Through the support form system and segmented symmetric casting technology without support frames, the problems of complex and high cost of supporting frames in V-shaped reinforced concrete inclined column construction are solved, and the construction accuracy and efficiency are improved. It is suitable for high-rise buildings. .

CN222066145UActive Publication Date: 2024-11-26CHINA METALLURGICAL CONSTR ENG GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202322945737.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-10-31
Publication Date
2024-11-26
Estimated Expiration
2033-10-31

AI Technical Summary

Technical Problem

The construction of V-shaped reinforced concrete inclined columns is difficult and has horizontal component forces, which leads to complex installation of support frames, high engineering volume, high cost, and high foundation treatment requirements.

Method used

Adopt a support formwork system without support frames. By setting up a tie structure and symmetric casting in sections between V-shaped reinforced concrete inclined columns, self-balancing of the force is achieved, the support frame is erected, and the use of fixed formwork, reinforced steel pipes, Components such as flower basket bolts, rigid pull rods and cable-stayed wire ropes ensure construction accuracy and quality.

Benefits of technology

It reduces the amount of support frame erecting projects, saves construction period and costs, is suitable for high-rise independent inclined column construction, and improves the adaptability and efficiency of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222066145U_ABST
    Figure CN222066145U_ABST
Patent Text Reader

Abstract

The utility model discloses a formwork system for a V-shaped reinforced concrete batter post. The formwork system comprises a shaping formwork arranged on the outer side of a reinforcement cage of an inner cavity of the batter post, a shaping steel hoop arranged on the outer side of the shaping formwork and a reinforcing steel pipe arranged between the shaping steel hoop and the shaping formwork. The reinforcing steel pipes are used for connecting and reinforcing the typified formworks at the formwork sections to enable the typified formworks to form a whole, the typified steel hoops are used for fixing the reinforcing steel pipes, and a tying structure is arranged between the two typified steel hoops located at the same height position of two inclined columns of the V-shaped reinforced concrete. According to the formwork supporting system provided by the utility model, the erection of a supporting frame body is canceled, and a tie structure between the inclined columns is adopted and concrete is combined to carry out segmented and symmetrical pouring, so that the self-balance mode of stress is achieved for construction; the formwork system does not need to be provided with a support, can save the construction period and cost, can be suitable for high independent inclined column construction, and is high in adaptability.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction, in particular to a formwork system for V-shaped reinforced concrete inclined columns. Background Art

[0002] Traditional reinforced concrete columns are basically vertical to the ground, with a small range of center of gravity change and simple positioning. However, in order to achieve functions or display effects, some frame columns of high-rise buildings are set as inclined columns. Since inclined columns and ordinary frame columns have certain differences in construction load transfer methods and construction processes, the construction of inclined columns is usually more difficult and requires higher construction precision.

[0003] The construction of V-shaped reinforced concrete inclined columns is even more difficult. Since the V-shaped reinforced concrete inclined columns form a certain angle with the ground, there is a horizontal force component during the construction of the inclined columns, and the column formwork has a tendency to overturn. In order to ensure the accuracy and quality of the column construction, it is usually adopted to add inclined supports on one side of the inclined columns or set up rigid trusses to resist the horizontal thrust. At the same time, when the inclined columns are cast in sections, the support frame is gradually erected as the column height increases, and the amount of work for the inclined support formwork will gradually increase. At the same time, the support force calculation and structure will become more complicated; the construction period and cost of erecting the support frame and the construction scaffolding separately are long and high, and the inclined columns transmit force to the ground foundation through the inclined supports, which requires high foundation treatment.

[0004] Therefore, in order to reduce the amount of work required to erect the inclined support frame and reduce the foundation treatment process, it is necessary to improve the existing V-shaped reinforced concrete inclined column formwork system, so as to achieve the purpose of reducing or eliminating the erection of the support frame, saving construction time and reducing costs. Utility Model Content

[0005] In view of this, the utility model provides a formwork system for V-shaped reinforced concrete inclined columns, which eliminates the need for setting up a support frame, and adopts a tie structure between the inclined columns and symmetrically casts concrete in sections to achieve self-balancing force. This formwork system does not require the setting up of a support frame, which can save construction time and reduce costs.

[0006] The utility model provides a formwork system for V-shaped reinforced concrete inclined columns, comprising a forming template arranged outside a steel cage of an inner cavity of the inclined column, a forming steel hoop arranged outside the forming template, and a reinforcing steel pipe arranged between the forming steel hoop and the forming template, the reinforcing steel pipe being used to connect and reinforce the forming template at the template sections so that the forming template forms a whole, the forming steel hoop being used to fix the reinforcing steel pipe, and a tie structure being arranged between two of the forming steel hoops located at the same height on two inclined columns of the V-shaped reinforced concrete.

[0007] Furthermore, the tie structure includes a basket bolt, which is used to adjust the horizontal spacing of the entire forming formwork on the two inclined columns of the V-shaped reinforced concrete to achieve positioning.

[0008] Furthermore, the tie structure also includes a rigid tie rod, and the rigid tie rod is used to ensure the overall rigidity of the shaping template.

[0009] Furthermore, the shaped steel hoop is composed of two semicircular hoops, and the ends of the semicircular hoops in the length direction are provided with connecting parts, and the connecting parts of the two semicircular hoops are fixed by bolts to form the shaped steel hoop as a whole.

[0010] Furthermore, one side connection parts of the two shaped steel hoops located at the same height on the two inclined columns of the V-shaped reinforced concrete are arranged opposite to each other, and the connecting ends of the basket bolts and the rigid pull rods are respectively connected to the connection parts of the two shaped steel hoops.

[0011] Furthermore, the other side connection parts of the two shaped steel hoops located at the same height position on the two inclined columns of the V-shaped reinforced concrete are connected to the steel anchors set on the ground through inclined steel wire ropes.

[0012] Furthermore, the shaping template is formed by splicing two semicircular templates and a cylindrical shaping template reinforcing steel belt is arranged on the outside for reinforcement, and the splicing structure between the two semicircular templates is a mortise and tenon structure.

[0013] The beneficial effects of the utility model are as follows: the formwork system for V-shaped reinforced concrete inclined columns provided by the utility model eliminates the erection of the support frame, and is constructed in a self-balancing manner by means of a tie structure between the inclined columns and symmetrical pouring of concrete in sections; compared with conventional inclined support methods, this construction method does not require the installation of supports, which can save construction time and costs, and can also be applied to the construction of relatively high independent inclined columns, with strong adaptability. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] The utility model is further described below in conjunction with the accompanying drawings and embodiments:

[0015] Figure 1 It is a structural schematic diagram of the formwork system of the V-shaped reinforced concrete inclined column in the utility model;

[0016] Figure 2 for Figure 1 AA cross-section diagram;

[0017] Figure 3 It is a schematic diagram of the coordination between the main reinforcement of the column and the positioning reinforcement in the utility model;

[0018] Figure 4 This is a schematic diagram of the structure of the shaped steel hoop in the utility model;

[0019] Explanation of the reference numerals: 1-main reinforcement of column; 2-hoops; 3-shaped steel hoops; 4-reinforced steel pipes; 5-angle steel; 6-angle steel fixing steel bars; 7-cylindrical shaped formwork; 8-scaffolding; 9-operating platform; 10-spatial positioning axis; 11-guardrails; 12-cylindrical shaped formwork reinforcement steel belt; 13-angle steel rigid pull rod; 14-oblique tension wire rope; 15-hand winch; 16-basket bolt; 17-pull-out anchor bolt; 18-wire rope; 19-plumb ball; 20-positioning steel bars; 21-ground; 22-cast section; 23-formwork installation section; 24-steel bar installation section; 25-wire rope suspension cross bar. DETAILED DESCRIPTION

[0020] As shown in the figure, the formwork system for V-shaped reinforced concrete inclined columns provided by the utility model includes a forming template arranged outside the steel cage of the inner cavity of the inclined column, a forming steel hoop 3 arranged outside the forming template, and a reinforcing steel pipe 4 arranged between the forming steel hoop and the forming template, the reinforcing steel pipe 4 is used to connect and reinforce the forming template at the template section to form the forming template as a whole, the forming steel hoop 3 is used to fix the reinforcing steel pipe 4, and a tie structure is arranged between the two forming steel hoops 3 located at the same height position on the two inclined columns of the V-shaped reinforced concrete; wherein in order to solve the problem of the concrete casting molding quality of the circular column while taking into account the cost, the forming template adopts a forming cylindrical template 1, and by arranging A reinforcing steel pipe 4 is arranged to realize the connection and reinforcement of multiple circular fixed formworks 1 at the formwork sections and to make the fixed formworks form an overall formwork structure, and the fixed steel hoop 3 can fix the reinforcing steel pipe 4 between the fixed steel hoop 3 and the circular fixed formwork 1 to form a formwork structure on the inclined column; and by arranging a tie structure between the two fixed steel hoops 3 located at the same height position on the two inclined columns of the V-shaped reinforced concrete during the formwork erection process, the formwork structures on the two inclined columns can be connected and form a tie structure, thereby reducing the workload of erecting the inclined support frame. Compared with the conventional inclined support method, this construction method does not require the installation of support, can save construction period and cost, and can be suitable for the construction of higher independent inclined columns, with strong adaptability.

[0021] In this embodiment, the anchoring structure includes a basket bolt 16, which is used to adjust the horizontal spacing of the overall shaped formwork on the two inclined columns of the V-shaped reinforced concrete to achieve positioning; the anchoring structure also includes a rigid tie rod, which is used to ensure the overall rigidity of the formwork system; wherein the rigid tie rod is an angle steel rigid tie rod 13. During the formwork erection process, in order to ensure that the overall formwork is consistent with the simulated BIM model, the basket bolt 16 is selected to adjust the horizontal spacing of the overall shaped formwork on the two inclined columns, and the angle steel rigid tie rod 13 can provide a guarantee for the overall rigidity of the formwork system after verification and adjustment.

[0022] In this embodiment, the shaped steel hoop 3 is composed of two semicircular hoops, and the ends of the semicircular hoops in the length direction are provided with connecting parts, and the connecting parts of the two semicircular hoops are fixed by bolts to form a shaped steel hoop as a whole; the connecting parts on one side of the two shaped steel hoops located at the same height position on the two inclined columns of the V-shaped reinforced concrete are arranged opposite to each other, and the connecting ends of the basket bolts and the rigid pull rods are respectively connected to the connecting parts of the two shaped steel hoops; the connecting parts on the other side of the two shaped steel hoops 3 located at the same height position on the two inclined columns of the V-shaped reinforced concrete are connected to the steel anchors set on the ground through inclined steel wire ropes 14. Figure 4 As shown, the connection parts of the two semicircular hoops are connected by high-strength bolts to form a fixed steel hoop 3 as a whole. The high-strength bolt connection side of the fixed steel hoop 3 should be aligned with the X-axis direction of the V-shaped column. In this formwork system, they are connected by inclined steel wire ropes 14, horizontal basket bolts 16 and angle steel rigid pull rods 13. The spatial structural system of the overall formwork system is stable and the quality is reliable.

[0023] In this embodiment, the shaping template is formed by splicing two semicircular templates and a cylindrical shaping template reinforcement steel belt 12 is arranged on the outside for reinforcement. The splicing structure between the two semicircular templates is a mortise and tenon structure; the cylindrical shaping template 7 adopts a shaped and processed wooden template, and the wooden template is fixed with a cylindrical shaping template reinforcement steel belt 12, and additional reinforcing steel 4 tubes and shaping steel clamps 3 are added, so that the overall template reinforcement has good rigidity and is not easy to deform, and the components can be used in a turnover manner.

[0024] This embodiment also relates to a construction method for a V-shaped reinforced concrete inclined column without support, wherein the fixed formwork is installed using the above-mentioned formwork system for formwork support, and the construction method includes the following steps:

[0025] S1. Measure the ground axis and set out: Lead the axis to the V-shaped column floor through the floor setting-out hole, and pop out the X-direction and Y-direction ground axis control lines on the ground in both directions of the V-shaped column to control the accurate positioning of the axis in the subsequent construction process in this construction section;

[0026] S2, gradually erect scaffolding 8 according to the column segment construction height, and set up construction operation platform 9 and install guardrail 11 at the segment position;

[0027] S3, column reinforcement binding: Cut the reinforcement according to the drawings, and install the column main reinforcement 1 and stirrups 2 one by one on the operating platform 9 to form an inclined column frame structure; after the column main reinforcement 1 is installed, the position of the inclined column frame structure is checked through the high-altitude positioning axis 10;

[0028] S4, installation of the finalized formwork: the cylindrical finalized formwork 7 is installed from the bottom of the column of the construction section upwards section by section, and a reinforcing steel pipe 4 is arranged on the outside of the formwork; a finalized steel clamp 3 for fixing the reinforcing steel pipe is arranged on the outside of the reinforcing steel pipe 4, and after the formwork is reviewed and positioned, an angle steel rigid tie rod 13 is installed between the finalized steel clamps 3 at the same height of adjacent inclined columns to ensure the overall rigidity;

[0029] S5, pouring concrete in layers, and vibrating with a concrete vibrator;

[0030] S6. Remove the formwork and carry out maintenance

[0031] S7. Repeat steps S1-S6 to carry out construction of the next construction section.

[0032] In step S1, the axis is mainly measured to the V-shaped column floor through the floor layout hole, and the X-direction and Y-direction ground axis control lines are popped up on the ground in two directions of the V-shaped column respectively; at the same time, before measuring and laying out, the three-dimensional coordinates of the edge of the shaped steel clamp 9 should be extracted through the BIM model to facilitate the control of the column space positioning; and the high-altitude column positioning and laying out is to hang a plumb bob 19 on the operating platform 9 to lead the ground axis to a high altitude, first hang an X-direction plumb line to lead the X-direction long axis to a high altitude, and then adjust the Y-direction column space positioning inclined steel wire rope 14 to ensure that the column is aligned with the axis in the Y direction, and then hang the Y-direction plumb line to lead the Y-direction short axis to a high altitude, and then use the coil to measure the X-direction distance from the axis, and adjust the basket bolt 16 and the inclined steel wire rope 14 to control the column in the X-direction column position. After the main reinforcement 1 of the column and the cylindrical forming formwork 7 are installed but before they are fixed, the axis line should be measured and the column position should be adjusted, and the total station should be used for re-measurement to ensure that the axis positioning is accurate; in step S5, the concrete pouring of the V-shaped inclined column should be carried out in layers, and the height of the asymmetric concrete pouring of the double columns should be strictly controlled. The concrete pouring must be sleeved to avoid direct impact of the concrete on the formwork; at the same time, the concrete vibrator is lowered along the angle steel 5 to the bottom of the column, and vibration is started to ensure that the concrete is dense.

[0033] In this embodiment, in step S2, a wire rope suspension cross bar 25 is provided on the top of the operating platform 9, and the wire rope 18 passes around the wire rope suspension cross bar 25 and a plumb bob 19 is suspended at the end to lead the ground axis of the ground XY direction to the top of the column for verifying the spatial position of the column; at the same time, in step S2, the scaffolding 8 is gradually erected according to the segmented construction height of the column, the construction operating platform 9 is set at the segmented position and the guardrail 11 is installed, and the operating platform 9 is firmly erected to meet the construction requirements of the concrete pouring operator.

[0034] In this embodiment, in step S3, the inclined column frame structure is also provided with angle steel fixing steel bars 6 and angle steel 5, the angle steel fixing steel bars 6 are welded to the stirrups 2, and the angle steel 5 is welded to the angle steel fixing steel bars 6; the purpose of providing the angle steel 5 is to allow the concrete vibrator to slide down along the angle steel to the bottom of the column to ensure that the concrete is vibrated and compacted along the entire height, wherein the number and spacing of the angle steels should be determined based on the calculation of the column cross section to ensure that the entire cross section of the column can be vibrated and compacted.

[0035] In this embodiment, at least one column positioning steel bar 20 should be provided when binding the column main reinforcement 1 to ensure the accurate position of the column main reinforcement 1; an inclined steel wire rope 14 is provided between the inclined column frame structure and the ground, and a hand winch 15 for adjusting the tightening degree is provided on the inclined steel wire rope 14; an anti-pullout anchor bolt 17 is provided in the inclined column frame structure, and a basket bolt 16 is provided between the anti-pullout anchor bolts 17 of adjacent inclined column frame structures, and the basket bolt 16 is used to connect adjacent inclined column frame structures and adjust the tightening degree; after the installation of the column main reinforcement 1 is completed, the position is verified through the high-altitude positioning axis 10 to ensure that it is correct, and then the inclined steel wire rope 14 and the basket bolt 16 are locked, wherein the length of the inclined steel wire rope 14 is adjusted by the hand winch 15, and the bottom of the inclined steel wire rope 14 is connected to the steel anchor provided on the ground 21; at the same time, the anti-pullout anchor bolt 17 is pre-embedded in the appropriate position of the steel cage, and is firmly welded to the inclined column frame structure.

[0036] In this embodiment, in step S4, the cylindrical shaping template 7 is formed by splicing two semicircular templates and fixing them with a cylindrical shaping template reinforcement steel belt 12, and the two semicircular templates are connected by a mortise and tenon structure; the cylindrical shaping template 7 adopts a shaped and processed wooden template, and the wooden template is connected by a concave and convex tenon groove. The cylindrical shaping template is spliced ​​by two semicircular templates and fixed with a cylindrical shaping template reinforcement steel belt 12; the cylindrical shaping template 7 is installed from the bottom of the column upward section by section, because the template section is not easy to fix, so along the entire A reinforcing steel pipe 4 is arranged on the outside of the formwork to form the entire formwork as a whole; a shaped steel hoop 3 is arranged on the outside of the reinforcing steel pipe 4 to reinforce the steel pipe 4. The shaped steel hoop 3 is composed of two semicircles and is connected by high-strength bolts. The high-strength bolt connection side of the shaped steel hoop 3 should be aligned with the X-axis direction of the V-shaped column. The X-direction distance of the formwork is adjusted by adjusting the basket bolts 16 arranged on the shaped steel hoop 3 to achieve the positioning purpose. After the high-altitude verification and positioning of the formwork is completed, an angle steel rigid pull rod 13 is installed on the shaped steel hoop 3 to ensure the overall rigidity.

[0037] In this embodiment, in step S6, when the formwork is removed, the concrete strength should reach more than 50%. First, remove the angle steel rigid pull rod 13, then loosen the inclined steel wire rope 14 and the basket bolt 16, remove the shaping steel clamp 3 and the cylindrical shaping formwork 4, and clean up the turnover materials; when the formwork is removed, clean out the connecting thread of the embedded anti-pullout anchor 17, screw on the pull ring, and use the basket bolt 16 to connect and tighten the two V-shaped columns.

[0038] In this embodiment, in step S6, after the formwork is removed, water is first poured and then a plastic film is wrapped around the column for maintenance.

[0039] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the utility model rather than to limit it. Although the utility model has been described in detail with reference to the preferred embodiments, ordinary technicians in the field should understand that the technical solution of the utility model can be modified or replaced by equivalents without departing from the purpose and scope of the technical solution of the utility model, which should be included in the scope of the claims of the utility model.

Claims

1. A formwork system for V-shaped reinforced concrete inclined columns, characterized in that: It includes a forming template arranged outside the steel cage of the inner cavity of the inclined column, a forming steel hoop arranged outside the forming template, and a reinforcing steel pipe arranged between the forming steel hoop and the forming template. The reinforcing steel pipe is used to connect and reinforce the forming template at the template sections so that the forming template forms a whole. The forming steel hoop is used to fix the reinforcing steel pipe. A tie structure is arranged between the two forming steel hoops located at the same height position on the two inclined columns of the V-shaped reinforced concrete.

2. The formwork system for V-shaped reinforced concrete inclined columns according to claim 1, characterized in that: The tie structure includes a basket bolt, which is used to adjust the horizontal spacing of the entire forming formwork on two inclined columns of the V-shaped reinforced concrete to achieve positioning.

3. The formwork system for V-shaped reinforced concrete inclined columns according to claim 2, characterized in that: The tie structure also includes a rigid tie rod, which is used to ensure the overall rigidity of the shaping template.

4. The formwork system for V-shaped reinforced concrete inclined columns according to claim 3, characterized in that: The shaped steel hoop is composed of two semicircular hoops, and the ends of the semicircular hoops in the length direction are provided with connecting parts. The connecting parts of the two semicircular hoops are connected and fixed by bolts to form the shaped steel hoop as a whole.

5. The formwork system for V-shaped reinforced concrete inclined columns according to claim 4, characterized in that: One side connection parts of the two shaped steel hoops located at the same height position on the two inclined columns of the V-shaped reinforced concrete are arranged opposite to each other, and the connecting ends of the basket bolts and the rigid pull rods are respectively connected to the connection parts of the two shaped steel hoops.

6. The formwork system for V-shaped reinforced concrete inclined columns according to claim 5, characterized in that: The other side connection parts of the two shaped steel clamps located at the same height position on the two inclined columns of the V-shaped reinforced concrete are connected to the steel bar anchors arranged on the ground through inclined steel wire ropes.

7. The formwork system for V-shaped reinforced concrete inclined columns according to claim 1, characterized in that: The shaping template is formed by splicing two semicircular templates and a cylindrical shaping template reinforcing steel belt is arranged on the outside for reinforcement. The splicing structure between the two semicircular templates is a mortise and tenon structure.