Injection molding raw material pretreatment device and injection molding machine cooling water waste heat circulation system
By using a water circulator and a circulation fan in the injection molding raw material pretreatment device to convert the heat energy of hot water into hot air for preheating treatment, and using the cooling water waste heat circulation system of the injection molding machine, the problems of high energy consumption and low efficiency in the prior art are solved. , realize efficient preheating and energy saving of injection molding raw materials.
Patent Information
- Application Number
- CN202420659286.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-02
- Publication Date
- 2024-12-10
- Estimated Expiration
- 2034-04-02
AI Technical Summary
The existing preheating treatment methods for injection molding raw materials rely on electrical energy conversion, resulting in high energy consumption and cost. The efficiency of the on-machine feed container is low, making it impossible to effectively utilize the waste heat of the cooling water of the injection molding machine.
A pretreatment device for injection molding raw materials is designed, and the heat energy of hot water is converted into hot air through heat exchange by using a water circulator and a circulation fan, and blown into the storage chamber for heat exchange with the injection molding raw materials to realize preheating treatment, and pass through the injection molding machine. The cooling water waste heat circulation system uses the thermal energy of the cooling water for pretreatment, reducing additional power consumption.
It realizes efficient preheating treatment of injection molding raw materials, saves energy and costs, improves energy utilization, and reduces dependence on electricity by recycling the waste heat of the cooling water of the injection molding machine.
Smart Images

Figure CN222135850U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to an injection molding raw material pretreatment device and an injection molding machine cooling water waste heat circulation system. Background Art
[0002] When injection molded products are produced, the injection molding machine needs to melt the injection molding materials under high temperature and high pressure conditions and inject them into the mold. Since it takes a certain amount of time to heat and melt the injection molding materials, in order to improve the processing efficiency of the injection molding machine and ensure the production progress, the injection molding materials are usually preheated before being added to the injection molding machine. At present, the preheating of injection molding materials is mainly completed by an external oven or an on-board feeding container. The heat energy used in both comes from the conversion of electrical energy, which not only increases the additional power loss, but also increases the cost of preheating treatment. Among them, the amount of injection molding materials heated by the on-board feeding container at a time is very limited, which is not only inefficient, but also further increases the consumption of electrical energy. Therefore, there is an urgent need for a pretreatment system that can complete the preheating treatment of injection molding materials and reduce energy consumption and processing costs. Utility Model Content
[0003] The utility model aims to provide a new injection molding raw material pretreatment device.
[0004] In order to achieve the above-mentioned purpose, the technical solution adopted by the utility model is: a pretreatment device for injection molding raw materials, the pretreatment device comprising:
[0005] A mounting seat, the mounting seat having a mounting cavity, an air supply port and an air outlet, wherein the air supply port is arranged on a side of the mounting seat and communicates with the mounting cavity, and the air outlet is arranged on an end of the mounting seat;
[0006] A hopper having a storage cavity for storing injection molding raw materials, the circumferential side wall of the hopper being densely covered with through holes penetrating in the thickness direction, all of the through holes being interconnected with the storage cavity, the hopper being arranged in the installation cavity and between the air supply port and the air outlet, wherein the air supply port faces the circumferential side wall of the hopper;
[0007] A heat exchange component, the heat exchange component includes a water circulator and a circulation fan, the water circulator has a water inlet and a water outlet, and a circulation pipe connected between the water inlet and the water outlet, the water circulator is arranged on the air supply path of the circulation fan, the heat exchange component is installed on the mounting base, and the air supply outlet is located on the air supply path.
[0008] Preferably, the accumulator is conical in shape, and has a first end and a second end respectively arranged at two different ends of its own length direction, and along a length extension direction perpendicular to the accumulator, the cross-sectional dimension of the first end is larger than the cross-sectional dimension of the second end, wherein the first end and the second end are respectively fixed on the mounting seat, and the first end is arranged closer to the air outlet than the second end.
[0009] In some embodiments, the mounting base includes a shell and a cover body, one end of the shell is provided with an opening, and the cover body can be cooperatively covered on one end of the shell and covers the opening, wherein the air supply port is opened on the side of the shell, the air outlet is arranged on the cover body, the storage container is fixedly installed in the shell, and the first end is adapted to the opening.
[0010] In some embodiments, the mounting seat includes a plurality of mounting plates sequentially connected along the circumferential direction, and the material storage container has a plurality of baffles sequentially connected along the circumferential direction, the number of the baffles is consistent with that of the mounting plates and they correspond one to one, each of the mounting plates is provided with an air supply port, the air supply port penetrates the mounting plate along the thickness direction, and each of the air supply ports corresponds to one of the baffles.
[0011] Preferably, a group of the heat exchange components is installed at each of the air outlets, wherein the heat exchange components are fixed on the mounting plate and located on the outside of the mounting seat.
[0012] Preferably, the baffle is connected to the mounting plate at the first end, the baffle and the mounting plate are arranged at an angle, and the angle formed between the two is an acute angle.
[0013] Preferably, the other end of the shell is provided with a communication port and a valve for closing and opening the communication port, and the second end portion of the accumulator is installed in the communication port.
[0014] Another object of the utility model is to provide a new cooling water waste heat circulation system for an injection molding machine.
[0015] In order to achieve the above-mentioned purpose, the technical solution adopted by the utility model is: an injection molding machine cooling water waste heat circulation system, the circulation system comprising:
[0016] The above-mentioned injection molding raw material pretreatment device;
[0017] The injection molding machine cooling pipe group is arranged in the cooling area of the injection molding machine and is used to cool the cooling area. The injection molding machine cooling pipe group has a first pipe opening and a second pipe opening. Cooling water flows through the cooling area through the first pipe opening and is discharged from the second pipe opening.
[0018] Wherein, the second pipe opening is connected to the water inlet of the heat exchange component.
[0019] Preferably, the circulation system further comprises a cooling tower, and the cooling tower is configured to cool water, wherein the cooling tower is connected to the first pipe opening.
[0020] Furthermore, the circulation system also includes a pipeline assembly, which includes a first pipeline connecting the water outlet and the cooling tower, a second pipeline connecting the water outlet and the first pipeline, a first switch provided on the first pipeline and used to control the on and off of the first pipeline, a second switch provided on the second pipeline and used to control the on and off of the second pipeline, and a control element for switching the working states of the first switch and the second switch. The circulation system also includes a temperature detector, which is provided at the water outlet and used to detect the temperature of water flowing out of the water outlet, and the temperature detector is communicatively connected to the control element.
[0021] Due to the application of the above technical scheme, the utility model has the following advantages compared with the prior art: the injection molding raw material pretreatment device of the utility model is provided with a water circulator, and hot water is introduced into the water circulator, and the hot water exchanges heat with the air around the water circulator. Under the action of the circulating fan, the heated air forms hot air and is blown into the storage chamber, and the hot air exchanges heat with the injection molding raw materials in the storage chamber, thereby achieving the effect of preheating the injection molding raw materials. In this way, only enough hot water is needed to achieve the pretreatment of the injection molding raw materials. In the process of producing injection molded products by the injection molding machine, a large amount of hot water will be produced, such as cooling water after cooling the injection molding machine. In this way, the pretreatment device of the utility model does not require additional electric energy, and can pretreat the injection molding raw materials, saving energy and reducing costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Attached Figure 1 It is a schematic diagram of a cooling water waste heat circulation system for an injection molding machine according to a specific embodiment of the utility model;
[0023] Attached Figure 2 This is a structural schematic diagram of an injection molding raw material pretreatment device according to a specific embodiment of the utility model;
[0024] Attached Figure 3 For attachment Figure 2 Schematic diagram of longitudinal section;
[0025] Attached Figure 4 For attachment Figure 2 Schematic diagram of the three-dimensional structure after longitudinal section;
[0026] Attached Figure 5 For attachment Figure 2Schematic diagram of the three-dimensional structure of the middle part;
[0027] Attached Figure 6 For attachment Figure 5 Schematic diagram of the decomposition of
[0028] Attached Figure 7 For attachment Figure 2 A schematic diagram of the three-dimensional structure of another part of the structure;
[0029] Attached Figure 8 This is a schematic diagram of the three-dimensional structure of the heat exchange assembly of this embodiment after removing the outer shell;
[0030] Among them: 1. storage container; 1a. first end; 1b. second end; 10. storage cavity; 11. through hole; 12. baffle; 2. heat exchange component; 21. water circulator; 211. circulation pipe; 212. shell; 22. circulation fan; 3. mounting seat; 30. mounting cavity; 31. shell; 31a. opening; 311. air outlet; 312. mounting plate; 313. connecting port; 32. cover; 321. air outlet. DETAILED DESCRIPTION
[0031] The technical solution of the utility model is described in detail below in conjunction with the accompanying drawings and specific embodiments, so that the advantages and features of the utility model can be more easily understood by those skilled in the art. Obviously, the embodiments described in this application are only part of the embodiments of the application, rather than all of the embodiments. Based on the embodiments in this application, all other embodiments obtained by those skilled in the art without making creative work are within the scope of protection of this application.
[0032] See also Figure 1 An injection molding machine cooling water waste heat circulation system is shown, including an injection molding machine cooling device and an injection molding raw material pretreatment device. Among them, the injection molding machine cooling device includes an injection molding machine cooling tube group, and the injection molding machine cooling tube group is arranged in the cooling area of the injection molding machine and is used to cool the cooling area. By cooling the injection molding machine through the injection molding machine cooling tube group, it is possible to prevent the injection molding machine from overheating and ensure that the injection molding machine can work normally. The injection molding machine cooling tube group can also cool the injection molded product to help the product cool and form. The injection molding raw material pretreatment device includes a hopper 1 and a heat exchange component 2. The hopper 1 has a storage cavity 10 for storing injection molding raw materials, and the heat exchange component 2 is configured to feed heat exchange gas into the storage cavity 10. The heat exchange gas can heat the injection molding raw materials in the storage chamber 10, which can not only dry the injection molding raw materials and eliminate moisture in the injection molding raw materials, but also preheat the injection molding raw materials before entering the injection molding machine, thereby saving part of the electric energy required for the injection molding machine to heat and melt the injection molding raw materials, thereby achieving energy-saving effect.
[0033] The cooling pipe group of the injection molding machine has a first pipe opening and a second pipe opening. The cooling water flows through the cooling area through the first pipe opening and is discharged from the second pipe opening. When the cooling water flows through the cooling area, the heat of the injection molding machine or the product will be transferred to the cooling water, and as the cooling water circulates away, the heat will also be taken away, thereby achieving a cooling effect. After this process, the temperature of the cooling water will rise, usually reaching 60-70℃, and there is considerable heat energy that can be utilized.
[0034] The heat exchange component 2 includes a water circulator 21 and a circulation fan 22. The water circulator 21 is arranged on the air supply path of the circulation fan 22. The water circulator 21 is used to provide heat, and it can transfer heat energy to the surrounding air and increase the temperature of the surrounding air. The circulation fan 22 can send the heated air into the storage chamber 10, and the gas sent in is the heat exchange gas. The water circulator 21 has a water inlet and a water outlet, and a circulation pipe 211 connected between the water inlet and the water outlet, wherein the water inlet is connected to the second pipe mouth, so that the cooling water heated by the cooling treatment of the injection molding machine cooling tube group can be transferred to the injection molding machine raw material pretreatment device to provide heat energy, thereby effectively utilizing the heat energy of the cooling water, that is, the waste heat of the injection molding machine and the injection molding machine cooling tube group, realizing the recycling of energy, not only saving energy, but also saving costs.
[0035] Take a certain injection molding factory as an example to calculate the thermal energy. The factory has 20 injection molding machines: the cooling water temperature difference is measured to be about 30°C. The preheating treatment device of each injection molding machine in the factory consumes 57.4kWh of electricity when working for 24 hours. The total energy consumption of the preheating treatment device in the injection molding factory working for 24 hours is 1148kWh.
[0036] The specifications of the circulating water pump in the plant show that the flow rate is 12.5m 3 / h; also calculated in 24 hours, the total mass of cooling water can be obtained. Knowing the specific heat capacity of water and the measured temperature difference, the thermal energy of water can be obtained according to the formula:
[0037] Q=cmΔT
[0038] Where Q is the thermal energy of circulating water; c is the specific heat capacity of water; m is the total mass of circulating water when the pump works for 24 hours; ΔT is the temperature difference of circulating water.
[0039] After calculation, the heat energy of cooling water is 3.78×10 10 J, the converted energy consumption of the preheating treatment device is 4.13×10 9 J, it can be seen that the heat energy provided by the circulating water is sufficient to meet the needs of heat treatment.
[0040] In this embodiment, see Figures 2 to 6As shown, the injection molding raw material pretreatment device also includes a mounting seat 3, the mounting seat 3 has a mounting cavity 30, an air supply port 311 and an air outlet 321, the air supply port 311 is arranged on the side of the mounting seat 3 and communicates with the mounting cavity 30, and the air outlet 321 is arranged on the end of the mounting seat 3. The accumulator 1 is arranged in the mounting cavity 30 and is located between the air supply port 311 and the air outlet 321, the heat exchange component 2 is installed on the mounting seat 3, and heat exchange gas is fed into the mounting cavity 30 through the air supply port 311. When performing the pretreatment operation, the heat exchange component 2 transports the heat exchange gas into the mounting cavity 30 through the air supply port 311, and the heat exchange gas can fill the storage cavity 10 of the accumulator 1, so that the injection molding raw material and the heat exchange gas fed are fully mixed and achieve sufficient heat exchange, and the gas after the heat exchange can be discharged from the air outlet 321. Setting the air outlet 321 at the end is conducive to the heat exchange gas filling the entire installation cavity 30. Preferably, the size of the air outlet 321 is smaller than the size of the air supply port 311, so that the heat exchange gas can better fill the entire installation cavity 30 and can more fully exchange heat energy.
[0041] See also Figures 3 to 6 As shown, the circumferential side wall of the accumulator 1 is densely covered with through holes 11 penetrating in the thickness direction, and all the through holes 11 are interconnected with the storage cavity 10, so that the heat exchange gas fed into the installation cavity 30 can enter the storage cavity 10 from the through holes 11. Specifically, the aperture of the through hole 11 is smaller than the size of the injection molding raw material, thereby preventing the injection molding raw material from entering the installation cavity 30 through the through hole 11. By increasing the number of through holes 11 and arranging the through holes 11 closely, it is convenient for the heat exchange gas to enter the storage cavity 10, thereby improving the heat exchange efficiency.
[0042] See also Figure 3 , Figure 6 As shown, in this embodiment, the accumulator 1 is conical, and the accumulator 1 has a first end 1a and a second end 1b which are arranged at two different ends in the length direction of the accumulator 1. In the direction perpendicular to the length extension of the accumulator 1, the cross-sectional size of the first end 1a is larger than the cross-sectional size of the second end 1b, wherein the first end 1a and the second end 1b are respectively fixed on the mounting seat 3, and the first end 1a is arranged closer to the air outlet 321 than the second end 1b. Specifically, in this embodiment, the accumulator 1 is arranged in a cone shape with a wide top and a narrow bottom, and the air outlet 321 is located at the upper end of the mounting seat 3. Such an arrangement not only facilitates the injection molding raw materials to be added into the storage cavity 10 from the top, but also facilitates the injection molding raw materials to be discharged from the bottom. At the same time, such an arrangement increases the stacking height of the injection molding raw materials, thereby increasing the area of direct contact with the heat exchange gas blown directly from the side. In this embodiment, the air outlet 321 and the first end 1a are located on the same side, which increases the contact probability and contact time between the heat exchange gas and the injection molding material located at the first end 1a, thereby ensuring that the injection molding material and the heat exchange gas can perform sufficient heat exchange.
[0043] In this embodiment, the mounting base 3 includes a shell 31 and a cover 32. An opening 31a is provided at one end of the shell 31. The cover 32 can be cooperatively covered on one end of the shell 31 and covers the opening 31a. The air supply port 311 is provided on the side of the shell 31, and the air outlet 321 is provided on the cover 32. The hopper 1 is fixedly installed in the shell 31, and the first end 1a is adapted to the opening 31a. Specifically, see Figure 6 As shown, the opening 31a is arranged at the upper part of the housing 31, and the cover 32 can be arranged on the upper part of the housing 31. When loading materials into the storage cavity 10, the cover 32 needs to be removed from the upper part of the housing 31 first, and then the injection molding raw materials are added into the storage cavity 10. In this embodiment, the cover 32 is a prism shape with a size gradually decreasing from bottom to top, and the air outlet 321 is arranged at the upper part of the cover 32, so that the gas discharge is guided, so that the gas is convenient to be discharged outside the installation cavity 30.
[0044] In this embodiment, a shielding member (not shown in the figure) is provided above the cover body 32. The shielding member is located on the air outlet path and covers the entire air outlet 321. The shielding member is provided with air outlet holes for gas to pass through. At the same time, the shielding member can prevent the injection molding material from flying out of the air outlet 321. The shielding member can be fixedly connected to the cover body 32. In some embodiments, the shielding member can also be detachably connected to the cover body 32. When performing the pre-treatment operation, the shielding member and the cover body 32 are fixed to each other.
[0045] In this embodiment, the mounting seat 3 includes a plurality of mounting plates 312 sequentially connected along the circumferential direction, and the accumulator 1 has a plurality of baffles 12 sequentially connected along the circumferential direction, the number of baffles 12 and the mounting plates 312 are consistent and one-to-one corresponding, each mounting plate 312 is provided with an air supply port 311, the air supply port 311 penetrates the mounting plate 312 along the thickness direction, and each air supply port 311 corresponds to a baffle 12. Specifically, see Figure 6 As shown, in this embodiment, the mounting seat 3 is provided with four mounting plates 312, which are connected in sequence along the circumference to form the side of the shell 31. The storage container 1 is in the shape of a quadrangular pyramid, and has four baffles 12 connected in sequence along the circumference, and the four baffles 12 correspond to the four mounting plates 312. Such a configuration increases the area in which the injection molding raw material in the storage cavity 10 is in direct contact with the heat exchange gas.
[0046] In this embodiment, see Figure 3 , Figure 4 As shown, the baffle 12 is connected to the mounting plate 312 at the first end 1a, and the baffle 12 and the mounting plate 312 are arranged at an angle, and the angle formed between the two is an acute angle. In this way, the heat exchange gas needs to pass through the first end 1a of the accumulator 1 when flowing to the air outlet 321, thereby improving the utilization rate of the heat exchange gas.
[0047] In this embodiment, a group of heat exchange components 2 are installed at each air outlet 311, wherein the heat exchange components 2 are fixed on the mounting plate 312 and located outside the mounting seat 3. Such a configuration increases the flow rate of the heat exchange gas sent into the mounting cavity 30 and improves the efficiency of heat exchange. Figure 7 As shown, in this embodiment, four groups of heat exchange components 2 are provided.
[0048] In this embodiment, the water circulator 21 is provided with a housing 212, the circulation pipe 211 is arranged in the housing 212, and the circulation fan 22 is fixedly arranged on a side of the housing 212 away from the mounting seat 3. Along the extension direction of the air outlet path of the circulation fan 22, the housing 212 is provided with a perforation, which is connected to the air outlet 311, so that the heat exchange gas can enter the mounting cavity 30.
[0049] See also Figure 8 As shown, in this embodiment, the circulation pipe 211 is bent in the housing 212, and multiple circulation pipes 211 are arranged at intervals in the up-down direction, and multiple groups of circulation pipes 211 are arranged along the extension direction of the air outlet path of the circulation fan 22, so as to provide sufficient heat energy. In this embodiment, the circulation pipe 211 is a finned tube, so that heat exchange between the cooling water in the circulation pipe 211 and the external air is facilitated.
[0050] In some embodiments, each group of heat exchange components 2 is provided with a separate water outlet, and the water outlets of all heat exchange components 2 converge together after extending a certain distance. In another embodiment, the circulation pipes 211 of all heat exchange components 2 are interconnected and share one water outlet.
[0051] In this embodiment, the other end of the housing 31 is provided with a connecting port 313 and a valve (not shown in the figure) for closing and opening the connecting port 313, and the second end 1b of the accumulator 1 is installed in the connecting port 313. When feeding into the storage chamber 10, the valve is closed to prevent the injection molding material from leaking out from the connecting port 313. In the process of pre-treating the injection molding material, the valve is still closed, and while preventing the injection molding material from leaking out, it can also prevent the heat exchange gas from being discharged from the connecting port 313, so that during the pre-treatment, the heat exchange gas fed in from the air supply port 311 can only be discharged from the air outlet 321. After the pre-treatment is completed, the valve can be opened and the injection molding material that has undergone the pre-treatment can be transferred to the injection molding machine for processing. In this embodiment, the pre-treatment system also includes a feeding device, which is connected between the accumulator 1 and the injection molding machine, and is used to transfer the injection molding material in the accumulator 1 to the processing area of the injection molding machine.
[0052] In this embodiment, the cooling device of the injection molding machine further includes a cooling tower, and the pretreatment system further includes a pipeline assembly and a temperature detector. The cooling tower is configured to cool water, wherein the cooling tower is connected to the first pipe opening. The pipeline assembly includes a first pipeline connecting the water outlet and the cooling tower, and a second pipeline connecting the water outlet and the first pipe opening, a first switch provided on the first pipeline and used to control the on-off of the first pipeline, a second switch provided on the second pipeline and used to control the on-off of the second pipeline, and a control element for switching the working state of the first switch and the second switch. The temperature detector is provided at the water outlet and used to detect the temperature of the water flowing out of the water outlet, and the temperature detector is communicatively connected to the control element.
[0053] After the cooling water transfers heat to the air through the water circulator 21, its temperature will decrease. When it is discharged from the water outlet, its temperature is first measured by the temperature detector. When its temperature does not exceed the preset value, the temperature detector sends a signal to the control element, and the control element controls the second switch to open. At this time, the second pipeline is connected, and the water can flow into the first pipe mouth through the second pipeline, that is, enter the injection molding machine cooling pipe group again and cool the injection molding machine. In this way, the first cycle is formed and the cooling water is recycled. When the temperature detector detects that the temperature of the water flowing out of the water outlet exceeds the preset value, the temperature detector sends another signal to the control element. After receiving the signal, the control element controls the first switch to open. At this time, the first pipeline is connected, and the outflowing water flows along the first pipeline into the cooling tower for cooling and cooling, and then flows into the first pipe mouth, thus forming the second cycle.
[0054] By setting up two pipelines and using a temperature detector and a control element connected by communication to divert the water flowing out of the outlet, it is not necessary to pass all the water flowing out of the outlet into the cooling tower for cooling, and the cooling tower does not need to be in working condition all the time, thereby saving the electricity of the cooling tower.
[0055] In summary, the injection molding raw material pretreatment device of the present embodiment is provided with a water circulator 21. By passing hot water into the water circulator 21, the hot water exchanges heat with the air around the water circulator 21. Under the action of the circulating fan 22, the heated air forms hot air and is blown into the storage chamber 10. The hot air exchanges heat with the injection molding raw material in the storage chamber 10, thereby achieving the effect of preheating the injection molding raw material. In this way, no additional electric energy is required when preheating the injection molding raw material. At the same time, in the cooling water waste heat circulation system of the injection molding machine of the present embodiment, the cooling water heated by the cooling treatment can flow into the water circulator 21, and the cooling water provides heat energy for the injection molding raw material pretreatment device, which not only saves energy and reduces costs, but also the heat exchange component 2 realizes the utilization of the heat energy carried by the cooling water, and uses the heat energy to preheat the injection molding raw material, realizing the recycling of energy, improving the utilization rate of energy, and more in line with environmental protection requirements.
[0056] The above embodiments are only for illustrating the technical concept and features of the utility model, and their purpose is to enable people familiar with the technology to understand the content of the utility model and implement it accordingly, and they cannot be used to limit the protection scope of the utility model. Any equivalent changes or modifications made according to the spirit of the utility model should be included in the protection scope of the utility model.
Claims
1. A device for pre-treating raw materials for injection molding, It is characterized in that The pre-processing device comprises: A mounting seat, the mounting seat having a mounting cavity, an air supply port and an air outlet, wherein the air supply port is arranged on a side of the mounting seat and communicates with the mounting cavity, and the air outlet is arranged on an end of the mounting seat; A hopper having a storage cavity for storing injection molding raw materials, the circumferential side wall of the hopper being densely covered with through holes penetrating in the thickness direction, all of the through holes being interconnected with the storage cavity, the hopper being arranged in the installation cavity and between the air supply port and the air outlet, wherein the air supply port faces the circumferential side wall of the hopper; A heat exchange component, the heat exchange component includes a water circulator and a circulation fan, the water circulator has a water inlet and a water outlet, and a circulation pipe connected between the water inlet and the water outlet, the water circulator is arranged on the air supply path of the circulation fan, the heat exchange component is installed on the mounting base, and the air supply outlet is located on the air supply path.
2. The injection molding raw material pretreatment device according to claim 1, Features: The material storage container is conical in shape, and has a first end and a second end which are respectively arranged at two different ends in the length direction of the material storage container. Along the length extension direction perpendicular to the material storage container, the cross-sectional dimension of the first end is greater than the cross-sectional dimension of the second end, wherein the first end and the second end are respectively fixed on the mounting seat, and the first end is arranged closer to the air outlet than the second end.
3. The injection molding raw material pretreatment device according to claim 2, Features: The mounting base includes a shell and a cover body, one end of the shell is provided with an opening, and the cover body can be cooperatively covered on one end of the shell and covers the opening, wherein the air supply port is opened on the side of the shell, and the air outlet is arranged on the cover body, the storage container is fixedly installed in the shell, and the first end is adapted to the opening.
4. The injection molding raw material pretreatment device according to claim 2, Features: The mounting seat includes a plurality of mounting plates sequentially connected along the circumferential direction, and the material storage container has a plurality of baffles sequentially connected along the circumferential direction, the number of the baffles is consistent with that of the mounting plates and they correspond one to one, each of the mounting plates is provided with an air supply port, the air supply port penetrates the mounting plate along the thickness direction, and each of the air supply ports corresponds to one of the baffles.
5. The injection molding raw material pretreatment device according to claim 4, Features: A group of the heat exchange components is installed at each of the air outlets, wherein the heat exchange components are fixed on the mounting plate and located outside the mounting seat.
6. The injection molding raw material pretreatment device according to claim 4, Features: The baffle is connected to the mounting plate at the first end, and the baffle and the mounting plate are arranged at an angle, and the angle formed between the baffle and the mounting plate is an acute angle.
7. The injection molding raw material pretreatment device according to claim 3, Features: The other end of the shell is provided with a communication port and a valve for closing and opening the communication port, and the second end portion of the accumulator is installed in the communication port.
8. An injection molding machine cooling water waste heat circulation system, It is characterized in that The circulatory system comprises: An injection molding raw material pretreatment device as claimed in any one of claims 1 to 7; The injection molding machine cooling pipe group is arranged in the cooling area of the injection molding machine and is used to cool the cooling area. The injection molding machine cooling pipe group has a first pipe opening and a second pipe opening. Cooling water flows through the cooling area through the first pipe opening and is discharged from the second pipe opening. Wherein, the second pipe opening is connected to the water inlet of the heat exchange component.
9. The cooling water waste heat circulation system for the injection molding machine according to claim 8, Features: The circulation system further includes a cooling tower, which is configured to cool water, wherein the cooling tower is connected to the first pipe opening.
10. The cooling water waste heat circulation system for the injection molding machine according to claim 9, Features: The circulation system also includes a pipeline assembly, which includes a first pipeline connecting the water outlet and the cooling tower, a second pipeline connecting the water outlet and the first pipeline, a first switch provided on the first pipeline and used to control the on and off of the first pipeline, a second switch provided on the second pipeline and used to control the on and off of the second pipeline, and a control element for switching the working states of the first switch and the second switch. The circulation system also includes a temperature detector, which is provided at the water outlet and used to detect the temperature of water flowing out of the water outlet, and the temperature detector is communicatively connected to the control element.
Citation Information
Cited By
Injection molding raw material waste heat pretreatment system and treatment method
CN118082136A