Fixing device for installing overhanging type steel and pull-up component and overhanging type scaffold
By combining clamp components and fixing bolts for locking, the connection stability and safety issues of the cantilevered steel structure and the upper tension member are solved, enabling flexible fixing and efficient installation of the cantilevered steel structure, and reducing construction complexity and cost.
Patent Information
- Application Number
- CN202323435874.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-14
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2033-12-14
AI Technical Summary
The fixing methods for cantilevered steel sections and upper tension members have shortcomings in terms of connection stability, safety and reliability. The welding method in the existing technology results in the position being unadjustable and damages the steel section, while the wire rope integration method requires high-altitude installation and consumes manpower.
The locking method adopts a combination of clamp components and fixing bolts. The clamp components consist of a first clamp and a second clamp. The hook part engages with different positions of the cantilevered steel and is locked through threaded holes and fixing bolts. The widening part is used to adapt to different steel widths.
It improves the connection stability, safety, and operability of cantilevered steel sections and upper tension members, avoids welding damage and defects of high-altitude installation, and reduces construction costs.
Smart Images

Figure CN222084006U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of scaffolding, and in particular to a fixing device for installing cantilever steel and upper pull members and a cantilever scaffolding. Background Art
[0002] In the early days, bamboo and wood scaffolding used in my country's construction, with the continuous development of the construction industry, has been unable to meet the needs of building development, and has been replaced by a more convenient new scaffolding. In the 1960s, my country began to use coupler steel pipe scaffolding. In the late 1970s, my country's buildings began to rise in large numbers, and coupler steel pipe scaffolding began to be used in large quantities. Coupler steel pipe scaffolding has the advantages of simple processing and convenient transportation. It is widely used in my country's building construction. It was the most used type at that time, and it is still used in some places today. In the past 30 years, some domestic companies have introduced advanced technology from abroad and developed a variety of new scaffolding, such as cantilever scaffolding, tower scaffolding, pin scaffolding, plug-in scaffolding, climbing scaffolding, etc. Among them, the most used external scaffolding is the cantilever scaffolding, and most high-rise buildings gradually use cantilever scaffolding. The types of cantilever scaffolding can be divided into several categories, but the most important components are cantilever steel and upper pull components.
[0003] In the related art, the fixing method of the cantilever layer steel and the upper pull member usually needs to be improved in terms of the stability, safety and reliability of the connection. Summary of the invention
[0004] In view of this, the present application provides a fixing device and a cantilever scaffolding for installing cantilever steel sections and upper pull members, which can improve the stability, safety and operability of the connection.
[0005] In a first aspect, the present application provides a fixing device for installing cantilever steel and upper pull-up members, comprising:
[0006] A clamp assembly having a fixed end hole, wherein the clamp assembly is formed by a first clamp and a second clamp, wherein the first clamp and the second clamp each have a hook portion and a threaded hole;
[0007] Among them, when the threaded holes of the first clamp and the threaded holes of the second clamp are in mutual assembly, the fixing bolts can lock the first clamp and the second clamp by screwing the two threaded holes at the same time, and the hook parts of the first clamp and the second clamp in the locked state can be hooked at different positions of the cantilever steel to fix the cantilever steel, and the upper pull member is installed in the fixed end hole.
[0008] Optionally, it also includes a widening piece for lining between the first clamp and the second clamp.
[0009] Optionally, the widening piece is provided with a widening piece hole for the fixing bolt to pass through.
[0010] Optionally, the hook portion of the first clamp is elastic.
[0011] Optionally, the hook portion of the second clamp is elastic.
[0012] Optionally, a positioning groove is formed in the hook portion of the first clamp.
[0013] Optionally, a positioning groove is formed in the hook portion of the second clamp.
[0014] Optionally, a wedge-shaped structure is provided at the end of the hook portion of the first clamp.
[0015] Optionally, a wedge-shaped structure is provided at the end of the hook portion of the second clamp.
[0016] In a second aspect, the present application provides a cantilever scaffolding, characterized in that it includes the fixing device as described above.
[0017] The fixing device and cantilever scaffolding disclosed in the present application for installing cantilever steel and upper pull-up members, when it is necessary to fix the cantilever steel and upper pull-up members, first hook the hook parts of the first clamp and the second clamp on different positions of the cantilever steel, then operate to overlap the first clamp and the second clamp to assemble, penetrate the threaded holes of the first clamp and the second clamp and insert the fixing bolts to tighten, and then the cantilever steel is fixed. Then install the upper pull-up member in the fixed end hole, so that the cantilever steel and the upper pull-up member are better fixed. Due to the use of the first clamp and the second clamp and the screw connection locking with the fixing bolts, the stability, safety and operability of the connection between the upper pull-up member and the cantilever steel are improved. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] The technical solution and other beneficial effects of the present application will be made apparent by describing in detail the specific implementation methods of the present application in conjunction with the accompanying drawings.
[0019] Figure 1 This is a schematic diagram of the structure of the fixing device disclosed in the embodiment of the present application;
[0020] Figure 2 It is a structural schematic diagram of the fixing device disclosed in the embodiment of the present application when it is installed with the cantilever steel;
[0021] Figure 3 It is a structural schematic diagram of the fixing device disclosed in the embodiment of the present application when it is installed with the cantilever steel and the upper pull member;
[0022] Figure 4 A schematic diagram of the structure of the first clamp or the second clamp disclosed in the embodiment of the present application;
[0023] Figure 5 A schematic structural diagram of a widening member disclosed in an embodiment of the present application from one viewing angle;
[0024] Figure 6 This is a structural schematic diagram of the widening member disclosed in the embodiment of the present application from another perspective.
[0025] In the above figure, the components are marked as follows:
[0026] 110-first clamp; 120-second clamp; 111, 121-hooking portion; 110a, 120a-threaded hole; 130-widening member; 130a-widening member hole; 200-fixing bolt; 300-cantilever steel; 400-upper pull member;
[0027] 140a-Fixed end hole. DETAILED DESCRIPTION
[0028] In order to make the above-mentioned purposes, features and advantages of the present application more obvious and easy to understand, the specific implementation methods of the present application are described in detail below in conjunction with the accompanying drawings. In the following description, many specific details are set forth to facilitate a full understanding of the present application. However, the present application can be implemented in many other ways different from those described herein, and those skilled in the art can make similar improvements without violating the connotation of the present application, so the present application is not limited by the specific embodiments disclosed below.
[0029] In the description of the present application, it should be understood that if the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential", etc. appear, the orientation or position relationship indicated by these terms is based on the orientation or position relationship shown in the accompanying drawings, which is only for the convenience of describing the present application and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present application.
[0030] In addition, if the terms "first" or "second" appear, these terms are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include at least one of the features. In the description of this application, if the term "plurality" appears, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.
[0031] In this application, unless otherwise clearly specified and limited, if the terms "installed", "connected", "connected", "fixed" and the like appear, these terms should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integrated connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to the specific circumstances.
[0032] In the present application, unless otherwise clearly specified and limited, if there is a description that a first feature is "above" or "below" a second feature, etc., or similar descriptions appear, it may mean that the first and second features are in direct contact, or that the first and second features are in indirect contact through an intermediate medium. Moreover, the first feature being "above", "above" and "above" the second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. The first feature being "below", "below" and "below" the second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.
[0033] It should be noted that if an element is referred to as being "fixed to" or "disposed on" another element, it may be directly on the other element or there may be a central element. If an element is considered to be "connected to" another element, it may be directly connected to the other element or there may be a central element at the same time. If any, the terms "vertical", "horizontal", "upper", "lower", "left", "right" and similar expressions used in this application are for illustrative purposes only and do not represent the only implementation method.
[0034] Before formally explaining the technical solution of this application, it is necessary to discuss the creation process of this application.
[0035] In the related art, there are usually two ways to fix the cantilever layer steel and the upper pull components. One is to weld steel on the cantilever steel to form a lifting ring; the other is to wrap the upper pull wire rope around the entire steel and then fix the wire rope with a buckle.
[0036] Both of the above fixing methods have certain disadvantages and shortcomings. For example, the hoist ring formed by welding: 1. It is impossible to adjust the position according to the actual situation on site, which may cause the angle of the upper pull wire rope or the pull rod to not meet the requirements, thus causing safety problems; 2. Welding damages the steel itself, and it must be cut for repeated use, which is low in economic efficiency. For example, the steel wire rope is integrated and wrapped around the steel: 1. Measures must be taken to prevent the steel wire rope from sliding sideways at the lower end of the steel. Welding the steel bar head is dangerous and damages the steel itself. Other devices require high-altitude installation, additional processes, and labor consumption.
[0037] In view of the problems of stability, safety and reliability of the connection mentioned above, the inventors have proposed a fixing device and a cantilever scaffolding for installing cantilever steel and upper pull members. When it is necessary to fix the cantilever steel and the upper pull member, first hook the hook parts of the first clamp and the second clamp at different positions of the cantilever steel, then operate to overlap the first clamp and the second clamp to assemble, penetrate through the threaded holes of the first clamp and the second clamp and insert the fixing bolts to tighten, and then the fixing operation of the cantilever steel is completed. Then install the upper pull member in the fixed end hole, so that the cantilever steel and the upper pull member are better fixed. Due to the use of screw connection and locking relying on the first clamp and the second clamp and cooperating with the fixing bolts, the stability, safety and operability of the connection between the upper pull member and the cantilever steel are improved. Based on this, the present invention was created.
[0038] Firstly, the present application provides a cantilever scaffolding, characterized in that it includes a fixing device.
[0039] Since the structure or principle of the cantilever scaffold is common technical knowledge for those skilled in the art, it will not be described in detail in this article. The following article will focus on the fixing device.
[0040] The embodiment of the present application is used to install the fixing device of the cantilever steel and the upper pull member, which is suitable for connecting the cantilever steel and the upper pull member. Here, it can be understood that the common forms of the upper pull member include but are not limited to steel wire ropes, tie rods, etc.
[0041] Please refer to Figure 1-Figure 4 , the above-mentioned fixing device comprises:
[0042] A clamp assembly having a fixed end hole 140a, wherein the clamp assembly is formed by a first clamp 110 and a second clamp 120, wherein the first clamp 110 and the second clamp 120 each have a hook portion 111, 121 and a threaded hole 110a, 120a;
[0043] Among them, when the threaded holes 110a, 120a of the first clamp 110 and the threaded holes 110a, 120a of the second clamp 120 are in mutual assembly, the fixing bolt 200 can lock the first clamp 110 and the second clamp 120 by screwing the two threaded holes 110a, 120a at the same time, and the hook parts 111, 121 of the first clamp 110 and the hook parts 111, 121 of the second clamp 120 in the locked state can be hooked at different positions of the cantilever steel 300 to fix the cantilever steel 300, and the upper pull member 400 is installed in the fixed end hole 140a.
[0044] It is obvious that the threaded holes 110a, 120a of the first clamp 110 and the second clamp 120 are joined together, which means that the threaded holes 110a, 120a of the two are mutually connected or aligned. The actual operation includes but is not limited to overlapping the first clamp 110 and the second clamp 120, and the threaded holes 110a, 120a of the first clamp 110 and the threaded holes 110a, 120a of the second clamp 120 are always mutually connected during the overlapping process.
[0045] The structure, shape or size of the threaded holes 110a, 120a of the first clamp 110 and the threaded holes 110a, 120a of the second clamp 120 may be completely the same or different. Similarly, the structure, shape or size of the hook portions 111, 121 of the first clamp 110 and the hook portions 111, 121 of the second clamp 120 may be completely the same or different. Similarly, the structure, shape or size of the first clamp 110 and the second clamp 120 may be completely the same or different.
[0046] The main body of the first clamp 110 (i.e., the part other than the hook portion 111, 121) may include a mounting portion for opening the threaded holes 110a, 120a and a connecting portion fixedly connected to the mounting portion. The mounting portion may be in the shape of a square plate, and the connecting portion may be in the shape of an L-shaped strip.
[0047] The main body of the second clamp 120 (i.e., the part other than the hook portion 111, 121) may include a mounting portion for opening the threaded holes 110a, 120a and a connecting portion fixedly connected to the mounting portion. The mounting portion may be in the shape of a square plate, and the connecting portion may be in the shape of an L-shaped strip.
[0048] The hook portions 111, 121 of the first clamp 110 may be connected integrally with the main body of the first clamp 110 and may be extended and bent to form an arc shape, or may be connected to the main body of the first clamp 110 in a non-integrated manner, such as a detachable connection such as a clamp connection or a screw connection. However, based on the connection strength of the hook portions 111, 121, it is more appropriate to use an integral connection with the main body of the first clamp 110.
[0049] Similarly, the hook portions 111, 121 of the second clamp 120 may be connected integrally with the main body of the second clamp 120 and may be extended and bent to form an arc shape, or may be connected to the main body of the second clamp 120 in a non-integrated manner, such as a detachable connection such as a clamp connection or a screw connection. However, based on the connection strength of the hook portions 111, 121, it is more appropriate to use an integral connection with the main body of the second clamp 120.
[0050] Suitably but not restrictively, the hook portions 111 , 121 of the first clamp 110 and the second clamp 120 are elastic.
[0051] Thus, the hook parts 111, 121 can be elastically stretched by the elasticity of the hook parts 111, 121. When the hook parts 111, 121 need to be hooked on the cantilevered steel 300, the hook parts 111, 121 can be opened by external force and the external force can be maintained until the corresponding part of the cantilevered steel 300 is sent into the hook parts 111, 121, and then the hook parts 111, 121 are released. Under the elastic effect, the hook parts 111, 121 will continue to apply a clamping force to the cantilevered steel 300.
[0052] Here, the elastic material may be TPU or highly elastic rubber.
[0053] As a suitable but non-limiting specific example, the hook portions 111 , 121 of the first clamp 110 and the second clamp 120 are recessed with positioning grooves (not shown in the figure).
[0054] Thus, through the positioning grooves, the corresponding parts of the cantilever steel section 300 can better contact the hook parts 111, 121 in an "embedded" posture, and the hook parts 111, 121 are prevented from being unhooked.
[0055] The positioning groove can be of any shape, such as a trapezoid that is wide at the top and narrow at the bottom. The opening of the positioning groove can also be an elastic opening to ensure that after the corresponding part of the cantilever steel 300 enters the positioning groove, the elasticity of its elastic opening continuously applies a clamping force.
[0056] In a suitable but non-limiting specific example, ends of the hook portions 111 , 121 of the first clamp 110 and the second clamp 120 are provided with wedge-shaped structures.
[0057] In this way, through the wedge-shaped structure, it is possible to form a "piercing" or "stabbing" posture when contacting the corresponding part of the cantilever steel 300. Note that "piercing" or "stabbing" here does not mean that the depth of the wedge-shaped structure inserted into the surface layer of the corresponding part of the cantilever steel 300 is obvious, but means that the wedge-shaped part applies a greater pressure on the surface of the corresponding part of the cantilever steel 300.
[0058] Of course, in order to further reduce the sliding of the hook portions 111 , 121 of the first clamp 110 and the second clamp 120 when they contact the corresponding parts of the cantilevered steel 300 , the ends of the hook portions 111 , 121 may be in a raised shape such as a claw.
[0059] Please refer to Figure 5 , Figure 6 As a suitable but non-limiting specific example, the invention further includes a widening member 130 for lining between the first clamp 110 and the second clamp 120 .
[0060] Thus, the widening member 130 can adapt to the situation where the wing plate of the cantilever steel 300 is wider, ensuring that the hook portions 111, 121 of the first clamp 110 and the second clamp 120 can both contact the appropriate position of the cantilever steel 300. Otherwise, if the wing plate of the cantilever steel 300 is too wide, the hook portions 111, 121 of the first clamp 110 and the second clamp 120 may not contact the cantilever steel 300 at the same time, that is, one of the hook portions 111, 121 is in a suspended state.
[0061] It can be understood that, since the widening piece 130 is cushioned between the first clamp 110 and the second clamp 120 , the clamping force generated by the first clamp 110 and the second clamp 120 is sufficient to maintain the fixation of the widening piece 130 .
[0062] However, in order to better position and fix the widening member 130 , the widening member 130 is provided with a widening member hole 130 a for the fixing bolt 200 to pass through.
[0063] In this way, when the fixing bolt 200 passes through the widening member hole 130a of the first clamp 110 and the second clamp 120, the widening member 130 can also be passed through, thereby avoiding the problem of unreliable clamping force generated by the first clamp 110 and the second clamp 120 on the widening member 130.
[0064] The width increasing member 130 may be in the shape of a flat plate.
[0065] As a deformable implementation of the threaded holes 110 a and 120 a in the widening member 130 , a bending portion may be provided at the end of the widening member 130 to form a better fit with the mounting portions of the first clamp 110 and the second clamp 120 .
[0066] Now, the operation process of fixing cantilever steel and upper pull-up members in this application is described for a relatively broad application scenario. It should not be misunderstood that although the following application scenarios involve some elements that do not appear in the basic solution of this application (i.e., the technical solution corresponding to the independent claim), these elements should not be regarded as the most basic constituent elements that affect the technical effect of this application.
[0067] Please refer again Figure 3The process of fixing the cantilever steel and upper pull-up components is as follows:
[0068] S1: Configure the appropriate width of the clamp assembly of the cantilever steel section 300.
[0069] The first clamp 110 and the second clamp 120 are matched according to the width of the upper wing plate of the cantilever steel 300 used on site, and it is selected whether the widening piece 130 of different widths is needed.
[0070] S2: Configure the installation position of the clamp assembly
[0071] According to the actual layout of the steel sections on site, the installation positions of the first clamp 110 and the second clamp 120 are determined:
[0072] S3: Assemble the first clamp 110 and the second clamp 120
[0073] The first clamp 110 and the second clamp 120 are butt-jointed at a selected position on the cantilever steel 300:
[0074] If the width is just right, the first clamp 110 and the second clamp 120 can be butted together;
[0075] If the width of the upper wing plate of the steel section is greater than the butt length of the first clamp 110 and the second clamp 120 , a matching widening piece 130 is selected.
[0076] S4: Install the fixing bolt 200
[0077] After the docking is completed, the fixing bolts 200 are installed in sequence through the bolt holes of the first clamp 110 and the second clamp 120 and are fastened with nuts.
[0078] S5: Install the pull-up member 400
[0079] After the most cantilevered steel section 300 is installed, the steel wire rope or the bolts of the tension rod are fixed through the fixed end hole 140a.
[0080] The above is only a preferred specific implementation of the present application, but the protection scope of the present application is not limited thereto. Any changes or substitutions that can be easily conceived by any technician familiar with the technical field within the technical scope disclosed in the present application should be covered within the protection scope of the present application.
Claims
1. A fixing device for installing cantilever steel and upper pull-up members, characterized in that: include: A clamp assembly having a fixed end hole, wherein the clamp assembly is formed by a first clamp and a second clamp, wherein the first clamp and the second clamp each have a hook portion and a threaded hole; Among them, when the threaded holes of the first clamp and the threaded holes of the second clamp are in mutual assembly, the fixing bolts can lock the first clamp and the second clamp by screwing the threaded holes of the first clamp and the second clamp at the same time, and the hook parts of the first clamp and the second clamp in the locked state can be hooked at different positions of the cantilever steel to fix the cantilever steel, and the upper pull member is installed in the fixed end hole.
2. The fixing device according to claim 1, characterized in that: It also includes a widening piece for lining between the first clamp and the second clamp.
3. The fixing device according to claim 2, characterized in that: The widening piece is provided with a widening piece hole for the fixing bolt to pass through.
4. The fixing device according to claim 1, characterized in that: The hook portion of the first clamp is elastic.
5. The fixing device according to claim 1, characterized in that: The hook portion of the second clamp is elastic.
6. The fixing device according to claim 1, characterized in that: The hook portion of the first clamp is concavely provided with a positioning groove.
7. The fixing device according to claim 1, characterized in that: The hook portion of the second clamp is concavely provided with a positioning groove.
8. The fixing device according to claim 1, characterized in that: A wedge-shaped structure is provided at the end of the hook portion of the first clamp.
9. The fixing device according to claim 1, characterized in that: A wedge-shaped structure is provided at the end of the hook portion of the second clamp.
10. A cantilever scaffold, characterized in that: Comprising the fixing device as claimed in claim 1.