Winter concrete steam curing device
By designing a winter concrete steam curing device in winter construction, and using sealed cavity and steam generator to provide water vapor, the problem that concrete cannot reach constant temperature and humidity is solved, and the effective curing of concrete on the opposite side wall is achieved, and the occurrence of cracks is avoided. .
Patent Information
- Application Number
- CN202420103424.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-16
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2034-01-16
AI Technical Summary
During winter construction, conventional concrete curing methods cannot ensure that the concrete reaches a constant temperature and humidity state, resulting in cracks during the hydration heat reaction.
A winter concrete steam curing device is designed, including side walls, curing frames, PO greenhouse films and steam generators. By forming a sealed cavity and supplying water vapor to it, effective maintenance is achieved in combination with expansion bolts and thermometers.
The constant temperature and humidity maintenance of the opposite wall concrete is achieved, which avoids the occurrence of cracks and ensures the quality and waterproof performance of the concrete.
Smart Images

Figure CN222121009U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of concrete curing, in particular to a winter concrete steam curing device. Background Art
[0002] With the development of subway construction, the requirements for the physical structure of underground projects are getting higher and higher, especially the requirements for the quality and waterproofing of the concrete wall of underground projects are more stringent. Subway construction requires the use of high-performance concrete materials for facing. The maintenance measures of high-performance concrete after demolding are very important. In summer, after the concrete pouring is completed, automatic spraying and geotextile covering maintenance measures are usually adopted. However, the conventional method of concrete maintenance during winter construction adopts the method of covering with quilts. This method has certain defects and cannot guarantee that the concrete can reach a constant temperature and humidity state, and thus cannot guarantee to avoid cracks during the thermal reaction of concrete hydration. This phenomenon has become a problem that needs to be solved urgently by people in this field. Utility Model Content
[0003] The utility model aims to provide a winter concrete steam curing device in view of the existing technical defects, so as to solve the problems raised in the above-mentioned background technology.
[0004] In order to solve the above technical problems, the utility model provides the following technical solutions: a winter concrete steam curing device, comprising a side wall, a middle plate concrete layer is fixedly connected to the lower side of the side wall, a plurality of curing frames are fixedly connected to the right side of the side wall, and connection frames are welded to the left and right sides of the upper parts of the plurality of curing frames;
[0005] A film pressing frame 1 is arranged on the upper left side of the curing frame, a film pressing frame 2 is arranged on the lower right side of the curing frame, a fixing frame is fixedly connected to the side of the lower side of the curing frame away from the film pressing frame 2, and each group of the fixing frames is provided with expansion bolts;
[0006] A PO greenhouse film is arranged on the side of the curing frame away from the side wall and the middle plate concrete layer, and a thermometer is hung on the left side of the side wall;
[0007] A sealed cavity is formed between the side wall, the middle plate concrete layer and the PO greenhouse film;
[0008] A steam generating device is arranged on the ground above the side wall, and the steam generating device injects steam into the sealed cavity through a pipeline.
[0009] The utility model further illustrates that the lower side of the curing frame is in direct contact with the upper side of the middle plate concrete layer.
[0010] The utility model further illustrates that the first film pressing frame is located on the upper side of a group of connecting frames on the left side, the left side of the first film pressing frame is in direct contact with the right side of the side wall, and the lower side of the second film pressing frame is in direct contact with the upper side of the middle plate concrete layer.
[0011] The utility model further illustrates that the first film pressing frame and the second film pressing frame are both 50*50mm angle steel or 100*100mm square wood.
[0012] The utility model further illustrates that the connecting frame is a 50*50mm square steel with a length of 4000mm, and the maintenance frame is welded and assembled by 50*50mm square steel.
[0013] The utility model further illustrates that the upper side of the maintenance frame is 200mm lower than the top side of the side wall, the distance between the right side of the maintenance frame and the side wall is between 100-150mm, and the fixing frame is a 50*50mm square steel.
[0014] Compared with the prior art, the beneficial effects achieved by the utility model are as follows: the utility model, by setting up a curing frame, fixing the curing frame to one side of the side wall by expansion bolts, attaching the PO greenhouse film to the curing frame to form a sealed cavity, and then supplying water vapor to the sealed cavity through a steam generating device, and detecting the temperature in the sealed cavity by a thermometer, thereby achieving effective curing of the concrete poured on the side wall. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:
[0016] Figure 1 It is a schematic diagram of the overall side structure of the utility model;
[0017] Figure 2 The utility model Figure 1 A local enlarged structural diagram of region A;
[0018] Figure 3 The utility model Figure 1 A schematic diagram of a local enlarged structure of region B;
[0019] Figure 4 It is a schematic diagram of the overall front view structure of the utility model;
[0020] In the figure: 1. Side wall; 2. Middle plate concrete layer; 3. Curing frame; 4. Connecting frame; 5. Film pressing frame 1; 6. Film pressing frame 2; 7. Fixing frame; 8. Expansion bolt; 9. PO greenhouse film; 10. Sealed cavity; 11. Steam generating device; 12. Thermometer. DETAILED DESCRIPTION
[0021] The following is a further non-limiting detailed description of the technical solution of the utility model in conjunction with the preferred embodiments and the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0022] See also Figure 1-4 The utility model provides a technical solution: a winter concrete steam curing device, including a side wall 1, a middle plate concrete layer 2 is fixedly connected to the lower side of the side wall 1, and a plurality of curing frames 3 are fixedly connected to the right side of the side wall 1, and the lower side of the curing frame 3 is in direct contact with the upper side of the middle plate concrete layer 2.
[0023] Connecting frames 4 are welded on both sides of the upper left and right sides of several groups of curing frames 3;
[0024] A film pressing frame 5 is arranged on the upper left side of the curing frame 3, and the film pressing frame 5 is located on the upper side of a group of connecting frames 4 on the left side, and the left side of the film pressing frame 5 is in direct contact with the right side of the side wall 1;
[0025] A film pressing frame 2 6 is arranged at the lower right side of the curing frame 3 , and the lower side of the film pressing frame 2 6 is in direct contact with the upper side of the middle plate concrete layer 2 .
[0026] A fixing frame 7 is fixedly connected to the lower side of the curing frame 3 away from the second film pressing frame 6 . Each set of fixing frames 7 is provided with expansion bolts 8 . The curing frame 3 is fixedly connected to the middle plate concrete layer 2 through the expansion bolts 8 and the fixing frames 7 .
[0027] A PO greenhouse film 9 is provided on the side of the curing frame 3 away from the side wall 1 and the middle plate concrete layer 2;
[0028] The side of the PO greenhouse film 9 close to the side wall 1 is pressed against the curing frame 3 by a film pressing frame 5;
[0029] The side of the PO greenhouse film 9 close to the middle plate concrete layer 2 is pressed against the curing frame 3 by the film pressing frame 2 6 , thereby forming a sealed cavity 10 between the side wall 1 , the middle plate concrete layer 2 and the PO greenhouse film 9 .
[0030] A steam generating device 11 is arranged on the ground above the side wall 1 . The steam generating device 11 injects steam into the sealed cavity 10 through a pipeline, so as to maintain the concrete layer cast on the side wall 1 .
[0031] A thermometer 12 is mounted on the left side of the side wall 1 to detect the actual temperature in the sealed cavity 10 .
[0032] The film pressing frame 1 5 and the film pressing frame 2 6 are both 50*50mm angle steel or 100*100mm square wood;
[0033] The connecting frame 4 is a 50*50mm square steel with a length of 4000mm;
[0034] The maintenance frame 3 is welded and assembled by 50*50mm square steel;
[0035] The upper side of the curing frame 3 is 200mm lower than the top side of the side wall 1, so as to avoid affecting the installation of the subsequent template;
[0036] The distance between the right side of the curing frame 3 and the side wall 1 is between 100-150 mm, and the fixing frame 7 is a 50*50 mm square steel.
[0037] In this embodiment, the curing frame 3 is built on the right side of the side wall 1, so that the left side of the curing frame 3 is close to the right wall of the side wall 1, and the thermometer 12 is hung on the right wall of the side wall 1;
[0038] Make the upper side of the curing frame 3 200mm lower than the top side of the side wall 1, and make the distance between the right side of the curing frame 3 and the side wall 1 between 100-150mm, and fix the curing frame 3 on the middle plate concrete layer 2 by expansion bolts 8;
[0039] Attach the PO greenhouse film 9 to the curing frame 3, and fix the PO greenhouse film 9 through the film pressing frame 1 5 and the film pressing frame 2 6, so that a sealed cavity 10 is formed between the side wall 1, the middle plate concrete layer 2 and the PO greenhouse film 9;
[0040] The output pipe of the steam generating device 11 is connected to the sealed cavity 10 to supply water vapor to the sealed cavity 10, thereby curing the concrete layer cast on the side wall 1. At the same time, the water vapor supply of the steam generator to the sealed cavity 10 is adjusted according to the displayed temperature of the thermometer 12 to meet the curing requirements.
[0041] In the description of the present invention, it should be understood that the terms "upper", "lower", "front", "back", "left", "right", etc., indicating directions or positional relationships, are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore should not be understood as a limitation on the present invention.
[0042] Finally, it should be pointed out that the above embodiments are only used to illustrate the technical solutions of the utility model, rather than to limit them. Although the utility model is described in detail with reference to the above embodiments, a person skilled in the art should understand that the technical solutions described in the above embodiments can still be modified, or some of the technical features can be replaced by equivalents, and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the embodiments of the utility model.
Claims
1. A winter concrete steam curing device, comprising a side wall (1), characterized in that: A middle plate concrete layer (2) is fixedly connected to the lower side of the side wall (1), a plurality of groups of curing frames (3) are fixedly connected to the right side of the side wall (1), and connection frames (4) are welded to the left and right sides of the upper parts of the plurality of groups of curing frames (3); A film pressing frame 1 (5) is arranged on the upper left side of the curing frame (3), a film pressing frame 2 (6) is arranged on the lower right side of the curing frame (3), a fixing frame (7) is fixedly connected to the lower side of the curing frame (3) away from the film pressing frame 2 (6), and each group of the fixing frames (7) is provided with expansion bolts (8); A PO greenhouse film (9) is provided on the side of the curing frame (3) away from the side wall (1) and the middle plate concrete layer (2), and a thermometer (12) is hung on the left side surface of the side wall (1); A sealed cavity (10) is formed between the side wall (1), the middle plate concrete layer (2) and the PO greenhouse film (9); A steam generating device (11) is arranged on the ground above the side wall (1), and the steam generating device (11) injects steam into the sealed cavity (10) through a pipeline.
2. A winter concrete steam curing device according to claim 1, characterized in that: The lower side of the curing frame (3) is in direct contact with the upper side of the middle plate concrete layer (2).
3. A winter concrete steam curing device according to claim 2, characterized in that: The first film pressing frame (5) is located on the upper side of a group of connecting frames (4) on the left side, the left side of the first film pressing frame (5) is in direct contact with the right side of the side wall (1), and the lower side of the second film pressing frame (6) is in direct contact with the upper side of the middle plate concrete layer (2).
4. A winter concrete steam curing device according to claim 3, characterized in that: The film pressing frame 1 (5) and the film pressing frame 2 (6) are both 50*50mm angle steel or 100*100mm square wood.
5. A winter concrete steam curing device according to claim 4, characterized in that: The connecting frame (4) is a 50*50mm square steel with a length of 4000mm, and the curing frame (3) is welded and assembled from 50*50mm square steel.
6. A winter concrete steam curing device according to claim 5, characterized in that: The upper side of the curing frame (3) is 200 mm lower than the top side of the side wall (1), the distance between the right side of the curing frame (3) and the side wall (1) is between 100 and 150 mm, and the fixing frame (7) is a 50*50 mm square steel.