Fixing device for gas extraction pipe

By designing a gas extraction pipe fixing device including a roof panel connecting seat, sliding connector and screw, the problems of installation inconvenience and safety hazards in the prior art are solved, and flexible fixing and stable installation of gas extraction pipe is realized, reducing the need for reducing the The cost is achieved and the safety of the equipment is ensured through the shock absorbing buffer layer.

CN222162718UActive Publication Date: 2024-12-13SHANXI XIANGNING COUNTRY TAITOU COAL CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420998386.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-10
Publication Date
2024-12-13
Estimated Expiration
2034-05-10

AI Technical Summary

Technical Problem

The existing gas extraction pipe fixing device has problems such as inconvenience, safety hazards and high cost during installation and adjustment, especially in complex tunnel environments, which are difficult to achieve flexible position fine adjustment.

Method used

A fixing device including a top plate connecting seat, a left fixing member and a right fixing member is designed to achieve position adjustment through sliding connection and screw mechanism, combining a shock absorbing buffer layer and a clamping fixing layer to ensure fixing stability and safety.

Benefits of technology

The flexible installation and stable fixation of the gas extraction pipe is achieved, which reduces costs and buffers the tiny vibration caused by gas pressure through the shock-absorbing buffer layer to ensure overall safety and stability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 00000000_0000_ABST
    Figure 00000000_0000_ABST
Patent Text Reader

Abstract

The fixing device for the gas extraction pipe comprises a top plate connecting base, a left fixing piece and a right fixing piece, the top of the left fixing piece and the top of the right fixing piece are connected into the top plate connecting base in a sliding mode, and a first screw rod and a second screw rod which are used for positioning the left fixing piece and the right fixing piece are arranged on the top plate connecting base. The left fixing part comprises a left sliding connecting seat, a left semicircular fixing plate and a left tail plate which are integrally formed, the right fixing part comprises a right sliding connecting seat, a right semicircular fixing plate and a right tail plate which are integrally formed, and the left semicircular fixing plate and the right semicircular fixing plate are spliced and fixed to form a fixing cavity penetrating through a gas extraction pipe; a third screw rod is in threaded connection between the left sliding connection seat and the right sliding connection seat; and a fourth screw rod is in threaded connection between the left tail plate and the right tail plate. The fixing device is scientific and reasonable in design, capable of adjusting the fixing position, good in fixing effect, easy to install, low in cost and capable of being used and popularized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to a pipeline fixing device, in particular to a gas extraction pipe fixing device. Background Art

[0002] Coal mine gas extraction is to drill into coal seams and gas concentration areas, connect the boreholes to special pipelines, and use extraction equipment to extract the gas in the coal seams and goaf to the ground for utilization or discharge it into the total return air flow.

[0003] Gas extraction can not only reduce the amount of gas outflow during mining, prevent gas over-limit and accumulation, but also is an important measure to prevent gas explosions and coal and gas outburst accidents. It can also turn harm into benefit and be developed and utilized as a resource associated with coal. Since various pipelines are laid in the tunnel, they cannot be laid flat on the ground. Laying pipelines on the ground has safety hazards. In order to make rational use of the tunnel space, a more reasonable way is to lay the gas extraction pipe on the tunnel roof. Since the laying environment of the gas extraction pipe is complex and changeable, in order to achieve a better laying effect, the fixing device needs to be able to fine-tune the position. Based on this need, a practical gas extraction pipe fixing device is designed. Utility Model Content

[0004] The technical problem to be solved by the utility model is to provide a fixing device for a gas extraction pipe in view of the deficiencies of the above-mentioned prior art. The device has a scientific and reasonable design, can adjust the fixing position, has a good fixing effect, is easy to install, has low cost, and can be widely used.

[0005] To solve the above technical problems, the technical solution adopted by the utility model is: a fixing device for a gas extraction pipe, characterized in that it includes a top plate connecting seat, a left fixing member and a right fixing member, the tops of the left fixing member and the right fixing member are slidably connected in the top plate connecting seat, and the top plate connecting seat is provided with a first screw and a second screw for positioning the left fixing member and the right fixing member, the left fixing member includes an integrally formed left sliding connecting seat, a left semicircular fixing plate and a left tail plate, the right fixing member includes an integrally formed right sliding connecting seat, a right semicircular fixing plate and a right tail plate, the left semicircular fixing plate and the right semicircular fixing plate are assembled and fixed to form a fixing cavity passing through the gas extraction pipe, a third screw is threadedly connected between the left sliding connecting seat and the right sliding connecting seat, and a fourth screw is threadedly connected between the left tail plate and the right tail plate.

[0006] Preferably, the inner walls of the left semicircular fixing plate and the right semicircular fixing plate are sequentially provided with a shock-absorbing buffer layer and a clamping fixing layer, and the two clamping fixing layers are clamped and fixed on the outer wall of the gas extraction pipe after being spliced. The shock-absorbing buffer layer is made of elastic materials such as rubber, and the clamping fixing layer is made of hard synthetic plastic.

[0007] Preferably, a sliding groove is provided in the top plate connecting seat, and the tops of the left sliding connecting seat and the right sliding connecting seat are slidingly connected in the sliding groove, the first screw rod passes through one side of the top plate connecting seat and contacts and presses with the left sliding connecting seat, and the second screw rod passes through the other side of the top plate connecting seat and contacts and presses with the right sliding connecting seat.

[0008] Preferably, the roof connecting seat is connected to the tunnel roof by a plurality of expansion bolts.

[0009] Compared with the prior art, the utility model has the following advantages:

[0010] 1. The utility model has a scientific and reasonable structural design, strong practicality, and is easy to install. The fixed position of the gas extraction pipe can be adjusted by adjusting the positions of the left fixing member and the right fixing member in the slide groove. The overall clamping and fixing of the gas extraction pipe is completed by the third screw and the fourth screw. The clamping is stable, flexible, practical, and can be promoted for use.

[0011] 2. The utility model directly clamps and fixes the gas extraction pipe by means of the clamping and fixing layer. When the gas pressure is too high, the gas extraction pipe will produce a small vibration, and the shock-absorbing buffer layer will be used to buffer and unload energy, thereby ensuring overall safety and stability.

[0012] The utility model is further described in detail below with reference to the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 It is a schematic diagram of the main cross-sectional structure of the utility model.

[0014] Figure 2 It is a side view cross-sectional structural diagram of the top plate connecting seat and the left sliding connecting seat in the utility model.

[0015] Description of reference numerals:

[0016] 1—top plate connection seat; 2—expansion bolt; 3—slide groove;

[0017] 4—first screw rod; 5—second screw rod; 6—left sliding connection seat;

[0018] 7—right sliding connection seat; 8—third screw rod; 9—right semicircular fixing plate;

[0019] 10—left semicircular fixing plate; 11—shock-absorbing and buffering layer; 12—clamping and fixing layer;

[0020] 13—gas extraction pipe; 14—left tail plate; 15—right tail plate;

[0021] 16—Fourth screw. DETAILED DESCRIPTION

[0022] like Figure 1 and Figure 2 As shown, the utility model includes a top plate connecting seat 1, a left fixing member and a right fixing member, the tops of the left fixing member and the right fixing member are slidably connected in the top plate connecting seat 1, and a first screw 4 and a second screw 5 for positioning the left fixing member and the right fixing member are provided on the top plate connecting seat 1, the left fixing member includes an integrally formed left sliding connecting seat 6, a left semicircular fixing plate 10 and a left tail plate 14, the right fixing member includes an integrally formed right sliding connecting seat 7, a right semicircular fixing plate 9 and a right tail plate 15, the left semicircular fixing plate 10 and the right semicircular fixing plate 9 are assembled and fixed to form a fixed cavity passing through the gas extraction pipe 13, a third screw 8 is threadedly connected between the left sliding connecting seat 6 and the right sliding connecting seat 7, and a fourth screw 16 is threadedly connected between the left tail plate 14 and the right tail plate 15.

[0023] In this embodiment, the inner walls of the left semicircular fixing plate 10 and the right semicircular fixing plate 9 are sequentially provided with a shock-absorbing buffer layer 11 and a clamping fixing layer 12, and the two parts of the clamping fixing layer 12 are spliced ​​and clamped and fixed on the outer wall of the gas extraction pipe 13. The shock-absorbing buffer layer 11 is made of elastic materials such as rubber, and the clamping fixing layer 12 is made of hard synthetic plastic.

[0024] In this embodiment, a sliding groove 3 is opened in the top plate connecting seat 1, and the tops of the left sliding connecting seat 6 and the right sliding connecting seat 7 are slidingly connected in the sliding groove 3. The first screw 4 passes through one side of the top plate connecting seat 1 and contacts and presses with the left sliding connecting seat 6, and the second screw 5 passes through the other side of the top plate connecting seat 1 and contacts and presses with the right sliding connecting seat 7.

[0025] In this embodiment, the roof connecting seat 1 is connected to the tunnel roof through a plurality of expansion bolts 2 .

[0026] When in use, first open the left fixing member and the right fixing member, then place the gas extraction pipe 13 between the left semicircular fixing plate 10 and the right semicircular fixing plate 9 and clamp it with the clamping fixing layer 12, tighten the third bolt 8 and the fourth bolt 16 in sequence, and then adjust the position of the left fixing member and the right fixing member by uniformly moving the first bolt 4 and the second bolt 5 to the left or right according to the overall routing layout of the gas extraction pipe 13.

[0027] The above is only a preferred embodiment of the utility model, and does not limit the utility model in any way. Any simple modification, change and equivalent change made to the above embodiment according to the essence of the utility model technology still falls within the protection scope of the technical solution of the utility model.

Claims

1. A fixing device for a gas extraction pipe, characterized in that: The invention comprises a top plate connecting seat (1), a left fixing member and a right fixing member, wherein the tops of the left fixing member and the right fixing member are slidably connected in the top plate connecting seat (1), and a first screw rod (4) and a second screw rod (5) for positioning the left fixing member and the right fixing member are arranged on the top plate connecting seat (1); the left fixing member comprises an integrally formed left sliding connecting seat (6), a left semicircular fixing plate (10) and a left tail plate (14); the right fixing member comprises an integrally formed right sliding connecting seat (7), a right semicircular fixing plate (9) and a right tail plate (15); the left semicircular fixing plate (10) and the right semicircular fixing plate (9) are assembled and fixed to form a fixing cavity passing through a gas extraction pipe (13); a third screw rod (8) is threadedly connected between the left sliding connecting seat (6) and the right sliding connecting seat (7), and a fourth screw rod (16) is threadedly connected between the left tail plate (14) and the right tail plate (15).

2. A gas extraction pipe fixing device according to claim 1, characterized in that: The inner walls of the left semicircular fixing plate (10) and the right semicircular fixing plate (9) are sequentially provided with a shock-absorbing buffer layer (11) and a clamping fixing layer (12); the two parts of the clamping fixing layer (12) are spliced ​​together and clamped and fixed on the outer wall of the gas extraction pipe (13).

3. A gas extraction pipe fixing device according to claim 1, characterized in that: A sliding groove (3) is provided in the top plate connecting seat (1), and the tops of the left sliding connecting seat (6) and the right sliding connecting seat (7) are slidingly connected in the sliding groove (3). The first screw rod (4) passes through one side of the top plate connecting seat (1) and contacts and presses with the left sliding connecting seat (6), and the second screw rod (5) passes through the other side of the top plate connecting seat (1) and contacts and presses with the right sliding connecting seat (7).

4. A gas extraction pipe fixing device according to claim 1, characterized in that: The roof connecting seat (1) is connected to the tunnel roof via a plurality of expansion bolts (2).