Tunnel equipment transportation device

By designing the transportation device of the cave and tunnel equipment, the combination of the door frame and the top -up mechanism solves the problem of insufficient use of time space in the installation of the cave and tunnel, realizing efficient transportation and installation, reducing mechanical costs and occupying space.

CN222388895UActive Publication Date: 2025-01-24CHINA 19TH METALLURGICAL CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421181870.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-28
Publication Date
2025-01-24
Estimated Expiration
2034-05-28

AI Technical Summary

Technical Problem

When installing or replacing equipment in tunnels, the existing technology is difficult to effectively utilize space, resulting in high mechanical costs and large space occupancy. Especially when the box corridor space is narrow, it is difficult to meet the needs of equipment installation.

Method used

A tunnel equipment transportation device is designed, including two gantry frames and a jacking mechanism. The gantry frame forms a doorway through columns, beams and running wheels. The two gantry frames are connected to form a channel for the passage of the mineral material transfer belt. , make reasonable use of the space above, and lift the equipment to the designated installation position through the lifting mechanism.

Benefits of technology

This device can not only efficiently transport equipment in the cave and tunnel, occupy small space, does not affect the normal use of the cave and tunnel, but also reduces the investment of other hanging machinery equipment and facilitates on -site operations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222388895U_ABST
    Figure CN222388895U_ABST
Patent Text Reader

Abstract

The utility model discloses a tunnel equipment transportation device, belongs to the field of transportation tools, and aims to save the occupied tunnel area. Comprising two door-shaped frames, each door-shaped frame comprises two stand columns, a cross beam and walking wheels at the bottom ends of the stand columns, and a door opening is defined by the stand columns and the cross beam; the two door-shaped frames are arranged front and back in the longitudinal direction, the front door-shaped frame and the rear door-shaped frame are connected into a whole through a longitudinal connecting rod, and door openings of the front door-shaped frame and the rear door-shaped frame are communicated to form a channel. A lower support is defined by cross beams and longitudinal connecting rods, and an upper support is arranged on the lower support. The upper support is movably supported on the lower support in the vertical direction through a jacking mechanism. The front door-shaped frame and the rear door-shaped frame stretch across a mineral aggregate transfer belt for transportation, the upper support is movably supported on the lower support in the vertical direction through the jacking mechanism, under the action of the jacking mechanism, the funnel can be jacked to the designated installation position of the top of the box gallery, transportation of the funnel can be completed, jacking can be achieved, and in the whole transportation and jacking process, the transportation efficiency is greatly improved. The occupied space is small, and normal use of the tunnel is not affected.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the field of transportation tools, in particular to a tunnel equipment transportation device. Background Art

[0002] A silo is a cavern or building that temporarily stores and facilitates the loading of ore. A silo used to store coal is called a coal bunker. The bottom of the bunker is generally higher than the ore receiving port of the loading container or transportation equipment. When the gate of the silo is opened, the ore is unloaded and automatically loaded, which can reduce the physical labor during loading and improve the loading efficiency.

[0003] like Figure 1 In the ore bin loading system shown in the figure, the lower part of the ore bin 11 is a box gallery 13, and a ore material transfer belt 14 extending longitudinally along the box gallery is arranged in the box gallery 13. The outlet of the ore bin 11 is connected to the funnel 12, which is located in the box gallery 13 and unloads the ore from the ore bin 11 to the ore material transfer belt 14. The funnel is installed on the top of the box gallery 13, and the ore material transfer belt 14 is located below the funnel. Of course, Figure 1 The system shown may also be a coal bunker loading system. If it is a coal bunker loading system, the ore bunker 11 is the coal bunker for loading coal.

[0004] When installing the hopper for the first time or when replacing it, if the gallery space is large enough, the hopper can be hoisted to the designated installation position beside the mineral material transfer belt by a lifting machine. Although this can meet the installation requirements of the hopper, the machinery cost is high and occupies a large space. If the gallery space is narrow and it is difficult to meet the use requirements of the lifting machinery, it will bring difficulties to the installation of the hopper. Utility Model Content

[0005] The utility model aims to provide a tunnel equipment transportation device, which can save the occupied tunnel area when the equipment is transported in the tunnel.

[0006] The technical scheme adopted by the utility model is as follows: a tunnel equipment transportation device comprises two pairs of portal frames, each pair of portal frames comprises two upright posts, a cross beam and walking wheels at the bottom ends of the upright posts, and a door opening is formed by being surrounded by the upright posts and the cross beam; the two pairs of portal frames are arranged front and back in the longitudinal direction, and the front and rear portal frames are connected into a whole through longitudinal connecting rods located on both sides, and the door openings of the front and rear portal frames are connected to form a passage; a lower bracket is surrounded by the cross beam and the longitudinal connecting rod to form a square, and an upper bracket is arranged above the lower bracket; the upper bracket is supported on the lower bracket in a vertically movable manner through a jacking mechanism.

[0007] Furthermore, a guide mechanism is provided to guide and limit the movement of the upper bracket.

[0008] Furthermore, the cross beam is vertically arranged in the middle of the column, and the column vertically includes an upper section located above the cross beam and a lower section located below the cross beam; the upper bracket is a square frame; the cross section of the upper section is right-angled, and its right-angled opening faces inward; the four corners of the upper bracket are vertically slidably matched with the right-angled opening of the upper section, and the guide mechanism is formed by the right-angled opening of the upper section and the corner of the upper bracket.

[0009] Furthermore, the lifting mechanism is a hydraulic cylinder.

[0010] Furthermore, equipment placement slots are provided in the middle of the four sides of the upper bracket.

[0011] Furthermore, component placement grooves extending longitudinally are respectively provided on both sides of the portal frame in the transverse direction, one end of the component placement groove is fixed to the column of the portal frame on the front side, and the other end is fixed to the column of the portal frame on the rear side.

[0012] Furthermore, the component placement groove is vertically arranged at the bottom of the column.

[0013] Furthermore, a diagonal brace is provided between the upright column of the front portal frame and the upright column of the rear portal frame.

[0014] The beneficial effects of the utility model are as follows: the utility model, through the door openings of the front and rear door frames, the passage formed is used for the mineral material transfer belt to pass through, so that the door frame crosses the mineral material transfer belt for transportation, which does not affect the operation of the mineral material transfer belt, and reasonably utilizes the space above the mineral material transfer belt, greatly reduces the occupied area, and is less affected by the size of the tunnel. The upper bracket is supported vertically on the lower bracket through the jacking mechanism, and under the action of the jacking mechanism, the funnel can be jacked to the designated installation position on the top of the box gallery for installation. The tunnel equipment transportation device can complete the transportation of the funnel and realize jacking, and in the entire transportation and jacking process, it occupies a small space, will not affect the normal use of the tunnel, and also reduces the investment in other lifting machinery and equipment and transfer machinery and equipment, which is convenient for on-site operation. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 This is a schematic diagram of the ore bin loading system;

[0016] Figure 2 It is a schematic diagram of the structure of the utility model;

[0017] Figure 3 This is the front view of the utility model;

[0018] Figure 4 It is the right view of the utility model.

[0019] In the figure, there are columns 1, upper segment 1A, lower segment 1B, cross beam 2, walking wheels 3, door opening 4, longitudinal connecting rod 5, jacking mechanism 6, upper bracket 7, equipment placement groove 8, component placement groove 9, diagonal brace 10, ore bin 11, funnel 12, box gallery 13, and ore transfer belt 14. DETAILED DESCRIPTION

[0020] The present invention is further described below in conjunction with the accompanying drawings and embodiments:

[0021] In the present invention, terms such as "center", "lateral", "longitudinal", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside" and "outside" indicate directions and positional relationships based on the directions or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and should not be understood as limiting the specific scope of protection of the present application.

[0022] Tunnel equipment transportation device, such as Figure 2 , Figure 3 and Figure 4 As shown, it includes two pairs of portal frames, each pair of portal frames includes two columns 1, a crossbeam 2 and a walking wheel 3 at the bottom of the column 1, and a door opening 4 is formed by the columns 1 and the crossbeam 2; the two pairs of portal frames are arranged front and back in the longitudinal direction, and the front and rear portal frames are connected into a whole through the longitudinal connecting rods 5 located on both sides, and the door openings 4 of the front and rear portal frames are connected to form a passage. In order to ensure the overall stability of the frame surrounded by the front and rear portal frames, preferably, a diagonal brace 10 is also provided between the columns 1 of the front portal frame and the columns 1 of the rear portal frame. The passage formed by the door openings 4 of the front and rear portal frames is used for the passage of the mineral material transfer belt, that is, when in use, the portal frame straddles the mineral material transfer belt and does not affect the operation of the mineral material transfer belt. Since the portal frame straddles the mineral material transfer belt, only the columns 1 on both sides of the mineral material transfer belt are supported on the ground. Compared with the overall station of the device on one side of the mineral material transfer belt, the space above the mineral material transfer belt is reasonably utilized, the floor area is greatly reduced, and the influence of the tunnel size is small. Furthermore, the upright column 1, the cross beam 2 and the longitudinal connecting rod 5 form a frame structure with good supporting performance. The arrangement of the traveling wheel 3 enables the traveling trolley of the tunnel equipment transport device type to travel as required.

[0023] A lower bracket is formed into a square by a crossbeam 2 and a longitudinal connecting rod 5, and an upper bracket 7 is arranged above the lower bracket; the upper bracket 7 is supported on the lower bracket along the vertical movement through a jacking mechanism 6, that is, under the drive of the jacking mechanism 6, the upper bracket 7 can adjust its installation height vertically, so that under the action of the walking wheel 3, the tunnel equipment transportation device moves longitudinally along the mineral material transfer belt to below the designated installation position of the funnel, and the upper bracket 7 can lift the funnel, and under the action of the jacking mechanism 6, the funnel is jacked to the designated installation position on the top of the box gallery for installation.

[0024] In order to guide the movement of the upper bracket 7 and prevent the upper bracket 7 from deviating, a guiding mechanism for guiding and limiting the movement of the upper bracket 7 is provided.

[0025] The guide mechanism can be a slide rail and a slide groove, etc. In this embodiment, the cross beam 2 is vertically arranged in the middle of the column 1, and the column 1 vertically includes an upper segment 1A located above the cross beam 2 and a lower segment 1B located below the cross beam 2; the upper bracket 7 is a square frame; the cross section of the upper segment 1A is right-angled, and its right-angle opening faces inward; the four corners of the upper bracket 7 are vertically slidably matched with the right-angle opening of the upper segment 1A, and the guide mechanism is formed by the right-angle opening of the upper segment 1A and the corner of the upper bracket 7. The upper bracket 7 is limited and guided by the corner structure of the upper segment 1A of the column 1, and there is no need to perform additional processing on the column 1, which saves processing steps; at the same time, the column 1 is an integral body, and the strength is guaranteed; the guide mechanism is formed by the corresponding structures of the column 1 itself and the upper bracket 7 itself, and the structure is simpler.

[0026] The lifting mechanism 6 may be a scissor mechanism, a rack and pinion mechanism, etc. In the present embodiment, the lifting mechanism 6 is a hydraulic cylinder.

[0027] Equipment such as funnels can be placed directly on the upper bracket 7, can be bound to the upper bracket 7, or can be fixed to the upper bracket 7 with bolts, etc. Of course, equipment placement grooves 8 may also be provided in the middle of the four sides of the upper bracket 7, and support legs may be provided at the bottom of equipment such as funnels, which are inserted into the equipment placement grooves 8 for lifting.

[0028] In order to transport components such as pipes and plates, preferably, component placement grooves 9 extending in the longitudinal direction are respectively provided on both sides of the portal frame in the transverse direction, and one end of the component placement groove 9 is fixed to the column 1 of the portal frame on the front side, and the other end is fixed to the column 1 of the portal frame on the rear side. Components such as pipes and plates are placed in the component placement grooves 9 on both sides for transportation.

[0029] In order to further improve the stability of transportation, preferably, the component placement groove 9 is vertically arranged at the bottom of the column 1. Compared with being arranged in the middle or top of the column 1, the component placement groove 9 arranged at the bottom of the column 1 is firstly convenient for placing the component into the component placement groove 9, and secondly, when the component is placed, the center of gravity of the entire transport device is lowered, and the stability is better.

[0030] The following uses the funnel as an example of the equipment to be transported and installed to explain the use of the tunnel equipment transportation device:

[0031] First, place the funnel on the upper support 7 outside the tunnel and fix it;

[0032] Next, the tunnel equipment transport device is driven by traction or driving wheels to straddle both sides of the transport belt and drive into the tunnel along the extension direction of the ore transport belt until the funnel reaches below the installation position; pipes, plates and other components can be placed in the component placement slot 9 at the same time and transported together with the funnel;

[0033] Then, the column 1 is used as a constraint, and the hydraulic cylinder synchronously lifts the upper bracket 7 to ensure that the funnel is lifted to the installation position stably and safely for installation.

[0034] The "tunnel" mentioned in the present invention can be a tunnel, a box gallery, a pipe gallery, etc.

[0035] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A tunnel equipment transportation device, characterized in that: The invention comprises two pairs of portal frames, each pair of portal frames comprises two upright posts (1), a crossbeam (2) and a walking wheel (3) at the bottom end of the upright posts (1), and a door opening (4) is formed by the upright posts (1) and the crossbeam (2); the two pairs of portal frames are arranged front and back in the longitudinal direction, and the front and rear portal frames are connected to form a whole through longitudinal connecting rods (5) located on both sides, and the door openings (4) of the front and rear portal frames are connected to form a passage; a square lower bracket is surrounded by the crossbeam (2) and the longitudinal connecting rod (5), and an upper bracket (7) is arranged above the lower bracket; the upper bracket (7) is supported on the lower bracket in a vertical direction through a lifting mechanism (6).

2. The tunnel equipment transportation device according to claim 1, characterized in that: A guide mechanism is provided for guiding and limiting the movement of the upper bracket (7).

3. The tunnel equipment transportation device according to claim 2, characterized in that: The cross beam (2) is vertically arranged in the middle of the column (1), and the column (1) vertically comprises an upper segment (1A) located above the cross beam (2) and a lower segment (1B) located below the cross beam (2); the upper bracket (7) is a square frame; the cross section of the upper segment (1A) is right-angled, and its right-angle opening faces inward; the four corners of the upper bracket (7) are vertically slidably matched with the right-angle opening of the upper segment (1A), and the guide mechanism is formed by the right-angle opening of the upper segment (1A) and the corner of the upper bracket (7).

4. The tunnel equipment transportation device according to any one of claims 1 to 3, characterized in that: The lifting mechanism (6) is a hydraulic cylinder.

5. The tunnel equipment transportation device according to any one of claims 1 to 3, characterized in that: Equipment placement slots (8) are provided in the middle of the four sides of the upper bracket (7).

6. The tunnel equipment transportation device according to any one of claims 1 to 3, characterized in that: Component placement grooves (9) extending in the longitudinal direction are respectively arranged on both sides of the portal frame in the transverse direction, and one end of the component placement groove (9) is fixed to the column (1) of the portal frame on the front side, and the other end is fixed to the column (1) of the portal frame on the rear side.

7. The tunnel equipment transportation device according to claim 6, characterized in that: The component placement groove (9) is vertically arranged at the bottom of the column (1).

8. The tunnel equipment transportation device according to any one of claims 1 to 3, characterized in that: A diagonal brace (10) is also provided between the upright column (1) of the front portal frame and the upright column (1) of the rear portal frame.