Passenger elevator spandrel girder mounting structure

By adopting the shaped layout of the main load-bearing beam and the secondary load-bearing beam in the elevator shaft, combined with welding fixing and load-bearing devices, the problem of large space occupied by the elevator load-bearing beam structure and interference with the door is solved, and the rational use of space and the improvement of installation efficiency is achieved. .

CN222312441UActive Publication Date: 2025-01-07GUANGDONG APXO ELEVATOR
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323656878.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-31
Publication Date
2025-01-07
Estimated Expiration
2033-12-31

AI Technical Summary

Technical Problem

The existing elevator load-bearing beam structure occupies a large space, resulting in insufficient net size of the computer room in the small tonnage shaft, which cannot meet the maintenance space requirements. In the case of back weight, the load-bearing beam interferes with the door, resulting in difficulty in opening the door.

Method used

The main load-bearing beam and two secondary load-bearing beams are adopted to reduce the main load-bearing beam one, and the welding and fixing of the car rope head plate and the counterweight rope head plate are used, and the main frame, longitudinal beam and cross beam of the load-bearing device are combined with the main frame, longitudinal beam and cross beam of the load-bearing device. Shock absorber improves installation efficiency.

Benefits of technology

The load-bearing beam structure is simplified, space occupation is reduced, sufficient maintenance space and door opening space is provided, and installation efficiency and installation convenience are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222312441U_ABST
    Figure CN222312441U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of elevators, in particular to a passenger elevator spandrel girder installation structure which comprises a main spandrel girder arranged in the middle of a hoistway in the longitudinal direction of the hoistway. The two auxiliary spandrel girders are arranged at intervals in the longitudinal direction of the hoistway, all the auxiliary spandrel girders are arranged in the transverse direction of the hoistway, one ends of the auxiliary spandrel girders are fixedly installed on the right side of the main spandrel girder, and the other ends of the auxiliary spandrel girders are fixedly installed on the side wall of the hoistway; the car rope hitch plate is fixedly mounted on the left side of the main bearing beam; the counter-weight rope hitch plate is fixedly mounted on the side part of the secondary bearing beam; and the bearing device is fixedly mounted between the two secondary bearing beams. The spandrel girder structure is only provided with one main spandrel girder and two auxiliary spandrel girders, the overall spandrel girder layout is arranged in the shape of the Chinese character'ba ', and compared with the prior art, one main spandrel girder is reduced, so that under the condition that the occupied space is reduced, the use of raw materials is reasonably reduced, the spandrel girder structure is simplified, and the problem that the previous structure is complex is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of elevators, in particular to a passenger elevator load-bearing beam installation structure. Background Art

[0002] Referring to the patent document with application number CN202320329115X, it discloses an installation structure of a counterweight load-bearing beam of an elevator with a machine room, including a main engine base load-bearing beam assembly installed at both ends in the elevator machine room and a counterweight load-bearing beam of the elevator with a machine room, wherein the main body is arranged on the side of the main engine base load-bearing beam assembly, one end of the main body is installed on the side of the main engine base load-bearing beam assembly, and the other end is installed on the side wall of the elevator machine room through a channel steel.

[0003] The disadvantages of this type of load-bearing beam structure: it takes up a large space. When the hoistway is small, the net size of the machine room is small. After the main and auxiliary load-bearing beams are placed, there is not enough space for the main engine and control cabinet, resulting in no maintenance space, which leads to the failure of the elevator acceptance and the problem of complex structure. In addition, when the elevator hoistway is built, under normal circumstances, the machine room door and the hall door are placed in the same direction, which can prevent the machine room door from being exposed to rain indoors. However, when the elevator is rear-counterweighted, the load-bearing beam will interfere with the machine room door, resulting in the inability to open the door, and non-standard rectification or lifting the door is required. Utility Model Content

[0004] The utility model aims to provide a passenger elevator load-bearing beam installation structure for the deficiencies in the prior art, and the use of the structure can solve the problem of complex structure.

[0005] The purpose of the utility model is achieved through the following technical solutions: The application provides a passenger elevator load-bearing beam installation structure, including a main load-bearing beam, which is arranged in the middle of the well along the longitudinal direction of the well; two auxiliary load-bearing beams are arranged at intervals along the longitudinal direction of the well, and each auxiliary load-bearing beam is arranged transversely along the well, one end of the auxiliary load-bearing beam is fixedly installed on the right side of the main load-bearing beam, and the other end is fixedly installed on the side wall of the well; a car rope head plate, which is fixedly installed on the left side of the main load-bearing beam; a counterweight rope head plate, which is fixedly installed on the side of the auxiliary load-bearing beam; and a load-bearing device, which is fixedly installed between the two auxiliary load-bearing beams.

[0006] Among them, the car rope head plate is fixed on the main load-bearing beam by welding.

[0007] Among them, the counterweight rope head plate is fixedly installed on the secondary load-bearing beam by welding.

[0008] Among them, the main load-bearing beam is an I-shaped channel steel structure.

[0009] Wherein, the secondary load-bearing beam is one of an I-shaped channel steel structure or a U-shaped channel steel structure.

[0010] Among them, the load-bearing device includes a main frame, a pair of longitudinal beams and a pair of cross beams. The pairs of longitudinal beams are arranged at intervals in the transverse direction on the top surface of the auxiliary load-bearing beams, and the pairs of cross beams are arranged at intervals in the longitudinal direction on the top surface of the longitudinal beams. The main frame is fixedly installed on the top surface of the cross beams, and shock-absorbing rubber is provided between the longitudinal beams and the auxiliary load-bearing beams.

[0011] The utility model provides a passenger elevator load-bearing beam installation structure with the following beneficial effects:

[0012] The load-bearing beam structure is provided with only one main load-bearing beam and two auxiliary load-bearing beams. The car rope head plate is placed on the side of the main load-bearing beam, and the counterweight rope head plate is placed on the side of the auxiliary load-bearing beam. The entire load-bearing beam layout is arranged in an "Y" shape. Compared with the prior art, the use of one main load-bearing beam is reduced, thereby reasonably reducing the use of raw materials while reducing space occupancy, simplifying the load-bearing beam structure, and solving the problem of complex structure in the past.

[0013] The main load-bearing beam is arranged horizontally to the middle of the shaft, so that there is enough space between the main load-bearing beam and the wall for placing the control cabinet, which can meet the operating space requirements of national standards.

[0014] When the rear is counterweighted, the machine room door and the hall door are in the same direction and will not interfere with the load-bearing beam. There is no need to change the door opening in a non-standard manner, nor to consider moving the load-bearing beam in a non-standard manner.

[0015] Compared with the traditional structure, the reduction of one main load-bearing beam makes the installation more convenient and quick, and the installation efficiency is also improved to a certain extent. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] The utility model is further described using the accompanying drawings, but the embodiments in the accompanying drawings do not constitute any limitation to the utility model. A person skilled in the art can obtain other drawings based on the following drawings without creative work.

[0017] Figure 1 It is a structural schematic diagram of a passenger elevator load-bearing beam installation structure in an embodiment.

[0018] Figure 2 Schematic diagram of the structure of the load-bearing device in the embodiment.

[0019] Figure numerals: hoistway 1, main load-bearing beam 2, secondary load-bearing beam 3, car rope head plate 4, counterweight rope head plate 5, load-bearing device 6, longitudinal beam 61, cross beam 62, main frame 63, shock-absorbing rubber 64. Implementation

[0020] The utility model is further described in conjunction with the following embodiments.

[0021] A specific implementation method of a passenger elevator load-bearing beam installation structure of the utility model is as follows Figure 1 and Figure 2 As shown, it includes a main load-bearing beam 2, two secondary load-bearing beams 3, a car rope head plate 4, a counterweight rope head plate 5 and a load-bearing device 6.

[0022] In this embodiment, the main load-bearing beam 2 is arranged in the middle of the shaft 1 along the longitudinal direction of the shaft 1. Two auxiliary load-bearing beams 3 are arranged at intervals along the longitudinal direction of the shaft 1, and each auxiliary load-bearing beam 3 is arranged transversely along the shaft 1.

[0023] As an improvement, one end of each secondary load-bearing beam 3 is fixedly installed on the right side of the main load-bearing beam 2, and the other end is fixedly installed on the side wall of the shaft 1. The car rope head plate 4 is fixedly installed on the left side of the main load-bearing beam 2, and the counterweight rope head plate 5 is fixedly installed on the side of the secondary load-bearing beam 3 located below. In addition, the load-bearing device 6 is fixedly installed between the two secondary load-bearing beams 3.

[0024] As a preferred solution, the car rope head plate 4 is fixedly installed on the main load-bearing beam 2 by welding. The welding method has a sufficiently high connection strength to ensure the working stability of the load-bearing beam. Similarly, the counterweight rope head plate 5 is fixedly installed on the secondary load-bearing beam 3 by welding.

[0025] As a preferred solution, the main load-bearing beam 2 is an I-shaped channel steel structure, specifically, an I-shaped steel of model 22-25 can be used, and the secondary load-bearing beam 3 is an I-shaped channel steel structure or a U-shaped channel steel structure, specifically, a channel steel of model 14 can be used.

[0026] Please see Figure 2 The load-bearing device 6 includes a main frame 63, a pair of longitudinal beams 61 and a pair of cross beams 62. The pair of longitudinal beams 61 are arranged at intervals in the transverse direction on the top surface of the auxiliary load-bearing beam 3, and the pair of cross beams 62 are arranged at intervals in the longitudinal direction on the top surface of the longitudinal beam 61. The main frame 63 is fixedly installed on the top surface of the cross beam 62, and a shock-absorbing rubber 64 is provided between the longitudinal beam 61 and the auxiliary load-bearing beam 3.

[0027] The load-bearing beam installation structure of a passenger elevator of this embodiment is provided with only one main load-bearing beam 2 and two auxiliary load-bearing beams 3. The rope head plate 4 of the car is placed on the side of the main load-bearing beam 2, and the counterweight rope head plate 5 is placed on the side of the auxiliary load-bearing beam 3. The entire load-bearing beam layout is arranged in a "Y" shape. Compared with the prior art, one main load-bearing beam 2 is reduced, thereby reducing the use of raw materials reasonably while reducing the space occupied, simplifying the load-bearing beam structure, and solving the problem of complex structure in the past. The main load-bearing beam 2 is horizontal to the middle position of the shaft 1, so that there is enough space between the main load-bearing beam 2 and the wall for placing the control cabinet, which can meet the operating space required by the national standard. When the rear counterweight is used, the machine room door and the hall door are in the same direction, and will not interfere with the load-bearing beam, and there is no need to change the door opening in a non-standard manner, nor to consider the non-standard moving position of the load-bearing beam. Compared with the traditional structure, after reducing one main load-bearing beam 2, the installation is more convenient and quick, and the installation efficiency is also improved to a certain extent.

[0028] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the utility model, rather than to limit the protection scope of the utility model. Although the utility model has been described in detail with reference to the preferred embodiments, ordinary technicians in this field should understand that the technical solution of the utility model can be modified or replaced by equivalents without departing from the essence and scope of the technical solution of the utility model.

Claims

1. A passenger elevator load-bearing beam installation structure, characterized in that: include: The main load-bearing beam is arranged in the middle of the shaft along the longitudinal direction of the shaft; Two auxiliary load-bearing beams are arranged at intervals along the longitudinal direction of the well, each of the auxiliary load-bearing beams is arranged transversely along the well, one end of the auxiliary load-bearing beam is fixedly installed on the right side of the main load-bearing beam, and the other end is fixedly installed on the side wall of the well; A car rope head plate, fixedly mounted on the left side of the main load-bearing beam; A counterweight rope head plate is fixedly mounted on the side of the secondary load-bearing beam; The load-bearing device is fixedly installed between the two secondary load-bearing beams.

2. A passenger elevator load-bearing beam installation structure according to claim 1, characterized in that: The car rope head plate is fixedly mounted on the main load-bearing beam by welding.

3. A passenger elevator load-bearing beam installation structure according to claim 1, characterized in that: The counterweight rope head plate is fixedly mounted on the secondary load-bearing beam by welding.

4. A passenger elevator load-bearing beam installation structure according to claim 1, characterized in that: The main load-bearing beam is an I-shaped channel steel structure.

5. The passenger elevator load-bearing beam installation structure according to claim 1, characterized in that: The secondary load-bearing beam is an I-shaped channel steel structure or a U-shaped channel steel structure.

6. A passenger elevator load-bearing beam installation structure according to claim 1, characterized in that: The load-bearing device includes a main frame, a pair of longitudinal beams and a pair of cross beams. The pair of longitudinal beams are arranged at intervals in the transverse direction on the top surface of the auxiliary load-bearing beam, and the pair of cross beams are arranged at intervals in the longitudinal direction on the top surface of the longitudinal beam. The main frame is fixedly installed on the top surface of the cross beam, and shock-absorbing rubber is provided between the longitudinal beam and the auxiliary load-bearing beam.