Steel structure building pipeline arrangement structure
By using anti-slip cushion layer and bracket components in steel structure buildings, the problem of pipeline sliding is solved, the stability of pipeline and the stability of the overall structure is improved, and the circuit transformation and maintenance process is simplified.
Patent Information
- Application Number
- CN202420179097.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-25
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2034-01-25
AI Technical Summary
In steel structure buildings, the layout of wire and pipelines is small due to the low friction between the pipeline and the inner wall of the line pipe, which causes pipelines to slide, affecting stability, and it is difficult to transform and repair later.
Adopt anti-slip cushion to fit the pipeline, increase friction, and design through the bracket assembly, connecting assembly and positioning assembly, including bracket base, stabilizing plate, support plate, bracket column, crossbar, engaging block, positioning seat and tight The solid knob is fixed with reinforcement ribs and bolts to improve the stability of the pipeline and connection stability.
It effectively increases the stability of the pipeline, prevents slippage, and simplifies the later circuit transformation and maintenance, improving the stability and convenience of the overall structure.
Smart Images

Figure CN222107530U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of pipeline arrangement, in particular to a pipeline arrangement structure for a steel structure building. Background Art
[0002] Steel structure building is a new type of building system, which breaks through the industry boundaries between real estate, construction and metallurgy, and integrates them into a new industrial system. This is the steel structure building system that is generally favored by industry insiders. Compared with traditional concrete buildings, steel structure buildings use steel plates or steel sections instead of reinforced concrete, which has higher strength and better earthquake resistance.
[0003] At present, most steel structure buildings arrange wires and pipelines on the keel layer of wall panels or floor slabs. However, due to the crisscrossing of wires and pipelines, when the keel conflicts with the position of internal pipelines, it is necessary to drill holes in the keel for normal installation, which affects the main structure of the steel structure. Since the layout design of wires and pipelines is concentrated on the keel layer, the later circuit transformation and maintenance are difficult. At the same time, the pipelines are directly placed in the line pipes. Due to the small friction between the pipelines and the inner wall of the line pipes, the pipelines slide after arrangement, which in turn affects the stability of the pipeline layout structure. Utility Model Content
[0004] In view of the above problems, the purpose of the utility model is to provide a pipeline layout structure for a steel structure building, so as to solve the problem that when the pipeline is directly placed inside the line pipe, the friction between the pipeline and the inner wall of the line pipe is small, which causes the pipeline to slide after layout, thereby affecting the stability of the pipeline layout structure. The line pipe is provided to layout the pipeline, and the anti-skid pad is provided to fit the pipeline, and the friction between the anti-skid pad and the pipeline is increased through the anti-skid pad, thereby ensuring the stability of the pipeline during layout. At the same time, gaps are provided between adjacent anti-skid pads to provide space for the anti-skid pad to be deformed under stress.
[0005] To achieve the above objectives, the technical solution adopted by the utility model is: a steel structure building pipeline layout structure, including a bracket assembly, a connecting assembly, and a positioning assembly. The bracket assembly includes a bracket base, the top of the bracket base is connected with a stabilizing plate, the end of the stabilizing plate away from the bracket base is connected with a supporting plate, the top of the bracket base is connected with a bracket column, and the end of the bracket column away from the bracket base is connected with a mounting plate. The connecting assembly includes a cross bar, the inner side of the cross bar is provided with a plug-in groove, and the two ends of the cross bar are symmetrically connected with locking blocks. The positioning assembly includes a positioning seat, the inner side of the positioning seat is provided with a fastening knob, one end of the positioning seat is connected with a mounting ring, the end of the mounting ring away from the positioning seat is connected with a line pipe, the inner wall of the line pipe is connected with an anti-slip pad, the inner side of the positioning seat is provided with a positioning groove, and the inner wall of the positioning groove is connected with a plug-in plate.
[0006] The beneficial effects of the utility model are as follows: the line pipe is provided for arranging the pipeline, the anti-skid pad is provided for fitting with the pipeline, and the friction between the anti-skid pad and the pipeline is increased through the anti-skid pad, thereby ensuring the stability of the pipeline during arrangement; at the same time, gaps are provided between adjacent anti-skid pads to provide space for the anti-skid pads to deform under stress; and the reinforcement ribs are provided to increase the connection area between the bracket column and the mounting plate, thereby improving the stability of the connection between the bracket column and the mounting plate; when in use, the mounting plate is brought into contact with and fitted on the steel structure building, and then the mounting plate is fixed with bolts, thereby achieving the fixing of the pipeline arrangement structure on the steel structure building.
[0007] In order to improve the support force of the support plate:
[0008] As a further improvement of the above technical solution: both ends of the support plate are connected to the bracket columns, and there are two stabilizing plates in total, which are symmetrically arranged, and the ends of the two stabilizing plates that are away from each other are connected to the side guard plates.
[0009] The beneficial effects of this improvement are: by setting the support plate, it is used to protect the pipeline placed on the bracket base, and by setting the stabilizing plate, it is used to increase the supporting force of the support plate, thereby ensuring the stability of the support plate when in use.
[0010] In order to improve the stability of the connection between the support column and the support base:
[0011] As a further improvement of the above technical solution: a side guard plate is connected to the top of the bracket base, and both ends of the side guard plate are connected to the bracket columns at the same time.
[0012] The beneficial effect of this improvement is: through the setting of the bracket base, it is used to fix and support the side guard plate and the bracket column. Through the setting of the side guard plate, the connection area between the bracket column and the bracket base can be increased, thereby improving the stability of the connection between the bracket column and the bracket base.
[0013] In order to increase the connection area between the bracket column and the mounting plate:
[0014] As a further improvement of the above technical solution: a screw hole is opened on the inner side of the mounting plate, a reinforcing rib is connected to the bottom of the mounting plate, and one end of the reinforcing rib away from the mounting plate is connected to the bracket column.
[0015] The beneficial effect of this improvement is that by setting the reinforcing ribs, the connection area between the bracket column and the mounting plate can be increased, thereby improving the stability of the connection between the bracket column and the mounting plate. When in use, the mounting plate is contacted and fitted with the steel structure building, and then the mounting plate is fixed with bolts, thereby fixing the pipeline layout structure on the steel structure building.
[0016] In order to improve the stability of the positioning assembly after being connected to the crossbar:
[0017] As a further improvement of the above technical solution: connecting angle plates are symmetrically arranged at the connection between the snap-fit block and the cross bar, and the snap-fit block is snap-connected with the bracket column.
[0018] The beneficial effect of this improvement is that by setting the connecting angle plate, the stability of the connection between the cross bar and the locking block can be improved, thereby improving the stability of the positioning assembly after being connected to the cross bar.
[0019] In order to achieve the installation and fixation of the positioning seat:
[0020] As a further improvement of the above technical solution: both ends of the crossbar are connected to the bracket columns through snap blocks, and the size of the plug-in slot matches the size of the plug-in board.
[0021] The beneficial effect of this improvement is that the cross bar is provided to connect with the positioning seat, thereby achieving installation and fixation of the positioning seat.
[0022] In order to facilitate the movement of the positioning seat by sliding the plug-in board in the plug-in slot:
[0023] As a further improvement of the above technical solution: the height of the positioning groove matches the height of the cross bar, and the positioning seat is rotatably connected to the tightening knob.
[0024] The beneficial effect of this improvement is: when in use, align the positioning slot of the positioning seat with the cross bar, insert the plug-in board into the plug-in slot, and then dock the positioning seat with the cross bar. After docking, move the positioning seat along the plug-in slot to achieve synchronous movement of the line pipe. After moving to the appropriate position, tighten the tightening knob to achieve the effect of installing and adjusting the line pipe for arranging the pipeline. By inserting the plug-in board into the plug-in slot, the stability of the connection between the positioning seat and the cross bar can be improved, and the movement of the positioning seat can be achieved by sliding the plug-in board in the plug-in slot.
[0025] In order to increase the friction between the anti-slip pad and the pipeline:
[0026] As a further improvement of the above technical solution: the anti-slip cushion layer is a rubber layer with an arc-shaped cross-section when viewed from the front, and the outer wall of the mounting ring away from the end of the line pipe is connected to three positioning seats.
[0027] The beneficial effects of this improvement are: through the provision of the line pipe, it is used to arrange the pipeline, through the provision of the anti-skid pad layer, it is used to fit the pipeline, and then the anti-skid pad layer increases the friction between it and the pipeline, thereby ensuring the stability of the pipeline during layout, and at the same time, there are gaps between adjacent anti-skid pad layers to provide space for the anti-skid pad layers to be deformed under stress. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 It is a front structural schematic diagram of the utility model.
[0029] Figure 2 It is a three-dimensional structural schematic diagram of the support base of the utility model.
[0030] Figure 3 for Figure 2 Schematic diagram of the enlarged structure at point A in the middle.
[0031] Figure 4 It is a structural schematic diagram of the positioning seat of the utility model.
[0032] Figure 5 It is a structural schematic diagram of the anti-skid cushion layer of the utility model.
[0033] In the figure: 1. bracket assembly; 11. bracket base; 12. stabilizing plate; 13. support plate; 14. side guard plate; 15. bracket column; 16. mounting plate; 17. reinforcing rib; 2. connecting assembly; 21. cross bar; 22. plug-in slot; 23. snap-fit block; 24. connecting angle plate; 3. positioning assembly; 31. positioning seat; 32. tightening knob; 33. positioning slot; 34. mounting ring; 35. line pipe; 36. anti-slip pad; 37. plug-in board. DETAILED DESCRIPTION
[0034] In order to enable those skilled in the art to better understand the technical solution of the utility model, the utility model is described in detail below in conjunction with the accompanying drawings. The description in this part is only exemplary and explanatory and should not have any limiting effect on the protection scope of the utility model.
[0035] like Figure 1-5As shown, a steel structure building pipeline arrangement structure includes a bracket assembly 1, a connecting assembly 2, and a positioning assembly 3. The bracket assembly 1 includes a bracket base 11, the top of the bracket base 11 is connected to a stabilizing plate 12, and the end of the stabilizing plate 12 away from the bracket base 11 is connected to a support plate 13, the top of the bracket base 11 is connected to a bracket column 15, and the end of the bracket column 15 away from the bracket base 11 is connected to a mounting plate 16, the connecting assembly 2 includes a cross bar 21, the inner side of the cross bar 21 is provided with a plug-in groove 22, and the two ends of the cross bar 21 are symmetrically connected with a snap-fit block 23, the positioning assembly 3 includes a positioning seat 31, the inner side of the positioning seat 31 is provided with a fastening knob 32, and the positioning One end of the seat 31 is connected to a mounting ring 34, and the end of the mounting ring 34 away from the positioning seat 31 is connected to a line pipe 35, and the inner wall of the line pipe 35 is connected to an anti-slip pad 36. A positioning groove 33 is provided on the inner side of the positioning seat 31, and the inner wall of the positioning groove 33 is connected to a plug-in plate 37. Both ends of the support plate 13 are connected to the bracket column 15. There are two stabilizing plates 12 in total, and the two stabilizing plates 12 are symmetrically arranged. The ends of the two stabilizing plates 12 away from each other are connected to the side guard plate 14; the support plate 13 is arranged to protect the pipeline placed on the bracket base 11, and the stabilizing plate 12 is arranged to increase the supporting force of the support plate 13, thereby ensuring the support plate 13 stability during use, the top of the bracket base 11 is connected with a side guard plate 14, and both ends of the side guard plate 14 are connected to the bracket column 15 at the same time; the bracket base 11 is provided to fix and support the side guard plate 14 and the bracket column 15, and the side guard plate 14 is provided to increase the connection area between the bracket column 15 and the bracket base 11, thereby improving the stability of the connection between the bracket column 15 and the bracket base 11, the inner side of the mounting plate 16 is provided with a screw hole, and the bottom of the mounting plate 16 is connected with a reinforcing rib 17, and the end of the reinforcing rib 17 away from the mounting plate 16 is connected to the bracket column 15; the reinforcing rib 17 is provided to increase the connection area between the bracket column 15 and the mounting plate 16 The mounting plate 16 is fixed to the steel structure building, and then the mounting plate 16 is fixed with bolts to fix the pipeline arrangement structure on the steel structure building. The connection between the snap block 23 and the cross bar 21 is symmetrically provided with a connecting angle plate 24, and the snap block 23 is snap-connected with the bracket column 15; the setting of the connecting angle plate 24 can improve the stability of the connection between the cross bar 21 and the snap block 23, thereby improving the stability of the positioning assembly 3 after being connected to the cross bar 21. The two ends of the cross bar 21 are connected to the bracket column 15 through the snap block 23, and the size of the plug-in slot 22 matches the size of the plug-in plate 37;The cross bar 21 is provided to be connected with the positioning seat 31, thereby realizing the installation and fixation of the positioning seat 31. The height of the positioning groove 33 matches the height of the cross bar 21, and the positioning seat 31 is rotatably connected with the fastening knob 32. When in use, the positioning groove 33 of the positioning seat 31 is aligned with the cross bar 21, and the plug-in plate 37 is inserted into the plug-in groove 22, and then the positioning seat 31 and the cross bar 21 are docked. After docking, the positioning seat 31 is moved along the plug-in groove 22, thereby realizing the synchronous movement of the line pipe 35. After moving to the appropriate position, the fastening knob 32 can be tightened, thereby achieving the effect of installing and adjusting the line pipe 35, so as to arrange the pipeline, by inserting the plug-in plate 37 into the plug-in groove 22 The positioning seat 31 is inserted into the plug-in slot 22, which can improve the stability of the connection between the positioning seat 31 and the cross bar 21, and facilitate the movement of the positioning seat 31 by sliding the plug-in board 37 in the plug-in slot 22. The anti-skid pad layer 36 is a rubber layer with an arc-shaped cross-section in the front view. The outer wall of the mounting ring 34 away from the end of the line pipe 35 is connected with three positioning seats 31; the line pipe 35 is set to arrange the pipeline, and the anti-skid pad layer 36 is set to fit the pipeline, and then the friction between the anti-skid pad layer 36 and the pipeline is increased, thereby ensuring the stability of the pipeline when arranged. At the same time, there is a gap between adjacent anti-skid pad layers 36, which is used for the space for the anti-skid pad layer 36 to deform under stress. ;
[0036] The working principle of the utility model is as follows: when in use, the positioning groove 33 of the positioning seat 31 is aligned with the cross bar 21, and the plug-in plate 37 is inserted into the plug-in groove 22, and then the positioning seat 31 and the cross bar 21 are docked, and after docking, the positioning seat 31 is moved along the plug-in groove 22, thereby realizing the synchronous movement of the line tube 35, and after moving to a suitable position, the fastening knob 32 can be tightened, thereby achieving the effect of installing and adjusting the line tube 35 for arranging the pipeline, and by inserting the plug-in plate 37 into the plug-in groove 22, it can improve The connection between the positioning seat 31 and the cross bar 21 is stable, and the positioning seat 31 can be moved by sliding the plug-in plate 37 in the plug-in slot 22. The line tube 35 is provided to arrange the pipeline, and the anti-skid pad 36 is provided to fit the pipeline, and the friction between the anti-skid pad 36 and the pipeline is increased. At the same time, there is a gap between adjacent anti-skid pads 36 to provide space for the anti-skid pads 36 to deform under stress. The cross bar 21 is provided to connect with the positioning seat 31, so as to realize The installation and fixation of the positioning seat 31 is now completed, and then the mounting plate 16 is contacted and fitted with the steel structure building, and then the mounting plate 16 is fixed with bolts, thereby fixing the pipeline arrangement structure on the steel structure building. By setting the reinforcing ribs 17, the connection area between the bracket column 15 and the mounting plate 16 can be increased, thereby improving the stability of the connection between the bracket column 15 and the mounting plate 16. By setting the connecting angle plate 24, the stability of the connection between the cross bar 21 and the locking block 23 can be improved, thereby improving the connection between the positioning assembly 3 and the cross bar 21. In order to ensure stability after use, the support base 11 is provided to fix and support the side guard plates 14 and the support columns 15. The side guard plates 14 can increase the connection area between the support columns 15 and the support base 11, thereby improving the stability of the connection between the support columns 15 and the support base 11. The support plate 13 can be provided to protect the pipelines placed on the support base 11. The stabilizing plate 12 can be provided to improve the supporting force of the support plate 13, thereby ensuring the stability of the support plate 13 when in use.
[0037] It should be noted that, in this article, the terms "comprises", "includes" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, article or apparatus that includes a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or apparatus.
[0038] This article uses specific examples to illustrate the principles and implementation methods of the utility model. The above examples are only used to help understand the method and core ideas of the utility model. The above is only the preferred implementation method of the utility model. It should be pointed out that due to the limitations of textual expression, there are objectively infinite specific structures. For ordinary technicians in this technical field, without departing from the principle of the utility model, they can make several improvements, modifications or changes, and can also combine the above technical features in an appropriate manner; these improvements, modifications, changes or combinations, or the direct application of the concept and technical solution of the utility model to other occasions without improvement, should be regarded as the protection scope of the utility model.
Claims
1. A steel structure building pipeline arrangement structure, comprising a bracket assembly (1), a connection assembly (2), and a positioning assembly (3), wherein the bracket assembly (1) comprises a bracket base (11), characterized in that: The top of the support base (11) is connected to a stabilizing plate (12), one end of the stabilizing plate (12) away from the support base (11) is connected to a supporting plate (13), the top of the support base (11) is connected to a support column (15), one end of the support column (15) away from the support base (11) is connected to a mounting plate (16), the connecting assembly (2) comprises a cross bar (21), the inner side of the cross bar (21) is provided with a plug-in slot (22), and the two ends of the cross bar (21) are symmetrically connected with a snap-fitting The block (23) comprises a positioning seat (31), a fastening knob (32) is arranged on the inner side of the positioning seat (31), one end of the positioning seat (31) is connected to a mounting ring (34), one end of the mounting ring (34) away from the positioning seat (31) is connected to a line pipe (35), the inner wall of the line pipe (35) is connected to an anti-slip pad layer (36), a positioning groove (33) is arranged on the inner side of the positioning seat (31), and the inner wall of the positioning groove (33) is connected to a plug-in board (37).
2. A steel structure building pipeline arrangement structure according to claim 1, characterized in that: Both ends of the support plate (13) are connected to the bracket columns (15), and two stabilizing plates (12) are provided. The two stabilizing plates (12) are symmetrically arranged, and the ends of the two stabilizing plates (12) that are away from each other are connected to the side guard plates (14).
3. A steel structure building pipeline arrangement structure according to claim 1, characterized in that: The top of the support base (11) is connected to a side guard plate (14), and both ends of the side guard plate (14) are simultaneously connected to the support column (15).
4. A steel structure building pipeline arrangement structure according to claim 1, characterized in that: A screw hole is provided on the inner side of the mounting plate (16), a reinforcing rib (17) is connected to the bottom of the mounting plate (16), and an end of the reinforcing rib (17) away from the mounting plate (16) is connected to the bracket column (15).
5. The steel structure building pipeline layout structure according to claim 1, characterized in that: A connecting angle plate (24) is symmetrically arranged at the connection between the snap-fit block (23) and the crossbar (21), and the snap-fit block (23) is snap-fitted and connected to the bracket column (15).
6. A steel structure building pipeline arrangement structure according to claim 1, characterized in that: The two ends of the crossbar (21) are connected to the bracket column (15) through a snap-fit block (23), and the size of the plug-in slot (22) matches the size of the plug-in board (37).
7. The steel structure building pipeline arrangement structure according to claim 1, characterized in that: The height of the positioning groove (33) matches the height of the crossbar (21), and the positioning seat (31) is rotatably connected to the tightening knob (32).
8. The steel structure building pipeline arrangement structure according to claim 1, characterized in that: The anti-slip cushion layer (36) is a rubber layer with an arc-shaped cross section when viewed from the front. The outer wall of the mounting ring (34) at one end away from the line pipe (35) is connected to three positioning seats (31).