Cast-in-place pile grouting pipe
Through the two-stage grouting pipe structure, the combination of Z-shaped connecting horizontal pipe and tripod frame is used to solve the problem of difficult grouting pipes on the top of the cast pile, and the simple structure is achieved, convenient installation and reuse, reducing the construction personnel's Workload.
Patent Information
- Application Number
- CN202421000540.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-10
- Publication Date
- 2024-12-27
- Estimated Expiration
- 2034-05-10
AI Technical Summary
In the construction of concrete cast-infused piles, the grouting pipe on the top of the cast-infused pile needs to be treated after the earth is excavated, resulting in an increase in the workload of construction workers, and the grouting pipe is easily damaged and difficult to reuse.
The two-stage grouting pipe structure is adopted, including the upper and lower section grouting pipes. The combination of the cross pipe and the tripod is connected by Z-shaped, and the connecting components are destroyed by wire ropes to realize the reuse of the upper section grouting pipe.
It realizes a two-stage grouting pipe with a simple structure and convenient installation, which can be recycled and reused, reducing the workload of construction workers and improving the service life of grouting pipes.
Smart Images

Figure CN222252123U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of building construction, in particular to a cast-in-place pile grouting pipe. Background Art
[0002] In some areas, bored concrete piles are constructed on the natural floor. After the bored concrete piles are constructed, foundation pit excavation is carried out. The top of the bored concrete pile is located 1 meter above the bottom of the foundation pit after excavation. The grouting process at the bottom of the pile is carried out 3-5 days after the pile is completed. After the grouting is completed, earth excavation is carried out. After the earth excavation, the grouting pipes from the top of the pile to the natural ground level need to be treated. At the same time, the construction workers of the earth excavation also need to pay attention to the grouting pipes from the top of the pile to the natural ground level to prevent the grouting pipes from being damaged, which greatly increases the workload of the earthwork construction workers. Utility Model Content
[0003] The utility model aims to provide a cast-in-place pile grouting pipe which has a simple structure, is easy to install, adopts a two-section grouting pipe, and the upper section of the grouting pipe can be repeatedly used.
[0004] The utility model is achieved through the following measures:
[0005] A grouting pipe for a cast-in-place pile, characterized in that it comprises an upper grouting pipe and a lower grouting pipe, a connecting portion is provided between the upper grouting pipe and the lower grouting pipe, and a breaking assembly is provided between the upper grouting pipe and the connecting portion;
[0006] The connecting portion comprises a Z-shaped connecting transverse tube, one end of the Z-shaped connecting transverse tube is provided with a first connecting sleeve, the other end of the Z-shaped connecting transverse tube is provided with a second connecting sleeve, the free end of the first connecting sleeve is provided with the upper section grouting pipe, and the free end of the second connecting sleeve is connected to the lower section grouting pipe;
[0007] The connecting part comprises a tripod, one end angle of the tripod is connected to the upper grouting pipe, the other end angle of the tripod is connected to the horizontal pipe of the Z-shaped connecting horizontal pipe, and a steel wire rope is arranged at the third end angle of the tripod;
[0008] Preferably, the first connecting sleeve is threadedly connected to the upper section grouting pipe, and the second connecting sleeve is threadedly connected to the lower section grouting pipe.
[0009] The specific features of the utility model also include:
[0010] A first mounting ring is fixedly provided at one end corner of the tripod, the first mounting ring is arranged at the periphery of the upper grouting pipe, a second mounting ring is fixedly provided at the other end corner of the tripod, the second mounting ring is arranged at the periphery of the horizontal pipe of the Z-shaped connecting horizontal pipe, and a steel wire rope is arranged at the third end corner of the tripod;
[0011] Preferably, the tripod is made of welded steel bars.
[0012] The lower section grouting pipe is arranged inside the cast-in-place pile, and the upper section grouting pipe is arranged outside the cast-in-place pile.
[0013] The first mounting ring is welded to the upper grouting pipe.
[0014] During grouting, the upper grouting pipe, the lower grouting pipe, the Z-shaped connecting transverse pipe and the tripod are pre-assembled, and then the lower grouting pipe is lowered into the cast-in-place pile for grouting. When the grouting is completed, the steel wire rope is pulled on the natural floor to pull the tripod to destroy the Z-shaped connecting transverse pipe. After that, the upper grouting pipe can be pulled out of the pile hole as a whole, and the residual slurry in the upper grouting pipe can be cleaned and reused.
[0015] The utility model has the following beneficial effects: simple structure, convenient installation, and a two-section grouting pipe, wherein the upper section of the grouting pipe can be repeatedly used. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a structural schematic diagram of an embodiment of the utility model.
[0017] Among them, the accompanying drawings are marked as: 1. natural floor; 2. foundation pit; 3. cast-in-place piles; 4. upper section grouting pipe; 5. first connecting sleeve; 6. Z-shaped connecting cross pipe; 7. second connecting sleeve; 8. lower section grouting pipe; 9. tripod; 10. first mounting ring; 11. second mounting ring; 12. wire rope. DETAILED DESCRIPTION
[0018] In order to clearly illustrate the technical features of this solution, this solution is described below through a specific implementation method.
[0019] See also Figure 1 A grouting pipe for a cast-in-place pile 3, comprising an upper grouting pipe 4 and a lower grouting pipe 8, a connecting portion is provided between the upper grouting pipe 4 and the lower grouting pipe 8, and a breaking assembly is provided between the upper grouting pipe 4 and the connecting portion;
[0020] The connecting part includes a Z-shaped connecting transverse pipe 6, one end of which is provided with a first connecting sleeve 5, the other end of which is provided with a second connecting sleeve 7, the free end of the first connecting sleeve 5 is provided with an upper section grouting pipe 4, and the free end of the second connecting sleeve 7 is connected to a lower section grouting pipe 8;
[0021] The connection part includes a tripod 9, one end corner of the tripod 9 is connected to the upper grouting pipe 4, the other end corner of the tripod 9 is connected to the horizontal pipe of the Z-shaped connecting horizontal pipe 6, and a steel wire rope 12 is arranged at the third end corner of the tripod 9;
[0022] Preferably, the first connecting sleeve 5 is threadedly connected to the upper section grouting pipe 4 , and the second connecting sleeve 7 is threadedly connected to the lower section grouting pipe 8 .
[0023] A first mounting ring 10 is fixedly provided at one end corner of the tripod 9, and the first mounting ring 10 is arranged on the periphery of the upper section grouting pipe 4. A second mounting ring 11 is fixedly provided at the other end corner of the tripod 9, and the second mounting ring 11 is arranged on the periphery of the horizontal pipe of the Z-shaped connecting horizontal pipe 6. A steel wire rope 12 is provided at the third end corner of the tripod 9.
[0024] The lower section grouting pipe 8 is arranged inside the cast-in-place pile 3 , and the upper section grouting pipe 4 is arranged outside the cast-in-place pile 3 .
[0025] The first mounting ring 10 is welded to the upper grouting pipe 4 .
[0026] During grouting, the upper grouting pipe 4, the lower grouting pipe 8, the Z-shaped connecting transverse pipe 6 and the tripod 9 are pre-assembled, and then the lower grouting pipe 8 is lowered into the cast-in-place pile 3 for grouting. When the grouting is completed, the steel wire rope 12 is pulled on the natural floor 1 to pull the tripod 9 to destroy the Z-shaped connecting transverse pipe 6. After that, the upper grouting pipe can be pulled out of the pile hole as a whole, and the residual slurry in the upper grouting pipe 4 can be cleaned and reused.
[0027] Technical features not described in the present invention can be achieved through or by adopting existing technologies, and will not be elaborated here. Of course, the above description is not a limitation of the present invention, and the present invention is not limited to the above examples. Changes, modifications, additions or substitutions made by ordinary technicians in this technical field within the essential scope of the present invention should also fall within the scope of protection of the present invention.
Claims
1. A grouting pipe for a bored pile, characterized in that: It comprises an upper grouting pipe and a lower grouting pipe, a connecting portion is arranged between the upper grouting pipe and the lower grouting pipe, and a breaking component is arranged between the upper grouting pipe and the connecting portion; The connecting portion comprises a Z-shaped connecting transverse tube, one end of the Z-shaped connecting transverse tube is provided with a first connecting sleeve, the other end of the Z-shaped connecting transverse tube is provided with a second connecting sleeve, the free end of the first connecting sleeve is provided with the upper section grouting pipe, and the free end of the second connecting sleeve is connected to the lower section grouting pipe; The connecting part comprises a tripod, one end angle of the tripod is connected to the upper grouting pipe, the other end angle of the tripod is connected to the horizontal pipe of the Z-shaped connecting horizontal pipe, and a steel wire rope is arranged at the third end angle of the tripod.
2. The cast-in-place pile grouting pipe according to claim 1, characterized in that: A first mounting ring is fixedly provided at one end corner of the tripod, and the first mounting ring is arranged on the periphery of the upper section grouting pipe. A second mounting ring is fixedly provided at the other end corner of the tripod, and the second mounting ring is arranged on the periphery of the horizontal pipe of the Z-shaped connecting horizontal pipe. A steel wire rope is provided at the third end corner of the tripod.
3. The cast-in-place pile grouting pipe according to claim 2, characterized in that: The lower section grouting pipe is arranged inside the cast-in-place pile, and the upper section grouting pipe is arranged outside the cast-in-place pile.
4. The cast-in-place pile grouting pipe according to claim 3, characterized in that: The first mounting ring is welded to the upper grouting pipe.