Integrated working platform for anti-curl construction of steel truss girder orthogonal special-shaped plate bridge deck block

By designing a working platform including steel pipe Bere beam brackets, assembly tire frames and positioning tooling at the bridge construction site, the problem of difficulty in assembling and welding accuracy and deformation control of bridge deck blocks is solved, and efficient and accurate bridge surfaces are achieved Block production, suitable for mountain construction.

CN222100634UActive Publication Date: 2024-12-03SICHUAN ROAD & BRIDGE CONSTRUCTION GROUP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420672814.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-03
Publication Date
2024-12-03
Estimated Expiration
2034-04-03

AI Technical Summary

Technical Problem

At the bridge construction site, during the assembly and welding of steel truss orthogonal special-shaped slab bridge deck blocks, it is difficult to ensure accuracy and control welding deformation, affecting the quality of the bridge.

Method used

An integrated working platform including steel pipe beret support, assembly tire frame and positioning tooling was designed. Through steel erection and pre-arching setting, the precise assembly and welding of the bridge deck block is ensured.

Benefits of technology

It effectively improves the on-site production accuracy and welding quality of the bridge deck block, is easy to set up, and is suitable for limited sites in mountain construction sites.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222100634U_ABST
    Figure CN222100634U_ABST
Patent Text Reader

Abstract

The utility model provides an integrated working platform for anti-curl construction of a steel truss girder orthogonal special-shaped plate bridge deck block. The device is implemented by the following steps: (1) erecting a steel pipe bailey beam bracket; (2) assembling the jig frame; (3) mounting a positioning tool; and (4) mounting upper and lower channels. The construction method has the advantages that the construction method is formed by erecting a profile steel structure, the limited site of a mountainous area construction site can be effectively utilized, and the structure is easy and convenient to erect; 2, by means of the positioning tool, pre-camber setting and the like, the problems that the requirement for the precision of on-site bridge deck block manufacturing is high, and welding deformation is difficult to control are effectively solved; and the on-site manufacturing quality of the bridge floor block body is effectively guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of bridge engineering, in particular to an integrated working platform for anti-curling construction of orthogonal special-shaped plate bridge deck blocks of steel trusses. Background Art

[0002] As the expressway network extends to the western mountainous areas, large bridges across mountainous areas, river valleys, gullies, etc. emerge in an endless stream, and bridges with strong spanning capacity such as suspension bridges, cable-stayed bridges, and arch bridges are constantly being used. Large-span steel truss structure bridges are widely used due to their convenient on-site construction advantages. Their structural rods can be transported to the construction site through the highway network, and the segments are assembled and welded on site. How to ensure the accuracy of on-site construction assembly and welding is a major problem in ensuring the quality of bridge construction. Utility Model Content

[0003] The purpose of this patent is to provide an integrated working platform for the anti-curling construction of steel truss orthogonal special-shaped plate bridge deck blocks. The construction platform for assembling and welding bridge deck blocks is built by steel sections, and construction tooling for positioning bridge deck blocks is set up at the same time to ensure accurate and efficient assembly of bridge deck blocks on site.

[0004] The utility model is realized by providing an integrated working platform for anti-curling construction of orthogonal special-shaped plate bridge deck blocks of steel trusses, which is characterized by: comprising

[0005] Steel tube Bailey beam bracket, assembly frame and positioning tooling;

[0006] The assembly frame is a steel pipe + steel plate structure, and the positioning tooling is arranged on both sides of the bridge deck block and arranged corresponding to the bridge deck block cross beam;

[0007] The steel tube Bailey beam support is composed of a concrete foundation, steel tube columns, a main beam, a Bailey beam, a distribution beam and a steel plate, and the structures are connected by welding;

[0008] An assembly frame is set on the steel tube Bailey beam support. The frame is arranged according to the size and segment division of the longitudinal beams and transverse beams of the bridge deck blocks. Steel plate pads are arranged on the frame. The pad height is set according to the pre-arch of the bridge deck blocks. The pre-arch setting is used to offset the curling deformation caused by the welds of the bridge deck blocks.

[0009] Furthermore, a positioning tool is set outside the bridge deck block assembly area and is set according to the position of the bridge deck block crossbeam; the positioning tool is composed of a steel column and a positioning steel plate.

[0010] Furthermore, upper and lower construction passages are set at the outermost part of the construction platform to facilitate construction workers to go to the bottom of the bridge deck block to carry out rod bolt connection, U-rib weld construction or panel longitudinal seam construction on the bridge deck block.

[0011] Furthermore, the pre-camber is set to resist deformation of the bridge deck blocks after welding.

[0012] Furthermore, the positioning tool is a steel plate structure with bolt holes, the steel plate is welded to the steel pipe column, and the installation position of the bridge deck block crossbeam rod is fixed by bolt connection.

[0013] The implementation process of this patent is:

[0014] Step 1: Erection of steel tube Bailey beam support: Construct concrete foundation, steel tube column, main beam, Bailey beam, distribution beam and steel plate from bottom to top in sequence at the bridge deck block assembly site.

[0015] Step 2: Installation of assembly tyre frame: An assembly tyre frame is set on the steel tube Bailey beam support. The tyre frame is arranged according to the longitudinal and transverse beam sizes and segment divisions of the bridge deck blocks. Steel plate pads are set on the tyre frame. The pad height is set according to the pre-arch of the bridge deck blocks. The pre-arch setting is used to offset the curling deformation caused by the welds of the bridge deck blocks.

[0016] Step 3: Installation of positioning fixtures: Install positioning fixtures outside the bridge deck assembly area and set them according to the position of the bridge deck crossbeam. The positioning fixtures consist of steel columns and positioning steel plates.

[0017] Step 4: Installation of upper and lower channels: Set up upper and lower construction channels at the outermost part of the construction platform to facilitate construction personnel to go to the bottom of the bridge deck block to carry out rod bolt connection, U-rib weld construction or panel longitudinal seam construction on the bridge deck block.

[0018] The advantages of this device are: 1. This device is constructed with a steel structure, which can effectively utilize the limited space on the mountain construction site and is easy to construct. 2. This device effectively solves the problem of high precision requirements for on-site bridge deck block production and difficult control of welding deformation through positioning tooling and pre-camber settings, effectively ensuring the on-site production quality of bridge deck blocks. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 This is the structural diagram of the integrated construction platform for this application.

[0020] Among them: 1-concrete foundation; 2-steel pipe column; 3-main beam; 4-Bailey beam; 5-positioning tooling; 6-construction frame; 7-bridge deck; 8-cross beam; 9-longitudinal beam. DETAILED DESCRIPTION

[0021] The following will be combined with the attached Figure 1The device is described in detail, and the technical solution in the embodiment of the device is described clearly and completely. Obviously, the described embodiment is only a part of the embodiment of this patent, not all of the embodiments. Based on the embodiments in this patent, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this patent.

[0022] The utility model provides an integrated working platform for anti-curling construction of steel truss orthogonal special-shaped plate bridge deck blocks; a construction platform for assembling and welding bridge deck blocks is set up by steel sections, and construction tooling for positioning the bridge deck blocks is set up at the same time, so as to ensure accurate and efficient assembly of the bridge deck blocks on site.

[0023] like Figure 1 As shown, an integrated working platform for anti-curling construction of orthogonal special-shaped slab bridge deck blocks of steel trusses; including a steel tube Bailey beam support, an assembly frame 6 and a positioning tool;

[0024] The assembly frame 6 is a steel pipe + steel plate structure, and the positioning tooling is arranged on both sides of the bridge deck block and arranged corresponding to the bridge deck block cross beam;

[0025] The steel tube Bailey beam support is composed of a concrete foundation 1, a steel tube column 2, a main beam 3, a Bailey beam 4, a distribution beam and a steel plate, and the structures are connected by welding;

[0026] An assembly frame 6 is arranged on the steel tube Bailey beam support. The frame 6 is arranged according to the size and segment division of the longitudinal beam 8 and the transverse beam 7 of the bridge deck block. Steel plate pads are arranged on the frame 6. The pad height is set according to the pre-arch of the bridge deck block. The pre-arch setting is used to offset the curling deformation caused by the welds of the bridge deck blocks.

[0027] In the present application, a positioning tool 5 is provided outside the bridge deck block assembly area, and is arranged according to the position of the bridge deck block cross beam 7; the positioning tool 5 is composed of a steel column and a positioning steel plate.

[0028] In this application, upper and lower construction passages are set at the outermost part of the construction platform to facilitate construction workers to go to the bottom of the bridge deck block to carry out rod bolt connection, U-rib weld construction or panel longitudinal seam construction on the bridge deck block.

[0029] In the present application, the pre-camber is set to resist deformation of the bridge deck blocks after welding.

[0030] In the present application, the positioning fixture is a steel plate structure with bolt holes. The steel plate is welded to the steel pipe column 2, and the installation position of the bridge deck block crossbeam rod is fixed by bolt connection.

[0031] The following is combined with Figure 1 Further explain the specific implementation method of this patent:

[0032] Step 1: Erection of steel tube Bailey beam support

[0033] At the bridge deck block assembly site, concrete foundation 1, steel pipe column 2, main beam 3, Bailey beam 4, distribution beam and steel plate are constructed in sequence from bottom to top.

[0034] Step 2: Assemble the tire frame and install it

[0035] An assembly frame 6 is arranged on the steel tube Bailey beam support. The frame 6 is arranged according to the size and segment division of the longitudinal beam 8 and the transverse beam 7 of the bridge deck block. Steel plate pads are arranged on the frame 6. The pad height is set according to the pre-arch of the bridge deck block. The pre-arch setting is used to offset the curling deformation caused by the welds of the bridge deck blocks.

[0036] Step 3: Positioning tooling installation

[0037] A positioning fixture 5 is arranged outside the bridge deck block assembly area, and is arranged according to the position of the bridge deck block cross beam 7. The positioning fixture 5 is composed of a steel column and a positioning steel plate.

[0038] Step 4: Upper and lower channel installation

[0039] Up and down construction passages are set up at the outermost part of the construction platform to facilitate construction workers to go to the bottom of the bridge deck block to carry out rod bolt connection, U-rib weld construction or panel longitudinal seam construction on the bridge deck block.

[0040] The advantages of the utility model are:

[0041] 1. This device is constructed with a steel structure, which can effectively utilize the limited space at the mountain construction site and has a simple structure.

[0042] 2. This device effectively solves the problems of high precision requirements for on-site bridge deck block production and difficult control of welding deformation through positioning tooling and pre-camber setting, effectively ensuring the on-site production quality of bridge deck blocks.

Claims

1. An integrated working platform for anti-curling construction of orthogonal special-shaped slab bridge deck blocks of steel trusses, characterized by: include Steel tube Bailey beam support, assembly frame (6) and positioning tooling; The assembly frame (6) is a steel pipe + steel plate structure, and the positioning tooling is arranged on both sides of the bridge deck block and arranged corresponding to the bridge deck block cross beams; The steel tube Bailey beam support is composed of a concrete foundation (1), a steel tube column (2), a main beam (3), a Bailey beam (4), a distribution beam and a steel plate, and the structures are connected by welding; An assembly frame (6) is arranged on the steel tube Bailey beam support. The frame (6) is arranged according to the size and segment division of the longitudinal beam (8) and the transverse beam (7) of the bridge deck block. A steel plate support is arranged on the frame (6). The support height is set according to the pre-camber of the bridge deck block. The pre-camber setting is used to offset the curling deformation generated by the weld of the bridge deck block.

2. The integrated working platform for anti-curling construction of orthogonal special-shaped slab bridge deck blocks of steel truss beams according to claim 1, characterized in that: A positioning tool (5) is arranged outside the bridge deck block assembly area and is arranged according to the position of the bridge deck block cross beam (7); the positioning tool (5) is composed of a steel column and a positioning steel plate.

3. The integrated working platform for anti-curling construction of orthogonal special-shaped slab bridge deck blocks of steel truss beams according to claim 1, characterized in that: Up and down construction passages are set up at the outermost part of the construction platform to facilitate construction workers to go to the bottom of the bridge deck block to carry out rod bolt connection, U-rib weld construction or panel longitudinal seam construction on the bridge deck block.

4. The integrated working platform for anti-curling construction of orthogonal special-shaped slab bridge deck blocks of steel truss beams according to claim 1, characterized in that: The pre-camber is set to resist the deformation of the bridge deck blocks after welding.

5. The integrated working platform for anti-curling construction of orthogonal special-shaped slab bridge deck blocks of steel truss beams according to claim 1, characterized in that: The positioning fixture is a steel plate structure with bolt holes, the steel plate is welded to the steel pipe column (2), and the installation position of the bridge deck block crossbeam rod is fixed by bolt connection.