Concrete beam-column joint combined partition plate structure

By using a combined structure of steel edges and central partitions in the beam and column node areas, the problem of airbag isolation device being prone to inlaid during concrete pouring and vibration is solved, and the flat contact surface and efficient construction are achieved, which significantly improves the construction Efficiency and quality.

CN222120500UActive Publication Date: 2024-12-06XINJIANG ROAD & BRIDGE CONSTR GRP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323406462.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-13
Publication Date
2024-12-06
Estimated Expiration
2033-12-13

Smart Images

  • Figure CN222120500U_ABST
    Figure CN222120500U_ABST
Patent Text Reader

Abstract

The embodiment of the utility model provides a concrete beam-column joint combined partition plate structure, and relates to the field of concrete beam-column joint spacing. The problem that air bag isolation in a beam-column joint area easily causes concrete collapse in the beam-column joint area is solved. The partition plates comprise two edge partition plates and a middle partition plate, each edge partition plate comprises a first plate body and a front telescopic plate, and the front telescopic plates have the movement tendency of moving outwards relative to the first plate bodies; the at least two middle partition plates are sequentially spliced and fixed side by side, and the two middle partition plates located on the outermost side are used for being spliced and fixed to the edge partition plates respectively. The edge partition plates and the middle partition plates are made of steel and not prone to deformation, and concrete pouring contact faces are flat. The edge partition plates and the middle partition plates which are assembled are convenient to dismantle and take out, and collapse is not prone to occurring. A front telescopic plate is arranged on the edge partition plate and can be tightly attached to the steel bars, and concrete is prevented from flowing from gaps of the steel bars.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of concrete beam-column node spacing, in particular to a concrete beam-column node combined partition structure. Background Art

[0002] At present, in the design of high-seismic-grade buildings, the strength of column concrete is often higher than that of beam concrete. In order to meet the design and specification requirements and prevent high-grade concrete from flowing in the core area of ​​the joint between beams and columns, it is necessary to adopt a partition construction process to ensure that all columns are cast with high-grade concrete and reduce its loss.

[0003] The existing airbag isolation device for the beam-column joint area sets multiple inflatable airbags in the beam reinforcement skeleton to isolate concrete of different grades. However, in the prior art, when the column concrete is poured and vibrated, the airbag in the center of the beam has no effective support and only relies on the friction with the reinforcement. The airbag is easy to sink under the lateral pressure during concrete pouring, and the airbag is easily disturbed during vibration, and the contact surface is uneven; and the contact surface between the airbag and the column concrete is easy to form a smooth surface, which is not conducive to the combination of the beam concrete and the airbag; when the beam concrete is poured, the airbag is deformed under the lateral pressure of vibration. When the airbag is taken out, the airbag is large in size, and the wrong deflation time is easy to cause the concrete in the poured beam-column joint area to collapse, and the airbag in the middle of the beam is not easy to take out when the reinforcement is dense. Utility Model Content

[0004] The purpose of the utility model includes, for example, providing a concrete beam-column joint combined partition structure, which can improve the problem that airbag isolation in the beam-column joint area easily causes concrete collapse in the beam-column joint area.

[0005] The embodiments of the present invention can be implemented as follows:

[0006] An embodiment of the utility model provides a combined partition structure of a concrete beam-column node, including an edge partition and a middle partition, wherein the number of the edge partitions is two, each of the edge partitions includes a first plate body and a front telescopic plate, the front telescopic plate is movably connected in the first plate body, and the front telescopic plate has a tendency to move outward relative to the first plate body; the number of the middle partitions is at least two; at least two of the middle partitions are spliced ​​and fixed side by side in sequence, wherein the two middle partitions located on the outermost sides are respectively used for splicing and fixing with one of the edge partitions; the same side of the front telescopic plate and at least two of the middle partitions are used together for forming concrete.

[0007] In addition, the concrete beam-column node composite diaphragm structure provided by the embodiment of the utility model may also have the following additional technical features:

[0008] Optionally, the edge partition includes a first elastic member; the front telescopic plate and the first plate body are connected via the first elastic member, and the first elastic member is used to enable the front telescopic plate to have a movement tendency to move outward relative to the first plate body.

[0009] Optionally, the edge partition also includes a side telescopic plate; the side telescopic plate is movably connected to the first plate body, and the side telescopic plate and the front telescopic plate are perpendicular to each other; the side telescopic plate has a tendency to move outward relative to the first plate body to approach the forming template.

[0010] Optionally, the edge partition further includes a second elastic member; the lateral telescopic plate and the first plate body are connected via the second elastic member, and the second elastic member has a movement tendency to move the lateral telescopic plate outward relative to the first plate body.

[0011] Optionally, a surface of the middle partition for forming concrete is provided with a plurality of protrusions or pits.

[0012] Optionally, a first connecting hole is provided on one side of the edge partition adjacent to the middle partition; a telescopic pin and a second connecting hole are respectively provided on two opposite sides of the middle partition; the telescopic pin is used to be spliced ​​and fixed with the first connecting hole of the adjacent edge partition, or the telescopic pin is used to be spliced ​​and fixed with the second connecting hole of the adjacent middle partition.

[0013] Optionally, the middle partition includes a second plate body, a supporting plate and a third elastic member; the supporting plate is movably connected to the second plate body, and the telescopic pin is fixed to the supporting plate and movably penetrates the second plate body; the supporting plate and the second plate body are connected by a third elastic member, and the third elastic member has a movement tendency to cause the supporting plate to move inward relative to the second plate body, and the supporting plate is used to move outward relative to the second plate body under the action of external force, so that the telescopic pin moves outward to be inserted into the first connecting hole or the second connecting hole.

[0014] Optionally, the concrete beam-column node combined partition structure further includes a force transmission rod; the force transmission rod is used to be detachably inserted into the second plate body, and the force transmission rod is used to push the supporting plate to move outward relative to the second plate body.

[0015] Optionally, the concrete beam-column node combined partition structure also includes a crossbeam; one end of a plurality of force transmission rods passing through the second plate body is passed through and fixed on the crossbeam, so that the edge partition and the middle partition are spliced ​​together.

[0016] Optionally, the concrete beam-column node combined diaphragm structure further includes stirrups; the stirrups are arranged at the upper and lower ends of the force transmission rod.

[0017] The beneficial effects of the concrete beam-column node combined diaphragm structure of the embodiment of the utility model include, for example:

[0018] A composite partition structure of a concrete beam-column node includes an edge partition and a middle partition. There are two edge partitions, each edge partition includes a first plate body and a front telescopic plate, the front telescopic plate is movably connected to the first plate body, and the front telescopic plate has a tendency to move outward relative to the first plate body; there are at least two middle partitions; at least two middle partitions are spliced ​​and fixed side by side in sequence, wherein the two outermost middle partitions are respectively used for splicing and fixing with an edge partition; the same side of the front telescopic plate and at least two middle partitions are used together for forming concrete.

[0019] The edge partitions and the middle partitions are made of steel and are not easy to deform. They are not easy to sink under the side pressure when pouring concrete, and the contact surface is flat. The edge partitions and the middle partitions are assembled, and they are quick-detached. They are small in width and volume, easy to remove and take out, and not easy to collapse. The edge partitions are equipped with front telescopic plates, which can fit tightly with the steel bars to prevent concrete from flowing through the gaps in the steel bars. Significantly improve construction efficiency and quality. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] In order to more clearly illustrate the technical solutions of the embodiments of the utility model, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the utility model and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other relevant drawings can be obtained based on these drawings without paying creative work.

[0021] Figure 1 A schematic diagram of a concrete beam-column node composite diaphragm structure provided in this embodiment applied to a beam-column node area;

[0022] Figure 2 A front view of an edge partition in a composite partition structure of a concrete beam-column node provided in this embodiment;

[0023] Figure 3 For along Figure 2 The cross-sectional view of AA in FIG.

[0024] Figure 4 For along Figure 3 A cross-sectional view of BB in FIG.

[0025] Figure 5 A front view of a middle partition in a composite partition structure of a concrete beam-column node provided in this embodiment;

[0026] Figure 6 A side view of a middle partition in a composite partition structure of a concrete beam-column node provided in this embodiment;

[0027] Figure 7 For along Figure 6 A cross-sectional view of CC in FIG.

[0028] Figure 8 A schematic diagram of the concrete beam-column node composite diaphragm structure provided in this embodiment before splicing;

[0029] Fig. 9 A schematic diagram of the concrete beam-column node composite partition structure after splicing provided in this embodiment.

[0030] Icons: 10-concrete beam-column node combined partition structure; 100-edge partition; 110-first plate body; 120-front telescopic plate; 130-first elastic member; 140-side telescopic plate; 150-second elastic member; 160-first connecting hole; 200-middle partition; 210-telescopic pin; 220-second connecting hole; 230-second plate body; 240-supporting plate; 250-third elastic member; 260-thorn; 300-force transmission rod; 400-crossbeam; 500-rebar. DETAILED DESCRIPTION

[0031] In order to make the purpose, technical scheme and advantages of the embodiments of the utility model clearer, the technical scheme in the embodiments of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiments of the utility model. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Generally, the components of the embodiments of the utility model described and shown in the drawings here can be arranged and designed in various different configurations.

[0032] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the present invention to be protected, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0033] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.

[0034] In the description of the present utility model, it should be noted that if the terms "upper", "lower", "inside", "outside", etc. appear, the orientation or position relationship indicated is based on the orientation or position relationship shown in the accompanying drawings, or is the orientation or position relationship in which the utility model product is usually placed when used. It is only for the convenience of describing the utility model and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it cannot be understood as a limitation on the present utility model.

[0035] In addition, the terms “first”, “second”, etc., if used, are merely used to distinguish between the descriptions and should not be understood as indicating or implying relative importance.

[0036] It should be noted that, in the absence of conflict, the features in the embodiments of the present invention may be combined with each other.

[0037] Combine the following Figures 1 to 9 The concrete beam-column node composite diaphragm structure 10 provided in this embodiment is described in detail.

[0038] Please refer to Figure 1 , Figure 8 and Fig. 9 The embodiment of the utility model provides a concrete beam-column node composite partition structure 10, including an edge partition 100 and a middle partition 200, the number of the edge partitions 100 is two, each edge partition 100 includes a first plate body 110 and a front telescopic plate 120, the front telescopic plate 120 is movably connected in the first plate body 110, and the front telescopic plate 120 has a movement tendency to move outward relative to the first plate body 110; the number of the middle partitions 200 is at least two; at least two middle partitions 200 are spliced ​​and fixed side by side in sequence, wherein the two outermost middle partitions 200 are respectively used for splicing and fixing with an edge partition 100; the same side of the front telescopic plate 120 and at least two middle partitions 200 are used together for forming concrete.

[0039] At least two middle partitions 200 are arranged side by side, and two edge partitions 100 are arranged on both sides. The two edge partitions 100 and at least two middle partitions 200 are spliced ​​together to form a beam-column node zone. The edge partitions 100 and the middle partitions 200 are both made of steel. The disturbance of concrete will not cause the edge partitions 100 and the middle partitions 200 to be dented, and the concrete is not easy to collapse; the edge partitions 100 and the middle partitions 200 are spliced, which is convenient for construction, high efficiency, and easy to dismantle; the edge partitions 100 are provided with front telescopic plates 120, which can fit tightly with the steel bars 500 to prevent concrete from flowing from the gaps of the steel bars 500 and improve the sealing. Thereby significantly improving the construction efficiency and quality.

[0040] With the side where the edge partition 100 and the middle partition 200 are molded for concrete as the front, the front telescopic plate 120 is arranged in front of the first plate body 110, and the front of the front telescopic plate 120 and the front of the middle partition 200 are used together for molding concrete.

[0041] Reference Figure 2 , Figure 3 and Figure 4 In this embodiment, the edge partition 100 includes a first elastic member 130; the front telescopic plate 120 and the first plate body 110 are connected by the first elastic member 130, and the first elastic member 130 is used to make the front telescopic plate 120 have a movement tendency to move outward relative to the first plate body 110.

[0042] The first elastic member 130 enables the front telescopic plate 120 to move outward even if it is resisted by the steel bar 500, so as to resist the concrete and improve the flatness and sealing of the concrete. The first elastic member 130 is a spring.

[0043] Reference Figure 2 , Figure 3 and Figure 4 In this embodiment, the edge partition 100 also includes a side telescopic plate 140; the side telescopic plate 140 is movably connected to the first plate body 110, and the side telescopic plate 140 and the front telescopic plate 120 are perpendicular to each other; the side telescopic plate 140 has a tendency to move outward relative to the first plate body 110 to approach the forming template.

[0044] The front telescopic plate 120 is located in front of the first plate body 110 as a relative position for description, and the side telescopic plate 140 is located to the left of the first plate body 110. The side telescopic plate 140 is close to the forming template to improve the sealing performance between the side telescopic plate 140 and the forming template to prevent concrete from flowing out of the gap of the steel bar 500.

[0045] Reference Figure 2 , Figure 3 and Figure 4 In this embodiment, the edge partition 100 also includes a second elastic member 150; the side telescopic plate 140 and the first plate body 110 are connected by the second elastic member 150, and the second elastic member 150 has a movement tendency to make the side telescopic plate 140 move outward relative to the first plate body 110.

[0046] The second elastic member 150 enables the side telescopic plate 140 to move toward the forming template relative to the first plate body 110. The side telescopic plate 140 is supported by the forming template to compress the second elastic member 150, so that the side telescopic plate 140 and the forming template fit together, effectively blocking the concrete and preventing the concrete from flowing out.

[0047] Reference Figure 5In this embodiment, a plurality of protrusions 260 or pits are arranged on the surface of the middle partition 200 for forming concrete.

[0048] The front of the middle partition 200, that is, the side facing the concrete, is provided with a spur 260 or a pit, which can form a rough surface on the contact surface between the concrete and the middle partition 200, which is conducive to the effective combination of the rough surface of the concrete with the subsequent pouring concrete after the middle partition 200 is removed, thereby improving the adhesion between the column concrete and the beam concrete.

[0049] Reference Figure 4 , Figure 7 and Figure 8 In this embodiment, a first connecting hole 160 is provided on one side of the edge partition 100 adjacent to the middle partition 200; telescopic pins 210 and second connecting holes 220 are respectively provided on two opposite sides of the middle partition 200; the telescopic pin 210 is used to be spliced ​​and fixed with the first connecting hole 160 of the adjacent edge partition 100, or the telescopic pin 210 is used to be spliced ​​and fixed with the second connecting hole 220 of the adjacent middle partition 200.

[0050] Specifically, the left side of the edge partition 100 located at the far left is provided with a side telescopic plate 140, and the right side is provided with a first connection hole 160; the left side of the edge partition 100 located at the far right is provided with a first connection hole 160, and the right side is provided with a side telescopic plate 140, and the first connection hole 160 is used to connect with the telescopic pin 210 of the adjacent middle partition 200. The left side of the middle partition 200 is provided with a telescopic pin 210, and the right side is provided with a second connection hole 220, and the telescopic pin 210 is connected with the adjacent first connection hole 160 or the second connection hole 220.

[0051] The telescopic pin 210 is inserted into the first connection hole 160 or the second connection hole 220, and the edge partition 100 and the middle partition 200 are spliced ​​in sequence. Before the initial setting of the column concrete, the beam concrete is poured, and the telescopic pin 210 is withdrawn from the first connection hole 160 or the second connection hole 220, and then the middle partition 200 and the edge partition 100 are taken out in sequence.

[0052] Reference Figure 4 , Figure 7 and Figure 8In this embodiment, the middle partition 200 includes a second plate body 230, a supporting plate 240 and a third elastic member 250; the supporting plate 240 is movably connected to the second plate body 230, and the telescopic pin 210 is fixed on the supporting plate 240 and movably penetrates the second plate body 230; the supporting plate 240 and the second plate body 230 are connected by the third elastic member 250, and the third elastic member 250 has a movement tendency to make the supporting plate 240 move inward relative to the second plate body 230, and the supporting plate 240 is used to move outward relative to the second plate body 230 under the action of external force, so that the telescopic pin 210 moves outward to be inserted into the first connecting hole 160 or the second connecting hole 220.

[0053] After the telescopic pin 210 is aligned with the first connection hole 160 or the second connection hole 220, the external force drives the telescopic pin 210 to move outward, and the telescopic pin 210 is inserted into the first connection hole 160 or the second connection hole 220, completing the splicing of the middle partition 200 and the edge partition 100, or the splicing of the middle partition 200 and the middle partition 200. When the casting is completed and the middle partition 200 and the edge partition 100 need to be removed, the external force driving the abutment plate 240 is removed, so that the telescopic pin 210 is withdrawn from the first connection hole 160 or the second connection hole 220, and the middle partition 200 and the edge partition 100 can be removed.

[0054] Reference Figure 4 , Figure 7 , Figure 8 and Fig. 9 In this embodiment, the concrete beam-column node combined partition structure 10 also includes a force transmission rod 300; the force transmission rod 300 is used to be detachably inserted into the second plate body 230, and the force transmission rod 300 is used to push the supporting plate 240 to move outward relative to the second plate body 230.

[0055] A space is formed between the abutting plate 240 and the second plate body 230, and the force transmission rod 300 is inserted into the space. The force transmission rod 300 pushes the abutting plate 240 to move outward and compresses the third elastic member 250. After the force transmission rod 300 is removed, the abutting plate 240 moves inward under the action of the third elastic member 250. The third elastic member 250 is a spring.

[0056] Reference Figure 4 , Figure 7 , Figure 8 and Fig. 9 In this embodiment, the concrete beam-column node composite partition structure 10 also includes a crossbeam 400; one end of a plurality of force transmission rods 300 passing through the second plate body 230 is passed through and fixed on the crossbeam 400 to splice the edge partition 100 and the middle partition 200 together.

[0057] A plurality of force transmission rods 300 are sequentially inserted into the second plate body 230 to complete the splicing of the edge partition 100 and the middle partition 200. The splicing of the edge partition 100 and the middle partition 200 on the far right can rely on the side telescopic plate 140 of the edge partition 100 to abut against the middle partition 200 with the forming template, or the edge partition 100 on the far right can adopt the same telescopic pin 210 structure as the middle partition 200 to achieve splicing with the middle partition 200 by using the telescopic pin 210 structure.

[0058] In this embodiment, the concrete beam-column node composite diaphragm structure 10 further includes stirrups; stirrups are provided at the upper and lower ends of the force transmission rod 300. The force transmission rod 300 in the diaphragm is supported by stirrups at the upper and lower ends, and no other retaining bars are required.

[0059] According to a concrete beam-column node composite diaphragm structure 10 provided in this embodiment, the working principle of the concrete beam-column node composite diaphragm structure 10 is:

[0060] A pouring construction method for setting a concrete beam-column node composite partition structure 10 at different concrete locations of the concrete beam-column node comprises the following steps:

[0061] The beams are tied by the formwork frame and then dropped or the beams are tied inside the formwork on one side of the beam. After the beam stirrups are tied, the concrete beam-column node composite diaphragm structure 10 is set inside the beam according to the specification requirements;

[0062] After the concrete beam-column node composite diaphragm structure 10 is set, check and confirm that the device is firmly fixed before pouring;

[0063] Organize the pouring of high-grade concrete for multiple columns to fill the beam-column joints and vibrate to make them dense; observe the timing, and before the initial setting of the column concrete, organize the pouring of beam concrete and remove the concrete beam-column joint combined partition structure 10, and vibrate the contact surfaces of concrete of different grades to make them dense.

[0064] The concrete beam-column node composite diaphragm structure 10 provided in this embodiment has at least the following advantages:

[0065] The edge partition 100 and the middle partition 200 are made of steel and are not easy to deform. When pouring concrete, they are not easy to sink under the side pressure, and the contact surface is flat. The assembled edge partition 100 and the middle partition 200 are quick-disassembled, small in width and volume, easy to remove and take out, and not easy to collapse. The edge partition 100 is provided with a front telescopic plate 120, which can fit tightly with the steel bar 500 to prevent concrete from flowing through the gap of the steel bar 500.

[0066] The surface of the middle partition 200 is granular, and the contact surface is rough after removal, which is conducive to the bonding of concrete.

[0067] The above is only a specific implementation of the utility model, but the protection scope of the utility model is not limited thereto. Any changes or substitutions that can be easily thought of by a person skilled in the art within the technical scope disclosed by the utility model should be included in the protection scope of the utility model. Therefore, the protection scope of the utility model should be based on the protection scope of the claims.

Claims

1. A concrete beam-column node composite diaphragm structure, It is characterized in that include: An edge partition (100), wherein the number of the edge partitions (100) is two, each of the edge partitions (100) comprises a first plate body (110) and a front telescopic plate (120), wherein the front telescopic plate (120) is movably connected inside the first plate body (110), and the front telescopic plate (120) has a tendency to move outward relative to the first plate body (110); and a middle partition (200), wherein the number of the middle partitions (200) is at least two; at least two of the middle partitions (200) are spliced ​​and fixed side by side in sequence, wherein the two middle partitions (200) located on the outermost sides are respectively used for splicing and fixing with one of the edge partitions (100); and the same side of the front telescopic plate (120) and at least two of the middle partitions (200) are used together for forming concrete.

2. The concrete beam-column node composite diaphragm structure according to claim 1, Features: The edge partition (100) comprises a first elastic member (130); the front telescopic plate (120) and the first plate body (110) are connected via the first elastic member (130), and the first elastic member (130) is used to enable the front telescopic plate (120) to have a movement tendency to move outward relative to the first plate body (110).

3. The concrete beam-column node composite diaphragm structure according to claim 1, Features: The edge partition (100) further comprises a side telescopic plate (140); the side telescopic plate (140) is movably connected inside the first plate body (110), and the side telescopic plate (140) and the front telescopic plate (120) are perpendicular to each other; the side telescopic plate (140) has a tendency to move outward relative to the first plate body (110) so as to approach the forming template.

4. The concrete beam-column node composite diaphragm structure according to claim 3, Features: The edge partition (100) further comprises a second elastic member (150); the lateral telescopic plate (140) and the first plate body (110) are connected via the second elastic member (150), and the second elastic member (150) has a movement tendency to cause the lateral telescopic plate (140) to move outward relative to the first plate body (110).

5. The concrete beam-column node composite diaphragm structure according to any one of claims 1 to 4, Features: The surface of the middle partition (200) used for forming concrete is provided with a plurality of thorns (260) or pits.

6. The concrete beam-column node composite diaphragm structure according to any one of claims 1 to 4, Features: A first connection hole (160) is provided on one side of the edge partition (100) adjacent to the middle partition (200); a telescopic pin (210) and a second connection hole (220) are respectively provided on two opposite sides of the middle partition (200); the telescopic pin (210) is used for splicing and fixing with the first connection hole (160) of the adjacent edge partition (100), or the telescopic pin (210) is used for splicing and fixing with the second connection hole (220) of the adjacent middle partition (200).

7. The concrete beam-column node composite diaphragm structure according to claim 6, Features: The middle partition (200) comprises a second plate body (230), a supporting plate (240) and a third elastic member (250); the supporting plate (240) is movably connected inside the second plate body (230), and the telescopic pin (210) is fixed on the supporting plate (240) and movably penetrates the second plate body (230); the supporting plate (240) and the second plate body (230) are connected via the third elastic member (250), and the third elastic member (250) has a movement tendency to make the supporting plate (240) move inward relative to the second plate body (230), and the supporting plate (240) is used to move outward relative to the second plate body (230) under the action of an external force, so as to make the telescopic pin (210) move outward to be inserted into the first connecting hole (160) or the second connecting hole (220).

8. The concrete beam-column node composite diaphragm structure according to claim 7, Features: The concrete beam-column node combined diaphragm structure also includes a force transmission rod (300); the force transmission rod (300) is used to be detachably inserted into the second plate body (230), and the force transmission rod (300) is used to push the supporting plate (240) to move outward relative to the second plate body (230).

9. The concrete beam-column node composite diaphragm structure according to claim 8, Features: The concrete beam-column node combined partition structure also includes a crossbeam (400); one end of a plurality of force transmission rods (300) passing through the second plate body (230) is passed through and fixed on the crossbeam (400) so that the edge partition (100) and the middle partition (200) are spliced ​​together.

10. The concrete beam-column node composite diaphragm structure according to claim 8, Features: The concrete beam-column node combined diaphragm structure further comprises stirrups; the stirrups are arranged at the upper and lower ends of the force transmission rod (300).