Ton bag conveying system

By designing a combination of pallets, conveying devices and centering devices, long-distance accurate conveying of ton bags is achieved, solving the problems of low efficiency and low automation of ton bags in the prior art, and improving the conveying efficiency and safety.

CN222081628UActive Publication Date: 2024-11-29ZHE JIANG RUAN KONG ZHI NENG KE JI GU FEN YOU XIAN GONG SI
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420424038.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-05
Publication Date
2024-11-29
Estimated Expiration
2034-03-05

AI Technical Summary

Technical Problem

The existing ton bag conveying methods are inefficient and poorly safe, with material pollution or leakage problems, and the robotic arm conveying distance is limited and precise positioning is difficult, resulting in low conveying efficiency.

Method used

A ton pack conveying system including a pallet, a conveying device, a centering device and a hoisting device are designed to realize long-distance movement of the pallet through roller lines and roller sprockets, and to realize ton packs of the pallets in combination with side thrust and forward thrust components. Accurate positioning and automated conveying, and optimize the conveying process with detector parts.

Benefits of technology

It improves the efficiency and automation of ton bags, realizes accurate long-distance transportation, reduces manpower investment, and enhances the stability and safety of the system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222081628U_ABST
    Figure CN222081628U_ABST
Patent Text Reader

Abstract

The utility model discloses a ton bag conveying system which is used for conveying ton bags and comprises a tray, a conveying device, a centering device and a jacking device, the conveying device comprises a first conveying unit and a second conveying unit, at the beginning, the ton bags are arranged on the tray, and the tray moves along the first conveying unit until reaching the second conveying unit; the jacking device jacks the tray upwards, then the centering device pushes the ton bag, the ton bag and the tray move relative to the jacking device, and after the ton bag and the tray are adjusted to the proper position, the centering device does not push the ton bag any more. In the process, the ton bag conveying system completes automatic conveying and centering of the ton bags, long-distance conveying and accurate positioning of the ton bags are achieved, and therefore the conveying efficiency of the ton bags is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of ton bag conveying equipment, in particular to a ton bag conveying system. Background Art

[0002] In the prior art, ton bags are used to store materials. When the materials are needed, the ton bags are manually placed at the designated location. This manual method of transporting ton bags is inefficient and unsafe, and there may be problems such as material contamination or leakage during the transportation process. In addition, in the prior art, a robotic arm is also used to transport ton bags, and the robotic arm is used to grab and clamp the ton bags to the designated location. This method of transporting ton bags has a large distance limitation and can only achieve close-range grabbing of ton bags. In addition, it is not easy for the robotic arm to accurately position the ton bags, resulting in low transportation efficiency for the ton bags. Therefore, the existing ton bag transportation process has problems such as low transportation efficiency, long transportation time, and low degree of transportation automation.

[0003] Therefore, how to improve the transportation efficiency of ton bags is a technical problem that technicians in this field currently need to solve. Utility Model Content

[0004] In view of this, the purpose of the utility model is to provide a ton bag conveying system to improve the conveying efficiency of ton bags;

[0005] In order to achieve the above purpose, the utility model provides the following technical solutions:

[0006] A ton bag conveying system is used to convey ton bags, comprising a pallet, a conveying device, a centering device and a lifting device, wherein:

[0007] Pallets are used to carry ton bags;

[0008] The conveying device comprises a first conveying unit and a second conveying unit;

[0009] The first conveying unit is connected to the second conveying unit, and the tray can move along the first conveying unit to the second conveying unit;

[0010] The lifting device is arranged below the second conveying unit and can be extended and retracted in the vertical direction;

[0011] The centering device is arranged on the side of the second conveying unit and is used to push the ton bag to move.

[0012] Optionally, in the above-mentioned ton bag conveying system, the first conveying unit is a roller line, the ton bag is arranged above the pallet, and the pallet is arranged on the roller line and can move along the roller line.

[0013] Optionally, in the above-mentioned ton bag conveying system, the second conveying unit includes a conveying bracket, a roller sprocket and a conveying motor. There are two roller sprockets, which are relatively arranged on the first side and the second side of the conveying bracket. The roller sprocket is connected to the roller line and is used to convey the pallet to a preset position. The conveying motor is connected to the roller sprocket and is used to drive the roller sprocket to move.

[0014] Optionally, in the above-mentioned ton bag conveying system, the ton bag conveying system also includes a control device, the second conveying unit also includes a deceleration signal detector and an in-place signal detector, the conveying motor, roller line, deceleration signal detector and in-place signal detector are electrically connected to the control device, the deceleration signal detector is arranged close to the first conveying unit, and is used to output a deceleration signal to the control device, and the in-place signal detector is arranged close to the lifting device, and is used to output an in-place signal to the control device.

[0015] Optionally, in the above-mentioned ton bag conveying system, the centering device includes a side push assembly, the side push assembly includes a side push bracket, a side push cylinder and a side push baffle, the side push bracket is used to carry the side push cylinder and the side push baffle, the side push cylinder is connected to the side push baffle, and is used to push out and retract the side push baffle, the number of side push assemblies is two, and they are arranged relative to the first side of the second conveying unit and the second side of the second conveying unit, and the side push baffle is used to push the ton bag to move along the first direction.

[0016] Optionally, in the above-mentioned ton bag conveying system, the centering device also includes a forward pushing assembly, which is away from the first conveying unit and arranged on the third side of the second conveying unit. The forward pushing assembly includes a forward pushing bracket, a forward pushing cylinder and a forward pushing baffle. The forward pushing bracket is used to carry the forward pushing cylinder and the forward pushing baffle. The forward pushing cylinder is connected to the forward pushing baffle and is used to push out and retract the forward pushing baffle. The forward pushing baffle is used to push the ton bag to move along the second direction, and the first direction is perpendicular to the second direction.

[0017] Optionally, in the above-mentioned ton bag conveying system, the jacking device includes a jacking bracket, a jacking cylinder, a movable plate, a steering wheel and a steering wheel mounting seat. The steering wheel mounting seat is arranged at the top of the jacking bracket for mounting multiple steering wheels. The movable plate is arranged at the top of the steering wheel. The jacking cylinder is arranged at the bottom of the movable plate for pushing out and retracting the movable plate in the vertical direction.

[0018] Optionally, in the above-mentioned ton bag conveying system, the ton bag conveying system also includes a back-push assembly, which is arranged on the fourth side of the second conveying unit, and includes a back-push cylinder and a back-push baffle. The back-push cylinder is connected to the back-push baffle and is used to push out and retract the back-push baffle. The back-push baffle is used to push the movable plate to move along the second direction.

[0019] Optionally, in the above-mentioned ton bag conveying system, the side push assembly also includes a reset cylinder and a reset baffle, the reset cylinder is arranged on the side push bracket, and the reset cylinder is connected to the reset baffle for pushing out and retracting the reset baffle, and the reset baffle is used to push the movable disk to move along the first direction.

[0020] Optionally, in the above-mentioned ton bag conveying system, the second conveying unit also includes two limiting plates, which are arranged relatively on the first side and the second side of the conveying bracket to limit the pallet.

[0021] The ton bag conveying system provided by the utility model is that, initially, the ton bag is arranged on the pallet, and the pallet moves along the first conveying unit until it reaches the second conveying unit, and the lifting device lifts the pallet upward, and then the centering device pushes the ton bag, and the ton bag and the pallet move relative to the lifting device. After being adjusted to a suitable position, the centering device no longer pushes the ton bag. In the above process, the ton bag conveying system completes the automatic conveying and centering of the ton bag, realizes the long-distance conveying and precise positioning of the ton bag, and thus improves the conveying efficiency of the ton bag. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0023] Figure 1 This is a schematic diagram of the structure of a ton bag disclosed in an embodiment of the utility model;

[0024] Figure 2 A schematic diagram of the structure of a first conveying unit disclosed in an embodiment of the utility model;

[0025] Figure 3 It is a front view of the first conveying unit disclosed in the embodiment of the utility model;

[0026] Figure 4 It is a structural schematic diagram of the second conveying unit disclosed in the embodiment of the utility model;

[0027] Figure 5 A three-dimensional diagram of a lifting device disclosed in an embodiment of the utility model;

[0028] Figure 6 It is a front view of the lifting device disclosed in the embodiment of the utility model;

[0029] Figure 7 It is a front view of the side thrust assembly disclosed in the embodiment of the utility model;

[0030] Figure 8 A three-dimensional diagram of a side thrust assembly disclosed in an embodiment of the utility model;

[0031] Fig. 9 It is a front view of the forward push assembly disclosed in the embodiment of the utility model;

[0032] Fig.10 A three-dimensional diagram of a forward push assembly disclosed in an embodiment of the utility model;

[0033] Fig.11 This is a front view of the ton bag conveying system disclosed in the embodiment of the utility model;

[0034] Fig.12 A three-dimensional diagram of a ton bag conveying system disclosed in an embodiment of the utility model;

[0035] in:

[0036] Tray 100;

[0037] First conveying unit 200, roller line 201;

[0038] The second conveying unit 300, the conveying bracket 301, the roller sprocket 302, the conveying motor 303, the deceleration signal detector 304, the in-position signal detector 305, and the limit plate 306;

[0039] Lifting device 400, lifting bracket 401, lifting cylinder 402, moving plate 403, steering wheel 404, steering wheel mounting seat 405;

[0040] Side thrust assembly 500, side thrust bracket 501, side thrust cylinder 502, side thrust baffle 503;

[0041] A forward push assembly 600, a forward push bracket 601, a forward push cylinder 602, and a forward push baffle 603;

[0042] A rear push assembly 700, a rear push cylinder 701, and a rear push baffle 702;

[0043] Reset cylinder 800 and reset baffle 801. DETAILED DESCRIPTION

[0044] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without making novel work are within the scope of protection of the utility model.

[0045] In the description of the present invention, it should be understood that the terms "upper", "lower", "top surface", "bottom surface" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the positions or elements referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore cannot be understood as limitations of the present invention. In addition, the terms "first" and "second" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.

[0046] like Figure 2-Figure 12 As shown, the ton bag conveying system disclosed in the utility model is used for conveying ton bags, and includes a pallet 100, a conveying device, a centering device and a lifting device 400, wherein the pallet 100 is used to carry the ton bag, the conveying device includes a first conveying unit 200 and a second conveying unit 300, the first conveying unit 200 is connected with the second conveying unit 300, and the pallet 100 can move from the first conveying unit 200 to the second conveying unit 300, the lifting device 400 is arranged below the second conveying unit 300, and can extend and retract in the vertical direction, and the centering device is arranged on the side of the second conveying unit 300, and is used to push the ton bag to move.

[0047] It should be noted that if Figure 1 As shown, the ton bag is an irregular oval shape, and a plurality of strip handles are arranged on the periphery of the ton bag. The robot arm in the prior art needs to lift the ton bag upward by grasping the handles. In the process of the robot arm grabbing the ton bag, the position of the robot arm needs to be adjusted multiple times to grasp the handles. After the robot arm grabs the ton bag, it drives the ton bag to move upward to the bag breaking chamber for bag breaking. The above-mentioned conveying process of the ton bag is the process of long-distance conveying, grabbing and sending the ton bag into the bag breaking chamber. In the utility model, after the centering device adjusts the position of the ton bag, it can enable the robot arm to grab the handles at one time, thereby improving the grabbing efficiency of the robot arm for the ton bag, that is, improving the conveying efficiency of the ton bag. The ton bag conveying system provided by the utility model is that initially, the ton bag is arranged on the pallet 100, and the pallet 100 moves along the first conveying unit 200 until it reaches the second conveying unit 300. The lifting device 400 lifts the pallet 100 upward, and then the centering device pushes the ton bag. The ton bag and the pallet 100 move relative to the lifting device 400. After being adjusted to a suitable position, the centering device no longer pushes the ton bag. In the above process, the ton bag conveying system completes the automatic conveying and centering of the ton bag, realizes the long-distance conveying and precise positioning of the ton bag, and thus improves the conveying efficiency of the ton bag.

[0048] In order to optimize the above technical solution, the first conveying unit 200 is a roller line 201, the ton bag is arranged above the pallet 100, and the pallet 100 is arranged on the roller line 201 and can move along the roller line 201. Specifically, the operator can change the length and arrangement position of the roller line 201 according to the transportation requirements of the ton bag. When in use, the ton bag moves along the roller line 201, reaches the connection between the roller line 201 and the second conveying unit 300, moves from the roller line 201 to the second conveying unit 300, and completes the centering process on the second conveying unit 300. By arranging the roller line 201, long-distance and directional transportation of the ton bag can be achieved, which saves manpower and reduces the time consumption of ton bag transportation, thereby improving the transportation efficiency of the ton bag.

[0049] In order to optimize the above technical solution, the second conveying unit 300 includes a conveying bracket 301, a roller sprocket 302 and a conveying motor 303. There are two roller sprockets 302, which are arranged relatively on the first side of the conveying bracket 301 and the second side of the conveying bracket 301. The roller sprocket 302 is connected with the roller line 201 to convey the pallet 100 to a preset position. The conveying motor 303 is connected with the roller sprocket 302 to drive the roller sprocket 302 to move. Specifically, the first side of the conveying bracket 301 and the second side of the conveying bracket 301 are in the same position as the first side of the second conveying unit 300 and the second side of the second conveying unit 300. The extension direction of the roller sprocket 302 is set as the second direction. The roller line 201 does not contact the roller sprocket 302, and only forms an upstream and downstream position connection relationship in the second direction. When in use, the ton bag reaches the junction of the roller line 201 and the roller sprocket 302. Driven by the roller of the roller line 201 and under the action of inertia, the pallet 100 reaches the top of the roller sprocket 302, and the conveying motor 303 drives the roller sprocket 302 to move. The roller sprocket 302 drives the pallet 100 to continue to move in the second direction. After reaching the preset position, the jacking device 400 jacks up the pallet 100, and the centering device pushes the ton bag to adjust the position of the ton bag so as to complete the subsequent ton bag grabbing step. By arranging the roller sprocket 302 relatively on the first side of the conveying bracket 301 and the second side of the conveying bracket 301, the pallet 100 can be effectively conveyed, and when the pallet 100 is arranged on the two roller sprockets 302, the jacking device 400 can act on the middle of the pallet 100, thereby jacking up the pallet 100, so that the centering device can move the ton bag. Therefore, such an arrangement improves the conveying efficiency of the ton bag.

[0050] In order to optimize the above technical solution, the ton bag conveying system also includes a control device, the second conveying unit 300 also includes a deceleration signal detector 304 and an in-place signal detector 305, the conveying motor 303, the roller line 201, the deceleration signal detector 304 and the in-place signal detector 305 are electrically connected to the control device, the deceleration signal detector 304 is arranged close to the first conveying unit 200, and is used to output a deceleration signal to the control device, and the in-place signal detector 305 is arranged close to the lifting device 400, and is used to output an in-place signal to the control device. Specifically, the control device is used to control the start and stop of the conveying motor 303 and the roller line 201, and the control device is electrically connected to the lifting device 400 and the centering device. When in use, the pallet 100 moves on the roller line 201 along the second direction. When the pallet 100 and the ton bag approach the second conveying unit 300, the deceleration signal detector 304 detects the pallet 100 and the ton bag, and outputs a deceleration signal to the control device. The control device controls the roller line 201 to decelerate, and controls the roller sprocket 302 to be in a working state, and conveys the pallet 100 to the top of the jacking device 400. The in-position signal detector 305 outputs an in-position signal to the control device, and the control device controls the roller sprocket 302 to be in a non-working state. The control device controls the jacking device 400 to extend in a vertical direction, and the jacking device 400 lifts the pallet 100. Then the control device controls the centering device to adjust the position of the ton bag. After adjusting to a suitable position, the centering device no longer pushes the ton bag, and the ton bag conveying system completes the automated conveying and centering of the ton bag. By arranging the deceleration signal detector 304, the ton bag can be decelerated in advance before reaching the preset position, avoiding the emergency stop and improving the stability of the ton bag transportation. By arranging the arrival signal detector 305, the automation of the ton bag lifting process and the centering process can be realized, further improving the automation degree of the ton bag conveying system and the conveying efficiency of the ton bags.

[0051] In order to optimize the above technical solution, the centering device includes a side push assembly 500, which includes a side push bracket 501, a side push cylinder 502 and a side push baffle 503. The side push bracket 501 is used to carry the side push cylinder 502 and the side push baffle 503. The side push cylinder 502 is connected to the side push baffle 503 and is used to push out and retract the side push baffle 503. There are two side push assemblies 500, which are arranged relatively on the first side of the second conveying unit 300 and the second side of the second conveying unit 300. The side push baffle 503 is used to push the ton bag to move along the first direction. Specifically, the first side of the second conveying unit 300 and the second side of the second conveying unit 300 are the left and right sides of the ton bag conveying path, respectively. When in use, after the lifting device 400 lifts the pallet 100 upward, the side push cylinder 502 pushes out the side push baffle 503, and the side push baffle 503 pushes the ton bag along the first direction until the ton bag is located at the preset position to be grabbed, and then the side push cylinder 502 retracts the side push baffle 503, and the robot arm grabs the handle of the ton bag and lifts the ton bag upward. By arranging two side push baffles 503, the position of the ton bag can be adjusted along the first direction, eliminating the process of the robot arm grabbing the ton bag multiple times, so that the robot arm can grab the ton bag at one time, thereby improving the grabbing efficiency of the robot arm for the ton bag, that is, improving the conveying efficiency of the ton bag conveying system for the ton bag.

[0052] In order to optimize the above technical solution, the centering device also includes a forward push assembly 600, which is away from the first conveying unit 200 and arranged on the third side of the second conveying unit 300. The forward push assembly 600 includes a forward push bracket 601, a forward push cylinder 602 and a forward push baffle 603. The forward push bracket 601 is used to carry the forward push cylinder 602 and the forward push baffle 603. The forward push cylinder 602 is connected to the forward push baffle 603 and is used to push out and retract the forward push baffle 603. The forward push baffle 603 is used to push the ton bag to move along the second direction, and the first direction is perpendicular to the second direction. Specifically, the first conveying unit 200 is arranged on the fourth side of the second conveying unit 300. When in use, after the lifting device 400 lifts the pallet 100 upward, the front push cylinder 602 pushes out the front push baffle 603, and the front push baffle 603 pushes the ton bag along the second direction, and the side push baffle 503 pushes the ton bag along the first direction until the ton bag is located at the preset position to be grabbed, and then the front push cylinder 602 retracts the front push baffle 603, and the side push cylinder 502 retracts the side push baffle 503, and the ton bag is accurately located at the preset position to be grabbed. By arranging the front push assembly 600, the position of the ton bag can be adjusted along the second direction, and the position of the ton bag can be adjusted along the first direction in conjunction with the side push assembly 500, and the ton bag can be accurately positioned, so that the mechanical arm grabs the ton bag at one time, thereby improving the transportation efficiency of the ton bag conveying system for the ton bag.

[0053] In order to optimize the above technical solution, the lifting device 400 includes a lifting bracket 401, a lifting cylinder 402, a moving plate 403, a steering wheel 404 and a steering wheel mounting seat 405. The steering wheel mounting seat 405 is arranged at the top of the lifting bracket 401 and is used to install multiple steering wheels 404. The moving plate 403 is arranged at the top of the steering wheel 404. The lifting cylinder 402 is arranged at the bottom of the moving plate 403 and is used to push out and retract the moving plate 403 in the vertical direction. Specifically, the steering wheels 404 are evenly mounted on the steering wheel mounting seat 405 and can roll in place. When in use, the pallet 100 reaches the top of the roller sprocket 302 from the roller line 201. When the pallet 100 reaches the top of the mobile disk 403, the lifting cylinder 402 pushes the mobile disk 403 in the vertical direction, and the front push assembly 600 and the side push assembly 500 push the ton bag. There is friction between the pallet 100 and the mobile disk 403 under the ton bag, that is, the ton bag, the pallet 100 and the mobile disk 403 move on multiple direction wheels 404 at the same time to achieve the position adjustment of the ton bag. When the ton bag is grabbed by the robot arm, the lifting cylinder 402 retracts the mobile disk 403 in the vertical direction, and the pallet 100 follows the mobile disk 403 to descend. Such an arrangement can realize the free movement of the ton bag, facilitate the position adjustment of the ton bag, and thus improve the transportation efficiency of the ton bag.

[0054] In order to optimize the above technical solution, the ton bag conveying system further includes a back-pushing assembly 700, which is arranged on the fourth side of the second conveying unit 300, and includes a back-pushing cylinder 701 and a back-pushing baffle 702. The back-pushing cylinder 701 is connected to the back-pushing baffle 702 and is used to push out and retract the back-pushing baffle 702. The back-pushing baffle 702 is used to push the movable plate 403 to move along the second direction. Specifically, the back-pushing baffle 702 is used to reset the movable plate 403, because in the process of adjusting the position of the ton bag, the front-pushing assembly 600 will push the ton bag to move along the second direction, and the movable plate 403 will also move along the second direction. When the ton bag leaves the pallet 100, the movable plate 403 needs to be pushed back to its original position. At this time, the back-pushing cylinder 701 pushes out the back-pushing baffle 702. After the movable plate 403 returns to its original position, the back-pushing cylinder 701 retracts the back-pushing baffle 702. By arranging the push-back assembly 700, the movable plate 403 can be reset so that the pallet 100 and the ton bag can reach the top of the movable plate 403 next time, thereby improving the automation degree of the ton bag conveying system and thus improving the conveying efficiency of the ton bag.

[0055] In order to optimize the above technical solution, the side push assembly 500 also includes a reset cylinder 800 and a reset baffle 801. The reset cylinder 800 is arranged on the side push bracket 501, and the reset cylinder 800 is connected to the reset baffle 801, and is used to push out and retract the reset baffle 801. The reset baffle 801 is used to push the movable plate 403 to move along the first direction. Specifically, the back push assembly 700 is used to reset the movable plate 403 in the second direction, and the reset cylinder 800 and the reset baffle 801 are used to reset the movable plate 403 in the first direction. When in use, the two reset cylinders 800 arranged on the first side of the second conveying unit 300 and the second side of the second conveying unit 300 push out the two reset baffles 801 respectively, push the movable plate 403 to move along the first direction, and cooperate with the back push assembly 700 to adjust the position of the movable plate 403. After the movable plate 403 is adjusted to a suitable position, the lifting cylinder 402 retracts the movable plate 403 in the vertical direction. By arranging the reset cylinder 800 and the reset baffle 801, the movable plate 403 can be freely moved, and the position of the movable plate 403 can be adjusted conveniently to prepare for lifting the ton bag again and adjusting the position of the ton bag, thereby further improving the conveying efficiency of the ton bag.

[0056] In order to optimize the above technical solution, the second conveying unit 300 also includes a limit plate 306, the number of which is two, and the limit plates 306 are relatively arranged on the first side of the conveying bracket 301 and the second side of the conveying bracket 301, and are used to limit the pallet 100. Specifically, the limit plates 306 are relatively arranged on the first side of the second conveying unit 300 and the second side of the second conveying unit 300, and the distance between the two limit plates 306 is slightly larger than the width of the pallet 100. The limit plates 306 are used to ensure that the ton bag can be transported along the specified route without excessive deviation. Specifically, the limit plates 306 are opened at both ends along the second direction to prevent collision between the ton bag and the pallet 100, further ensuring the transportation stability of the ton bag. Such an arrangement can avoid the deviation of the ton bag, ensure that the ton bag reaches the initial position of the jacking device 400 more accurately, thereby coordinating the side push assembly 500 to adjust the position of the ton bag, and improve the overall transportation efficiency of the ton bag conveying system.

[0057] The advantages of the utility model are:

[0058] (1) Improved the efficiency of transporting ton bags;

[0059] (2) The automation of ton bag transportation is realized;

[0060] (3) Save manpower and be practical.

[0061] It should be noted that the ton bag conveying system provided by the utility model can be used in the technical field of ton bag conveying equipment or other fields. Other fields are any fields other than the technical field of ton bag conveying equipment. The above is only an example and does not limit the application field of the ton bag conveying system provided by the utility model.

[0062] The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.

[0063] The above description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.

[0064] In the description of this specification, the description with reference to the terms "one embodiment", "example", "specific example", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the utility model. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.

[0065] The preferred embodiments of the utility model disclosed above are only used to help explain the utility model. The preferred embodiments do not describe all the details in detail, nor do they limit the utility model to only specific implementation methods. Obviously, many modifications and changes can be made according to the content of this specification. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the utility model, so that technicians in the relevant technical field can well understand and use the utility model. The utility model is limited only by the claims and their full scope and equivalents.

Claims

1. A ton bag conveying system, characterized in that: Used to transport ton bags, including pallets, conveying devices, centering devices and lifting devices, including: The pallet is used to carry the ton bag; The conveying device comprises a first conveying unit and a second conveying unit; The first conveying unit is connected to the second conveying unit, and the tray can move along the first conveying unit to the second conveying unit; The lifting device is arranged below the second conveying unit and can be extended and retracted in the vertical direction; The centering device is arranged on the side of the second conveying unit and is used to push the ton bag to move.

2. The ton bag conveying system according to claim 1, characterized in that: The first conveying unit is a roller line, the ton bag is arranged above the pallet, and the pallet is arranged on the roller line and can move along the roller line.

3. The ton bag conveying system according to claim 2, characterized in that: The second conveying unit includes a conveying bracket, a roller sprocket and a conveying motor. There are two roller sprockets, which are relatively arranged on the first side and the second side of the conveying bracket. The roller sprocket is connected to the roller line and is used to convey the pallet to a preset position. The conveying motor is connected to the roller sprocket and is used to drive the roller sprocket to move.

4. The ton bag conveying system according to claim 3, characterized in that: The ton bag conveying system also includes a control device, and the second conveying unit also includes a deceleration signal detector and an in-place signal detector. The conveying motor, the roller line, the deceleration signal detector and the in-place signal detector are electrically connected to the control device. The deceleration signal detector is arranged close to the first conveying unit and is used to output a deceleration signal to the control device. The in-place signal detector is arranged close to the lifting device and is used to output an in-place signal to the control device.

5. The ton bag conveying system according to claim 1, characterized in that: The centering device includes a side-pushing assembly, which includes a side-pushing bracket, a side-pushing cylinder and a side-pushing baffle. The side-pushing bracket is used to carry the side-pushing cylinder and the side-pushing baffle. The side-pushing cylinder is connected to the side-pushing baffle and is used to push out and retract the side-pushing baffle. There are two side-pushing assemblies, which are arranged relatively to the first side of the second conveying unit and the second side of the second conveying unit. The side-pushing baffle is used to push the ton bag to move along the first direction.

6. The ton bag conveying system according to claim 5, characterized in that: The centering device also includes a forward pushing component, which is away from the first conveying unit and arranged on the third side of the second conveying unit. The forward pushing component includes a forward pushing bracket, a forward pushing cylinder and a forward pushing baffle. The forward pushing bracket is used to carry the forward pushing cylinder and the forward pushing baffle. The forward pushing cylinder is connected to the forward pushing baffle and is used to push out and retract the forward pushing baffle. The forward pushing baffle is used to push the ton bag to move along the second direction, and the first direction is perpendicular to the second direction.

7. The ton bag conveying system according to claim 6, characterized in that: The jacking device includes a jacking bracket, a jacking cylinder, a movable plate, a steering wheel and a steering wheel mounting seat. The steering wheel mounting seat is arranged at the top of the jacking bracket and is used to mount a plurality of steering wheels. The movable plate is arranged at the top of the steering wheel. The jacking cylinder is arranged at the bottom of the movable plate and is used to push out and retract the movable plate in the vertical direction.

8. The ton bag conveying system according to claim 7, characterized in that: The ton bag conveying system also includes a backward push component, which is arranged on the fourth side of the second conveying unit and includes a backward push cylinder and a backward push baffle. The backward push cylinder is connected to the backward push baffle and is used to push out and retract the backward push baffle. The backward push baffle is used to push the movable plate to move along the second direction.

9. The ton bag conveying system according to claim 7, characterized in that: The side thrust assembly also includes a reset cylinder and a reset baffle. The reset cylinder is arranged on the side thrust bracket and is connected to the reset baffle for pushing out and retracting the reset baffle. The reset baffle is used to push the movable plate to move along the first direction.

10. The ton bag conveying system according to claim 3, characterized in that: The second conveying unit further includes two limiting plates, which are arranged relatively on the first side of the conveying bracket and the second side of the conveying bracket to limit the tray.

Citation Information

Cited By

  • Cutter adjusting mechanism of cloth cutting machine

    CN224620302U