time and garbage generation, ensures the continuity of building usage functions, and achieves rapid repair through local cutting and replacement parts.
Smart Images

Figure CN222065818U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of deformation joint waterproofing, in particular to a repairable deformation joint waterproofing structure. Background Art
[0002] During the construction of subway stations, the location of the deformation joints of the underground side walls has always been the focus of anti-leakage. At present, the combination of external waterstops, embedded waterstops, and sealing caulking materials is mainly used for defense. The construction is relatively complicated, and once leakage occurs, it is difficult to repair it in time. For example:
[0003] 1. With the deformation caused by uneven settlement and rubber aging, the buried waterstop will lose its waterproof performance once it is damaged, and it is impossible to repair the waterstop. It can only be treated by oblique drilling of concrete holes on the underground side wall and grouting on the back water surface. One grouting may not solve the leakage problem and requires repeated treatment, with a long maintenance cycle and high cost.
[0004] 2. To prevent diffuse leakage in the expansion joint, a stainless steel water box rigidly fixed with cement nails is used. The cost is high. After the expansion joint has relative displacement, the stainless steel water box is easily damaged and fails. After failure, diffuse leakage occurs, affecting the normal use function of the building.
[0005] 3. The expansion joint adopts a fully blocked structure. It is impossible for the failure points of multiple waterproof measures to be consistent, and it is impossible to monitor the leakage in real time. Check the leakage point
[0006] 4. After the expansion joint waterproofing fails, the demolition work is large. Utility Model Content
[0007] The purpose of the utility model is to provide a repairable deformation joint waterproof structure, a construction method and a repair method to solve the problems that leakage of the existing underground side wall deformation joint waterproof structure affects the normal use of the building, leakage detection is difficult and the construction period is long.
[0008] The utility model is realized as follows: a repairable deformation joint waterproof structure, wherein an outer waterproof layer and an outer water stop strip are arranged at the water-facing surface of the deformation joint of the underground side wall;
[0009] A groove is provided in the deformation joint, and a first elastic rod is embedded in the groove;
[0010] A sealant is provided at the back-water opening of the deformation joint, and a second elastic rod is filled inside the sealant;
[0011] A drainage cavity is formed between the first elastic rod and the sealant, and a flexible drainage pipe communicating with the outside is arranged in the drainage cavity.
[0012] Furthermore, the first elastic rod and the second elastic rod are both in the shape of long strips, and are made of elastic materials with telescopic properties, such as rubber, SBS, PE, TPO, etc., so as to play a role in tightly filling and resisting leakage water pressure. Preferably, the width of the groove is the same as the design width of the deformation joint, and the groove is not less than 2mm deep in the wall based on the surface of the deformation joint; the center point of the groove is not less than 60mm away from the back water surface.
[0013] Preferably, the diameter of the first elastic rod is greater than the design width of the deformation joint, the diameter of the first elastic rod is 1.4-1.5 times the design width of the deformation joint, and the length of the first elastic rod is the total length of the deformation joint structure.
[0014] Preferably, the second elastic rod comprises an upper section and a lower section;
[0015] The upper section is filled upward from the position of the flexible drain pipe;
[0016] The lower section is filled upwards from 5cm-30cm above the junction of the underground side wall and the floor decorative surface layer, with a filling height of 30-50cm. The top of the lower section is bent toward the outdoors until it contacts the first elastic rod.
[0017] Preferably, the bending angle of the top of the lower section is 30°-45°.
[0018] Preferably, sealant is filled downward along the second elastic rod from 30 cm above the contact point between the second elastic rod and the first elastic rod.
[0019] Preferably, the tail of the flexible drainage pipe is flush with the inner side surface of the second elastic rod, and an upwardly folded wing is provided at the tail of the pipe.
[0020] By adopting the above technical scheme, the utility model utilizes the drainage cavity to drain the leaking water to the designed position. The first and second elastic rods on both sides can effectively resist water pressure and prevent the accumulated water in the drainage cavity from overflowing. When the amount of water seepage is small, the water seepage can be directly discharged through the flexible drainage pipe, which can effectively reduce the probability of diffuse leakage. There is no trace of water seepage on the wall, no major repair is required, and the use function of the building is not affected. The preferred high-elasticity and low-modulus modified silicone sealant has the strongest ability to resist water leakage, and the water seepage site is inside the colloid. When the leaking water does not completely destroy the colloid, it can recover by itself, and can effectively resist no-pressure or low-pressure water leakage. After serious leakage occurs in the deformation joint of the underground side wall, the leakage point and leakage situation can be found through local cutting and release, and the repair location can be determined. The repair speed is fast, less construction waste is generated, and it is green and environmentally friendly. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0022] Figure 1 It is a top view cross-sectional schematic diagram of the deformation joint of the utility model;
[0023] Figure 2 It is a side cross-sectional schematic diagram of the deformation joint of the utility model;
[0024] Figure 3 It is a structural schematic diagram of the flexible drainage pipe of the utility model;
[0025] Figure 4 It is a schematic diagram of the location of the waterproof structure of the utility model;
[0026] Figure 5 yes Figure 3 Schematic cross-sectional view of .
[0027] In the figure: 1—external waterproof layer, 2—external water stop, 3—extension joint, 4—groove, 5—first elastic rod, 6—sealant, 7—drainage cavity, 8—flexible drainage pipe, 9—second elastic rod, 10—wing, 11—underground side wall, 12—floor decorative surface layer, 13—drainage ditch. DETAILED DESCRIPTION
[0028] The following is a further detailed description of the implementation of the present invention in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but cannot be used to limit the scope of the present invention.
[0029] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.
[0030] like Figure 1-Figure 5As shown, a repairable deformation joint waterproof structure is provided with an outer waterproof layer 1 and an outer water stop 2 in sequence on the water-facing surface of the deformation joint 3 of the underground side wall 11 to form two waterproof layers. A groove 4 is provided in the deformation joint 3, and a first elastic rod 5 is embedded in the groove 4 to form a third waterproof layer. Furthermore, the first elastic rod 5 can be provided as a long round rod, and the material is preferably uniform discontinuous closed-cell foamed EPDM or natural rubber. The compressive stress generated by the first elastic rod 5 is used to resist possible penetration water pressure. For this purpose, the utility model of the present application has tested the material selection of the first elastic rod 5, as follows:
[0031] In this test example, the first elastic rod 5 and the non-foamed EPDM type II rubber sealing gasket conforming to GB18173.4 were subjected to a water pressure resistance test after compression. The test method was to compress the test piece to 50% of the initial thickness starting from 0 MPa, pressurize by 0.1 MPa every 2 hours until leakage occurs, and record the leakage water pressure. The test results are shown in Table 1.
[0032] plan Leakage water pressure The first elastic rod 0.5Mpa Non-foamed EPDM type II rubber sealing gasket 0.3Mpa
[0033] Table 1
[0034] As shown in Table 1, the first elastic rod can effectively resist water pressure and prevent leakage from the deformation joint.
[0035] Furthermore, a sealant 6 is provided at the back-water opening of the deformation joint 3. The sealant 6 preferably adopts a high-elasticity and low-modulus modified silicone sealant material. The sealant 6 forms a water-proof layer and has the function of preventing water from overflowing. The author of the present application conducted tests on the selection of the sealant 6, as follows:
[0036] In this test example, the water pressure resistance test of high-elasticity low-modulus modified silicone sealant, polysulfide sealant and polyurethane sealant was carried out. The test method was to apply the sealant in the through-joint of a rectangular through-joint concrete anti-seepage test block. The width and depth of the sealant were both 20 mm. After reaching the curing age, the test piece was subjected to a water pressure resistance test. The test method was to start pressurization from 0 MPa, and pressurize by 0.1 MPa every 2 hours until leakage occurred. The leakage water pressure and leakage location were recorded. After the water pressure was removed from the test piece and it was dried for 24 hours, the leakage location was searched again. The test results are shown in Table 2.
[0037] plan Leakage water pressure Water seepage area Part Search High elasticity and low modulus modified silicone sealant 0.4Mpa Inside the colloid Directly visible Polysulfide sealant 0.03Mpa Bonding surface The colloid can be seen when pressing with fingers Polyurethane sealant 0.04Mpa Bonding surface The colloid can be seen when pressing with fingers
[0038] Table 2
[0039] As shown in Table 2, sealants can effectively resist water leakage without pressure or at low pressure. For intermittent water leakage, the leakage site can be found by pressing the colloid with fingers or by direct visual inspection. The preferred high-elasticity low-modulus modified silicone sealant has the strongest ability to resist water leakage, and the leakage site is inside the colloid. When the leakage does not completely destroy the colloid, it can recover by itself without major repairs.
[0040] A drainage cavity 7 is formed between the first elastic rod 5 and the sealant 6 of the deformation joint 3, and a flexible drainage pipe 8 connected to the outside is arranged in the drainage cavity 7. After the three waterproof layers at the deformation joint 3 of the underground side wall fail, the deformation joint 3 has a slight leakage. The drainage cavity 7 is used to drain the leaking water to the designed position, that is, the flexible drainage pipe 8 and discharge it. No additional maintenance is required, and the use function of the building is not affected. Further, after a serious leakage occurs in the deformation joint of the underground side wall, it is easy to find the leakage point and determine the repair position. After a serious leakage occurs, the drainage layer fails. Except for the outer waterproof layer and the outer water stop, other measures can be partially cut off for inspection, and the leakage path of the outer waterproof layer can be directly observed, which is convenient for determining the leakage point. The maintenance process is fast and simple. After determining the leakage point, the outer waterproof layer can be vertically penetrated through the deformation joint to perform grouting maintenance operations without drilling holes in the side wall concrete. After the third waterproof layer is partially cut, the failed part can be directly replaced on site and installed to produce a waterproof effect.
[0041] Furthermore, a second elastic rod 9 is provided inside the deformation joint 3 and located inside the sealant 6. The second elastic rod 9 is a long strip of material, and the material is preferably PE, which can further improve the function of preventing water from overflowing.
[0042] Furthermore, one end of the flexible drainage pipe 8 is arranged in the drainage cavity 7, and the other end extends out after passing through the second elastic rod 9 and the sealant 6. A wing 10 is arranged at the inner end of the flexible drainage pipe 8, i.e., the pipe tail. The pipe tail of the flexible drainage pipe 8 is flush with the inner side of the second elastic rod 9. The wing 10 is folded upward along the pipe tail. The wing 10 is made of the same material as the flexible drainage pipe 8. During construction, the wing 10 can be supported on the inner side of the second elastic rod 9 to prevent position changes during construction and use.
[0043] The construction method of the repairable deformation joint waterproof structure of the utility model comprises the following steps:
[0044] Step S1, reserve grooves 4 on both sides of the deformation joint 3 before pouring concrete; further, the width of the groove 4 is the same as the design width of the deformation joint 3, the groove 4 is recessed into the wall by not less than 2mm based on the surface of the deformation joint, and the center point of the groove 4 is not less than 60mm away from the back water surface of the structure.
[0045] Step S2 includes:
[0046] S21, pouring deformation joint 3;
[0047] S22. After the deformation joint 3 is poured, the water stop strip 2 and the waterproof layer 1 are attached to the outside.
[0048] Step S3 includes:
[0049] S31, clean the concrete on both sides of the groove 4 and the deformation joint 3 to ensure that there is no weak base, garbage, etc.;
[0050] S32, fill the first elastic rod 5; the diameter of the first elastic rod 5 is greater than the design width of the deformation joint, preferably, the diameter is not less than 1.4-1.5 times the design width of the deformation joint 3, and the length is the total length of the deformation joint 3 structure.
[0051] The first elastic rod 5 is filled with special machinery. The starting joint is reserved outside the deformation joint 3. The first elastic rod 5 is filled in place step by step and continuously, and a distance of 30 to 50 cm from the starting joint is reserved for the joint. After the joint is completed, a hammer and a nylon chisel are used to fill the closed loop with the independent closed-cell first elastic rod.
[0052] Step S4 includes:
[0053] S41, filling the upper section of the second elastic rod 9;
[0054] Before filling the second elastic rod 9, clean both sides of the deformation joint 3. The diameter of the second elastic rod 9 is about 1.3 to 1.5 times the design width of the deformation joint. Except for the 30 to 50 cm above the intersection of the underground side wall and the floor decoration surface layer inside the deformation joint, the rest of the parts are filled with the second elastic rod 9. The distance between the second elastic rod 9 and the back water surface structure surface layer is greater than 1 / 2 of the design width of the deformation joint.
[0055] S42. Paste masking tape with a width of not less than 16mm. The inner side of the masking tape should be parallel to the edge of the expansion joint. Apply the matching sealant primer if necessary, fill the expansion joint with high-elasticity and low-modulus modified silicone sealant along the second elastic rod, squeeze it tightly, and then remove the masking tape.
[0056] Step S5, filling the lower section of the second elastic rod 9 and placing a flexible drainage pipe at the same time; comprising:
[0057] S51, starting from the position 5cm-30cm upward from the inside of the deformation joint along the intersection of the underground side wall 11 and the floor decorative surface layer 12, the lower section of the second elastic rod 9 is filled upward, preferably at 5cm, and the top of the lower section of the second elastic rod 9 forms an angle of 30°-45° with the ground, and slopes toward the outdoors;
[0058] S52, fill the sealant 6 with a height of not less than 30 cm upwards from the intersection of the second elastic rod 9 and the first elastic rod 5, and fill the sealant 6 downwards along the second elastic rod. The width of the sealant 6 is the same as the design width of the deformation joint, and the depth is 1 / 2 of the width.
[0059] S53. Place a flexible drainage pipe with a single-sided wing 10, with the pipe outlet at least 2 cm from the deformation joint. The side with the wing is the pipe tail, which is flush with the inner side of the outer sealant; the outer diameter of the flexible drainage pipe is at least 6 mm smaller than the width of the deformation joint, and the flexible drainage pipe is placed in the center.
[0060] S6. Fill with sealant: Use sealant to fill the unconstructed area of 30cm to 50cm from the back of the deformation joint and the structural joint on the water surface.
[0061] The drainage ditch 13 is used to guide the water flowing out of the flexible drainage pipe 8 through the drainage cavity 7 to the basement water collection well.
[0062] The utility model discloses a method for repairing leakage of a repairable deformation joint waterproof structure. When leakage occurs in the deformation joint of an underground side wall, there are three situations: A1, A2 and A3.
[0063] A1. If the leakage does not cause the sealant to fall off or seep, no treatment will be required.
[0064] A2. If the leakage causes the sealant to fall off or seep water, check the sealant adhesion by finger pressure, use a utility knife to cut the poorly bonded parts along both sides of the deformation joint concrete, and the cutting length should be at least 10cm longer than the part with the bonding problem on each side, and cut the second elastic rod on the back side of the sealant, remove the cut material, and check the first elastic rod for water leakage until the leakage point is found.
[0065] Further, a1. Use professional removal tools to remove the first elastic rod at the leaking part. If there is sealant blocking the removal process, the sealant blocking the sealant should be further removed, and the first elastic rod at the leaking part should be pulled out of the deformation joint; cut the removed first elastic rod, and pull both ends of the cut first elastic rod out of the deformation joint. The length of the deformation joint at each end should be no less than the damaged part plus 10cm. Cut the first elastic rod along the diameter direction along the cut-off position of the damaged part at each end, and put the cut end into a steel pipe with a length of 5-8cm and an inner diameter of the same size as the first elastic rod, and reserve more than 1cm for cutting. Perform a second cut on the first elastic rod along the end side of the steel pipe to ensure a smooth cutting surface.
[0066] a2. If water gushes or appears at the leakage site, the leakage situation should be observed, the deformation joints should be cleaned and grouting materials should be used to pass through the outer waterproof layer to seal the leakage site. After the visible water stops, the deformation joints should be cleaned and dried.
[0067] a3. Use a new first elastic rod with the same diameter and length as the cut part to connect the two ends, so that the first elastic rod forms a closed loop again and is inserted into the groove of the deformation joint. Restore the removed sealant.
[0068] A3. If the waterproofing fails because the actual width of the expansion joint increases, the waterproofing structure of the part where the expansion joint width changes should be removed, or the entire expansion joint can be removed, and the first elastic rod with a suitable diameter should be reselected, using the method described above.
[0069] The utility model utilizes the drainage cavity to drain the leaking water to the designed position. The first and second elastic rods on both sides can effectively resist the water pressure and prevent the accumulated water in the drainage cavity from overflowing. When the amount of water seepage is small, the water seepage can be directly discharged through the flexible drainage pipe, which can effectively reduce the probability of diffuse leakage. There is no trace of water seepage on the wall, no major repair is required, and the use function of the building is not affected. The preferred high-elasticity and low-modulus modified silicone sealant has the strongest ability to resist water leakage, and the water seepage site is inside the colloid. When the leaking water does not completely destroy the colloid, it can recover by itself, and can effectively resist no-pressure or low-pressure water leakage. After serious leakage occurs in the deformation joint of the underground side wall, it is easy to find the leakage point and leakage situation, determine the repair location, and the repair speed is fast, less construction waste is generated, and it is green and environmentally friendly.
[0070] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A repairable deformation joint waterproof structure, characterized in that An external waterproof layer and an external water stop are provided on the water-facing surface of the underground side wall deformation joint; A groove is provided in the deformation joint, and a first elastic rod is embedded in the groove; A sealant is provided at the back-water opening of the deformation joint, and a second elastic rod is filled inside the sealant; A drainage cavity is formed between the first elastic rod and the sealant, and a flexible drainage pipe communicating with the outside is arranged in the drainage cavity.
2. The repairable expansion joint waterproof structure according to claim 1 is characterized in that: The width of the groove is the same as the design width of the deformation joint, and the groove is recessed into the wall by no less than 2 mm based on the surface of the deformation joint; the center point of the groove is no less than 60 mm away from the back water surface.
3. The repairable deformation joint waterproof structure according to claim 1 is characterized in that: The diameter of the first elastic rod is greater than the design width of the deformation joint, the diameter of the first elastic rod is 1.4-1.5 times the design width of the deformation joint, and the length of the first elastic rod is the total length of the deformation joint structure.
4. The repairable deformation joint waterproof structure according to claim 1 is characterized in that: The second elastic rod comprises an upper section and a lower section; The upper section is filled upward from the position of the flexible drain pipe; The lower section is filled upwards from 5cm-30cm above the junction of the underground side wall and the floor decorative surface layer, with a filling height of 30-50cm. The top of the lower section is bent toward the outdoors until it contacts the first elastic rod.
5. The repairable deformation joint waterproof structure according to claim 4 is characterized in that: The bending angle of the top of the lower section is 30°-45°.
6. The repairable expansion joint waterproof structure according to claim 4 is characterized in that: The sealant is filled downward along the second elastic rod from 30 cm above the contact point between the second elastic rod and the first elastic rod.
7. The repairable expansion joint waterproof structure according to claim 1 is characterized in that: The tail of the flexible drainage pipe is flush with the inner side surface of the second elastic rod, and an upwardly folded wing is arranged at the tail of the pipe.
Citation Information
Cited By
Repairable deformation joint waterproof structure, construction method and repairing method
CN117926926A