Reinforcing formwork for floor concrete pouring

The reinforced formwork system with rotating components and nailing assemblies addresses inefficiencies in wooden formworks by ensuring non-deflectable nailing and efficient storage, enhancing concrete pouring by channel steel and right-angle molds.

CN222120820UActive Publication Date: 2024-12-06CHINA CONSTR THIRD ENG BUREAU GRP CO LTD +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420495627.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-13
Publication Date
2024-12-06
Estimated Expiration
2034-03-13

AI Technical Summary

Technical Problem

Existing wooden formworks for floor construction are inefficient due to the need for nailing and result in deflection during concrete pouring, leading to leaks and post-use storage issues with triangular brackets and dowel bars.

Method used

A reinforced formwork system using channel steel with rotating columns, rotating drums, and extension beams, along with a nailing assembly and diagonal tie rods, ensuring non-deflectable nailing and efficient storage.

Benefits of technology

The system provides anti-tilt strength, reduces storage volume, and prevents nail rod loss, enhancing efficiency and usability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222120820U_ABST
    Figure CN222120820U_ABST
Patent Text Reader

Abstract

The utility model discloses a reinforcing formwork for floor concrete pouring. The reinforcing formwork comprises channel steel, a rotary column, a rotary drum and an extension beam. A plurality of rotating columns vertically welded on the channel steel are arranged at an inner notch of the channel steel, a rotating cylinder is rotationally matched on the rotating columns, an extension beam of a rod-shaped structure is vertically welded on the rotating cylinder in the direction far away from the channel steel, a nail cylinder of a cylindrical structure is welded at the other end of the extension beam, the axis of the nail cylinder is vertical, and a ground nailing assembly is arranged in the nail cylinder. A main body of the ground nailing assembly is a nail rod with a conical tip, the nail rod is in sliding fit with the nail barrel in the mode that the conical tip faces downwards, a first fixing sleeve and a second fixing sleeve with the horizontal axis are fixed to the two sides of the channel steel respectively, and the first fixing sleeve and the second fixing sleeve are correspondingly arranged in size, number and position. A bolt with a rod-shaped structure is inserted into the first fixing sleeve; the utility model has the advantages of inclination prevention and high bearing strength; and the nail rod is stored along with the nail rod, so that the nail rod is not inconvenient to find.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of floor pouring, and in particular relates to a reinforcement template for pouring floor concrete. Background Art

[0002] The ground of a large factory building is usually a heavy-loaded floor. The progress of pouring the heavy-loaded floor concrete layer affects the delivery time of the factory building. The existing wooden formwork for floor construction has low efficiency because it needs to be nailed together for reinforcement. In order to improve the efficiency of formwork reinforcement, the existing technology adopts the method of splicing channel steel to achieve formwork fixation. For example, a channel steel forming formwork for pavement concrete with publication number CN102776826A is composed of channel steel and triangular bracket. The triangular bracket is connected to the channel steel through a sleeve welded on the concave surface of the channel steel. The other end of the triangular bracket is connected to a straight sleeve with dowels inside. The two ends of the channel steel have formwork joint sleeves with joint pins inside the formwork joint sleeves. The channel steel forming formwork for pavement concrete construction of the present invention is simple to erect and dismantle, has a high number of reuses, is low in cost, and is conducive to the quality control of concrete molding.

[0003] When the above-mentioned comparative document is in use, since the triangular bracket and the channel steel are in a rotational fit relationship through the sleeve, when pouring concrete, the bottom of the channel steel is easily deflected outward around the sleeve under the squeezing of the concrete fluid, causing the poured concrete to leak. At the same time, because the triangular bracket and the sleeve rotate horizontally, the triangular bracket cannot be stored after the channel steel is used, resulting in the recycled channel steel occupying a large amount of volume, and its triangular bracket relies on dowel bars for fixation. After recycling, the dowel bars are in a separated state and are small in size, so they are easy to lose, which is inconvenient for next use. Utility Model Content

[0004] The purpose of the utility model is to provide a reinforced formwork for pouring floor concrete to solve the problems mentioned in the above background technology.

[0005] The above technical objectives of the present invention are achieved through the following technical solutions:

[0006] A reinforcement formwork for pouring floor concrete comprises: channel steel, rotating columns, rotating drums, and extension beams; the inner recess of the channel steel is provided with a plurality of rotating columns vertically welded to the channel steel, a rotating drum is rotatably fitted on the rotating column, an extension beam of a rod-shaped structure is vertically welded to the rotating drum in a direction away from the channel steel, and a nail barrel of a cylindrical structure is welded to the other end of the extension beam, the axis of the nail barrel is vertical, a ground nailing assembly is provided in the nail barrel, the main body of the ground nailing assembly is a nail rod with a tapered tip, the nail rod is slidably fitted with the nail barrel in a manner that the tapered tip faces downward, a first fixing sleeve and a second fixing sleeve with a horizontal axis are fixed on both sides of the channel steel respectively, the size, quantity and position of the first fixing sleeve and the second fixing sleeve are correspondingly set, wherein a pin of a rod-shaped structure is inserted into the first fixing sleeve.

[0007] Furthermore, in order to prevent the nail rod from being lost due to inconvenience in storage after recovery, the nail rod is provided with a sliding pin perpendicular to its axis, and the nail barrel is provided with a sliding groove that provides a sliding position for the sliding pin.

[0008] Furthermore, in order to enable the nail barrel to adapt to the outer surface of the mold with different heights or flatness, the length of the rotating barrel is smaller than the length of the rotating column, so that the rotating barrel not only rotates with the rotating column, but also slides with the rotating column.

[0009] Furthermore, in order to improve the anti-tilting capability and structural strength of the channel steel, a diagonal tie rod with an oblique rod structure is provided between the nail cylinder and the rotating cylinder.

[0010] Furthermore, in order to facilitate the shaping of right-angle positions when constructing the template of the present invention, the channel steel is connected at the right angle by a right-angle mold, and the right-angle mold is spliced ​​by two groups of mutually perpendicular channel steels. When spliced, the inner concave of the channel steel is located at the outer corner. Similarly, the right-angle mold is also provided with a rotating column, a rotating cylinder, an extension beam, a nail cylinder, a nailing assembly, a first fixed sleeve, a second fixed sleeve, a pin and other structures. The connection structure of each component is the same as the above, so it is not repeated.

[0011] Furthermore, in order to facilitate driving the nail rod into the ground, the nailing assembly further includes: a hammer head, which is located at the top of the nail rod and is made of a metal material that is not easily deformed.

[0012] Furthermore, in order to facilitate pulling out the nail rod from the ground during recovery, the nailing assembly further includes an auxiliary pulling rod, and the top of the nail rod is crossed by an auxiliary pulling rod with a rod-shaped structure.

[0013] Furthermore, in order to enable the auxiliary pull rod to be stored when the channel steel is recovered, the axis of the auxiliary pull rod is arranged parallel to the axis of the extension beam.

[0014] In summary, the present invention has the following beneficial effects:

[0015] ① Anti-tilt, high bearing strength: Through the parallel rotating cylinder and nail cylinder, after the nail cylinder is nailed, the nail cylinder is in a non-deflectable state. Because the nail cylinder and the rotating cylinder are connected by extension beams and inclined rods, the rotating cylinder is also non-deflectable in the vertical direction, that is to say, the channel steel and the rotating column will not tilt or deflect as a whole, thereby improving the bearing strength of the mold.

[0016] ② Small space occupied when stored: Due to the rotation coordination of the rotating cylinder and the rotating column, the extension beam, nail cylinder, nailing assembly and diagonal rod are deflected around the axis of the rotating column. As shown in the figure, the extension beam, nail cylinder, nailing assembly and diagonal rod are stored in the notch of the channel steel. In this way, a large amount of space occupied can be saved when storing the channel steel after the mold is reversed.

[0017] ③ The nail rod is stored and will not be inconvenient to find: Due to the establishment of the sliding groove and the sliding pin, the nail rod will not slide out of the nail tube. That is to say, when the utility model is used for the second time, there is no need to find the nail rod and then pass it through the nail tube and then nail it into the ground as in the reference document. The nail rod can be directly nailed into the ground from the nail tube without the need to adapt to find the nail rod. At the same time, the nail rod is also stored to prevent the smaller nail rod from being lost during storage. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0019] Figure 2 This is a schematic structural diagram of the right-angle die in the utility model;

[0020] Figure 3 yes Figure 1 A magnified view of the structure at center A;

[0021] Figure 4 This is a schematic diagram of the folding and storage principle of the utility model;

[0022] Figure 5 This is a schematic diagram of the splicing principle of the utility model;

[0023] In the figure, 1. channel steel; 2. rotating column; 3. rotating cylinder; 4. extension beam; 5. nail cylinder; 6. nailing assembly; 7. first fixing sleeve; 8. second fixing sleeve; 9. latch; 10. right-angle mold; 11. diagonal tie rod; 51. slide groove; 61. nail rod; 62. cone tip; 63. sliding pin; 64. hammer head; 65. auxiliary pull rod. DETAILED DESCRIPTION

[0024] The present invention will be described in further detail below with reference to the accompanying drawings.

[0025] Example:

[0026] See also Figure 1-Figure 5 , this utility model provides a technical solution:

[0027] First embodiment:

[0028] A reinforcement formwork for pouring floor concrete comprises: a channel steel 1, a rotating column 2, a rotating drum 3, and an extension beam 4; the inner recess of the channel steel 1 is provided with a plurality of rotating columns 2 vertically welded to the channel steel 1, and a rotating drum 3 is rotatably fitted on the rotating column 2, and the rotating drum 3 is vertically welded with an extension beam 4 of a rod-shaped structure in the direction away from the channel steel 1, and the other end of the extension beam 4 is welded with a nail barrel 5 of a cylindrical structure, the axis of the nail barrel 5 is vertical, and a ground nailing assembly 6 is provided in the nail barrel 5, the main body of the ground nailing assembly 6 is a nail rod 61 with a conical tip 62, and the nail rod 61 slides with the nail barrel 5 in a manner that the conical tip 62 faces downward, and a first fixing sleeve 7 and a second fixing sleeve 8 with a horizontal axis are respectively fixed on both sides of the channel steel 1, and the size, quantity and position of the first fixing sleeve 7 and the second fixing sleeve 8 are correspondingly set, wherein a rod-shaped structure pin 9 is inserted into the first fixing sleeve 7.

[0029] The nail rod 61 is provided with a sliding pin 63 perpendicular to its axis, and the nail barrel 5 is provided with a sliding groove 51 that provides a sliding position for the sliding pin 63 to slide.

[0030] The length of the rotating drum 3 is smaller than that of the rotating column 2 , so that the rotating drum 3 is not only in rotational cooperation with the rotating column 2 , but also in sliding cooperation with the rotating column 2 .

[0031] A diagonal pull rod 11 with an oblique rod structure is provided between the nail barrel 5 and the rotating barrel 3 .

[0032] The channel steel 1 is connected at the right angle by a right-angle mold 10. The right-angle mold 10 is spliced ​​by two groups of mutually perpendicular channel steels 1. When spliced, the inner concave of the channel steel 1 is located at the outer angle. The right-angle mold 10 is also provided with a rotating column 2, a rotating cylinder 3, an extension beam 4, a nail cylinder 5, a nailing assembly 6, a first fixing sleeve 7, a second fixing sleeve 8, a pin 9 and other structures. The connection structure of each component is the same as the above, so it is not repeated.

[0033] The nailing assembly 6 further includes a hammer head 64 , which is located on the top of the nail rod 61 and is made of a metal material that is not easily deformed.

[0034] The nailing assembly 6 further includes an auxiliary pulling rod 65 . The top of the nailing rod 61 is crossed by an auxiliary pulling rod 65 with a rod-shaped structure.

[0035] The axis of the auxiliary pull rod 65 is parallel to the axis of the extension beam 4 .

[0036] When using, Figure 5 As shown, according to the area and size of the on-site floor, channel steels 1 and right-angle molds 10 of reasonable length and quantity are selected, and the second fixing sleeves 8 in adjacent channel steels 1 and right-angle molds 10 are inserted with pins 9 to complete the assembly of all channel steels 1 and right-angle molds 10.

[0037] Then use a hammer to hit the hammer head 64, hammer the conical tip 62 of the nail rod 61 into the ground outside the mold, and nail the nail barrel 5 tightly. At this time, the nail barrel 5 is in a non-deflectable state. Because the nail barrel 5 and the rotating cylinder 3 are connected by an extension beam 4 and a diagonal rod 11, the rotating cylinder 3 is also in a non-deflectable direction in the vertical direction, that is, the channel steel 1 and the rotating column 2 as a whole will not be tilted or deflected, thereby improving the bearing strength of the mold.

[0038] Then, the floor concrete can be poured into the assembled channel steel 1 and the right-angle mold 10.

[0039] After the poured concrete is completely dry, first use the auxiliary pulling rod 65 to pull out all the nail rods 61 from the ground, and then pull out all the pins 9 from the second fixing sleeve 8. After pulling out, all the channel steels 1 and the right-angle mold 10 can be separated. Then, the extension beam 4, nail tube 5, nailing assembly 6, and diagonal rod 11 are deflected around the axis of the rotating column 2. Figure 4 As shown, the extension beam 4, nail tube 5, ground nail assembly 6, and diagonal rod 11 are integrally housed in the recess of the channel steel 1 (the housing principle of the right-angle mold 10 is the same, so it is not repeated); in this way, a large amount of occupied volume can be saved when housing the channel steel 1 after the mold is reversed.

[0040] At the same time, due to the establishment of the sliding groove 51 and the sliding pin 63, the nail rod 61 will not slide out of the nail tube 5. That is to say, when using the utility model for the second time, there is no need to find the nail rod 61 and then penetrate the nail tube 5 and then nail it into the ground as in the reference document. The nail rod 61 can be directly nailed into the ground from the nail tube 5 without adapting to find it. At the same time, the nail rod 61 is also stored to prevent the smaller nail rod 61 from being lost during storage.

[0041] This specific embodiment is merely an explanation of the present invention and is not a limitation of the present invention. After reading this specification, those skilled in the art may make non-creative modifications to the present embodiment as needed. However, as long as they are within the scope of the claims of the present invention, they are protected by patent law.

Claims

1. A reinforced formwork for pouring floor concrete, comprising: Channel steel (1), rotating column (2), rotating cylinder (3), extension beam (4); characterized in that: the inner recess of the channel steel (1) is provided with a plurality of rotating columns (2) vertically welded to the channel steel (1), a rotating cylinder (3) is rotatably fitted on the rotating column (2), an extension beam (4) of a rod-shaped structure is vertically welded to the rotating cylinder (3) in a direction away from the channel steel (1), a nail cylinder (5) of cylindrical structure is welded to the other end of the extension beam (4), the axis of the nail cylinder (5) is vertical, and the inside of the nail cylinder (5) is A ground nailing assembly (6) is provided. The main body of the ground nailing assembly (6) is a nail rod (61) with a cone tip (62). The nail rod (61) is slidably matched with the nail tube (5) in a manner that the cone tip (62) faces downward. A first fixing sleeve (7) and a second fixing sleeve (8) with a horizontal axis are respectively fixed on both sides of the channel steel (1). The size, quantity and position of the first fixing sleeve (7) and the second fixing sleeve (8) are correspondingly arranged. A rod-shaped structured latch (9) is inserted into the first fixing sleeve (7).

2. A reinforced formwork for pouring floor concrete according to claim 1, characterized in that: The nail rod (61) is provided with a sliding pin (63) perpendicular to its axis, and the nail cylinder (5) is provided with a sliding groove (51) for providing a sliding position for the sliding pin (63).

3. The reinforced formwork for pouring floor concrete according to claim 1, characterized in that: The length of the rotating drum (3) is smaller than the length of the rotating column (2), so that the rotating drum (3) not only rotates with the rotating column (2), but also slides with the rotating column (2).

4. The reinforced formwork for pouring floor concrete according to claim 1, characterized in that: An inclined rod (11) with an inclined rod structure is provided between the nail cylinder (5) and the rotating cylinder (3).

5. The reinforced formwork for pouring floor concrete according to claim 1, characterized in that: The channel steel (1) is connected at a right angle by a right angle die (10). The right angle die (10) is formed by splicing two sets of channel steels (1) perpendicular to each other. When splicing, the inner concave of the channel steel (1) is located at the outer angle. Similarly, the right angle die (10) is also provided with a rotating column (2), a rotating cylinder (3), an extension beam (4), a nail cylinder (5), a nailing assembly (6), a first fixing sleeve (7), a second fixing sleeve (8), and a bolt (9) structure.

6. The reinforced formwork for pouring floor concrete according to claim 1, characterized in that: The ground nailing assembly (6) further comprises a hammer head (64), wherein the hammer head (64) is located at the top of the nail rod (61) and is made of a metal material that is not easily deformed.

7. The reinforced formwork for pouring floor concrete according to claim 1, characterized in that: The nailing assembly (6) further comprises an auxiliary pulling rod (65), wherein the top of the nailing rod (61) is crossed by an auxiliary pulling rod (65) having a rod-shaped structure.

8. The reinforced formwork for pouring floor concrete according to claim 7, characterized in that: The axis center line of the auxiliary pull rod (65) and the axis center line of the extension beam (4) are arranged in parallel.

Citation Information

Cited By

  • Cement stabilized macadam construction structure for expressway pavement

    CN121473202A