Connecting structure of steel pipe stand column and parallel connection

By using a detachable structure to connect the flat joints and steel pipe columns in a few brackets, the problems of welding connection difficulty and stress concentration are solved, construction efficiency and material utilization are improved, and structural stability and recycling are achieved.

CN222101432UActive Publication Date: 2024-12-03CHINA MCC5 GROUP CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420184150.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-24
Publication Date
2024-12-03
Estimated Expiration
2034-01-24

AI Technical Summary

Technical Problem

In the construction of existing few brackets, it is difficult to weld the connection between the flat coupler and the steel pipe column, the welding quality is difficult to ensure, and welding and flame cutting lead to the concentration of material stress, reducing structural stability and recycling rate.

Method used

The detachable structure is adopted, including a first connecting seat, a second connecting seat and a first bolt assembly, and the horizontal couplet is connected to the steel pipe column to reduce construction difficulty, avoid welding and flame cutting, and improve connection quality and material utilization.

Benefits of technology

It reduces construction difficulty, improves connection quality, avoids material stress concentration, improves the stability and recycling rate of less brackets, and reduces the waste rate.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222101432U_ABST
    Figure CN222101432U_ABST
Patent Text Reader

Abstract

The utility model discloses a connecting structure of a steel pipe stand column and a parallel connection, and relates to the technical field of less-support construction. The connecting structure of the steel pipe stand column and the parallel connection comprises the steel pipe stand column and the parallel connection. The parallel connection is connected with the steel pipe stand column through a detachable structure, and the detachable structure comprises a first connecting base connected with the parallel connection, a second connecting base connected with the steel pipe stand column and a first bolt assembly connected between the first connecting base and the second connecting base. According to the connecting structure of the steel pipe stand column and the parallel connection, the parallel connection and the steel pipe stand column are connected together through the detachable structure composed of the first connecting base, the second connecting base and the first bolt assembly, the installing and detaching difficulty of the parallel connection can be lowered, the construction efficiency is improved, and the connecting quality between the parallel connection and the steel pipe stand column is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of construction with few supports, and in particular to a connection structure of a steel pipe column and a flat joint. Background Art

[0002] Cast-in-place beam construction generally adopts three methods: full support, less support and no support. Among them, less support construction is suitable for casting cast-in-place beams with high clearance and complex geographical conditions.

[0003] The short-short bracket mainly includes a plurality of steel pipe columns and a flat joint connected between two adjacent steel pipe columns. At present, the construction method of the short-short bracket is: first install the steel pipe columns with the cooperation of lifting equipment, and when the steel pipe columns are installed, the flat joint is hoisted to the installation position with the cooperation of lifting equipment and welded to the steel pipe columns. After use, the flat joint is disassembled from the steel pipe columns by flame cutting.

[0004] The installation of flat joints requires aerial vertical welding, which is not only difficult and time-consuming, but also requires workers to have high skills, and the welding quality is difficult to guarantee. Flat joints and steel pipe columns are installed and removed by welding and flame cutting. Each disassembly and assembly will produce residual stress in the material, causing stress concentration in the short-term support during normal operation, reducing the stability of the short-term support; each disassembly and assembly will cause material loss, resulting in a large consumption of materials, resulting in a low recycling rate of the short-term support and an increased scrap rate. Utility Model Content

[0005] The purpose of the present application is to provide a connection structure between a steel pipe column and a flat joint, so as to solve the problem that welding is difficult and the welding quality is difficult to ensure when the flat joint and the steel pipe column are connected by welding.

[0006] The technical solution adopted by the present application to solve its technical problems is: a connection structure between a steel tube column and a flat joint, comprising a steel tube column and a flat joint; the flat joint is connected to the steel tube column through a detachable structure, and the detachable structure comprises a first connecting seat connected to the flat joint, a second connecting seat connected to the steel tube column, and a first bolt assembly connected between the first connecting seat and the second connecting seat.

[0007] Furthermore, the second connecting seat includes two arc-shaped plates, which are respectively arranged on both sides of the steel pipe column and close to the outer surface of the steel pipe column. The two ends of the two arc-shaped plates are respectively connected by second bolt assemblies, and one of the arc-shaped plates is provided with a second connecting plate for connecting with the first bolt assembly.

[0008] Furthermore, the second connecting seat also includes an anti-fall rib plate fixed on the steel pipe column, and the arc-shaped holding plate is supported on the anti-fall rib plate.

[0009] Furthermore, the anti-fall ribs include a plurality of anti-fall ribs, and the plurality of anti-fall ribs are evenly distributed along the circumference of the steel pipe column.

[0010] Furthermore, the anti-fall rib is connected to the steel pipe column by welding.

[0011] Furthermore, the first connecting seat includes a first connecting plate.

[0012] Furthermore, the first connecting plate is connected to the flat joint by welding.

[0013] Furthermore, the first bolt assembly includes a first bolt for passing through the first connecting plate and the second connecting plate, and a first nut threadedly connected to an end of the first bolt.

[0014] Furthermore, the parallel connection includes two vertical poles, and a cross bar is connected between the two ends of the two vertical poles, and an oblique rod is also connected between the vertical poles and the cross bar; one of the vertical poles is connected to the steel pipe column through a detachable structure.

[0015] Furthermore, both ends of the upright pole are connected to the steel pipe upright column via a detachable structure.

[0016] Beneficial effects of this application:

[0017] The connection structure of the steel pipe column and the flat joint provided in the embodiment of the present application connects the flat joint and the steel pipe column together through a detachable structure composed of a first connection seat, a second connection seat and a first bolt assembly. Compared with the existing welding method, it has lower requirements on the skill level of workers, reduces the construction difficulty, improves the construction efficiency, and ensures the connection quality between the flat joint and the steel pipe column. After the use of the short bracket composed of the steel pipe column and the flat joint is completed, it only needs to remove the first bolt assembly to remove the flat joint from the steel pipe column. Compared with the existing flame cutting method, there is no need to use fire, avoid residual stress in the material, prevent the short bracket from generating stress concentration during normal operation, improve the stability of the short bracket, and prevent material loss at the same time, improve the recycling rate of the short bracket, and reduce the scrap rate. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.

[0019] Figure 1It is a structural diagram of the connection between the flat joint and the steel pipe column;

[0020] Figure 2 Schematic diagram of the structure of the second connecting socket.

[0021] Reference numerals:

[0022] 1-steel pipe column; 2-parallel joint; 21-vertical pole; 22-cross bar; 23-diagonal rod; 3-first connecting seat; 31-first connecting plate; 4-second connecting seat; 41-arc-shaped holding plate; 42-second bolt assembly; 43-second connecting plate; 44-anti-fall rib plate; 5-first bolt assembly; 51-first bolt; 52-first nut. DETAILED DESCRIPTION

[0023] In order to make the purpose, technical solutions and advantages of the embodiments of the present application clearer, the technical solutions in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application.

[0024] It should be noted that similar numbers and letters represent similar items in the following drawings, so once an item is defined in one drawing, it does not need to be further defined and explained in the subsequent drawings. In addition, the embodiments and features in the embodiments of this application can be combined with each other without conflict.

[0025] In the description of the embodiments of the present application, the indicated orientation or positional relationship is based on the orientation or positional relationship shown in the accompanying drawings, or is the orientation or positional relationship in which the product of the application is usually placed when in use, or is the orientation or positional relationship commonly understood by those skilled in the art. The terms "disposed", "opened", "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, and an integral connection; it can be a mechanical connection or an electrical connection; it can be directly connected or indirectly connected through an intermediate medium, and it can be the internal connection of two elements.

[0026] See also Figure 1 A connection structure of a steel pipe column and a flat joint provided in an embodiment of the present application includes a steel pipe column 1 and a flat joint 2; the flat joint 2 is connected to the steel pipe column 1 through a detachable structure, and the detachable structure includes a first connecting seat 3 connected to the flat joint 2, a second connecting seat 4 connected to the steel pipe column 1, and a first bolt assembly 5 connected between the first connecting seat 3 and the second connecting seat 4.

[0027] See also Figure 1The process of connecting the flat joint 2 to the steel pipe column 1 using a detachable structure is as follows: connect the first connecting seat 3 to the flat joint 2, connect the second connecting seat 4 to the steel pipe column 1, install the steel pipe column 1 with the cooperation of the lifting equipment, and after the installation of the steel pipe column 1 is completed, hoist the flat joint 2 to the installation position between two adjacent steel pipe columns 1 with the cooperation of the lifting equipment, and then connect the first connecting seat 3 on the flat joint 2 with the second connecting seat 4 on the steel pipe column 1 through the first bolt assembly 5 to complete the installation of the flat joint 2. The dismantling process of the flat joint 2 can be reversed according to the above steps. Among them, the detachable structure can include one, two or more than two, and no specific limitation is made here. Of course, the more detachable structures there are, the higher the reliability of the connection between the flat joint 2 and the steel pipe column 1, but the higher the installation cost.

[0028] The connection structure between the steel pipe column and the flat joint provided in the embodiment of the present application connects the flat joint 2 and the steel pipe column 1 together through a detachable structure composed of a first connection seat 3, a second connection seat 4 and a first bolt assembly 5. Compared with the existing welding method, it has lower requirements on the skill level of workers, reduces the construction difficulty, improves the construction efficiency, and also ensures the connection quality between the flat joint 2 and the steel pipe column 1. After the use of the short bracket composed of the steel pipe column 1 and the flat joint 2 is completed, it is only necessary to remove the first bolt assembly 5 to remove the flat joint 2 from the steel pipe column 1. Compared with the existing flame cutting method, there is no need to use fire, avoid residual stress in the material, prevent the short bracket from generating stress concentration during normal operation, improve the stability of the short bracket, and at the same time prevent the loss of materials, improve the recycling rate of the short bracket, and reduce the scrap rate.

[0029] The second connection seat 4 can be a plate-like structure or a frame structure, which is not specifically limited here. The second connection seat 4 can be fixedly connected to the steel pipe column 1 by welding, or can be detachably connected to the steel pipe column 1 by fasteners such as bolts.

[0030] See also Figure 1 , Figure 2 The second connecting seat 4 includes two arc-shaped plates 41, which are respectively arranged on both sides of the steel pipe column 1 and close to the outer surface of the steel pipe column 1. The two ends of the two arc-shaped plates 41 are respectively connected by second bolt assemblies 42, and one of the arc-shaped plates 41 is provided with a second connecting plate 43 for connecting with the first bolt assembly 5.

[0031] Specifically, the inner diameter of the arc-shaped holding plate 41 is consistent with the outer diameter of the steel pipe column 1. The arc-shaped holding plate 41 can be made by bending a 10 mm thick steel plate. When two arc-shaped holding plates 41 are arranged on both sides of the steel pipe column 1 and fit with the outer surface of the steel pipe column 1, the two ends of the two arc-shaped holding plates 41 are connected together by two second bolt assemblies 42, so that the two arc-shaped holding plates 41 hold the steel pipe column 1 tightly, and the connection between the arc-shaped holding plates 41 and the steel pipe column 1 is realized. The second connecting plate 43 can be welded to one of the arc-shaped holding plates 41, and connected to the first connecting seat 3 through the first bolt assembly 5.

[0032] The second connecting seat 4 provided in the embodiment of the present application, by providing two arc-shaped holding plates 41 and a second bolt assembly 42 connecting the two arc-shaped holding plates 41 together, can also enable the arc-shaped holding plates 41 to serve as a positioning function during use, so as to improve the installation efficiency of the flat joint 2. For example, during operation, the second connecting seat 4 is not connected to the steel pipe column 1 first, the first connecting seat 3 is connected to the flat joint 2, and the second connecting plate 43 on one of the arc-shaped holding plates 41 is connected to the first connecting seat 3 through the first bolt assembly 5; after the steel pipe column 1 is installed with the cooperation of the lifting equipment, the flat joint 2 is hoisted to the installation position between two adjacent steel pipe columns 1 with the cooperation of the lifting equipment, and then the arc-shaped holding plate 41 connected to the flat joint 2 is fitted with the steel pipe column 1, and the cooperation between the arc-shaped holding plate 41 and the steel pipe column 1 can be used to achieve rapid positioning of the flat joint 2, and then another arc-shaped holding plate 41 is fitted with the steel pipe column 1, and the two arc-shaped holding plates 41 are connected together through the second bolt assembly 42, which can improve the installation efficiency of the flat joint 2 and save construction time.

[0033] See also Figure 1 , Figure 2 , the second connection seat 4 also includes an anti-fall rib 44 fixed on the steel pipe column 1, and the arc-shaped holding plate 41 is supported on the anti-fall rib 44. By setting the anti-fall rib 44, it is used to support the arc-shaped holding plate 41. During use, even if the second bolt assembly 32 is loosened due to vibration, collision, etc., the arc-shaped holding plate 41 can be prevented from falling on the steel pipe column 1, thereby preventing the flat link 2 from falling. Among them, the anti-fall rib 44 can be made of a steel plate thicker than 10mm. In order to improve the supporting strength of the anti-fall rib 44, illustratively, the anti-fall rib 44 includes a plurality of anti-fall ribs 44, and the plurality of anti-fall ribs 44 are evenly distributed along the circumference of the steel pipe column 1. For example, four anti-fall ribs 44 are evenly distributed around the circumference of the steel pipe column 1. The anti-fall rib 44 is welded to the steel pipe column 1 to ensure the connection strength between the anti-fall rib 44 and the steel pipe column 1.

[0034] See also Figure 2The first connection seat 3 includes a first connection plate 31, and the first connection plate 31 is welded to the flat joint 2. Of course, in other embodiments, the first connection seat 3 can also be a frame structure, and the first connection seat 3 can also be connected to the flat joint 2 by fasteners such as bolts, which is not specifically limited here.

[0035] See also Figure 2 The first bolt assembly 5 includes a first bolt 51 for passing through the first connecting plate 31 and the second connecting plate 43, and a first nut 52 threadedly connected to the end of the first bolt 51. The first connecting plate 31 and the second connecting plate 43 are both provided with a through hole for the first bolt 51 to pass through, and the diameter of the through hole is about 2 to 3 mm of the outer diameter of the first bolt 51, so that the first bolt 51 can pass through the through hole smoothly.

[0036] See also Figure 1 The flat joint 2 includes two vertical poles 21, and a cross bar 22 is connected between the two ends of the two vertical poles 21, and an oblique rod 23 is also connected between the vertical poles 21 and the cross bar 22; one of the vertical poles 21 is connected to the steel pipe column 1 through a detachable structure. The vertical poles 21, the cross bar 22 and the oblique rod 23 can be connected by welding, and of course, they can also be connected by fasteners such as bolts. The vertical poles 21, the cross bar 22 and the oblique rod 23 can all be made of channel steel, and can also be made of other steel sections such as angle steel and I-beam. The two ends of the vertical pole 21 are connected to the steel pipe column 1 through a detachable structure. The two vertical poles 21 are respectively connected to the two steel pipe columns 1.

[0037] The above is only a preferred embodiment of the present application and does not constitute any form of limitation to the present application. Based on the technical essence of the present application and within the spirit and principles of the present application, any simple modification, equivalent replacement and improvement of the above embodiments shall still fall within the protection scope of the technical solution of the present application.

Claims

1. A connection structure between a steel pipe column and a flat joint, It is characterized in that It comprises a steel tube column (1) and a flat joint (2); the flat joint (2) is connected to the steel tube column (1) via a detachable structure, and the detachable structure comprises a first connection seat (3) connected to the flat joint (2), a second connection seat (4) connected to the steel tube column (1), and a first bolt assembly (5) connected between the first connection seat (3) and the second connection seat (4); The second connection seat (4) comprises two arc-shaped holding plates (41), the two arc-shaped holding plates (41) are respectively arranged on both sides of the steel pipe column (1) and are closely attached to the outer surface of the steel pipe column (1), the two ends of the two arc-shaped holding plates (41) are respectively connected by a second bolt assembly (42), and one of the arc-shaped holding plates (41) is provided with a second connecting plate (43) for connecting with the first bolt assembly (5); The second connecting seat (4) also includes an anti-fall rib plate (44) fixed on the steel pipe column (1), and the arc-shaped holding plate (41) is supported on the anti-fall rib plate (44).

2. The connection structure of the steel pipe column and the flat joint according to claim 1, It is characterized in that The anti-fall ribs (44) include a plurality of anti-fall ribs (44), and the plurality of anti-fall ribs (44) are evenly distributed along the circumference of the steel pipe column (1).

3. The connection structure of the steel pipe column and the flat joint according to claim 2, It is characterized in that The anti-fall rib plate (44) is welded to the steel pipe column (1).

4. The connection structure of the steel pipe column and the flat joint according to claim 1, It is characterized in that The first connecting seat (3) comprises a first connecting plate (31).

5. The connection structure of the steel pipe column and the flat joint according to claim 4, It is characterized in that The first connecting plate (31) is connected to the flat link (2) by welding.

6. The connection structure of the steel pipe column and the flat joint according to claim 4 or 5, It is characterized in that The first bolt assembly (5) comprises a first bolt (51) for passing through the first connecting plate (31) and the second connecting plate (43), and a first nut (52) threadedly connected to the end of the first bolt (51).

7. The connection structure of the steel pipe column and the flat joint according to claim 2, It is characterized in that The parallel connection (2) comprises two vertical poles (21), and a cross bar (22) is connected between the two ends of the two vertical poles (21), and an oblique rod (23) is also connected between the vertical poles (21) and the cross bar (22); one of the vertical poles (21) is connected to the steel pipe column (1) through a detachable structure.

8. The connection structure of the steel pipe column and the flat joint according to claim 7, It is characterized in that Both ends of the upright pole (21) are connected to the steel pipe upright column (1) via detachable structures.